Professional Documents
Culture Documents
The Associated General Contractors of America (AGC) is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion are available on request. This program is registered with the AIA/CES for continuing professional education. As such it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
Copyright
This presentation and the materials provided are protected by U.S. and International copyright laws. Reproduction, distribution, display and use of the presentation or materials without written permission is prohibited. AGC of America, 2012
Course Description
In the world of design and construction the technological revolution started with the advent of computer analysis in the 70s and accelerated through the use of CAD in the 80s and 90s. BIM, Integrated Project Delivery, and Design Build are driving changes, that, if implemented effectively, offer the promise of reductions of up to 25% in cost and schedule relative to a project delivered by the conventional design-bid-build process. In structural engineering, the use of design models with construction level detail, HiDef BIM, and Functional Integrated Project Delivery to implement performance based engineering enables unprecedented reliability, coordination, and true lean construction based on actual labor, means, methods, and sequences. This technology is disruptive at its core and will require fundamental changes in the delivery process and scopes of services on the design side well beyond contractual arrangements.
Learning Objectives
Attendees will be able to identify achievable levels of detail (LOD) in design models. Attendees will be able to summarize the Integration prerequisites for incorporating construction level detail in a design model. Attendees will be able to identify the work flow for a vertically integrated design-construction process.
Insanity is doing the same thing over and over again and expecting different results
Albert Einstein, German born American Physicist 1879-1955
Luth Corollaries Corollary 1: If you want the same results, do the same thing. Corollary 2: If you want something better, do something different
HiDef BIM
Database of Information Knowledge Heuristics Shop Drawing Level Detail Concept to Facilities Clash avoidance Virtual Design & Construction ------ GIGO Effect ------
HiDef BIM
High Definition BIM (HiDef BIM) incorporates shop drawing level detail into the design model (AIA LOD = 5) There is only one BIM model, and it is used for all life cycle processes. During one short interval in the life cycle designconstruction the model is used to produce shop drawings and support design, fabrication, construction, and maintenance processes.
This requires explicit consideration of and provision for, means, methods, and sequences during the design phase.
This is possible today in structural engineering
HiDef BIM
This is a disruptive technology The design/construction processes must change to get maximum benefit from the technology. Scope shifts from construction to design Construction knowledge must be deployed to support design we pull the knowledge forward in the process In a complementary fashion, knowledge of design processes can inform construction facilitating the identification of the optimum vertically integrated solution
Functional IPD
f IPD: Incorporating detailed construction knowledge and planning into the design Means, methods, and sequencing Enabling details Prefabrication Precision
Knowing the details of both the design and construction facilitates true lean construction getting exactly the right resources in exactly the right place at exactly the right time.
Panelized Light Gage Roof Decreases Schedule Less Off Ground Work Acoustical Details Included Plywood, LG Studs 12 OC, Insulation, 2 Layers of ceiling Gyp Board
Savings: roof finished in 3 days 3 weeks exterior 3 weeks interior eliminated scaffolding
Decreased Schedule (with EOR detailing) Phase 1 6 weeks Phase 2 15 weeks (30% schedule) Saves Space On Site
Rebar hoops 4 O.C. in slit plates require precision in prefabrication & placing
Conventional Practice
Fixed price is an estimate based incomplete details. Subcontractors have to cover risk in price. Final quantities arent known until after shop drawings. Final price is adjusted through change order process based on revised estimates of concept drawings.
Isle of Capri Cape Girardeau Rebar modeling and Shop Drawings by EOR accelerated the schedule and resulted in higher quality end product. 2000 yd pour with 250 tons of rebar starting at 7 pm 2 weeks after award of concrete contract. Photo at noon on day of pour.f pour.
Conventional Practice
Construction sequence is determined by superintendent long after contract is awarded and detailed construction means and methods by the foreman of the trade involved. Quite often the details of the design have to be amended by the RFI process to tune the design to the eventual means and methods
Livermore Performing Arts Center Construction sequence 3D HiDef BIM visualization construction steps 1-4, concrete substructure and partial superstructure
Livermore Performing Arts Center Construction sequence 3D HiDef BIM visualization steps 5-8 at concept steel & facade
Livermore Performing Arts Center Roof truss with temporary construction bracing
Conventional Practice
The structural steel and rebar detailers have to interpret the SEORs intent in preparing complete shop drawings. Any question are resolved using the RFI process. The shop drawings have to be submitted to the SEOR to verify that the intent has been faithfully captured. Drawings are marked up by hand or manually in PDF and iterated until a clean set is produced. The process takes months.
A bonus is that constructibility conflicts are trapped and corrected during design. The EOR starts including constructibility as a basis of design.
Challenge: 10 Rouge fill & fast schedule Enabling Concepts Single pile foundations Prefabricated 5-piece cages detailed for quick install.
Conventional Practice
The process is cumbersome, fraught with opportunities for miscommunication, conflict, and abuse.
Design Build Team: Mortenson Construction Heery International Architecture Martino & Luth Structural Engineers
Volume of Water Storage on Roof Modeled Roof Slopes, Insulation, Crickets etc in HiDef BIM Made Solid called Water and Raised Up until Volume = Civil Engineer Calcs Determined Water Depth and Structural Design Load
Structural Model Sent To Steel Fabricator Zimmerman Metals Also on HiDef BIM Shop Drawing Creation Faster and Easier
3D Rebar Detailing
Rebar Takeoffs At DD
DD Quantity 375 Tons Used to Sign unit price Contract Shop Drawing Quantity 365 Tons (2.6% from DD)
Final Delivered Quantity 372 Tons (0.8% From DD, +1.9% from Detailed
Rebar Bar Lists for Fabrication (Typical Foundation Wall Shown) M&L worked with Rio Grande to produce a Bar List that was Compatible with their process. Fabricator Redlined and Checked our Bar list, vice versa from Normal
Coordinated Constructible Shop Drawings Produced Directly From the Model Every Member Modeled as it is and where it will go
IPD and HiDef BIM Concluding Remarks from an Architects Perspective Cliff Bourland
A more expansive view is required. IPD doesnt start with design and it doesnt end with construction. We need to elevate our goals.
Life Cycle savings should match those of construction. For example stop building throw away buildings We can design efficient buildings that can be managed efficiently, but only if the knowledge is passed from one phase to the next. Means and methods is not just about construction. The owner needs a Users Manual. And the general contractor is in the best position to provide it.
Our objective is to produce as the deliverable product of the design a model with sufficient detail and data to facilitate Lean Construction and Functional Integrated Project delivery today, using technology that is scalable to support Life Cycle Facility Management processes in the future.
Note the tower at the center of the site used to deliver concrete to all parts of the low rise building an early pumper. Note the plate girder over the car entries on the south side in the foreground.
The completed building includes the 8 story tower in foreground as well as a concert hall and bowling alley housed in the pop up immediately behind the tower. The construction was completed in 11 months by Whitney-Steen Engineers and Builders. By the time the photos were archived, Whitney-Steen had dropped the word Engineers from their name.
USC PII Building B Pivoting Wall Model, Shop Drawings, & Constructed
The World can no longer tolerate anything but the very best design and construction. We cannot afford less.
Natural disasters cost a record $380 billion in 2011 HiDEF BIM can propel the industry to achieve better results
20% OF THE WORLD POPULATION lives in or near an earthquake zone. MORE than 70% of that percentage is in poverty level socio-economic classes.
The Construction Model is the Facilities Management Model Construction/ Operations & Capital Projects Maintenance
As Built Intelligence & Building Performance Proforma O&M Guidelines/Requirements, Operational Standards
Capital Planning
Design
Construction
Facility Mgmt
Asset Mgmt
Space Mgmt
Lease Mgmt
Integrating people, processes and systems throughout the building lifecycle creates the opportunity for portfolio value optimization.
PROJECT TIMELINE
1/1/2010 4/1/2010 7/1/2010 7/1/20 010
Clash Detected Clash Detected SET-UP
DESIGN MODEL
NO Coordinated (No Clashes) NO Coordinated Architect YES YES YES Updated Issuance MEP (Revit / IFC) Collaborate Significant Issuance (Pre-Bid) Post Pos st Bid Upd Updates dates NO Suspended Su uspended
Family Place Holders Identify f Parameters fy Confirm Shared Parameters Populate as Applicable University Guidelines Attributes & Parameters
Owner / FMS
DESIGN MODEL
YES START YES Architect Civil (Civil 3D)
YES
Validate & Update Owner Requested Data / Parameters (Cx Agent or A&E)
NO
VALIDATE
CMMS
Manage Ma nag ge Model g Revision R Rev is sio on Control Model M Mod el S Standards Model Mo del l Content Le Lead ead Co Coordination oordination
CONSTRUCTION MODEL
Suspended NO PreConstruction Complete GC / Modeler Issue Update As Required (Monthly) YES Suspended Suspended
VALIDATE
EMS
END
Manage Model Revision Control Model Standards Model Content Lead Coordination
Collaborate
YES
Complete & Clashed: IFC & CAM Collaborated Navis Model (GC Owns)
10/1/2008 9/1/2008
1/1/2009
4/1/2009
7/1/2009
10/1/2009
1/1/2010
4/1/2010
7/1/2010
10/1/2010 12/31/2010
Questions?
Gregory P. Luth & Associates
Structural Engineers and Builders