AGGREGATE IMPACT VALUE-AIV JOB No: 037-AS2009-10-079 Sample No Quarry Material Location : : : Aggregates for__________work :_________Km Tested by:

Date of testing :

Observation sheet: Test nos. 1 Wt. Container

2 3 4 5 Wt. Wt. Wt. Wt. Container Aggregate Aggregate Aggregate + aggregate before retained on passing on compaction 2.36 mm 2.36 mm sieve sieve Gms.
---

6 Aggregate Impact Value

Gms.
---

Gms.
(2-1)

Gms.

Gms.
(3-4)

%
(5/3) x 100

1 2 3 Average % : Remarks:

APWD REPRESENTATIVE

CONTRACTOR'S REPRESENTATIVE

FLAKINESS TEST OF AGGREGATES JOB No: 037-AS2009-10-079 Sample No Quarry Material Location : : : CA for_________work :_________Km Tested by : Date of testing :

Observation Sheet: Wt. of the fraction Thickness Wt. of the Size of aggregates consisting of gauge size aggregates in each Passing through Retained on IS atleast 200 pieces. (0.6 times the fraction passing IS sieve. sieve (gm) mean size) thickness gauge (mm) (mm) (mm) (gm)
1 2 3 4 5

63 50 40 31.5 25 20 16 12.5 10 Total=

50 40 25 25 20 16 12.5 10 6.3

W1 = W2 = W3 = W4 = W5 = W6 = W7 = W8 = W9 = W=

33.90 27.00 19.50 16.95 13.50 10.80 8.55 6.75 4.89

w1= w2= w3= w4= w5= w6= w7= w8= w9= w=

Flakiness index= (w/W) x 100= % Remarks:

APWD REPRESENTATIVE

CONTRACTOR'S REPRESENTATIVE

REPRESENTATIVE

WATER ABSORPTION TEST OF AGGREGATE JOB No: 037-AS2009-10-079 Sample No : Quarry Material Location : : CA for_________work :_________Km Tested by : Date of testing :

Observation Sheet: Sl.No. 1 Determination No. Weight of saturated surface-dried sample in gm (A) Weight of oven-dried sample in gm (B) Water absorption (A - B) = x 100% B Average Value: I II III

Remark:

APWD REPRESENTATIVE

CONTRACTOR'S REPRESENTATIVE

STRIPPING TEST OF AGGREGATE JOB No: 037-AS2009-10-079 Sample No : Quarry Material Location : : CA for___________work :_________Km Tested by : Date of testing :

Observation Sheet: Type of Aggregate: Type of binder: Percentage of binder used: Total wt. of aggreagte : Total wt. of binder : Temparature of water bath Determination No: Stripping % Average Value: Remark: I II III

APWD REPRESENTATIVE

CONTRACTOR'S REPRESENTATIVE

DAILY PROGRESS REPORT: JOB NO: 037-AS-2009-10-079


DATE WEATHER AM PM ACTIVITIES (Item No., description, locations, quantity of work, etc.) MANPOWER EQUIPMENT (Type, No. (Engineers, working/idle) foremen, skilled labourers, operators, others) PROBLEMS/ ISSUES ENCOUNTERED (Disturbances, strike, accidents, etc.) Recorded by: (Contractor's representative) Noted: (APWD Representative) REMARKS (Inspecting officers, site instructions, emergency work orders, etc.)