! Mini-Test #1" ! SimpleFinish in FlexSim (cont.)"
! For Today" ! Read Revised OFD methodology (on myCourses)" ! Read Sect. 1, 2, and 3 in Ch. 7" ! Read Sect. 1, 2 and 5 in Appendix to Ch. 7" ! View SIS videos 7.0, 7.1, and 7.2" ! Wed. 18 Sept." ! System Denition 2 (Project)" ! Thurs. 19 Sept." ! Read Sect. 8.1 in Ch. 8" ! View SIS videos 8.0, 8.1, and 8.2" ! Try Gift Pak Exercise" ! Tues. 24 Sept." ! Mini-Test #2"
Allen G. Greenwood, Ph.D., P.E."

IE 4773/6773: Systems Simulation I Fall 2013

! !

!Department of Industrial & Systems Engineering" !Mississippi State University"

Mini-Test #1"

! Mini-Test #2: Tuesday 24 Sept."

IE 4773/6773: Systems Simulation I Fall 2013

! !

!Department of Industrial & Systems Engineering" !Mississippi State University"

Object Flow Diagram for SimpleCell example"


Analysis Question: Can the Simple Cell area handle an increase in production rate from its upstream process? "

Base case"
wait time utilization throughput

speed/ distance

(1) Finishing Operator

(cap?) Empty Pallet 1


Full Pallet Storage (cap)

TBF

TTR

utilization

TBF

TTR

Empty Pallets ? ?

IE 4773/6773: Systems Simulation I Fall 2013

! !

!Department of Industrial & Systems Engineering" !Mississippi State University"

Fork Truck

time between arrivals

Part 1

Overhead Conveyor (cap?)

Part 1

Finishing Station
Process time

Palletizer Product

Process time

Pallet

Full Pallet Storage (cap)

Pallet

SimpleFinish problem description"


! Parts arrive to the SimpleFinish work cell via an overhead conveyor. TBA~T(12,24,15), i.e. average TBAs is 17 minutes (or, the average arrival rate is 3.5 per hour)." The Finishing Operator unloads a part from the conveyor, moves it to the Finishing Station, and nishes it. Finish time: minimum 6 minutes, maximum 16 minutes, most likely 8 minutes; i.e., ST~T(6,16,8) or average ST is 10 minutes." After nishing, the operator moves the part to the palletizer and the process is repeated." Four parts are loaded to a pallet." Once a pallet has four parts, the palletizer wraps the parts (30 seconds) and moves the pallet of parts into a storage area where it awaits pickup by a fork truck. The fork truck moves the pallet of parts to the warehouse." After the palletizer moves a pallet is moved out of the way, the Finishing Operator gets an empty pallet and places it on the appropriate place on the palletizer." Pallets arrive in batches of 4 every hour." The Finishing Station goes down periodically and the repairs are made by the Finishing Operator. TBFs are exponentially distributed with a mean of 100 minutes; TTR is uniformly distributed between 10 and 20 minutes." The Finishing Operator takes breaks. 15 minutes after 2 hours, 30 minutes after 4 hours, and 15 minutes after 6 hours." The supervisor checks with the Finishing Operator periodically; for about 3 minutes roughly once per hour."
! ! !Department of Industrial & Systems Engineering" !Mississippi State University"

! ! !

! !

! !

IE 4773/6773: Systems Simulation I Fall 2013

SimpleFinish-1"

! Expected server utilization?!" ! IAT ~ triangular(12, 24, 15)" ! ST ~ triangular(6, 16, 8)"
IE 4773/6773: Systems Simulation I Fall 2013 ! ! !Department of Industrial & Systems Engineering" !Mississippi State University"

SimpleFinish ! NewFinish"
! Parts arrive to the work cell via an overhead conveyor at a rate of 4 per hour rather than 3.5 per hour. Assume the new overall TBA~triangular(10, 20, 15)" The increase in rate is due to a new product (Blue)."

! ! !

Blues take twice as long to process as the base product (Yellow)." Blues are placed 3 per pallet, using the same pallet." Yellow and blue products must be on different pallets; no comingling of products."
! ! !Department of Industrial & Systems Engineering" !Mississippi State University"

IE 4773/6773: Systems Simulation I Fall 2013

Combiner (pack mode) and Separator (unpack)"


Container object
Setup & Process
Port 1

2 2

Setup & Process

IE 4773/6773: Systems Simulation I Fall 2013

! !

!Department of Industrial & Systems Engineering" !Mississippi State University"

Gift Pak Exercise (Quiz 4, Spring 2013)"


! BullDawg Specialty, Inc. is considering producing a new product, Maroon and White Gift Paks, but they are concerned about the production and buffer space required. Therefore, they plan to do a simulation analysis to assess space needs. They plan to use two identical boxing machines; each machine will load two Maroons and two Whites into a box and gift wrap it. The wrap time is estimated to be triangularly distributed with the minimum, maximum, and most likely times of 3, 7, and 5 minutes, respectively. The assumed arrival rate of the Maroons, and of the Whites, to the boxing area are each Poisson distributed with a mean of 40 per hour. When wrapped, the boxed items will travel on a 20-foot long conveyor to the next process (conveyor speed is 100 feet per minute). 80 boxes are delivered at the beginning of the shift and again half-way through the 8-hour shift. Model this proposed system in FlexSim and run the simulation for one shift. "