Professional Documents
Culture Documents
AECOM Singapore
LIM Chi-Sharn
Associate / Principal Engineer (Geotechnical) Chisharn.lim@aecom.com
09 May 2013
Outline
Challenges
09 May 2013 Page 2
Tunnelling and Excavation causes Ground Movements & Other Changes which are kept Within Acceptable Limits in order to Ensure Safety & Protect Adjacent Structures
09 May 2013 Page 3
Instrumentation is
Monitoring is
a Surveillance System
at Site
09 May 2013 4
Objectives To Verify Design Assumptions by Comparing Monitored responses against Predicted Values
09 May 2013
Page 5
Equipment reliable
Processes clearly defined People clear roles and responsibilities
09 May 2013 Page 6
Defines initial site conditions such as groundwater, background conditions (temperature, noise, vibration, tides)
Proof testing (test piles) Safety and Risk Management Observational approach to design and design verification that is based on data Construction control Legal protection Enhances public relations
09 May 2013 Page 7
Ground Water
Water Table / Pore Water Pressure
Structural Forces
Strut/Ground-Anchor Supports, Tunnel Lining
Structural Deformations
Tilt & Crack Widths of Buildings/Structures Utilities; Cables & Pipes Profile & Shape of Tunnels
TYPICAL INSTRUMENTATION
09 May 2013 Page 9
09 May 2013
Page 10
Settlement Plates
09 May 2013
Page 11
09 May 2013
Page 12
09 May 2013
Page 13
09 May 2013
Page 14
09 May 2013
Page 15
09 May 2013
Page 16
09 May 2013
Page 17
09 May 2013
Page 18
09 May 2013
Page 19
Piezometer
09 May 2013
Page 20
10
09 May 2013
Page 21
11
09 May 2013
Page 23
Tilt Meter
09 May 2013
Page 24
12
EL Beam Sensor
09 May 2013
Page 25
09 May 2013
Page 26
13
Convergence Monitoring
09 May 2013
Page 27
Convergence Monitoring
09 May 2013
Page 28
14
Tape Extensometer
09 May 2013
Page 29
Crack Meter
09 May 2013
Page 30
15
09 May 2013
Page 31
09 May 2013
Page 32
16
09 May 2013
Page 33
09 May 2013
Page 34
17
09 May 2013
Page 35
09 May 2013
Page 36
18
09 May 2013
Page 37
09 May 2013
Page 38
Distributed strain sensor BOTDR Average strain over 1m every 20cm Range ~5-10km Resolution 30 (0.003%) Low cost sensors - optical fibre 5 - 25 minutes per measurement Can link or switch between fibres
19
DESIGN
09 May 2013 Page 39
Location of instrument
Where is it to be installed?
Review levels
What are the safe limits?
Contingencies
What should be done when the limits are exceeded, and who should do it?
09 May 2013 Page 40
20
09 May 2013
Page 41
09 May 2013
42
21
09 May 2013
43
09 May 2013
Page 44
22
09 May 2013
Page 45
09 May 2013
Page 46
23
09 May 2013
Page 47
09 May 2013
Page 48
24
09 May 2013
Page 49
09 May 2013
Page 50
25
7m from breakout
0m 2m
09 May 2013
Monitoring Ground Water Level Currently Not Monitored at Close Interval To Determine Correct Face Pressure with Reference to Ground Water Pressure for Both Slurry and EPBM To limit Ground settlement To avoid Ground heave, slurry spouts and foam spews To validate the design of tunnel segment
09 May 2013
26
Examples
09 May 2013
Page 53
Examples
09 May 2013
Page 54
27
Examples
09 May 2013
Page 55
Examples
09 May 2013
Page 56
28
Role in Risk Management Managing residual design risk and construction risk Tunnelling
Start of tunnelling
09 May 2013
Page 57
09 May 2013
58
29
09 May 2013
59
09 May 2013
Page 60
30
09 May 2013
Page 61
09 May 2013
Page 62
31
09 May 2013
Page 63
09 May 2013
Page 64
32
Examples
09 May 2013
Page 65
Examples
09 May 2013
Page 66
33
Examples
09 May 2013
Page 67
Examples
09 May 2013
Page 68
34
Examples
09 May 2013
Page 69
Back-Analysis of Unpredicted Sway of a Cut-And-Cover Deep Excavation in Singapore Marine Clay (Lim et. al. 2011. Proc of ICAGE)
09 May 2013 Page 70
35
Role in Risk Management Managing residual design risk and construction risk Excavations
3D (??) 2D (ok)
The Impact of Geometry on Re-Entrant Corner Behaviour in Deep Excavation Retaining Walls: Two Case Studies from Stage 4 of the Circle Line. (Lim C.S. and Jee Y.Y., 2008, Proc. Of ICDE)
09 May 2013 Page 71
Ensuring Safety and Minimizing Impact Adjacent Structures Comparing predictions with outcomes / safety limits
Ground movements Groundwater changes Building movements and strains
09 May 2013
Page 72
36
Structure Monitoring
09 May 2013
Page 73
09 May 2013
Page 74
37
Structure Monitoring
09 May 2013
Page 75
Structure Monitoring
09 May 2013
Page 76
38
Base Load B
W=F+B F
Volume Loss Shaft Friction F B Tunnel volume loss causes base load B to reduce, pile settles and shaft friction F Volume Loss increases
09 May 2013 Page 77
Bored tunnelling below full scale pile trials in the Second Heinenoordtunnel site (Kaalberg et al, 2005) (slide from Mair,
distance from tunnel (m)
-30 -20 -10 0 10 4 -1 -6 -11 tunnel -16 -21 -30 -20 -10 0 10
2009)
0 -10
settlments (mm)
Field trials : wooden and concrete piles above two 8.3m OD tunnels End-bearing piles, shaft friction very low Volume losses
Piles in Zone A settle > ground surface Piles in Zone B settle ~ ground surface 09 May 2013 Page 78 Piles in Zone C settle < ground surface
39
09 May 2013
Page 79
09 May 2013
Page 80
40
PLANNING
(For the construction phase)
09 May 2013 Page 82
41
Supervision Role of the Qualified Person for Geotechnical Aspects of GBWs (8th Schedule, Part II, Building Control Regulations) Tunnels
09 May 2013
Page 83
Supervision Role of the Qualified Person for Geotechnical Aspects of GBWs (8th Schedule, Part II, Building Control Regulations) Deep excavations
09 May 2013
Page 84
42
Equipment reliable
Processes clearly defined People clear roles and responsibilities
09 May 2013 Page 85
Equipment reliable
Processes clearly defined People clear roles and responsibilities
09 May 2013 Page 86
43
3 Activity
against trend
2 Trend
graphically
visible
1 X-axis
FORM IS FUNCTION
4 Key plan
with instrumentation locations
5 Table
readings against Review Levels
09 May 2013
44
09 May 2013
98
45
Voluminous Data
Timely
Interpretation
construction
activities
Tracking
Predicted Levels
against
09 May 2013
Page 100
THANK YOU
09 May 2013
46