You are on page 1of 5

LIST OF MATERIALS.

Sl.no 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 20 21 22

Particulars PSC CEMENT POLE 200Kg D.P Line channel Transformer base channel Channel for AB switch & HG Fuse set. D.P . Line Channel For Tapping DSS CLAMP Complete Tr. Belting angle complete 11/.4KV 100KVA Dist. Tr. Earthing set complete HG Fuse set complete ACSR RABBIT conductor LT Bracket BACK Clamp 11KV pin insulator with pin L T Shackle insulator complete 11KV Disc insulator with fitting G.I Stay set complete 11 kv Gurd bracket M.S. angle 75x40x6 M.S Nuts & Bolts AB Switch complete

Qty. 3 1 1 2 1 8 1 1 3 1 0.8 6 8 6 24 6 4 5 6 25 1

UNIT No Set Set Set Set Pair Set No Set Set Km No No No Set Mtr Mtr No Mtr Kg No

JEE/ SARAIYAGANJ-2

N.B.P.D.C.Ltd.
Estimate for installation of additional 100KVA D/S/S at NEW SHANTI BIHAR COLONY , NEAR HOUSING BOARD COLONY, DAMODARPUR under electric supply section DAMODARPUR , Electric supply subdivision MUZ(WEST). DIVISION MUZ(WEST).

Sl.no 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 17 19 20 21 23
1 2 3 4 5

Particulars PSC Cement pole 200kg PSC Cement pole 400kg D.P Line channel Transformer base channel Channel for AB switch & HG Fuse set. D.P . Line Channel For Tapping DSS CLAMP COMPLETE Tr. Belting angle complete 11/.4KV 100KVA Dist. Tr. Earthing set complete with wire HG Fuse set complete ACSR RABBIT conductor ACSR WEASEL Conductor LT Bracket BACK Clamp 11KV pin insulator with pin L T Shackle/PIN insulator complete 11KV Disc insulator with fitting G.I Stay set complete with clamp 11 kv Gurd bracket M.S. angle 75x40x6 M.S Nuts & Bolts AB Switch complete set
COST OF MATERIALS T & P COST @ 2% CONTIGENCY @ 2% TRANSPORTATION @ 4% LABOUR COST L.SGRAND TOTAL

Qty. 5 3 1 1 2 1 8 1 1 3 1 0.4 1.3 12 16 6 54 9 6 5 6 28 1


Rs Rs Rs Rs Rs

RATE 2290.00 3000.00 1630.00 3169.53 2955.42 1630.00 80.85 1450.58 92848.00 450.00 1200.00 34610.00 20546.00 225.09 50.04 88.00 26.00 484.00 999.90 630.25 1450.58 70.50 14585.00 TOTAL
217608.60 4352.17 4352.17 8704.34 13000.00 248017.30

UNIT no no set set set set pair set no set set km km no no no set set mtr no mtr kg no

AMOUNT 11450.00 9000.00 1630.00 3169.53 5910.84 1630.00 646.80 1450.58 92848.00 1350.00 1200.00 13844.00 29276.00 2701.08 800.64 528.00 1404.00 4356.00 5999.40 3151.25 8703.48 1974.00 14585.00 217608.60

say

248018.00

GENERAL AND TECHNICAL REPORT :- Estimate for installation of additional 100KVA D/S/S at NEW SHANTI BIHAR COLONY , NEAR HOUSING BOARD COLONY, DAMODARPUR under electric supply section DAMODARPUR , Electric supply subdivision MUZ(WEST). DIVISION MUZ(WEST).. The Existing transformer is extremely overloaded. The fuse blown activity is very high and having very long LT line crates severe voltage problem. The newly builded colony SHANTI BIHAR is far way from the existing transformer. Hence For proper regular power supply and reliability of our system additional transformer is necessary at that very place, Since the total sanctioned load is higher than capacity of transformer. Hence as per his requirement and for proper regular power supply and for reliability of our system an additional transformer may be installed. The total estimated cost comes to Rs. 248018./- only. The estimate may kindly be sanctioned for system improvement and reliability of our system.

LINE DIAGRAM:-

AEE/MUZ(WEST)

JEE/ DAMODARPUR

APPLICATION FOR WORK ORDER


THE ELECTRICAL EXECUTIVE ENGINEER ELECTRIC SUPPLY DIVISION MUZAFFARPUR (WEST)

SIR, Please Issue work order for the undermentioned work. NAME OF WORK:- Installation of additional 100KVA D/S/S at NEW SHANTI BIHAR COLONY , NEAR HOUSING BOARD COLONY, DAMODARPUR under electric supply section DAMODARPUR , Electric supply subdivision MUZ(WEST). DIVISION MUZ(WEST).. 1. 2. 3 4 5 COST OF MATERIAL T & P COST @ 2% CONTIGENCY @ 2% TRANSPORTATION @ 4% LOBOUR COST L.STOTAL AMOUNT GRAND TOTAL Rs Rs Rs Rs Rs Rs Rs 217608.60 4352.17 4352.17 8704.34 13000.00

248017.30
248018.00

AEE/MUZ(WEST)

JEE/DAMODARPUR

ISSUED WORK ORDER NO.

APPROVED

EEE/MUZAFFAPUR(WEST)