Professional Documents
Culture Documents
• Voltage is the energy difference between the positive and negative terminals of
the battery.
• Voltage causes current to flow in the wire.
• Voltage=Current x Resistance (Ohm's law)
• The energy consumed per second is the power.
• Power=Voltage x Current
• Power=Current x Current x Resistance
• Units: Voltage-Volt, Current-Ampere, Resistance-Ohm, Power-Watt
• Energy=Power x Time
• Electricity Consumption Unit=Number of hours of operation x Power in KW
• DC Circuit: Current always flows in one direction
• AC (Alternating Current): The higher the voltage, the higher the current and
vice-versa.
• The number of times the current changes its direction in a second is called
frequency.
• Nearly all the power systems today operate on AC because AC Power can easily
be 'transformed' or changed from one voltage to another. This is of great help in
sending the power over long distances.Current will be less if voltage is increased.
Power loss in the wires in the form of heat is proportional to the square of the
current. Therefore, higher the voltage level, the greater the reduction in power
loss. Furthermore, it is easier to generate AC power and motors operating on AC
are cheaper and easier to maintain. High voltages are dangerous since there is a
higher chance of electric shock. AC helps resolve this. Power can be generated at
low voltage at generating stations. Then it can be transformed to high voltage
and transmitted to consumer locations. At consumer's place voltage can be
lowered.
• In AC circuit there are two components which resist the flow of current. They
are resistance and reactance. Reactance is caused by coils(typically found in
motors) or capacitors.
• Net effect of resistance and reactance is called impedence.
• If current wave and voltage wave coincide then power factor is one as in the case
of a resistor like bulb.If current lags behind voltage then the load is said to be
inductive, as in the case of a motor. If current leads voltage, the load is
capacitive, caused by capacitors. In an AC System, active power and reactive
power depend on voltage, current and power factor.
• The power required by electrical equipment to operate is called load.
• Load is made up of an active part(measured by watt) and a reactive
part(measured by VAR(Volt-Ampere-Reactive)s)
• Depending on consumer behaviour, load keeps changing from second to second.
• Average Load=Sum of hourly loads/24
• Load Factor=Average Load/Maximum Load
• The installed Capacity of a generating unit is its maximum MW capacity at the
time of installation.
• The minimum capacity is the minimum MW at which the generating unit can
operate in a stable way.
• Energy generated by a generating unit is measured by metering instruments at
the station and can also be calculated if one knows the average hourly MW
generation. It is typically measured in Millions of Units(MU) and is usually
calculated for a period of one year,i.e 8760 hours (8784 hours for a leap year.)
• MU=Sum of hourly MW values for one year/1000
• Average Capacity is the average of all the hourly MW generation values.
• Average Capacity=Annual Energy Generation/ Number of hours in a year.
• Firm Capacity of a unit is the MW power that can be assured from the unit at
any point in time.
• Plant Load Factor = 100 x (Energy Generated in a Year)
(Maximum energy generation possible in a Year)3
Base load stations have high PLF and peaking stations have low PLF.
• That's why power generation by base load stations is cheap and that by peaking
stations is costly. High PLF implies economy of scale due to high capacity. Since
base load is assured, high capacity stations can be set up and run continuously to
meet this load.
• Availability of a generating unit is the per hour average of the declared
generating capacity values over a period of time (typically a year)
• Availability = 100 x (Hours for which the unit is available for generating
power)/ (Total Hours in the Year).
Hydropower
• Penstocks are huge pipelines that carry water from the reservoir to the turbine.
• The Full Reservoir level is the maximum height of the water in the reservoir.
• The Minimum Draw Down Level is the minimum permissible level in the
reservoir.
• Hydro stations located right on the water stream are called 'run of the river'
stations. They don't have a reservoir to store and regulate water flow.
• Pumped Storage Stations: These are special type hydro stations with two
reservoirs-one upstream, near the dam at high level and another downstream,
after the tail race at low level. Water from the dam reservoir is guided to the
turbine making it and the generator rotate to generate power. Water leaves the
turbine to the tail race reservoir through a pipe called the tail race. This is the
generating mode. In the pumping mode, water is pumped up from the tail race
reservoir to the dam reservoir. In this mode, it draws power from the grid. The
pumped storage station is run in pumping mode during off-peak hours so as to
increase the storage in the dam reservoir. During peak hours, it is run as a
generator to supply energy needs at that time. This arrangement can reduce the
cost of peak period energy generation.
• The difference in levels of water at the storage reservoir and the turbine is called
the 'Head'. Head is measured in metres.
• When water flows through the penstock and the valves, some pressure is lost due
to friction. The friction head is around 5% and the remaining 'net head'
contributes to power generation.
• Power (kw) = 8 x Net Head (metres) x Flow Rate(Litres/sec)/100
• Hydro plants can also generate some reactive power.
• Hydro plants in the condenser mode can generate only reactive power. In this
mode of operation, a minimum water flow is to be maintained and the unit will
consume some active power from the grid.
• A hydro station can be started up or put off in a few minutes. It can be easily
operated over a wide range of power output with high efficiency. Ideal for peak
load.
• Low auxiliary power consumption-2-3% of the power generated
• Simple to operate, high overall efficiency
• Hydro-power is clean
• Hydro-power is cheap-no fuel cost (though construction costs are high)
• If there is a natural high head, initial costs are lower.
• Environmental costs and R&R costs.
• Run of the river stations without adequate storage cannot be used as peaking
stations.
• Hydro-power is renewable-long life
• Execution of hydro projects requires thorough survey and investigation,
preparation of DPR, development of infrastructure, Environment Impact
Assessment and other preparatory works which are time consuming and take 2-5
years.
Coal-based Station :
Gas-based Station:
Diesel-based Station:
Nuclear Station:
Generation Scheduling:
• Planning the level of generation of the available generating units to meet the load
is called generation scheduling.
• The base load generating units (big coal based, nuclear, irrigation dependent
hydro etc.) are scheduled first to meet the base load. Then the peaking stations
(open cycle gas, small hydro) are scheduled during the morning and evening
peak hours. The intermediate loaded stations (CCGT, small coal based and
hydro) are used to meet the remaining load.
• While scheduling the units of a particular type (say peak load), units with low
operating cost are scheduled first and the costlier ones last. Ordering of units on
the basis of operating costs is called the merit order, which is prepared based on
the Variable Cost values.
• If there is sufficient generation capacity, some units may not be scheduled at all.
On the other hand, if available generating units are not sufficient to meet the
load, then power may have to be imported from another utility. If all the
generating units and the imported power cannot meet the demand of the state,
and then load shedding has to be resorted to. Broad plans for load shedding
should be prepared as part of the annual plan.
• Generation Capacity has to be planned to meet the load forecast. The total
available generation capacity in the state and power imports should be sufficient
to meet the peak load at all times of the year. Energy from these should meet the
annual energy requirement of consumers.
• Step 1: Prepare a load duration curve for the 10 year horizon. (Load Duration
Curve captures the load behaviour and the energy requirements)
• Step 2: After finding the energy requirement at the consumer location this is
converted to the requirement at generating stations by adding the estimated
T&D losses over the planning horizon.
• Step 3: Then account for the auxiliary consumption, spinning reserve and
expected outage of generating units. (Spinning reserve means generation
capacity which is already spinning and can be used at short notice.This is
managed by ensuring that some generators, which are 'on' and connected to the
system, are not fully loaded so that they have some spare capacity.)
• Expected Outage includes planned outage and forced outage. Planned Outage is
owing to routine maintenance planned for all generators. On the other hand
unforeseen failure of a generator is called forced outage. Based on the type of the
generator, it is possible to reasonably predict the percentage of time in a year
during which such failures occur.
• When generation is not sufficient to meet the load it is called loss of load. Loss of
load probability (LOLP) is the probability that available installed capacity falls
short of load.
• If high excess capacity is planned and the spinning reserve is high, LOLP will be
low and vice-versa.
• The transmission system consists of transmission lines, substation and support
services.
• Transmission voltages are very high and can be AC or DC. Therefore
transmission lines have to be very tall.
• Lines are connected to towers by a chain of insulators.
• Lines run from one tower to another which are 100-200m apart.
• A set of three lines is called a circuit.
• Normally a tower carries one circuit but some carry two.
• Tower also carries one or two more lines which are lightning arrestors.
• The utility purchases the land around the route of the line which is called 'right
of way'.
• A transmission line starts and ends at 'substations'.
• Substation consists of a transformer, bus bar, circuit breaker, protective relays
and isolator.
• A transformer is used to convert one AC voltage to another.
• Power generated at 10-15 Kv at the generating station is 'stepped up' to high
transmission voltage at the substation in the generating stations. Local
substations 'step down' the voltage to distribution level voltage. These step up
and step downs are done by the transformers.
• Another function of the transformer is to correct for small variations in voltage.
• A substation that handles 500 MVA power and has 400 and 220 kv voltage levels,
may be called a 500 MVA-400/220 kv substation.
• Transformers are identified by the upper and lower voltages and the power they
handle. At a 220 kv substation, there are two 220/132 kv transformers, each
capable of handling 100 MVA power.
• Bus bar is a line at one voltage level to which many connections are made. In a
220/132 kv substation there will be one 220 kv and one 132 kv bus bar.
• All 220 kv lines and the 220 kv terminals of the transformers terminate on the
220 kv bus bar.
• In big substations, there can be more than one bus bar at the same voltage level.
• A Circuit Breaker is an elaborate switch used at high voltages and currents.A
typical CB used in a 220 kv substation is designed to withstand 220 kv, 600
Amperes and weighs hundreds of kilograms.A CB is designed to automatically
turn off when there is very high current.It can be operated remotely from a
control room.
• Protective Relays in the substation are designed to sense when there are
abnormal voltages and currents, high/low frequency, mismatch in frequency etc.
• An Isolator is also a switch but it cannot be operated when there is current
flowing in the circuit. To isolate a piece of equipment, first CB is opened, then the
isolator. To bring the equipment back to circuit, first isolator is closed, then CB.
• Most of the substation's equipments are located in open air, the switchyard.
• The protective relays, meters, switches for remote operation, communication
equipments etc are located in the control room.
• The transmission system consists of many substations inter-connected by
transmission lines. It is like a mesh and is called the transmission grid.
• Power is fed into grid at the generating stations; power flows on the lines
towards load centres; substations near load centres step the voltages down and
supply power to the loads.
• Grid collapse occurs when many transmission lines open(i.e., blocked), loads lose
supply and many generators trip.
• A fault occurs when two transmission lines touch each other, or if one or many of
the lines touch the ground. Then very high currents may flow through
equipments thereby damaging them. The relays detect the fault and give a signal
to open the CB.
• The cycle of open/close operation to test the fault is called 'auto reclosing'.
• At the State level, the minute to minute operation of the power system is
coordinated from the Load Dispatch Centre, typically located in the State
capital.
• The LDC is connected to three or four Sub-LDCs, which in turn are connected to
major substations and generating stations.
• LDC gets information about: