BP-18

STOREFRONTS, GLASS AND GLAZING

SCOPE OF WORK

DESIGNATED 35% CBE SUBCONTRACTING SET-ASIDE REQUIREMENT

DEFINITION OF PROJECT AREA:

The Scope of Work includes the glass and glazing systems at the Mount Pleasant
Neighborhood Library which is located at 3260 R Street, NW, Washington, DC.

WOOD WINDOWS, STOREFRONTS, GLASS AND GLAZING


Contractor shall be responsible for labor, material and equipment for all glazing systems
including but not limited aluminum curtain wall, storefronts, glass and glazing and
skylights at the existing building and the new addition as indicated in bid documents
(100% Final Construction Drawings and Specifications dated July 9, 2009). Available on
CD. Work includes but is not limited to the following specification sections
Division 1 – General Requirements
Division 7 – Thermal and Moisture Protection
07920 Joint Sealants (As applicable for your work)
Division 8 – Doors and Windows
08113 Glass Firewall Window and Door System
08450 All-Glass Entrances
08550 Wood Windows
08710 Door Hardware (As applicable for your work)
08716 Automatic Door Operators
08800 Glazing

1. Furnish and install new wood replacement windows at 3rd level dormers
and Lower Level as indicated.
2. Furnish and install new frameless glass door systems complete with
finish hardware.
3. Furnish and install new fire rated glass partition and door systems.
4. Furnish and install new interior aluminum storefront and all-glass
systems including door units with finish hardware.
5. Furnish and install wood window as noted on Drawing AS-0.02
6. Furnish and install new steel windows. Verify opening sizes in field.
7. Furnish and install glass panels in hollow metal and wood frames (i.e.
sidelites, transoms, etc.)
8. Furnish and install glazing film as indicated.
9. Furnish and install glass panels in hollow metal and wood doors
10. Furnish and install edge trim and sill flashings around new exterior
openings.
11. Furnish and install frameless mirrors.
12. Exterior caulking between the Work and adjacent materials.
13. Hoisting as required for this work.
14. Provide any Independent Testing & Inspection Services required for this
Work, including materials testing and inspections;
15. During the period of this work, contractor agrees that all employees
must be experienced in performing the work.
16. Contractor is required to provide pre-existing surveying (photographs or
video taping).
17. Contractor shall coordinate this work with other work in progress.
18. The Contractor shall ensure that no elements determined to be unstable
are left unsupported. Any and all required structural bracing for
structural systems to remain shall be included in this scope of work.
19. Contractor shall remove and transport debris resulting from erection
operations and materials to site disposal area. Recyclable materials shall
be separated and stored or stockpiled without intermixing with other
surplus materials before transporting to recycling facilities in accordance
with a recycling program consistent with the Project LEED Certification
Program.
20. Contractor shall comply with all identified performance and
specification requirements to achieve LEED points toward the Silver
certification goal as indicated in the bid documents.
21. Contractor shall take all necessary precautions to avoid damage to all
existing and completed construction in place.
22. It is Contractor’s responsibility to read the Hazardous Materials Survey
Report for Georgetown Neighborhood Library, including the July 8th
2008 addendum.
23. Contractor shall submit bids detailing their proposed means, methods
and schedule for this scope of work, and shall include evidence of their
experience with similar projects as well as references who may be
contacted by the Client.
24. Labor for incidental project clean-up
25. Miscellaneous temporary protection of existing conditions during
construction as specifically specified herein and OSHA safety
barricades, rails and floor coverings, for this Work.
26. Engineering, site survey and layout for this Work including any required
field measurements.
27. Contractor shall leave the workplace in a clean and presentable
condition ready for subsequent trades and prepared for finishes as
specified.
28. Submittals will be required for approval prior to execution of the work.

Exclusions.
1. Replacement glass at restored wood windows.