You are on page 1of 46

Design and Planning of Instrumentation Works

AECOM Singapore
LIM Chi-Sharn
Associate / Principal Engineer (Geotechnical) Chisharn.lim@aecom.com

09 May 2013

Outline

Introduction and Objectives Design of Instrumentation and Monitoring Systems


Bored tunnelling Mined tunnelling Deep excavation

Planning of Instrumentation and Monitoring Systems


Risk Management Information Management Contingency Planning Ensuring Reliability (System Assurance)

Challenges
09 May 2013 Page 2

Tunnelling and Excavation causes Ground Movements & Other Changes which are kept Within Acceptable Limits in order to Ensure Safety & Protect Adjacent Structures
09 May 2013 Page 3

What is Instrumentation & Monitoring?

Instrumentation is

Monitoring is

a Surveillance System

at Site
09 May 2013 4

Objectives To Verify Design Assumptions by Comparing Monitored responses against Predicted Values

To Ensure Safety by Limiting Magnitudes & Restricting Trends of Responses

To Minimize Damage of surrounding Structures & Buried Cables, Pipes etc.

09 May 2013

Page 5

Construction Works as an Engineered System


QUALITY ability to satisfy requirements
Serviceability use for purpose and for conditions Safety acceptability of risks

Compatibility acceptability of impacts

Durability freedom from unanticipated degradation

(Bea, 1994, 2002)

Equipment reliable
Processes clearly defined People clear roles and responsibilities
09 May 2013 Page 6

Benefits of Instrumentation & Monitoring


(from Dunnicliff, 1993)

Defines initial site conditions such as groundwater, background conditions (temperature, noise, vibration, tides)
Proof testing (test piles) Safety and Risk Management Observational approach to design and design verification that is based on data Construction control Legal protection Enhances public relations
09 May 2013 Page 7

What are Monitored? Ground Movement


Settlement (& at Depths), Heave (& at Base) Lateral Displacement (& along Depths)

Ground Water
Water Table / Pore Water Pressure

Structural Forces
Strut/Ground-Anchor Supports, Tunnel Lining

Structural Deformations
Tilt & Crack Widths of Buildings/Structures Utilities; Cables & Pipes Profile & Shape of Tunnels

Vibration and Noise


09 May 2013 Page 8

TYPICAL INSTRUMENTATION
09 May 2013 Page 9

Ground Settlement Markers

09 May 2013

Page 10

Settlement Plates

09 May 2013

Page 11

Settlement at Depth (Magnetic Extensometer)

09 May 2013

Page 12

Settlement at Depth (Hydraulic Hook)

09 May 2013

Page 13

Settlement at Depth (Hook Sensor)

09 May 2013

Page 14

Deep Leveling Datum

09 May 2013

Page 15

Water Stand Pipe

09 May 2013

Page 16

Water Stand Pipe & Piezometer

09 May 2013

Page 17

09 May 2013

Page 18

Vibrating Wire Piezometer

09 May 2013

Page 19

Piezometer

09 May 2013

Page 20

10

Push-in Type Piezometer

09 May 2013

Page 21

Building Settlement Markers

For Concrete Surface


09 May 2013 Page 22

For Asphalt Surface

11

Building Settlement Markers

09 May 2013

Page 23

Tilt Meter

09 May 2013

Page 24

12

EL Beam Sensor

09 May 2013

Page 25

EL Beam Sensor As In-Place Inclinometer & for Settlement Profile

09 May 2013

Page 26

13

Convergence Monitoring

09 May 2013

Page 27

Convergence Monitoring

09 May 2013

Page 28

14

Tape Extensometer

09 May 2013

Page 29

Crack Meter

09 May 2013

Page 30

15

09 May 2013

Page 31

09 May 2013

Page 32

16

09 May 2013

Page 33

Strut Load Measurement

09 May 2013

Page 34

17

09 May 2013

Page 35

09 May 2013

Page 36

18

09 May 2013

Page 37

Brillouin optical time domain reflectometry (BOTDR)

Diagram courtesy of ntt.co.jp/news

09 May 2013

Page 38

Distributed strain sensor BOTDR Average strain over 1m every 20cm Range ~5-10km Resolution 30 (0.003%) Low cost sensors - optical fibre 5 - 25 minutes per measurement Can link or switch between fibres

19

DESIGN
09 May 2013 Page 39

Design Aspects Purpose of instrument


What is to be monitored?

Location of instrument
Where is it to be installed?

Review levels
What are the safe limits?

Frequency and duration


When and how often is it to be monitored?

Contingencies
What should be done when the limits are exceeded, and who should do it?
09 May 2013 Page 40

20

Design Verification Tunnelling Verification of parameters


Water table Volume loss Ground relaxation

Comparing predictions with outcomes


Ground movements Groundwater changes Convergence / radial displacement

Monitoring at areas of risk


To manage residual design risk, construction risk

09 May 2013

Page 41

Trough Measurements Help to Identify Types of Ground Movement

09 May 2013

42

21

Settlements at Surface Vs at Depth

09 May 2013

43

Monitoring Arrays (Tunnelling)

09 May 2013

Page 44

22

Monitoring Arrays (Tunnelling)

09 May 2013

Page 45

Monitoring Arrays (Tunnelling)

09 May 2013

Page 46

23

Monitoring Arrays (Tunnelling)

09 May 2013

Page 47

Monitoring Arrays (Tunnelling)

09 May 2013

Page 48

24

Interpreted Monitoring Data

09 May 2013

Page 49

Convergence Monitoring (Bored Tunnel) For Both Tunnels,


Min 1 for each drive Min. 1 at each soil type encountered

For 1st tunnel,


Min one at every 100m if clear space < Min one at every 25m if clear space < 3m

09 May 2013

Page 50

25

Convergence Monitoring (Cross Passages using SCL) Every 2m from breakout

7m from breakout
0m 2m

Every 20m thereafter


4m 6m 7m 20m
Page 51 52

09 May 2013

Monitoring Ground Water Level Currently Not Monitored at Close Interval To Determine Correct Face Pressure with Reference to Ground Water Pressure for Both Slurry and EPBM To limit Ground settlement To avoid Ground heave, slurry spouts and foam spews To validate the design of tunnel segment

09 May 2013

26

Examples

09 May 2013

Page 53

Examples

09 May 2013

Page 54

27

Examples

09 May 2013

Page 55

Examples

09 May 2013

Page 56

28

Role in Risk Management Managing residual design risk and construction risk Tunnelling

Before tunnelling under buildings


(esp. with mixed ground)

Start of tunnelling

09 May 2013

Page 57

Cavities are Not Always Fully Grouted


Leca, E. & Domieux, L. (1990)

09 May 2013

58

29

Subsurface Monitoring Rod extensometers @ Close Intervals?

Drawback Risk of Slurry Path

09 May 2013

59

Monitoring for unplanned stoppages

09 May 2013

Page 60

30

09 May 2013

Page 61

Design Verification Excavation Verification of parameters


Water table Soil properties

Comparing predictions with outcomes


Ground movements Groundwater changes Retaining wall deflections Strut forces

Monitoring at areas of design risk


To manage residual design risk

09 May 2013

Page 62

31

Monitoring Arrays - Excavations

09 May 2013

Page 63

Monitoring Arrays - Excavations

09 May 2013

Page 64

32

Examples

09 May 2013

Page 65

Examples

09 May 2013

Page 66

33

Examples

09 May 2013

Page 67

Examples

09 May 2013

Page 68

34

Examples

09 May 2013

Page 69

Interpreted Monitoring Data Possible causes


Observed soil profile different from design no F2 at the East Wall Marine clay Cu and Eu lower than adopted at design

Back-Analysis of Unpredicted Sway of a Cut-And-Cover Deep Excavation in Singapore Marine Clay (Lim et. al. 2011. Proc of ICAGE)
09 May 2013 Page 70

35

Role in Risk Management Managing residual design risk and construction risk Excavations
3D (??) 2D (ok)

The Impact of Geometry on Re-Entrant Corner Behaviour in Deep Excavation Retaining Walls: Two Case Studies from Stage 4 of the Circle Line. (Lim C.S. and Jee Y.Y., 2008, Proc. Of ICDE)
09 May 2013 Page 71

Ensuring Safety and Minimizing Impact Adjacent Structures Comparing predictions with outcomes / safety limits
Ground movements Groundwater changes Building movements and strains

Comparing outcomes with legal limits / guidelines


Noise Vibration

09 May 2013

Page 72

36

Structure Monitoring

09 May 2013

Page 73

09 May 2013

Page 74

37

Structure Monitoring

09 May 2013

Page 75

Structure Monitoring

09 May 2013

Page 76

38

Effects of tunnelling on pile foundations


(slide from Mair, 2009)

Base Load B

W=F+B F

Volume Loss Shaft Friction F B Tunnel volume loss causes base load B to reduce, pile settles and shaft friction F Volume Loss increases
09 May 2013 Page 77

Bored tunnelling below full scale pile trials in the Second Heinenoordtunnel site (Kaalberg et al, 2005) (slide from Mair,
distance from tunnel (m)
-30 -20 -10 0 10 4 -1 -6 -11 tunnel -16 -21 -30 -20 -10 0 10

2009)

0 -10

settlments (mm)

pile settlement surface settlement piles

-20 -30 -40 -50

Field trials : wooden and concrete piles above two 8.3m OD tunnels End-bearing piles, shaft friction very low Volume losses

depth below ref. level (m)

Zone B Zone A Zone C


30o 45o

1st tunnel : 1~2% 2nd tunnel : 0.75%


0.5D was considered to be safe distance between pile toe and tunnel

Piles in Zone A settle > ground surface Piles in Zone B settle ~ ground surface 09 May 2013 Page 78 Piles in Zone C settle < ground surface

39

Structure Monitoring (Real Time)

09 May 2013

Page 79

Structure Monitoring (Real Time)

09 May 2013

Page 80

40

Design Role of the Qualified Person for Geotechnical Aspects of GBWs

(Building Control Regulations)


09 May 2013 Page 81

PLANNING
(For the construction phase)
09 May 2013 Page 82

41

Supervision Role of the Qualified Person for Geotechnical Aspects of GBWs (8th Schedule, Part II, Building Control Regulations) Tunnels

09 May 2013

Page 83

Supervision Role of the Qualified Person for Geotechnical Aspects of GBWs (8th Schedule, Part II, Building Control Regulations) Deep excavations

09 May 2013

Page 84

42

Construction Works as an Engineered System


QUALITY ability to satisfy requirements
Serviceability use for purpose and for conditions Safety acceptability of risks

Compatibility acceptability of impacts

Durability freedom from unanticipated degradation

(Bea, 1994, 2002)

Equipment reliable
Processes clearly defined People clear roles and responsibilities
09 May 2013 Page 85

Monitoring Works as an Engineered System


QUALITY ability to satisfy requirements
Serviceability use for purpose and for conditions Safety acceptability of risks

Compatibility acceptability of impacts

Durability freedom from unanticipated degradation

(Bea, 1994, 2002)

Equipment reliable
Processes clearly defined People clear roles and responsibilities
09 May 2013 Page 86

43

Role in Risk Management

Safety & Design RISKS are Managed


by

Setting Limits on Each Response


&

Comparing Monitored Responses Against these Set Limits


09 May 2013 Page 87

3 Activity
against trend

Interpreting monitoring data key information required

2 Trend
graphically
visible

1 X-axis

annotated with dates

FORM IS FUNCTION

4 Key plan
with instrumentation locations

5 Table
readings against Review Levels
09 May 2013

Land Transportation Excellence Awards 2011

Best Innovation Partner


Page 97

44

Instrumentation & Monitoring Quality Plan (1 of 2) Sufficient & Correct Instrumentation

Proper Installation & Establishment of Initial Readings


Monitoring Schedule Updated Regularly & Strictly Adhered To Readings Taken by Competent Technicians Proper Data Deduction & Verification Daily Results into Summary Format

09 May 2013

98

Instrumentation & Monitoring Quality Plan (2 of 2) Daily Trend Watch

Daily Check on Results Vs Review Levels


Weekly Reports with Tables, Trend Plots Regular Meetings among Key Personnel Full Participation of QP(S) & PE Increased Monitoring at High Risk Area Increased Monitoring at High Activity Area Prompt Replacement of Damaged Instruments Calibration of Tools as per Schedule Manual checks of automated real-time monitoring
09 May 2013 99

45

Challenges of Instrumentation & Monitoring


Key responses of ground and structures are monitored Correct type of instrumentation is used Review Levels are set for each instrumentation Monitoring frequency matched with site activities Prompt processing of monitored data Graphical outputs to visualized trends Responses are tracked against Review Levels Regular review of monitored readings with key personnel Relate to Continuous training of personnel involved

Voluminous Data

Timely

Interpretation

Monitor and Analyze trend


Graphical output

construction

activities

Tracking
Predicted Levels
against

09 May 2013

Page 100

THANK YOU

09 May 2013

46

You might also like