TABLE OF CONTENTS
1. SITE ACCEPTANCE/COMPLETION CERTIFICATE 2. OUTSTANDING TASKS 3. SITE SURVEY REPORT 4. SITE DRAWINGS 5. SITE INVENTORY 5.1 CHANGES TO SITE INVENTORY 6. FACTORY TEST REPORT (OPTIONAL) 7. INSTALLATION CHECKLIST 4 5 6 7 8 8 10 11
7.1 CHECKING THE AVAILABILITY OF DOCUMENTS AND TOOLS NEEDED FOR INSTALLATION 12 7.2 PREPARING THE EQUIPMENT ROOM 7.3 UNPACKING AND INSPECTING EQUIPMENT 7.4 PREPARING THE CABINET FOR INSTALLATION 7.5 INSTALLING THE CABINET ON THEIR OWN FEET 7.6 INSTALLING THE CABINET ON FLOOR RAILS 7.7 MOUNTING THE CABINET ON FLOOR RAILS 7.8 INSTALLING THE SIDE CABLE CONDUIT (SCC) 7.9 GROUNDING (EARTHING) THE CABINET 7.10 CONNECTING THE SITE POWER SUPPLY 7.11 ATTACHING AND FILLING IN THE LABELS AND STICKERS 7.12 INSTALLING THE INTERNAL CABLES 7.13 REPLACING FAN TRAYS (FTRB-A OR FTRB) 7.15 EQUIPPING CARTRIDGES WITH PLUG-IN UNITS 7.16 CABLING TO ENVIRONMENT 7.17 INSTALLING THE EXAU-A OR EXAU 7.18 FINISHING 7.19 FLEXI BSC (3000) INSTALLATION CERTIFICATE OF COMPLETION 8. COMMISSIONING CHECKLIST 8.1 FLEXI BSC COMMISSIONING LOG
Copyright Nokia Siemens Networks
12 13 13 14 14 16 16 17 17 17 18 18 19 20 22 22 22 24 25
Page 2 (58) 183089629.doc.doc
8.2 FLEXI BSC (3000) COMMISSIONING CERTIFICATE OF COMPLETION 9. INTEGRATION 9.1 PREPARING THE INTEGRATION 9.2 CREATING THE A-INTERFACE AND TCSM 9.3 SYNCHRONIZATION OF A INTERFACE 9.4 CREATION OF ABIS INTERFACE 9.5 BASE STATION INITIALIZATION 9.6 CREATION OF TRANSMISSION CONNECTIONS 9.7 CONNECTION OF BSC TO OMC(NMS) 9.8 TEST TRANSACTION 9.9 FINISHING 9.10 FLEXI BSC (3000) INTEGRATION CERTIFICATE OF COMPLETION 10. CUSTOMER-SPECIFIC DATA AND SITE ASSESSMENT REPORT 11. ADDITIONAL DOCUMENTS 11.1 DOCUMENTATION CHECKLIST
41 42 43 43 45 45 46 46 47 49 53 54 55 57 57
Without a Certificate of Completion, the next phase of work cannot begin. Only when a Certificate of Completion has been produced for each phase of work can the Site Acceptance Certificate be completed. A NSN Networks Customer Operations Representative and Customer Representative must complete this form upon system acceptance. Original: Customer Copy: Accounting Copy: Project Manager
2. OUTSTANDING TASKS
Item 1 Description of Outstanding Work Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Raised by: Completed by: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date: Sign.: Name: Date:
10
11
12
13
14
15
4. SITE DRAWINGS
Site-specific drawings that apply to NSN equipment installation are developed by NSN Site Engineering and contain site-specific installation information, such as: Site layout (equipment room floor layout) Site Power cabling layout Site ground cabling layout Site communications cabling layout
5. SITE INVENTORY
This section includes the following: The Equipment Packing Lists The Installation Hardware List
The serial numbers of the Installation Hardware List are recorded on completion of commissioning and may be added to the Site Folder either as a paper copy or on diskette.
7. INSTALLATION CHECKLIST
The Installation Team is to carry out the BSC Installation in accordance with the BSC User Manual. The Installation Team Supervisor is responsible for: Ensuring that each team member has the correct tools, installation materials, and User Manual. Checking the delivery against the packing list and placing it in Section 5 of the Site Folder. Completing this checklist, including the signature and date. Completing the necessary Site Deficiency Reports. Completing the necessary Fault Reports. Informing the Installation Manager/Site Manager of work progress, including any problems as they arise. Completing the Certificate of Completion and placing it in Section 1 of the Site Folder.
7.1 Checking the availability of documents and tools needed for installation
INSTALLATION PHASE AND RELATED DOCUMENTS Check the availability of documents needed for installation. Acquire missing documents. See: Installing FLEXI BSC and TCSM3i, section about the installation of FLEXI BSC and TCSM3i Check the availability of the tools needed for installation. Acquire missing tools. See: Installing FLEXI BSC and TCSM3i, section about the installation of FLEXI BSC and TCSM3i OK COMPLETED OK
INSTALLATION PHASE AND RELATED DOCUMENTS If find any defects in the site itself or the facility, notify the party responsible and ensure that corrective actions will be taken immediately. See: Installing FLEXI BSC and TCSM3i, section Unpacking and checking the equipment
COMPLETED OK
OK
INSTALLATION PHASE AND RELATED DOCUMENTS Drill the holes for the screws and lodge a wedge anchor in each hole. See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails Repeat the procedure mentioned above for the other rails. See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails Place the rails to their final places and level them off. See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails In IBN installation, mount the insulation tube in the first hole, followed by the insulation washer, the washer and the attachment screws. Screw in the screw slowly. Repeat the procedure mentioned above to all attachment points for both rails. See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails After attaching all screws, tighten them. See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails In IBN installation, check the attachment screws are not electrically connected to the rail. See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails Insert the cabinet attachment pieces inside the floor rails See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails Place the support bars crosswise to the rails, each bar on a pair of cabinet attachment pieces See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails. Move the support bars to approximately their final positions lengthwise on the rails. See: Installing FLEXI BSC and TCSM3i, section Installing the cabinets on floor rails.
COMPLETED OK
OK
OK
OK
OK
OK
OK
OK
OK
OK
COMPLETED OK
OK
COMPLETED OK
INSTALLATION PHASE AND RELATED DOCUMENTS Fill in the labels. See: Installing FLEXI BSC and TCSM3i, section Attaching identification stickers and marking labels.
COMPLETED OK
OK
OK
OK
OK
INSTALLATION PHASE AND RELATED DOCUMENTS Use the EDS wrist strap earthing device. - Insert the plug-in units (including I/O devices) in the cartridges after checking of identification labels. - Leave the plug-in unit unconnected. See: Installing FLEXI BSC and TCSM3i, section Equipping the cartridges with plug-in units. Install the power supply units. See: Installing FLEXI BSC and TCSM3i, section Equipping the cartridges with plug-in units. Switch power supply units on. Check the functions of the units from the LED indications. See: Installing FLEXI BSC and TCSM3i, section Equipping the cartridges with plug-in units.
COMPLETED OK
OK
OK
OK
INSTALLATION PHASE AND RELATED DOCUMENTS Ground and tie the outgoing cables (E1/T1, X.25, alarm) in the grounding element of CPGO panel. See: Connector Panels and External Cables in FLEXI BSC and TCSM3i Section CPGO See also: Site documents interconnection Cables in FLEXI BSC and TCSM3i,and Cabling instruction for FLEXI BSC and TCSM3i Cut the cable to proper length and connect them to the DDF. See: Connector Panels and External Cables in FLEXI BSC and TCSM3i Section CPGO See also: Site documents interconnection Cables in FLEXI BSC and TCSM3i,and Cabling instruction for FLEXI BSC and TCSM3i CPRJ45-A in S12 first delivery of FLEXI BSC1000/2000, and CPRJ45 in upgrade deliveries in FLEXI BSC660 Prepare the cabling going to the CPRJ45 panel (Lan, LPT/VDU, Synchronization, alarm and external alarm unit interface) See: Connector Panels and External Cables in FLEXI BSC and TCSM3i Section CPGO See also: Site documents interconnection Cables in FLEXI BSC and TCSM3i,and Cabling instruction for FLEXI BSC and TCSM3i E1/T1 (PCM) balance trunk cable panels CPETS-E and CPETS-F Prepare and cable the balanced trunk going to the connector panels CPETS-E and CPETS-F either at the cabinet top or in the Cabling cabinet. See: Connector Panels and External Cables in FLEXI BSC and TCSM3i Section CPGO See also: Site documents interconnection Cables in FLEXI BSC and TCSM3i,and Cabling instruction for FLEXI BSC and TCSM3i E1/T1 (PCM) balance trunk cable panels CPETC-E and CPETC-F Prepare and cable the balanced trunk going to the connector panels CPETC-E and CPETC-F either at the cabinet top or in the Cabling cabinet. See: Connector Panels and External Cables in FLEXI BSC and TCSM3i Section CPGO See also: Site documents interconnection Cables in FLEXI BSC and TCSM3i,and Cabling instruction for FLEXI BSC and TCSM3i
COMPLETED
OK
OK
OK
OK
OK
OK
OK
OK
7.18 Finishing
INSTALLATION PHASE AND RELATED DOCUMENTS Remove all temporary markings. Check the corrections in drawings used during the installation. Reinstall the doors See: Installing FLEXI BSC and TCSM3i, section Finishing the installation Connect the grounding cables between the doors and the cabinet frame. See: Installing FLEXI BSC and TCSM3i, section Finishing the installation Clean the installation site Fill in the Installation Certificate of Completion OK OK OK COMPLETED OK OK OK
CHECKED (INITIALS) OK
COMMENTS
Unpacking and checking the equipment Preparing the cabinet for installation Installing the cabinet on its own feet Installing the cabinet on floor rails Installing the Side Cable Conduit Grounding (earthing) the cabinet Connecting the station power supply Attaching and filling in the labels and stickers Installing the internal cables Replacing the Fan trays Creating a temporary ESD protected area Equipping the cartridges with plug-in units Cables to environment Installing the External Alarm Unit Finishing
OK OK OK OK OK OK OK OK OK OK OK OK OK OK OK
NSN hereby states that the whole of supplies detailed above have been inspected, tested and unless otherwise stated conform to the specified requirements in the contract or order identified above.
NSN Site Representative (print name): NSN Site Representative (signature): Customer Representative (print name): Customer Site Representative (signature): Date: Date:
8. COMMISSIONING CHECKLIST
The Commissioning Engineer is to carry out all commissioning tests in accordance with the FLEXI BSC Commissioning Procedure, using the FLEXI BSC User Manual and other approved reference material. Customer-specific parameters are to be used where applicable. A signed Certificate of Completion for the installation work must be included in Section 1 of the Site Folder, certifying that the installation work has been completed to the required standard. The Commissioning Engineer is responsible for: Checking the quality of the installation. Correcting any installation problems/faults or deficiencies. Familiarization with current Technical Notes. Commissioning the FLEXI BSC system in preparation for integration. Completing this checklist, including signature and date. Completing the necessary Site Deficiency Reports. Completing the necessary Fault Reports. Informing the Site Manager of work progress, including any problems as they arise. Completing the Certificate of Completion and placing it in Section 1 of the Site Folder.
The commissioning starts with initial inspections during which the condition of the hardware and software is checked. After these inspections, the order of the tests can be determined freely. The tester marks the results of the tests in the test logs. Reading the instructions is recommended before starting the tests. After the tests, fill in the Commissioning Checklist.
Table 3: Inspecting FLEXI BSC internal cabling Commissioning phase Compare the internal cabling with Interconnection Cables List in the Site Specific Documents. OK = everything is in order NOK = something is wrong Completed OK
Table 4: Inspecting FLEXI BSC hardware functioning Commissioning phase Compare the interchange ability codes of the plug-in units and cartridges with BSC and TCSM Hardware Revision List in the Site Specific Documents. Check the jumpers and EPROM versions of plug-in units and cartridges by comparing them to the version list. Tick the box in the following tables when ready. Connect ET cables after checking the units. OK = everything is in order NOK = something is wrong Completed OK
OK
CPU FLASH
OMU Unit
OMU Unit
OK
OMU
OK = everything is in order
Table 6: Inspecting strappings, DIP switches, memory, and EPROMs of MCMU's Unit MCMU0 MCMU1 Unit CPU jumpers CPU DIP switches OK OK OK OK CPU FLASH 3.11-0 & 3.12-0 3.11-0 & 3.12-0 SWPRO EPROMs CPU memory 1073MB 1073MB ADMODD DIP swiches OK OK NIU = Not in Use SWPRO jumper ESB jumpers NIU NIU NIU NIU
MCMU0 OK MCMU1 OK
OK OK
OK = everything is in order
Table 7: Inspecting strappings of GSWP Unit GSW2KB 0 GSW2KB 1 OK = everything is in order SW256B jumpers NIU NIU NOK = something is wrong DIP swicth OK OK NIU = Not in Use
Table 8: Inspecting strappings, DIP switches, memory, and EPROMs of BCSU's Unit CPU CPU DIP CPU FLASH CPU MBIF DIP AS7
Page 26 (58) 183089629.doc.doc
jumpers BCSU0 BCSU1 BCSU2 BCSU3 BCSU4 BCSU5 BCSU6 BCSU7 BCSU8 BCSU9 BCSU10 OK OK OK OK OK N/A N/A N/A N/A N/A N/A
switches OK OK OK OK OK N/A N/A N/A N/A N/A N/A 3.11-0 & 3.12-0 3.11-0 & 3.12-0 3.11-0 & 3.12-0 3.11-0 & 3.12-0 3.11-0 & 3.12-0 N/A N/A N/A N/A N/A N/A
Unit
PCU FLASH
BCSU0 BCSU1 BCSU2 BCSU3 BCSU4 BCSU5 BCSU6 BCSU7 BCSU8 BCSU9 BCSU10
2.4-0 2.4-0 2.4-0 2.4-0 2.4-0 N/A N/A N/A N/A N/A N/A
Table 9: Inspecting strappings and EPROMs of ET's Unit ET16 SLOT 1 ET16 SLOT 2 ET16 SLOT 3 ET16 SLOT 4 ET16 SLOT 5 ET16 SLOT 6 ET16 SLOT 7 ET16 SLOT 8 ET16 SLOT 9 ETC-0 OK OK OK OK OK OK OK OK N/A ETC-1 OK OK OK OK OK OK OK OK OK ETC-2 OK OK OK OK OK OK OK OK N/A ETC-3 N/A N/A N/A N/A N/A N/A N/A N/A N/A ETC-4 N/A N/A N/A N/A N/A N/A N/A N/A N/A ETC-5 N/A N/A N/A N/A N/A N/A N/A N/A N/A
OK = everything is in order NIU = Not in use Unit ETS2 SLOT 1 ETS2 SLOT 2 ETS2 SLOT 3 ETS2 SLOT 4 ETS2 SLOT 5 ETS2 SLOT 6 ETS2 SLOT 7 ETS2 SLOT 8
NOK = something is wrong VER xx.xx = EPROM version GTIC 0 OK OK NIU NIU NIU NIU NIU NIU GTIC 1 NIU NIU NIU NIU NIU NIU NIU NIU
Table 10: Inspecting strappings and EPROMs of clock equipment Unit CLS 0 CLS 1 CLOC jumpers OK OK CLOC EPROM OK OK TON FIA EPROM OK OK Cartridge jumpers OK OK
Table 11: Testing power supply Commissioning phase Measure the supply voltage from the PDE power supply lines: Nominal voltage: -48V to -60V Tolerance: -40.5V to -72V OK = everything is in order NOK = something is wrong Completed OK
-52 V OK
Table 12: Testing peripheral units Commissioning phase Check that the settings of VDU are as follows: Baud Rate: 9600 Data Bits: 7 Completed OK OK OK
Commissioning phase Stop Bits: 2 Parity: Even Page Length: 23 Line Length: 80 Check that the settings of the printer are as follows: Baud Rate: 9600 Data Bits: 7 Stop Bits: 2 Parity: Even Page Length: 65 Line Length: 80 OK = everything is in order NOK = something is wrong
Completed OK OK OK OK
OK OK OK OK OK OK
Table 13: Monitoring start-up of units Commissioning phase Loading of OMU Loading of MCMU's Loading of BCSU's OK = everything is in order NOK = something is wrong Completed OK OK OK
Table 14: Opening the first MML session in the BSC Commissioning phase USERNAME <SYSTEM> PASSWORD <SYSTEM>
Copyright Nokia Siemens Networks
Completed OK OK
Page 30 (58) 183089629.doc.doc
OK = everything is in order
Table 15: Verifying the BSC's SW version Commissioning phase Print out all SW builds installed in the disk Perform verification for each build and compare the printout with the Delivery Catalogue. OK = everything is in order NOK = something is wrong Completed OK OK
Table 16: Inspecting the BSC's I/O system Commissioning phase Display all I/O devices OK = everything is in order NOK = something is wrong Completed OK
Table 17: Testing the BSC's Ethernet Message Bus connections Commissioning phase Unit OMU MCMU 0 MCMU 1 BCSU 0 BCSU 1 BCSU 2 BCSU 3 BCSU 4 BCSU 5 BCSU 6 BCSU 7 BCSU 8 BCSU 9 EMB address (Hex) 00 04 05 30 31 32 33 34 N/A N/A N/A N/A N/A OK OK OK OK OK OK OK OK N/A N/A N/A N/A N/A
Page 31 (58) 183089629.doc.doc
Completed
Commissioning phase Unit BCSU 10 EMB address (Hex) N/A NOK = something is wrong
Completed
OK = everything is in order
Table 18: Testing the wired alarms Unit MCMU 0 MCMU 1 BCSU 0 BCSU 1 BCSU 2 BCSU 3 BCSU 4 BCSU 5 BCSU 6 BCSU 7 BCSU 8 BCSU 9 BCSU 10 PDFU 0(1) PDFU 1(1) PDFU 2(1) PDFU 3(1) PDFU 0(2) Alarm no 2757 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A OK OK NIU NIU NIU Alarm no 2758 OK OK OK OK OK OK OK OK OK N/A N/A N/A N/A NIU NIU NIU NIU NIU Alarm no 2759 N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A OK OK NIU NIU NIU Alarm no 3146 OK OK OK OK OK OK OK OK OK N/A N/A N/A N/A OK OK NIU NIU NIU
Unit PDFU 1(2) PDFU 2(2) PDFU 3(2) FTRB 0(1) FTRB 1(1) FTRB 2(1) FTRB 3(1) FTRB 0(2) FTRB 1(2) FTRB 2(2) FTRB 3(2) GSWB 0 GSWB 1 CLOC 0 CLOC 1 CLAC 0 CLAC 1 CLAC 2 CLAC 3 CLAC 4 CLAC 5 LANU 0 LANU 1 LANU 2 LANU 3 GTIC 0
Alarm no 2757 NIU NIU NIU OK OK OK OK NIU NIU NIU NIU OK OK OK NIU OK OK NIU NIU NIU NIU NIU NIU NIU NIU OK
Alarm no 2758 NIU NIU NIU OK OK OK OK NIU NIU NIU NIU OK OK OK NIU OK OK NIU NIU NIU NIU OK OK NIU NIU OK
Alarm no 2759 NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU
Alarm no 3146 NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU NIU OK OK OK NIU OK OK NIU NIU NIU NIU OK OK NIU NIU OK
Alarm no 2759 NIU NIU NIU NIU NIU NIU NIU NIU =Not in Use
OK = everything is in order
Test the external alarms by creating one external alarm and connecting alarm inputs one by one to this alarm. Test the alarm inputs by wiring them one by one. Table 19: Testing the external alarms Alarm AEI00 MAIN FAILLURE AEI02 MODULE RECT FAILURE AEI04 DOOR OPEN AEI06 GENSET FAIL AEI08 HIGH TEMPERATURE AEI10AC BURGLAR AEI12 AEI14 AEI16 AEI18 AEI20 AEI22 OK = everything is in order Completed OK OK OK OK OK OK NIU NIU NIU NIU NIU NIU Alarm AEI01 BATTERY FUSE FAILURE AEI03 LOAD FUSE FAILURE AEI05 GENSET RUNNING AEI07 BATTERY LOW VOLTAG AEI09 BATTERY CHARGING AEI11 GROUNDING BURGLAR AEI13 AEI15 AEI17 AEI19 AEI21 AEI23 Completed OK OK OK OK OK OK NIU NIU NIU NIU NIU NIU
OK = everything is in order
Table 21: Testing the recovery from complete power break in the system Commissioning phase Disconnect the power from the system Connect the power to the system OK = everything is in order NOK = something is wrong Completed OK OK
Table 22: Testing power break in the PDFU Commissioning phase Remove the fuse. Wait until the recovery measures have been completed and connect the fuse. Repeat for all fuses. OK = everything is in order NOK = something is wrong Completed OK
Commissioning phase Disconnect the power from each of the PDFU one by one OK = everything is in order NOK = something is wrong
Completed OK
Table 24: Testing the state transition and unit diagnostics of the BSC's units Commissioning phase Testing the state transition and diagnostics of all units. Tick the box in the following tables when ready. OK = everything is in order NOK = something is wrong Completed OK
Table 25: Testing the state transition and unit diagnostics of computer units Unit OMU MCMU 0 MCMU 1 BCSU 0 BCSU 1 BCSU 2 BCSU 3 BCSU 4 BCSU 5 BCSU 6 BCSU 7 BCSU 8 BCSU 9 BCSU 10 CLS 0 CLS 1 CLAB 0
Copyright Nokia Siemens Networks
Unit CLAB 1 CLAB 2 CLAB 3 CLAB 4 CLAB 5 EMB 0 EMB 1 SBUS 0 SBUS 1 SWU 60 SWU 61 STMU 32 STMU 36 STMU 38 STMU 40 ET16 (512-527) ET16 (528-543) ET16 (544-559) ET16 (560-575) ET16 (576-591) ET16 (592-607) SET 0 SET 1 SET 2
MCMU 0 WO state NIU NIU NIU NIU NIU OK OK (SP) NIU NIU OK OK OK OK OK NIU OK OK OK OK OK OK OK OK OK
MCMU 1 WO state NIU NIU NIU NIU NIU OK (SP) OK NIU NIU OK OK OK OK OK NIU OK OK OK OK OK OK OK OK OK
Unit SET 3 SET 64 SET 65 SET 66 SET 67 SET 128 SET 129 OK = everything is in order
Table 26: Checking the switchover and the alarms from the clock synchronization unit Commissioning phase Check the alarms from the clock units Test the switchover of the clock units with MML Test the switchover of the clock units with the front panel switch / (and) by remove power cable OK = everything is in order NOK = something is wrong Completed OK OK OK
Table 27: Checking the BSC's hardware configuration Commissioning phase Print the hardware configuration and compare it to the Hardware List in Site Specific Documentation. OK = everything is in order NOK = something is wrong Completed OK
Table 28: Checking the ESB switch Unit MCMU0 Local reset and hot swap OK Built-in self test OK Completed OK
Completed OK OK OK OK OK
Table 29: Copying additional software Commissioning phase Install the customer specific diskette Install Change Deliveries Set the time zone Restart the system OK = everything is in order NOK = something is wrong Completed OK OK OK OK
Site Address:
INSTALLATION STAGE Checking hardware functional of BSC3i Opening the first MML session in BSC3i Monitoring the FLEXI BSC start-up Checking the I/O system of BSC3i Checking the EMB in BSC3i Checking the clock equipment in BSC3i Checking the hardware configuration of BSC3i Checking the maintenance system of BSC3i Checking the ESB switch in BSC3i Verifying the software version of BSC3i Copying additional software and setting the time zone in BSC3i
CHECKED (INITIALS)
OK OK OK OK OK OK OK OK OK OK OK
COMMENTS
NSN hereby states that the whole of supplies detailed above have been inspected, tested and unless otherwise stated conform to the specified requirements in the contract or order identified above.
NSN Site Representative (print name): NSN Site Representative (signature): Customer Representative (print name): Customer Site Representative (signature): Date: Date:
9. INTEGRATION
The FLEXI BSC Integration Engineer is to carry out all integration tests in accordance with the FLEXI BSC User Manual and other approved Integration Procedure. The Integration Engineer is to ensure that a signed Certificate of Completion is produced, certifying that the FLEXI BSC system has been commissioned and is ready for Integration. The Integration Engineer is responsible for: Clearing any Installation/Commissioning problems, faults or deficiencies. Familiarization with current Technical Notes. Checking that Site Folder documentation is complete. Completing this checklist including signature and date. Completing the necessary Site Deficiency Reports. Completing the necessary Fault Reports. Informing the Site Manager of work progress, including any problems as they arise. Completing the Certificate of Completion and placing it in Section 1 of the Site Folder.
OK
OK
Create the TCSM3I with commands WT_, WUC and USC. TR3_PXSX TRZ_PXSX T55_PXSX E16TCSSX ZWTU:TCSM,1664:1C2-0:; ZWTP:TCSM,1664:TR3T,0,1,::GENERAL,8,166 4,TSL,1::; ZWUC:TCSM,1664:TR3T,0:; ZWGC:1664,1:POOL=28:BCSU,0:; OK OK OK OK
Through connect the signalling channel with remote command ZWGS, ZWGA PCM TSL PCM TSL PCM TSL PCM TSL PCM TSL PCM TSL PCM TSL 3392>1-31 3393>1-31 3394>1-31 3395>1-31 3396>1-31 3397>1-31 3398>1-31 - -> - -> - -> - -> - -> - -> - -> TCSM TCSM TCSM TCSM TCSM TCSM TCSM 1664 1664 1664 1664 1665 1665 1665 TC PCM-TSL TC PCM-TSL TC PCM-TSL TC PCM-TSL TC PCM-TSL TC PCM-TSL TC PCM-TSL TSL 1-8 TSL 9-16 TSL 17-24 TSL 25-30 TSL 1-8 TSL 9-16 TSL 17-24 OK OK OK OK OK OK OK
Page 43 (58) 183089629.doc.doc
PCM TSL PCM TSL PCM TSL PCM TSL PCM TSL
TSL 25-30 TSL 1-8 TSL 9-16 TSL 17-24 TSL 25-30
OK OKOK OK OK OK
Set cyclic redundancy check of TCSM3I on or off. For ET1E the DBLF checking is set by strapping and for ET2E it is set by MML (commands YEI and YEC). A interface (TCSM23I- MSC) A interface (BSC TCSM3I) CRC4 CRC4 on on off off OK OK
Create Message Transfer Part (MTP) (command class N and command group OB). Signalling link number: External PCM - TSL: 0,1,2,3 287,1055,543,607
Local signalling point code (H/D): D4364 / 11OC Local signalling point name: Signalling network: MSC signalling point code (H/D): MSC signalling point name FB-PENGAYOMAN 3 N/A D4124 / 101C MSS UPD 3 OK
MGW signalling point code (H/D): D4053 / FD5 MGW signalling point name MGW UPD4
Create A interface circuit group for the MSC (speech circuits) with command RCC. Circuit group name: Circuit group number: Line signalling parameter (LSI): MUPD3,UPD5_2,UPD5_3 1 AINO , 2 , 3 OK
Add circuits to the circuit group with command RCA. ET - PCM 1664 CRCT CRCT CRCT 2 1&& - 31 3 - 1&& - 31 4 - 1&& - 31 CCS PCM CCS PCM CCS PCM 1 2 3 OK OK OK
ET - PCM 1665
4 5 6
OK OK OK
ET - PCM 1667
7 8 9
OK OK OK
Completed
CRC
on
off 19009
510 10
BTS_3033.014
FLEXI_EP3MP3
BTS_3033.016
FLEXI_EP3MP3
Completed
Page 46 (58) 183089629.doc.doc
Create the service channel with commands QWC. Service channel number Service channel number PCM PCM TSL TSL
N/A
BSS Integration Manuals /2/ ETSI (4.1.3.) and /3/ ANSI (9.2.) Add equipments to the service channel with commands QWC and QWS. Service ch. no. Service ch. no. Service ch. no. Service ch. no. Device name: Device name: Device name: Device name: address: address: address: address:
N/A
Set system authorities (command group IA). User_id User_id <SYSTEM> Password Password <SYSTEM> Authorities Authorities 250
N/A
EITHER creates an analog X.25 connection (command class Q). Interface type: Bit rate:
N/A
OR create a digital X.25 connection (command class Q). Physical channel number: PCM TSL
Through connected signalling channel in TCSM2: PCM TSL -> PCM - TSL
Create OSI connections (command class Q). SNPA ADDRESS Created applications: CMISE VFS VTP TPU PAD
Set up the logical file that is used for buffered events in the BSC with command IIS.
N/A
Integration phase Create redundant connections (command class Q): EITHER creates an analog X.25 connection. Interface type: Bit rate:
Copyright Nokia Siemens Networks
Completed
N/A
Through connected signalling channel in TCSM2: PCM TSL -> PCM - TSL
Check that the TRX and the BTS to be tested are in working state and operative.
Check that the expected results are fulfilled: - Alarm concerning a TRX lock. - When the TRX is locked locally an announcement concerning this state is also sent to the BSC, and the BSC MML also shows that the TRX is locked and not available for traffic.
Check the settings of the TCSM with remote MML ZDDT. Check that the TCSM2 hardware configuration matches the hardware in the racks. Use the service terminal command ZGT. If necessary, delete extra hardware with command ZGD (HW created by the system by default is maximum configuration).
OK
Cause a channel fault to the transcoder unit for example by pulling out a TR16 plug-in unit.
N/A
N/A N/A
Check that the expected result is fulfilled: - Alarm 2952 Transcoder plug-in unit failure is active.
OK
Check that the expected result is fulfilled: - The mobile station finds the network and ends on service state.
OK
9.8.4 MS TO MS CALL
Integration phase Make a call from subscriber A (the calling subscriber) to subscriber B (the called subscriber). Completed OK
OK
OK
OK
OK
OK
Check that the expected result is fulfilled: - The call succeeds and speech quality is good.
OK
Clear the call at subscriber As MS after observing the busy tone at subscriber As MS.
OK
OK
OK
Check that the expected result is fulfilled: - Subscriber A receives the busy tone.
OK
OK
OK
OK
Check that the expected results are fulfilled: - There are no hanging resources. - The call is set up as required and subscriber A releases the call.
OK
8.7 Successful Handover: Free TCH Integration phase Check that there are free TCH in the BTS where the subscriber A will move. Completed
Check that the expected result is fulfilled: - The call succeeds and speech quality is good all the time.
Check that the expected result is fulfilled: - The handover fails and the call is released by the network.
9.9 Finishing
Integration phase Fill in the BSC Integration Certificate of Completion. Completed OK
OK
Date :
INTEGRATION STAGE Preparation of Integration Creation of A interface and TCSM Synchronization of A interface Creation of Abis interface Base Station Initialization Creation of transmission connections Connection of BSC to OMC(NMS) Test Transactions Finishing
CHECKED (INITIALS)
OK OK OK OK OK OK OK OK OK
COMMENTS
NSN hereby states that the whole of supplies detailed above have been inspected, tested and unless otherwise stated conform to the specified requirements in the contract or order identified above.
NSN Site Representative (print name): NSN Site Representative (signature): Customer Representative (print name): Customer Site Representative (signature): Date: Date:
SITE INFORMATION BUILDING NAME: TTC 1 CUSTOMER SITE NAME: PENGAYOMAN 3 JL. PENGAYOMAN NO.1 . SITE ADDRESS: KELURAHAN BUAKANA. KECAMATAN PANAKUKANG. MAKASSAR SULAWESI SELATAN.
SITE ACCESS INFORMATION CUSTOMER KEYS: NAME: TEL. NSNS SUPERVISOR: NAME: TEL.
The Site assessment Report is the last report to check overall site situation together with customer and mutual agree and sign whether site is implemented following standards, nothing damages impact to the building structure. Any open issues which both NSN and customer accept to do later on after the site assessment done.
HARD COPIES/SOFT FILES Site Acceptance Certificate Form, Document support in Section 1 Site Survey Report Form, Document support in Section 3 Site Drawings, Documents support in Section 4 HW inventory file / Equipment Packing List , Documents support in Section 5 Operational HW database HW inventory file / Equipment Packing List MMI test log file Site Assessment Report / Site Visit, Documents support in Section 10