You are on page 1of 5

Prof D.A. Pathak et al.

/ International Journal of Engineering Science and Technology (IJEST)

Quality Enhancement of Manufacturing Process by Simulation Technique: A Case Study


Prof D.A. Pathak
Research Scholar, Production Engineering Department, K.I.Ts College of Engineering Kolhapur, Dist: - Kolhapur, India 416234 deven_ patak@yahoo.co.in

Prof J.S.Bagi,
Associate Professor, Production Engineering Department, K.I.Ts College of Engineering Kolhapur, Dist: - Kolhapur, India 416234 jaysbagi@gmail.com

Abstract: Industries need quality improvement of manufacturing process as it helps to decrease the operation cost, to improve product quality, etc. Quality improvement can be established by controlling quality of raw material. A technique that can be used to do this task is simulation. The paper mainly focuses upon one of the case studies of the quality improvement of one of the printing machine product in ABC company with simulation technique. The simulation software used is the FLEXSIM 5 which is developed by Canyon Park Technology Center, Orem-Utah, USA. The software can be freely downloaded from the internet with negligible cost. Simulation had a lot influence on the manufacturing process because inventing more powerful tools will make the user to work easily and also to implement any kind of models. Operating within large complex systems also possible by using distributed technology and which also addressed as web based simulation.

Keywords: Quality improvement, simulation, flexsim, manufacturing process. 1. Introduction: Now days industries are facing an ever increasing demand to improve product quality, not only to minimize scrapping and increase productivity but also to ensure customers satisfaction. Concerning the latter, measures can be taken to ensure final product quality. The most common procedure consists in ensuring absence of unwanted defects through a variety of non-destructive testing methods, repairing defects when possible and scrapping when not. The cycle time of an assembly line is predetermined by a desired production rate. Such the production rate is set so that the desired amount of end product is produced within a certain time period. [Supaporn Suwannarongsri (2007)]. While this allows for defects detection and guarantees the final product conformity, it does not affect defect occurrence and therefore does not help reduce scrapping. Defect formation may happen at different stages along any product manufacturing route (casting, cooling, rolling, etc). In many cases the production planner is mainly concerned with the due dates, and the minimization of the set-up times may sometimes conflict with this goal. [Timo Hayrinen Mika Johnsson Tommi Johtela (Oct 1998)]. Different simulation soft wares are today of considerable help in these tasks, as they allow for a reasonably accurate modelling of different products processing and current status at any point of the processing route. The software mentioned above FLEXSIM 5 is used to overcome these problems. Simulation can directly identify areas of cost savings or efficiency as well as playing a major role in risk analysis. Simulation provides insight into risk analysis by providing increased knowledge of system dynamics and interactions. It also identifies possible scenarios resulting from various actions. Simulation may not be able to predict specific demands for future goods and services but it can be used to assess the impact of such demand variability on a systems ability to react. All these requirements for understanding dynamic systems have placed a new emphasis on simulation
ISSN : 0975-5462 Vol. 4 No.06 June 2012 2576

Prof D.A. Pathak et al. / International Journal of Engineering Science and Technology (IJEST)

technologies and applications. People across an entire organization use simulation to make good decisions. The use of simulation as a common tool to can be used to: Test new concepts and options. Analyze systems for improvement. Match project scope with business requirements. Share information across organizations. Focus on the impact of complex dynamics.

2. Quality Dimensions: 2.1 Reliability: - Product reliability is a critical part of total product quality. Reliability is a measure of a products performance that affects both product function and operating and repair costs. Too often performance is thought of only in terms of speed, capacity, range, and other normal measures. The objective of reliability prediction is to support decisions related to the operation and maintenance of the product including to: Reduce output penalties including labor costs and outage repair. Help in the design of future products, by improved safety margins and reduced failures. Increase profitability. Optimize maintenance cycles and spares holdings. 2.2 Performance: - Performance is also one of the important quality parameter in manufacturing process. Performance measures whether the product or the service does what it is suppose to do within its defined tolerances. So after the product is designed and is used in actual implementation, testing is done whether that product is performing according to its function or not within the given conditions or not and if problem is been found there then necessary steps are taken and problem is been eliminated. 3. Case Study of ABC Company:

3.1 Component Description:As stated earlier the case study is about quality improvement of the manufacturing process of one of the product of the printing machine. The component is blanket cylinder. The cylinders are one of the important part of printing machine. The main function of the cylinder is to pass and support the paper with required tension between the preceding cylinders. These are supported to the walls and also properly aligned to the walls to have the smooth functioning of entire machine. For the quality improvement of the manufacturing process the main focus is on the total cycle time reduction. So the data required was collected like setting time operating time etc. The basic input to flexsim given is the setting time, operating time for one shift (8 hrs) and simulation run time is given in seconds (8hrs*60min*60sec) i.e. 28800 sec. And having the present given things model was developed and simulated. Refer fig 1 for present simulation model of manufacturing process for blanket cylinder.

Fig.1. Simulation model of the present manufacturing process for blanket cylinder

Following are the results of the present manufacturing process. Refer table1for the detailed results.

ISSN : 0975-5462

Vol. 4 No.06 June 2012

2577

Prof D.A. Pathak et al. / International Journal of Engineering Science and Technology (IJEST)
Table.1. Present total cycle time calculation

Object Source Queue Bendsaw_hexsaw Initial Manual operations (cleaning, inspecting) Turning 1 Facing Turning 2 Grinding Drilling Milling Tapping Dynamic Balancing Drilling 1 Third Tapping Final Manual operations ( QC, Epoxy coating, packing) Sink

Class Source Queue Processor Processor Processor Processor Processor Processor Processor Processor Processor Processor Processor Processor Processor Sink

Processing time (min) 0 0 5 10 390 50 190 122 70 250 60 180 140 120 121 0 =1708

Idle time (min) 0 0 10 10 30 0 30 31 30 225 24 30 20 20 10 0 =470

Processing time (%) 0 0 0.29 0.58 22.83 2.92 11.12 7.14 4.09 14.63 3.51 10.53 8.19 7.02 7.08 0

Idle Time(%) 0 0 2.12 2.12 6.38 0 6.38 6.59 6.38 47.87 5.10 6.38 4.25 4.25 2.12 0

Total Time

Total cycle time = Processing time + Idle time = 1708+470= 2178 min Above results state the processing and idle time in minutes. The total cycle time calculated was 2178 min. From the above simulation model it is found that more idle time was incurred for the workstations namely milling, turning1, dynamic balancing etc. So there was need to reduce the idle time and make the optimum utilization of the workstations. So proposed model for the same is prepared and results are interpreted.

Fig 2.Simulation model of proposed manufacturing process for blanket cylinder

Following are the results of the present manufacturing process. Refer table2for the detailed results.

ISSN : 0975-5462

Vol. 4 No.06 June 2012

2578

Prof D.A. Pathak et al. / International Journal of Engineering Science and Technology (IJEST)
Table 2 Proposed total cycle time calculation

Object Source Queue

Class Source Queue Processor

Processing time (min) 0 0

Idle time (min) 0 0

Processing time % 0 0

Idle Time % 0 0

Bendsaw_hexsaw Initial Manual operations (cleaning, inspecting) Facing Turning 1 Turning 2 Milling Drilling Grinding Tapping Dynamic balancing Drilling 1 Third Tapping Final Manual operations ( QC, Epoxy coating, packing) Sink

5 Processor Processor Processor Processor Processor Processor Processor Processor Processor Processor Processor Processor Sink Total time 9 49 384 192 246 65 119 59 179 136 119 120 0 =1682

8 10 0 25 27 224 29 28 23 27 17 17 6 0 =441

0.29 0.53 2.91 22.82 11.41 14.62 3.86 7.07 3.50 10.64 8.08 7.07 7.13 0

1.81 2.26 0 5.66 6.12 50.79 6.57 6.34 5.21 5.66 3.85 3.85 1.36 0

Total cycle time = Processing time + Idle time = 1682+441 = 2123 min 3.2 Interpretation of results:Table. 3 Summary of Blanket Cylinder

Component name Blanket Cylinder

Present simulation time (min) 2178

Proposed simulation time (min) 2123

Reduction in time (min) 55

Reduction in (%) 2.52

1) So after comparing the simulation model and results of the present and proposed one, we observed that, the present total cycle time calculated was 2178 min & proposed total cycle time calculated was 2123 min. 2) So the difference in both the present and proposed simulation results was about 55 min. i.e. about 2.52% of the total cycle time was reduced. 3) In the present simulation model, facing workstation was used between two workstations turning1, turning 2 and after turning 2 grinding workstation was used. 4) But in the proposed model, before turning 1 & turning 2 facing was used and then after turning 2, milling workstation was used. And grinding workstation was used after drilling workstation. That means in the present model, sequence of workstation was the main problem identified. And in proposed model, it got eliminated in terms of the total cycle time. i.e total cycle time was reduced with the help of simulation. 5) So ultimately process was optimized. And thus by changing the sequence of workstations, total cycle time was reduced.

ISSN : 0975-5462

Vol. 4 No.06 June 2012

2579

Prof D.A. Pathak et al. / International Journal of Engineering Science and Technology (IJEST)

4.

Results and discussions:-

From the above discussion of the case study, it revealed the problem affecting the cycle time of the blanket cylinder in the present model and results. Near about 2.52% of the total cycle time was reduced. So ultimately the two quality parameters i.e. performance and reliability were also improved. The workstations line problem was dealt with using simulation technique to improve the quality of manufacturing process. Future study can enhance the results obtained here by incorporating other variables such as breakdown, bottlenecking in the manufacturing process. Acknowledgement:First of all, I would like to express utmost gratitude to my Co-author Prof.J.S.Bagi, for his continued support, encouragement and guidance provided in articulating this paper. Finally, I am very much thankful also to those who extended their help directly or indirectly in preparation of this paper. 5. References:Endra Joelianto and Linda Kadarusman. (2009). Industrial Control Quality Improvement using Statistical Process Control: Tennessee Eastman Process Simulation Case Bandung Institute of Technology Jalan Ganesha 10, Bandung 40132, Indonesia. International Conference on Instrumentation, Control & Automation ICA2009October 20-22, Bandung, Indonesia, 2009 ICA, ISBN 978-979-886105-5. [2] Hsiu-Hsueh Kao, CPM-based Heuristics for Type-I Assembly Line Balancing Problems, Department of Finance, Yuanpei University, No.306, Yuanpei St., Hsin-Chu, Taiwan. [3] Introduction to FLEXSIM simulation software. [4] Kana Yokoyama, Katsumi Morikawa, and Katsuhiko Takahashi. (2010). A modified multi agent system for simple assembly line balancing, 8th International Conference of Modeling and Simulation - MOSIM10 - May 10-12 - Hammamet Tunisia. [5] Khusna Dwijayanti, Siti Zawiah Md Dawal, Jamasri, and Hideki Aoyama. (2010). A Proposed Study on Facility Planning and Design in Manufacturing Process Proceedings of International Multiconference of Engineers and Computer Scientists, Vol III, IMECS 2010, March 17-19 2010 Hong Kong, ISBN: 978-988-18210-5-8, ISSN: 2078-0958 (Print) [6] Supaporn Suwannarongsri. (2007). A Hybrid Tabu Search Method For Assembly Line balancing, Department of Industrial engineering, Bangkok 10520 International conference of simulation September pp.15-17. [7] S. Aharonov, Y. Bukchin and T. Raviv, Integrated assembly line and inspection allocation problem in an online rework environment, Tel Aviv University, Department of Industrial Engineering. [8] Timo Hayrinen Mika Johnsson Tommi Johtela. ( 1998). Scheduling algorithms for computer aided line balancing in printed circuit board assembly, Turku Centre for Computer Science UCS Technical Report No 21October [9] Teerapun Saeheaw, Nivit Charoenchai, and Wichai Chattinnawat. (2009). Line balancing in the hard disk drive process using simulation techniques World Academy of Science, Engineering and Technology 60. [10] Weida Xu Tianyuan Xiao. (2008). Mixed model assembly line balancing problem with fuzzy operations time and drifting operations, Proceedings of the Winter Simulation Conferences. J. Mason, R. R. Hill, L. Mnch, O. Rose, T. Jefferson, J. W. Fowler eds [1]

ISSN : 0975-5462

Vol. 4 No.06 June 2012

2580

You might also like