You are on page 1of 42

Lecciones del terremoto de Chile 2010 y su impacto en el suministro elctrico

Hugh Rudnick

Seguridad de abastecimiento elctrico


Preocupacin en la sociedad moderna

Suministro seguro de servicios bsicos


Alta dependencia de suministro elctrico Impactos diversos en suministro elctrico por
Problemas de abastecimiento de combustibles Guerras, conflictos polticos, terrorismo Desastres naturales (huracanes, terremotos, maremotos, erupciones volcnicas, etc.)

Necesidad estar preparados para enfrentarlos


2

Araneda, Juan Carlos (Transelec), Rudnick, Hugh (PUC), Mocarquer, Sebastian (Systep), Miquel, Pedro (Systep), "Lessons from the 2010 Chilean earthquake and its impact on electricity supply", 2010 International Conference on Power System Technology (Powercon 2010), Hangzhou, China, October 24-28, 2010

Large earthquakes in Chile


1575 1730 1751 1835 1868 1906 1922 1943 1960 1985 1995 Valdivia Valparaiso Concepcin Concepcin Arica Valparaso Vallenar Coquimbo Valdivia Santiago Antofagasta 8.5 8.7 8.5 8.5 9.0 8.2 8.5 8.2 9.5 8.0 8.0
4

The 2010 earthquake


03:34 hrs. February 27 2010
8.8 Richter shakes 6 regions of Chile along 500 km (80 % of population) Tsunami hits the cost minutes after

Death toll: 521; Missing: 56 Injured: 12,000; Displaced: 800,000 Infrastructure affected:
370,000 houses 4,013 schools 79 hospitals 4,200 boats damaged

Economic loss: 30 billion US dollars Acceleration of 0.65 g in Concepcion 10 meter average plaques displacement

Large acceleration for long time


Peak acceleration of 0.65 g for one of the horizontal records. Duration of strong shaking for 70 seconds

Its effects structural collapses

Its effects building collapses

Effects of the tsunami

Norms and standards in Chile


High standard of seismic requirements for its civil works. Building codes in Chile are substantially the same as US codes (ACI 318, a leading concrete design reference for building codes worldwide issued by the American Concrete Institute). High voltage electrical facilities, the national technical standard establishes that facilities must obligatorily fulfill the ETG 1.015 Chilean standard or the IEEE 693 standard in the condition of High Performance Level. It specifies a maximum 0.50 g acceleration and a maximum horizontal displacement of 25 cm. to be considered in the design as the seismic intensity at the facility location. Specific electrical requirements for installation construction and maintenance through Technical Norm of Security and Quality of Service, which defines technical and economic evaluations to determine the reliability level on the planning and operation of the power system.

10

SIC
Immediate blackout for 4,522 load (peak demand of 6,145 MW and installed capacity of 11,023 MW) Longitudinal transmission system over 2,200 km long Grid lines mainly at 220 kV and 500 kV Five, then two, island scheme for grid supply recovery Distribution networks severely damaged

11

Evolution of electricity supply

12

Evolution of electricity demand


Black out with loss of 3,000 MW

13

Impact on operation
Severe impacts on country communication systems. Basic systems (mobile networks, emergency alert schemes, public order control), electricity dependant, did not operate as desired and caused additional harm. Difficulties also arose in the communications and telecontrol schemes of most electricity installations, transmission substations and generating plants, complicating plant and system recovery and operation. No alternative backup radio systems.
14

Impact on operation
System operator (CDEC-SIC) had additional difficulties throughout the emergency as the SCADA system in use (for over ten years), was not able to provide information required for system recovery (alarms could not be trusted as they were often incorrect). Traditional phone calls had to be used to learn on local conditions and supervise actions for equipment and system restoration.

15

Dispatched generation at event


4,522 MW dispatched Immediate blackout

16

Damage in generation plants

Bocamina plant

17

But most remain available


3,000 MW became unavailable immediately 693 MW (13 plants) went to major repairs 950 MW being built also damaged
Cooling systems, transformers, communications, lines, etc.

MW (thermal plants) unavailable

18

Damages in lines
Transelec has 8,239 km. of lines, 50 substations, 10,486 MW transformation capacity

Hualpen-Bocamina line (3 towers)

19

Damages in substations

20

Damages in substations

21

But most remain available


Capacitor bank

without damage

22

But most remain available


Circuit breakers with sufficient damping

23

Transmission assesment
Damages concentrated in one transmission line
3 towers 154 kV line (1.6 km)

Substation damage (12 out of 46 substations, 26%). Mainly focused at:


500 kV bushings (high failure rate, particularly in transmission bushings) 500 kV pantograph disconnector switches 220 kV circuit breakers (live tank type) 154 kV circuit breakers (air compressed type)

24

Transmission interconnection recovery


Recovery process of the interconnected system

25

Worse extended damage in distribution

26

Worse extended damage in distribution

27

Worse extended damage in distribution

28

But most remains standing

29

Distribution damage
4.5 million people were initially affected by the extended blackout that took place because of the earthquake and it took days, and even weeks in some areas, to recover full electricity supply. Most affected areas supplied by CGE, Emelectric and Emelat. Chilectra also affected in Santiago. 80% of clients were without supply the day after the earthquake and this reduced to 0.4% two weeks after (related mainly to Concepcion and Talcahuano, next to the earthquake epicenter).
30

Distribution damage
Some distribution networks were destroyed by the effects of the earthquake, as houses fell over street lines or simply were washed away by the tsunamis (for example 40,000 houses were destroyed out of 1.5 million supplied by CGE). Besides those distribution installations directly damaged, there was little damage elsewhere. Distribution poles in Chile are mainly compressed pre-stressed concrete poles, which are well founded, and support important mechanical stresses. Exceptions in overloaded city poles.

31

Worse extended damage in distribution


Heavily loaded poles in main cities

32

Small percentage damage

760,000 poles in CGE and 300,000 in Chilectra

50,000 transformers in CGE and 20,000 in Chilectra.

33

Challenges in supply recovery

34

Damage in distribution
Distribution aerial transformers are often placed between two poles and a steel support, thus they also withstand well an earthquake. Main difficulties in restoring supply to houses took place at the connection point between the low voltage lines and the buildings. Companies have equipment and human resources to repair normal failures within one or two days. But when several hundred thousand of those connections fail, as in an earthquake, the problem is quite different. Communication problems, difficult physical access to locations, no resources to manage the huge number of needed repairs. Companies involved human resources brought from other regions.

35

Damage in distribution
Mobile generating sets brought to support recovery of supply, particularly in more isolated areas. Challenges for distribution companies lasted months after the earthquake (many latent faults, caused by the quake, that could not be detected when repairs were been made days after the event, or if detected, were secondary to the objective of supplying consumers as fast as possible). Arrival of winter, with rain and wind, started igniting these faults in a a massive way, demanding the companies to comply.

36

Araneda, Juan Carlos (Transelec), Rudnick, Hugh (PUC), Mocarquer, Sebastian (Systep), Miquel, Pedro (Systep), "Lessons from the 2010 Chilean earthquake and its impact on electricity supply", 2010 International Conference on Power System Technology (Powercon 2010), Hangzhou, China, October 24-28, 2010

37

Balance y conclusiones
Experiencia internacional indica mayores daos en transmisin y distribucin Altos estndares y cdigos constructivos civiles y en equipos elctricos de generacin Imposible evitar impactos de desastre natural de esa magnitud en instalaciones elctricas Necesidad aprovechar experiencia y producir necesarios cambios en mtodos de prevencin y de recuperacin
38

Balance y conclusiones
Balance negativo de capacidad de respuesta del pas y su institucionalidad de emergencia. Inaceptables niveles de fallas de infraestructura de comunicacin Balance positivo del nivel ssmico de la infraestructura elctrica (particularmente en generacin/transmisin) Claras oportunidades de mejoras, particularmente a nivel de CDEC y de redes de distribucin
39

Balance y conclusiones
Cuidado con reacciones excesivas a evento de baja frecuencia de ocurrencia Necesidad evaluar econmicamente acciones preventivas versus correctivas.

40

Agradecimientos
Transelec CGE Distribucin CGE Transmisin CDEC-SIC Chilectra American Society of Civil Engineers PostDisaster Assessment Teams (Dr. Anshel Schiff, Stanford University)

41

Lecciones del terremoto de Chile 2010 y su impacto en el suministro elctrico

Hugh Rudnick

You might also like