PHASESTOCERTIFICATION;
FINALTESTS
APPROVALOFPROJECTSANDCALCULATIONSAREEXECUTEDACCORDINGTOAPI 650,653
QUALIFICATIONOFWELDINGPROCEDURES WeldingprocedurequalificationrecordsmustmeettherequirementsofSectionIXof theASMECode. Either AWSD1.1 or AWSD1.6 arealsoacceptableforladderand platformassemblies, handrails,stairways,andothermiscellaneous assemblies,butnottheirattachmentsto thetank.
INSPECTIONOFMATERIALS;
AFTERFORMINGOFSHELLPLATES RADIUSOFEACHPLATEMUSTBECHECKED NOTTOSPENDMUCHTIMEDURINGTHISSTEP,APREFORMEDPATTERNMODEL MADEOFTHINMETALSHEETCANBEUSED. PRIMERSHOULDBEAPPLIEDBEFORETRANSPORTINGTHESHEETSTOPLANT,AND INCASEOFNOTTOAFFECTTHEQUALITYOFWELDS,ALLWELDFACESSHOULDBE COVEREDBYPAPERTAPEPREVIOUSLYTOKEEPCLEANFROMPAINTRESIDUE. RESIDUE INCASEANYDEFORMATIONMAYOCCURDURINGTRANSPORTANDSTACKING, PREFORMEDSHELLPLATESSHOULDBESETTLEDONAPACKSADDLE.
10
11
12
TWOTYPESOFTANKFLOORINGARE; BOTTOMDOWN:Generally, y bottomdownisdesign g forconerooftanks.Centre oftheflooringisinstalledwithdrainpit.Waterinthetankis accumulatedinthepit (lowestpointofthebottomplate/floor). BOTTOMUP:Generally,thistypeofdesignisusedforfloatingrooftanks, 3to4 collectorpitsareinstalled,closetotheshellplate. Eachofthepitisprovidedwitha waterdrawoffline.
Aslope p of1:120issuitable
13
DRAWOFFSUMP
Theerectionprocedureshallincludethefollowingsteps: (a)aholeshallbecutinthebottomplateorasumpshall beplacedinthe foundationbeforebottomplacement; (b)aneatexcavationshallbemadetoconformtothe shapeofthedrawoffsump,thesumpshallbeput inplace, andthefoundationshallbecompactedaroundthesump afterplacement;and (c)thesumpshallbeweldedtothebottom.
14
15
ADJUSTMENTOFSECONDCOURSE
UPRIGHTNESS,ANDROUNDNESSOFTHESHELLISMEASUREDMIN.AT8POINTS. THENVERTICALWELDSAREEXECUTEDOFTHEFIRSTCOURSE.
16
ADJUSTMENTOFTHIRDCOURSE
17
FOURTH
THIRD
SECOND
FIRST COURSE
18
TYPICALANCHORAGE
19
TYPICALANCHORAGE
20
Vacuumtestingisperformedusingatesting box approximately150mm(6in.)wideby750mm (30in.)long withaclearwindowinthetop, whichprovidespropervisibility toviewthearea underinspection. During gtesting, g,illumination shallbeadequate q forproperevaluationand interpretationofthe test. Theopenbottomshallbesealed againstthe tanksurfacebyasuitablegasket. gasket Connections, Connections valves,lightingandgauges,shallbeprovidedas required. A soapfilmsolutionor commercial,leak detectionsolution, applicabletotheconditions, shallbeused.
21
CONSTRUCTIONOFROOF
22
TYPICALWELDJOINTSATROOF
23
NONDESTRUCTIVEEXAMINATIONOFATANK
Completepenetrationandcompletefusionarerequiredfor weldsjoiningshell platestoshellplates. Inspectionforthe qualityoftheweldsshallbemadeusingeithertheradiographic method, oralternatively,byagreement betweenthepurchaserandthe manufacturer,usingtheultrasonic method.Inadditiontotheradiographic or ultrasonicexamination, ,theseweldsarealsovisually yexamined.
Ingeneral,radiographicinspectionisrequiredforshellbuttwelds,annularplate buttwelds,andflushtypeconnectionswithbuttwelds.
24
TESTINGOFTHESHELL
Aftertheentiretankandroofstructureiscompleted,the shellis testedbyoneofthe following methods: 1 Ifwaterisavailablefortestingtheshell,thetankshallbe filledwithwateras follows: itothemaximumdesignliquid level; iiforatankwithatightroof,to50mmabovetheweldconnectingtheroofplateor compressionbar tothetopangleorshell
2 Ifsufficientwatertofillthetankisnotavailable,thetank maybetestedby painting all llof fthe th joints j i t onthe th i inside id with ithahi highly hl penetrating t ti oil il
25
FIREPROTECTION FireprotectionsystemshallbeestablishedaccordingtotheNFPAstandards. Thissystem y isinspected p during gmanufacturing goftheinstallationandafterthat functions,andperformanceareexamined. Systemshallinclude; Foambasedextinguishing, Watercooling Monitors Dikeprotection
26
TobeonthesafesideforexposureprotectionwerecommendandapplyNFPA rate.
27
28
29
30
31
Thanksyouforyourattention