List of variables of study and their levels in the STATA

data set c:\bos\pm1.dta


The data set c:\bos\pm1.dta contains the following 30
variables of study (A dependent variable of study + 29
independnet variables of study).
Dependent or outcome variable of study (Y)

success: Successful completion of project (Yes, No)

List of 29 independent or explanatory variables of study


(X1, X2, ., X29)

relationship: Problems related to relationship (Very low,


Low, Average, High, Very high)

experience: Problems related to lack of experience (Very


low, Low, Average, High, Very high)

type: Type of project (Buildings, Roads, Lights, Water, IT)

race: Race group of project leader (Black, White, Coloured,


Indian)

rivals: Problems related to rivals (Very low, Low, Average,


High, Very high)

resources: Problems related to shortage of resources


(Very low, Low, Average, High, Very high)

scope: Problems due to change of scope of project (Very


low, Low, Average, High, Very high)

objectives: Problems related to failure to meet objectives


(Very low, Low, Average, High, Very high)

quality: Problems related to quality of workmanship (Very


low, Low, Average, High, Very high)

cost: Problems related to cost over-run (Very low, Low,


Average, High, Very high)

time: Problems related to time over-run (Very low, Low,


Average, High, Very high)

control: Problems related to lack of control (Very low,


Low, Average, High, Very high)

procurement: Problems related to procurement (Very low,


Low, Average, High, Very high)
2

contract: Problems related to contractual agreement (Very


low, Low, Average, High, Very high)

interference: Problems due to interference (Very low, Low,


Average, High, Very high)

communication: Problems due to poor communication


(Very low, Low, Average, High, Very high)

stakeholders: Problems related to stakeholders (Very low,


Low, Average, High, Very high)

planning: Problems due to poor planning (Very low, Low,


Average, High, Very high)

accountability: Problems due to lack of accountability


(Very low, Low, Average, High, Very high)

transparency: Problems due to lack of transparency (Very


low, Low, Average, High, Very high)

audit: Problems due to lack of proper auditing (Very low,


Low, Average, High, Very high)

training: Problems related to lack of training (Very low,


Low, Average, High, Very high)

leadership: Problems related to lack of leadership (Very


low, Low, Average, High, Very high)

conflicts: Problems related to internal conflicts (Very low,


Low, Average, High, Very high)

risk: Problems related to unforeseen potential risks (Very


low, Low, Average, High, Very high)

skills: Problems related to lack of skills (Very low, Low,


Average, High, Very high)

harmony: Problems related to lack of harmony (Very low,


Low, Average, High, Very high)

labour: Problems related to labour (Very low, Low,


Average, High, Very high)

trust: Problems related to lack of trust in project leader


(Very low, Low, Average, High, Very high)

Procedure 1: Frequency tables for categorical


variables of study

. use c:\bos\pm1.dta, clear


. des
Contains data from c:\bos\pm1.dta
obs:

120

vars:

30

size:

35,040

------------------------------------------------------------------------------------------------storage
variable name

type

display

value

format

label

variable label

------------------------------------------------------------------------------------------------success

str3

%9s

Successful completion of project

relationship
str10
project manager

%10s

Problems related to working relationship with

experience

str10

%10s

Problems related to lack of experience

type

str11

%11s

Type of project

race

str8

%9s

Race group of project leader

rivals

str10

%10s

Problems related to rivals

resources

str10

%10s

Problems related to shortage of resources

scope

str10

%10s

Problems related to change of scope of project

objectives

str10

%10s

Problems related to failure to meet objectives

quality

str10

%10s

Problems related to quality of work

cost

str10

%10s

Problems related to cost overrun

time

str10

%10s

Problems related to time overrun

control

str10

%10s

Problems related to lack of control of project

procurement

str10

%10s

Problems related to procurement issues

contract

str10

%10s

Problems related to contractual obligations

interference

str10

%10s

Problems related to interference

communication

str10

%10s

Problems related to poor communication

stakeholders

str10

%10s

Problems related to stakeholders

planning

str10

%10s

Problems related to poor planning

accountability

str10

%10s

Problems related to lack of accountability

transparency

str10

%10s

Problems related to lack of transparency

audit

str10

%10s

Problems related to poor auditing

training

str10

%10s

Problems related to lack of proper training

leadership

str10

%10s

Problems related to lack of leadership

conflicts

str10

%10s

Problems related to internal conflicts

risk

str10

%10s

Problems related to unforeseen risk

skills

str10

%10s

Problems related to lack of skills

harmony
members

str10

%10s

Problems related to lack of harmony among team

labour

str10

%10s

Problems related to labour issues

trust

str10

%10s

Problems related to lack of trust in project leader

------------------------------------------------------------------------------------------------Sorted by:

. tab1 success relationship experience


type race rivals resources scope
objectives quality cost time control
procurement contract interference
communication stakeholders planning
accountability transparency audit

training leadership conflicts risk


skills harmony labour trust
-> tabulation of success

Successful |
completion |
of project |

Freq.

Percent

Cum.

------------+----------------------------------No |

21

17.50

17.50

Yes |

99

82.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of relationship

Problems |
related to |
working |
relationshi |
p with |
project |
manager |

Freq.

Percent

Cum.

------------+----------------------------------Average |

37

30.83

30.83

High |

47

39.17

70.00

Low

1.67

71.67

Very high

30

25.00

96.67

Very low

3.33

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of experience

Problems |
related to |
lack of |
experience |

Freq.

Percent

Cum.

------------+----------------------------------Average |

36

30.00

30.00

High |

43

35.83

65.83

Low

26

21.67

87.50

Very high

3.33

90.83

Very low

11

9.17

100.00

------------+----------------------------------Total |

120

100.00

Freq.

Percent

-> tabulation of type

Type of |
project |

Cum.

------------+----------------------------------Buildings

26

21.67

21.67

IT |

18

15.00

36.67

Lights |

18

15.00

51.67

Roads

38

31.67

83.33

Water |

20

16.67

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of race

Race group |

of project |
leader |

Freq.

Percent

Cum.

------------+----------------------------------Black

29

24.17

24.17

Coloured |

18

15.00

39.17

34

28.33

67.50

White |

39

32.50

100.00

Indian

------------+----------------------------------Total |

120

100.00

-> tabulation of rivals

Problems |
related to |
rivals |

Freq.

Percent

Cum.

------------+----------------------------------Average |

23

19.17

19.17

High |

34

28.33

47.50

Low

14

11.67

59.17

Very high

34

28.33

87.50

Very low

15

12.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of resources

Problems |
related to |
shortage of |
resources |

Freq.

Percent

Cum.

------------+----------------------------------Average |

10

8.33

8.33

High |

35

29.17

37.50

Low

12

10.00

47.50

Very high

53

44.17

91.67

Very low |

10

8.33

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of scope

Problems |
related to |
change of |
scope of |
project |

Freq.

Percent

Cum.

------------+----------------------------------Average |

2.50

2.50

High |

31

25.83

28.33

Low |

15

12.50

40.83

Very high

70

58.33

99.17

Very low

0.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of objectives

Problems |
related to |
failure to |
meet |
objectives |

Freq.

Percent

Cum.

------------+----------------------------------Average |

5.00

5.00

10

High |

24

20.00

25.00

Low |

14

11.67

36.67

76

63.33

100.00

Very high

------------+----------------------------------Total |

120

100.00

-> tabulation of quality

Problems |
related to |
quality of |
work |

Freq.

Percent

Cum.

------------+----------------------------------Average |

19

15.83

15.83

High |

46

38.33

54.17

Low

18

15.00

69.17

Very high

36

30.00

99.17

Very low

0.83

100.00

------------+----------------------------------Total |

120

100.00

Freq.

Percent

-> tabulation of cost

Problems |
related to |
cost |
overrun

Cum.

------------+----------------------------------Average |

11

9.17

9.17

High |

38

31.67

40.83

Low

22

18.33

59.17

Very high

48

40.00

99.17

11

Very low

0.83

100.00

------------+----------------------------------Total |

120

100.00

Freq.

Percent

-> tabulation of time

Problems |
related to |
time |
overrun

Cum.

------------+----------------------------------Average |

11

9.17

9.17

High |

49

40.83

50.00

Low

15

12.50

62.50

Very high

45

37.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of control

Problems |
related to |
lack of |
control of |
project |

Freq.

Percent

Cum.

------------+----------------------------------Average |

24

20.00

20.00

High |

51

42.50

62.50

Low

16

13.33

75.83

Very high

29

24.17

100.00

------------+----------------------------------Total |

120

100.00

12

-> tabulation of procurement

Problems |
related to |
procurement |
issues |

Freq.

Percent

Cum.

------------+----------------------------------Average |

29

24.17

24.17

High |

48

40.00

64.17

Low

13

10.83

75.00

Very high

29

24.17

99.17

Very low

0.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of contract

Problems |
related to |
contractual |
obligations |

Freq.

Percent

Cum.

------------+----------------------------------Average |

19

15.83

15.83

High |

50

41.67

57.50

Low

20

16.67

74.17

Very high

31

25.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of interference

13

Problems |
related to |
interferenc |
e |

Freq.

Percent

Cum.

------------+----------------------------------Average |

21

17.50

17.50

High |

47

39.17

56.67

Low

12

10.00

66.67

Very high

38

31.67

98.33

Very low

1.67

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of communication

Problems |
related to |
poor |
communicati |
on |

Freq.

Percent

Cum.

------------+----------------------------------Average |

2.50

2.50

High |

25

20.83

23.33

Low

18

15.00

38.33

Very high

74

61.67

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of stakeholders

Problems |
related to |

14

stakeholder |
s |

Freq.

Percent

Cum.

------------+----------------------------------Average |

10

8.33

8.33

High |

40

33.33

41.67

Low

13

10.83

52.50

Very high

57

47.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of planning

Problems |
related to |
poor |
planning |

Freq.

Percent

Cum.

------------+----------------------------------Average |

21

17.50

17.50

High |

29

24.17

41.67

Low

25

20.83

62.50

Very high

34

28.33

90.83

Very low

11

9.17

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of accountability

Problems |
related to |
lack of |
accountabil |
ity

Freq.

Percent

Cum.

15

------------+----------------------------------Average |

15

12.50

12.50

High |

47

39.17

51.67

Low

17

14.17

65.83

Very high

41

34.17

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of transparency

Problems |
related to |
lack of |
transparenc |
y |

Freq.

Percent

Cum.

------------+----------------------------------Average |

20

16.67

16.67

High |

39

32.50

49.17

Low

24

20.00

69.17

Very high

35

29.17

98.33

Very low

1.67

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of audit

Problems |
related to |
poor |
auditing

Freq.

Percent

Cum.

------------+----------------------------------Average |

16

13.33

13.33

16

High |

44

36.67

50.00

Low

21

17.50

67.50

Very high

38

31.67

99.17

Very low

0.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of training

Problems |
related to |
lack of |
proper |
training |

Freq.

Percent

Cum.

------------+----------------------------------Average |

26

21.67

21.67

High |

35

29.17

50.83

Low

27

22.50

73.33

Very high

31

25.83

99.17

Very low

0.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of leadership

Problems |
related to |
lack of |
leadership |

Freq.

Percent

Cum.

------------+----------------------------------Average |

4.17

4.17

High |

29

24.17

28.33

17

Low

17

14.17

42.50

Very high

66

55.00

97.50

Very low

2.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of conflicts

Problems |
related to |
internal |
conflicts

Freq.

Percent

Cum.

------------+----------------------------------Average |

14

11.67

11.67

High |

41

34.17

45.83

Low

18

15.00

60.83

Very high

47

39.17

100.00

------------+----------------------------------Total |

120

100.00

Freq.

Percent

-> tabulation of risk

Problems |
related to |
unforeseen |
risk |

Cum.

------------+----------------------------------Average |

15

12.50

12.50

High |

42

35.00

47.50

Low

18

15.00

62.50

Very high

45

37.50

100.00

------------+-----------------------------------

18

Total |

120

100.00

-> tabulation of skills

Problems |
related to |
lack of |
skills |

Freq.

Percent

Cum.

------------+----------------------------------Average |

29

24.17

24.17

High |

37

30.83

55.00

Low

24

20.00

75.00

Very high

27

22.50

97.50

Very low

2.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of harmony

Problems |
related to |
lack of |
harmony |
among team |
members |

Freq.

Percent

Cum.

------------+----------------------------------Average |

33

27.50

27.50

High |

37

30.83

58.33

Low

13

10.83

69.17

Very high

33

27.50

96.67

Very low

3.33

100.00

------------+-----------------------------------

19

Total |

120

100.00

-> tabulation of labour

Problems |
related to |
labour |
issues |

Freq.

Percent

Cum.

------------+----------------------------------Average |

37

30.83

30.83

High |

44

36.67

67.50

Low

11

9.17

76.67

Very high

21

17.50

94.17

Very low

5.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of trust

Problems |
related to |
lack of |
trust in |
project |
leader |

Freq.

Percent

Cum.

------------+----------------------------------Average |

33

27.50

27.50

High |

45

37.50

65.00

Low

14

11.67

76.67

Very high

26

21.67

98.33

Very low

1.67

100.00

------------+-----------------------------------

20

Total |

120

100.00

Procedure 2: Pearsons chi-square tests of


associations between the dependent variable of
study and the other 29 variables of study
. use c:\bos\pm1.dta, clear
. tab2 success relationship,

exp

cell

chi2

-> tabulation of success by relationship

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

Successful | Problems related to working relationship with project


completion |
of project |

manager
Average

High

Low

Very high

Very low

Total

-----------+-------------------------------------------------------+---------No |

4 |

21

6.5

8.2

0.3

5.3

0.7 |

21.0

7.50

4.17

0.83

1.67

3.33 |

17.50

-----------+-------------------------------------------------------+---------Yes |

28

42

28

0 |

99

30.5

38.8

1.6

24.8

3.3 |

99.0

21

23.33

35.00

0.83

23.33

0.00 |

82.50

-----------+-------------------------------------------------------+---------Total |

37

47

30

4 |

120

37.0

47.0

2.0

30.0

4.0 |

120.0

30.83

39.17

1.67

25.00

3.33 |

100.00

Pearson chi2(4) =

25.4853

Pr = 0.000

Note that there are 4 expected cell


frequencies that are less than 5 in the
above cross-tab table. As such, the P-value
(Pr=0.000) obtained from the above
procedure is not reliable. The remedial
action is to reduce the number of
categories of the variable relationship
from 5 to 2 by recoding.
Recoding procedure in STATA
Open up the STATA data file c:\bos\pm1.dta

. use c:\bos\pm1.dta, clear


. tab1

relationship

-> tabulation of relationship


22

Problems |
related to |
working |
relationshi |
p with |
project |
manager |

Freq.

Percent

Cum.

------------+----------------------------------Average |

37

30.83

30.83

High |

47

39.17

70.00

Low

1.67

71.67

Very high

30

25.00

96.67

Very low

3.33

100.00

------------+----------------------------------Total |

120

100.00

Reduce the number of categories of each of your categorical


variables from 5 to 2 as follows:

Very low = Low


Low = Low
Average = Moderate
High = Moderate
Very high = Moderate
23

Save the resulting data file as c:\bos\pm2.dta

Frequency tables for the variables in the STATA data file


c:\bos\pm2.dta

. use c:\bos\pm2.dta, clear


. tab1 success relationship experience type race
rivals resources scope objectives quality cost
time control procurement contract interference
communication stakeholders planning
accountability transparency audit training
leadership conflicts risk skills harmony labour
trust
-> tabulation of success

success |

Freq.

Percent

Cum.

------------+----------------------------------No |

21

17.50

17.50

Yes |

99

82.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of relationship

relationshi |

24

p |

Freq.

Percent

Cum.

------------+----------------------------------Low |

5.00

5.00

Moderate |

114

95.00

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of experience

experience |

Freq.

Percent

Cum.

------------+----------------------------------Low |

37

30.83

30.83

Moderate |

83

69.17

100.00

------------+----------------------------------Total |

120

100.00

Freq.

Percent

-> tabulation of type

type |

Cum.

------------+----------------------------------Buildings

26

21.67

21.67

IT |

18

15.00

36.67

Lights |

18

15.00

51.67

Roads

38

31.67

83.33

Water |

20

16.67

100.00

------------+----------------------------------Total |

120

100.00

Freq.

Percent

-> tabulation of race

race |

Cum.

------------+-----------------------------------

25

Black

29

24.17

24.17

Coloured |

18

15.00

39.17

34

28.33

67.50

White |

39

32.50

100.00

Indian

------------+----------------------------------Total |

120

100.00

-> tabulation of rivals

rivals |

Freq.

Percent

Cum.

------------+----------------------------------Low |

29

24.17

24.17

Moderate |

91

75.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of resources

resources |

Freq.

Percent

Cum.

------------+----------------------------------Low |

22

18.33

18.33

Moderate |

98

81.67

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of scope

scope |

Freq.

Percent

Cum.

------------+----------------------------------Low |

16

13.33

13.33

Moderate |

104

86.67

100.00

------------+-----------------------------------

26

Total |

120

100.00

-> tabulation of objectives

objectives |

Freq.

Percent

Cum.

------------+----------------------------------Low |

14

11.67

11.67

Moderate |

106

88.33

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of quality

quality |

Freq.

Percent

Cum.

------------+----------------------------------Low |

19

15.83

15.83

Moderate |

101

84.17

100.00

------------+----------------------------------Total |

120

100.00

Freq.

Percent

-> tabulation of cost

cost |

Cum.

------------+----------------------------------Low |

23

19.17

19.17

Moderate |

97

80.83

100.00

------------+----------------------------------Total |

120

100.00

Freq.

Percent

-> tabulation of time

time |

Cum.

27

------------+----------------------------------Low |

15

12.50

12.50

Moderate |

105

87.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of control

control |

Freq.

Percent

Cum.

------------+----------------------------------Low |

16

13.33

13.33

Moderate |

104

86.67

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of procurement

procurement |

Freq.

Percent

Cum.

------------+----------------------------------Low |

14

11.67

11.67

Moderate |

106

88.33

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of contract

contract |

Freq.

Percent

Cum.

------------+----------------------------------Low |

20

16.67

16.67

Moderate |

100

83.33

100.00

------------+----------------------------------Total |

120

100.00

28

-> tabulation of interference

interferenc |
e |

Freq.

Percent

Cum.

------------+----------------------------------Low |

14

11.67

11.67

Moderate |

106

88.33

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of communication

communicati |
on |

Freq.

Percent

Cum.

------------+----------------------------------Low |

18

15.00

15.00

Moderate |

102

85.00

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of stakeholders

stakeholder |
s |

Freq.

Percent

Cum.

------------+----------------------------------Low |

13

10.83

10.83

Moderate |

107

89.17

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of planning

29

planning |

Freq.

Percent

Cum.

------------+----------------------------------Low |

36

30.00

30.00

Moderate |

84

70.00

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of accountability

accountabil |
ity |

Freq.

Percent

Cum.

------------+----------------------------------Low |

17

14.17

14.17

Moderate |

103

85.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of transparency

transparenc |
y |

Freq.

Percent

Cum.

------------+----------------------------------Low |

26

21.67

21.67

Moderate |

94

78.33

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of audit

audit |

Freq.

Percent

Cum.

------------+-----------------------------------

30

Low |

22

18.33

18.33

Moderate |

98

81.67

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of training

training |

Freq.

Percent

Cum.

------------+----------------------------------Low |

28

23.33

23.33

Moderate |

92

76.67

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of leadership

leadership |

Freq.

Percent

Cum.

------------+----------------------------------Low |

20

16.67

16.67

Moderate |

100

83.33

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of conflicts

conflicts |

Freq.

Percent

Cum.

------------+----------------------------------Low |

18

15.00

15.00

Moderate |

102

85.00

100.00

------------+----------------------------------Total |

120

100.00

31

-> tabulation of risk

risk |

Freq.

Percent

Cum.

------------+----------------------------------Low |

18

15.00

15.00

Moderate |

102

85.00

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of skills

skills |

Freq.

Percent

Cum.

------------+----------------------------------Low |

27

22.50

22.50

Moderate |

93

77.50

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of harmony

harmony |

Freq.

Percent

Cum.

------------+----------------------------------Low |

17

14.17

14.17

Moderate |

103

85.83

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of labour

labour |

Freq.

Percent

Cum.

------------+----------------------------------Low |

18

15.00

15.00

32

Moderate |

102

85.00

100.00

------------+----------------------------------Total |

120

100.00

-> tabulation of trust

trust |

Freq.

Percent

Cum.

------------+----------------------------------Low |

16

13.33

13.33

Moderate |

104

86.67

100.00

------------+----------------------------------Total |

120

100.00

Pearsons chi-square tests of associations between the dependent


variable success (yes, no) and each of the categorical variables in
the STATA data file c:\bos\pm2.dta

. use c:\bos\pm2.dta, clear


. tab2 success relationship experience rivals
resources scope objectives quality cost time
control procurement contract interference
communication stakeholders planning
accountability transparency audit training
leadership conflicts risk skills harmony labour
trust, cell chi2 expected firstonly

33

-> tabulation of success by relationship

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

relationship
Low

Moderate |

Total

-----------+----------------------+---------No |

16 |

21

1.1

19.9 |

21.0

4.17

13.33 |

17.50

-----------+----------------------+---------Yes |

98 |

99

5.0

94.0 |

99.0

0.83

81.67 |

82.50

-----------+----------------------+---------Total |

114 |

120

6.0

114.0 |

120.0

5.00

95.00 |

100.00

Pearson chi2(1) =

18.9595

Pr = 0.000

-> tabulation of success by experience

34

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

experience
Low

Moderate |

Total

-----------+----------------------+---------No |

13 |

21

6.5

14.5 |

21.0

6.67

10.83 |

17.50

-----------+----------------------+---------Yes |

29

70 |

99

30.5

68.5 |

99.0

24.17

58.33 |

82.50

-----------+----------------------+---------Total |

37

83 |

120

37.0

83.0 |

120.0

30.83

69.17 |

100.00

Pearson chi2(1) =

0.6294

Pr = 0.428

-> tabulation of success by rivals

+--------------------+
| Key

|--------------------|

35

frequency

| expected frequency |
|

cell percentage

+--------------------+

rivals

success |

Low

Moderate |

Total

-----------+----------------------+---------No |

17

4 |

21

5.1

15.9 |

21.0

14.17

3.33 |

17.50

-----------+----------------------+---------Yes |

12

87 |

99

23.9

75.1 |

99.0

10.00

72.50 |

82.50

-----------+----------------------+---------Total |

29

91 |

120

29.0

91.0 |

120.0

24.17

75.83 |

100.00

Pearson chi2(1) =

44.7885

Pr = 0.000

-> tabulation of success by resources

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

36

resources

success |

Low

Moderate |

Total

-----------+----------------------+---------No |

20

1 |

21

3.9

17.1 |

21.0

16.67

0.83 |

17.50

-----------+----------------------+---------Yes |

97 |

99

18.1

80.8 |

99.0

1.67

80.83 |

82.50

-----------+----------------------+---------Total |

22

98 |

120

22.0

98.0 |

120.0

18.33

81.67 |

100.00

Pearson chi2(1) = 100.5508

Pr = 0.000

-> tabulation of success by scope

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

scope
Low

Moderate |

Total

-----------+----------------------+---------No |

15

6 |

21

2.8

18.2 |

21.0

37

12.50

5.00 |

17.50

-----------+----------------------+---------Yes |

98 |

99

13.2

85.8 |

99.0

0.83

81.67 |

82.50

-----------+----------------------+---------Total |

16

104 |

120

16.0

104.0 |

120.0

13.33

86.67 |

100.00

Pearson chi2(1) =

74.3457

Pr = 0.000

-> tabulation of success by objectives

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

objectives
Low

Moderate |

Total

-----------+----------------------+---------No |

14

7 |

21

2.5

18.6 |

21.0

11.67

5.83 |

17.50

-----------+----------------------+---------Yes |

99 |

99

11.6

87.5 |

99.0

0.00

82.50 |

82.50

38

-----------+----------------------+---------Total |

14

106 |

120

14.0

106.0 |

120.0

11.67

88.33 |

100.00

Pearson chi2(1) =

74.7170

Pr = 0.000

-> tabulation of success by quality

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

quality
Low

Moderate |

Total

-----------+----------------------+---------No |

15

6 |

21

3.3

17.7 |

21.0

12.50

5.00 |

17.50

-----------+----------------------+---------Yes |

95 |

99

15.7

83.3 |

99.0

3.33

79.17 |

82.50

-----------+----------------------+---------Total |

19

101 |

120

19.0

101.0 |

120.0

15.83

84.17 |

100.00

39

Pearson chi2(1) =

59.0375

Pr = 0.000

-> tabulation of success by cost

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

cost
Low

Moderate |

Total

-----------+----------------------+---------No |

16

5 |

21

4.0

17.0 |

21.0

13.33

4.17 |

17.50

-----------+----------------------+---------Yes |

92 |

99

19.0

80.0 |

99.0

5.83

76.67 |

82.50

-----------+----------------------+---------Total |

23

97 |

120

23.0

97.0 |

120.0

19.17

80.83 |

100.00

Pearson chi2(1) =

53.4245

Pr = 0.000

-> tabulation of success by time

+--------------------+

40

| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

time

success |

Low

Moderate |

Total

-----------+----------------------+---------No |

13

8 |

21

2.6

18.4 |

21.0

10.83

6.67 |

17.50

-----------+----------------------+---------Yes |

97 |

99

12.4

86.6 |

99.0

1.67

80.83 |

82.50

-----------+----------------------+---------Total |

15

105 |

120

15.0

105.0 |

120.0

12.50

87.50 |

100.00

Pearson chi2(1) =

56.8048

Pr = 0.000

-> tabulation of success by control

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

41

+--------------------+

control

success |

Low

Moderate |

Total

-----------+----------------------+---------No |

12 |

21

2.8

18.2 |

21.0

7.50

10.00 |

17.50

-----------+----------------------+---------Yes |

92 |

99

13.2

85.8 |

99.0

5.83

76.67 |

82.50

-----------+----------------------+---------Total |

16

104 |

120

16.0

104.0 |

120.0

13.33

86.67 |

100.00

Pearson chi2(1) =

19.2008

Pr = 0.000

-> tabulation of success by procurement

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

procurement
Low

Moderate |

Total

-----------+----------------------+----------

42

No |

12 |

21

2.5

18.6 |

21.0

7.50

10.00 |

17.50

-----------+----------------------+---------Yes |

94 |

99

11.6

87.5 |

99.0

4.17

78.33 |

82.50

-----------+----------------------+---------Total |

14

106 |

120

14.0

106.0 |

120.0

11.67

88.33 |

100.00

Pearson chi2(1) =

24.0291

Pr = 0.000

-> tabulation of success by contract

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

contract
Low

Moderate |

Total

-----------+----------------------+---------No |

14

7 |

21

3.5

17.5 |

21.0

11.67

5.83 |

17.50

-----------+----------------------+---------Yes |

93 |

99

43

16.5

82.5 |

99.0

5.00

77.50 |

82.50

-----------+----------------------+---------Total |

20

100 |

120

20.0

100.0 |

120.0

16.67

83.33 |

100.00

Pearson chi2(1) =

45.8182

Pr = 0.000

-> tabulation of success by interference

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

interference
Low

Moderate |

Total

-----------+----------------------+---------No |

11

10 |

21

2.5

18.6 |

21.0

9.17

8.33 |

17.50

-----------+----------------------+---------Yes |

96 |

99

11.6

87.5 |

99.0

2.50

80.00 |

82.50

-----------+----------------------+---------Total |

14

106 |

120

14.0

106.0 |

120.0

44

11.67

88.33 |

Pearson chi2(1) =

40.9437

100.00

Pr = 0.000

-> tabulation of success by communication

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

communication
Low

Moderate |

Total

-----------+----------------------+---------No |

18

3 |

21

3.1

17.9 |

21.0

15.00

2.50 |

17.50

-----------+----------------------+---------Yes |

99 |

99

14.9

84.2 |

99.0

0.00

82.50 |

82.50

-----------+----------------------+---------Total |

18

102 |

120

18.0

102.0 |

120.0

15.00

85.00 |

100.00

Pearson chi2(1) =

99.8319

Pr = 0.000

-> tabulation of success by stakeholders

45

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

stakeholders
Low

Moderate |

Total

-----------+----------------------+---------No |

13

8 |

21

2.3

18.7 |

21.0

10.83

6.67 |

17.50

-----------+----------------------+---------Yes |

99 |

99

10.7

88.3 |

99.0

0.00

82.50 |

82.50

-----------+----------------------+---------Total |

13

107 |

120

13.0

107.0 |

120.0

10.83

89.17 |

100.00

Pearson chi2(1) =

68.7316

Pr = 0.000

-> tabulation of success by planning

+--------------------+
| Key

|--------------------|
|

frequency

46

| expected frequency |
|

cell percentage

+--------------------+

planning

success |

Low

Moderate |

Total

-----------+----------------------+---------No |

13

8 |

21

6.3

14.7 |

21.0

10.83

6.67 |

17.50

-----------+----------------------+---------Yes |

23

76 |

99

29.7

69.3 |

99.0

19.17

63.33 |

82.50

-----------+----------------------+---------Total |

36

84 |

120

36.0

84.0 |

120.0

30.00

70.00 |

100.00

Pearson chi2(1) =

12.3383

Pr = 0.000

-> tabulation of success by accountability

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

accountability

47

success |

Low

Moderate |

Total

-----------+----------------------+---------No |

14

7 |

21

3.0

18.0 |

21.0

11.67

5.83 |

17.50

-----------+----------------------+---------Yes |

96 |

99

14.0

85.0 |

99.0

2.50

80.00 |

82.50

-----------+----------------------+---------Total |

17

103 |

120

17.0

103.0 |

120.0

14.17

85.83 |

100.00

Pearson chi2(1) =

57.6979

Pr = 0.000

-> tabulation of success by transparency

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

transparency
Low

Moderate |

Total

-----------+----------------------+---------No |

20

1 |

21

4.5

16.4 |

21.0

16.67

0.83 |

17.50

48

-----------+----------------------+---------Yes |

93 |

99

21.4

77.5 |

99.0

5.00

77.50 |

82.50

-----------+----------------------+---------Total |

26

94 |

120

26.0

94.0 |

120.0

21.67

78.33 |

100.00

Pearson chi2(1) =

81.1792

Pr = 0.000

-> tabulation of success by audit

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

audit
Low

Moderate |

Total

-----------+----------------------+---------No |

18

3 |

21

3.9

17.1 |

21.0

15.00

2.50 |

17.50

-----------+----------------------+---------Yes |

95 |

99

18.1

80.8 |

99.0

3.33

79.17 |

82.50

-----------+----------------------+----------

49

Total |

22

98 |

120

22.0

98.0 |

120.0

18.33

81.67 |

100.00

Pearson chi2(1) =

77.1886

Pr = 0.000

-> tabulation of success by training

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

training
Low

Moderate |

Total

-----------+----------------------+---------No |

16

5 |

21

4.9

16.1 |

21.0

13.33

4.17 |

17.50

-----------+----------------------+---------Yes |

12

87 |

99

23.1

75.9 |

99.0

10.00

72.50 |

82.50

-----------+----------------------+---------Total |

28

92 |

120

28.0

92.0 |

120.0

23.33

76.67 |

100.00

Pearson chi2(1) =

39.7548

Pr = 0.000

50

-> tabulation of success by leadership

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

leadership
Low

Moderate |

Total

-----------+----------------------+---------No |

18

3 |

21

3.5

17.5 |

21.0

15.00

2.50 |

17.50

-----------+----------------------+---------Yes |

97 |

99

16.5

82.5 |

99.0

1.67

80.83 |

82.50

-----------+----------------------+---------Total |

20

100 |

120

20.0

100.0 |

120.0

16.67

83.33 |

100.00

Pearson chi2(1) =

87.3766

Pr = 0.000

-> tabulation of success by conflicts

+--------------------+
| Key

51

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

conflicts

success |

Low

Moderate |

Total

-----------+----------------------+---------No |

13

8 |

21

3.1

17.9 |

21.0

10.83

6.67 |

17.50

-----------+----------------------+---------Yes |

94 |

99

14.9

84.2 |

99.0

4.17

78.33 |

82.50

-----------+----------------------+---------Total |

18

102 |

120

18.0

102.0 |

120.0

15.00

85.00 |

100.00

Pearson chi2(1) =

43.9227

Pr = 0.000

-> tabulation of success by risk

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

52

risk

success |

Low

Moderate |

Total

-----------+----------------------+---------No |

16

5 |

21

3.1

17.9 |

21.0

13.33

4.17 |

17.50

-----------+----------------------+---------Yes |

97 |

99

14.9

84.2 |

99.0

1.67

80.83 |

82.50

-----------+----------------------+---------Total |

18

102 |

120

18.0

102.0 |

120.0

15.00

85.00 |

100.00

Pearson chi2(1) =

74.7520

Pr = 0.000

-> tabulation of success by skills

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

skills
Low

Moderate |

Total

-----------+----------------------+---------No |

16

5 |

21

53

4.7

16.3 |

21.0

13.33

4.17 |

17.50

-----------+----------------------+---------Yes |

11

88 |

99

22.3

76.7 |

99.0

9.17

73.33 |

82.50

-----------+----------------------+---------Total |

27

93 |

120

27.0

93.0 |

120.0

22.50

77.50 |

100.00

Pearson chi2(1) =

42.0800

Pr = 0.000

-> tabulation of success by harmony

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

harmony
Low

Moderate |

Total

-----------+----------------------+---------No |

11

10 |

21

3.0

18.0 |

21.0

9.17

8.33 |

17.50

-----------+----------------------+---------Yes |

93 |

99

14.0

85.0 |

99.0

54

5.00

77.50 |

82.50

-----------+----------------------+---------Total |

17

103 |

120

17.0

103.0 |

120.0

14.17

85.83 |

100.00

Pearson chi2(1) =

30.5698

Pr = 0.000

-> tabulation of success by labour

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

labour
Low

Moderate |

Total

-----------+----------------------+---------No |

12

9 |

21

3.1

17.9 |

21.0

10.00

7.50 |

17.50

-----------+----------------------+---------Yes |

93 |

99

14.9

84.2 |

99.0

5.00

77.50 |

82.50

-----------+----------------------+---------Total |

18

102 |

120

18.0

102.0 |

120.0

15.00

85.00 |

100.00

55

Pearson chi2(1) =

35.4571

Pr = 0.000

-> tabulation of success by trust

+--------------------+
| Key

|--------------------|
|

frequency

| expected frequency |
|

cell percentage

+--------------------+

|
success |

trust
Low

Moderate |

Total

-----------+----------------------+---------No |

11

10 |

21

2.8

18.2 |

21.0

9.17

8.33 |

17.50

-----------+----------------------+---------Yes |

94 |

99

13.2

85.8 |

99.0

4.17

78.33 |

82.50

-----------+----------------------+---------Total |

16

104 |

120

16.0

104.0 |

120.0

13.33

86.67 |

100.00

Pearson chi2(1) =

33.5864

Pr = 0.000

56

Summary

of

results

obtained

from

cross-tab

analyses
Table 1 shows the top 5 influential predictor variables of success. Each test
of association was performed between the dependent variable of study
(successful completion of project) and the other independent variables
of study that are known to affect the capacity of the project manager to
successfully complete the project work being done.
At the 5% level of significance, a two-by-two test of association among two
categorical variables is said to be statistically significant if the P-value is
below 0.05. Otherwise, the association is said to be insignificant at the same
level of significance. At the 5% level of significance, significant associations
are characterized by P-values that are smaller than 0.05 and large observed
values of the chi-square random variable. In this study, the top 5 highly
significant predictors of success were selected based on these criteria.
In each chi-square test of association performed in this section, the expected
cell frequencies were all greater than 5. As such, results obtained from crosstab analysis were valid.
Table 1: Top 5 significant variables based on cross-tab analysis
Variable of study associated with Y Observed
(Successful completion of project)
chi-square
value
Resources

P-value

100.5508

0.0000***

Communication

99.8319

0.0000***

Leadership

87.3766

0.0000***

Transparency

81.1792

0.0000***

57

Audit

77.1886

0.0000***

Key: Significance at * P<0.05; ** P<0.01;*** P<0.001.

List of top 5 influential variables of study


Y: Success (1 if project was not successful, 0 otherwise)
X1: Resources (1 if resources were inadequate, 0 otherwise)
X2: Communication (1 if communication was poor, 0 otherwise)
X3: Leadership (1 if leadership was poor, 0 otherwise)
X4: Transparency (1 if there was no transparency, 0 otherwise)
X5: Audit (1 if audit exercises were inadequate, 0 otherwise)

Suitable methods for further multivariate


analysis

Results

obtained

from

Pearsons

chi-square

tests

of

association are not as reliable as robust multivariate methods


such as binary logistic regression analysis and factor analysis.

Further multivariate analysis should be done by performing


the non-linear regression of Y on X1, X2, X3, X4 and X5 in
order to achieve theoretically more reliable estimates for
predictors of success.

58