CHAPTER 1 INTRODUCTION

With increasingly complex and sophisticated buildings and equipment, a single lightning stroke can result in physical damage and catastrophic failure. It can initiate fire, cause major failures to electrical, telephone and computer services and simultaneously cause substantial loss of revenue through down-time. There are no devices or methods capable of modifying the natural weather phenomena to the extent that they can prevent lightning discharges. Lightning flashes to, or nearby, structures (or lines connected to the structures) are hazardous to people, to the structures themselves, their contents and installations as well as to lines. This is why the application of lightning protection measures is essential. The lightning protection system is generally considered in two parts. The external lightning protection system intercepts, conducts and dissipates the lightning flash to earth. The internal lightning protection system prevents dangerous sparking within the structure (using equipotential bonding or separation distance) [6]. The design of a lightning protection system needs to: Intercept lightning flash (i.e. create a preferred point of strike) Conduct the lightning current to earth Dissipate current into the earth Create an equipotential bond to prevent hazardous potential differences between LPS, structure and internal elements/circuits In achieving this, the lightning protection system must: Not cause thermal or mechanical damage to the structure Not cause sparking which may cause fire or explosion Limit step and touch voltages to control the risk of injury to occupants Limit damage to internal electrical and electronic systems

Dept. of EEE

TEC, Vellarakkad

Lightning protection systems typically follow two approaches, Non-isolated system where

potentially damaging voltage differentials are limited by bonding the lightning protection system to the structure Isolated system where the

lightning protection system is isolated from the structure by a specified separation distance. This distance should be sufficient that energy is contained on the LPS and does not spark to the structure [6].
Fig. 1.1) Isolated and Non-Isolated protection

1.1 Step and touch voltages Touch voltage is the voltage acting upon a person between his position on the earth and the position of down conductor, when touching the down conductor. The current path leads from the hand via the body to the feet. Step voltage is a part of the earthing potential which can be bridged by a person taking a step over 1m. The current path runs via the human body from one foot to the other [7].

Fig. 1.2) Step and Touch voltage gradients

Dept. of EEE

TEC, Vellarakkad

1.2 Separation (isolation) distance requirements A separation distance,

between the external LPS and the structural metal parts is essentially required. This will minimize any chance of partial lightening
Fig. 1.3) Concept of separation distance

current

being

introduced internally in the structure. This can be achieved

by placing lightening conductors sufficiently far away from any conductive parts that have routes leading into the structure. So, if the lightening discharge strikes the lightening conductor, it cannot bridge the gap and flash over to the adjacent metal work.

Fig. 1.4) Bonding & separation distance

The separation distance between the item to be considered and the LPS (to ensure that the dangerous sparking between them does not occur) is determined by the following equation,

Dept. of EEE

TEC, Vellarakkad

Where, k i is a factor that depends upon the chosen lightning protection level. k c is a factor that depends upon the number of down-conductors (note that a range is given for 2 or more down-conductors, and depends on the current-sharing between down-conductors). k m is a factor that depends upon the electrical insulation material (1.0 for air, 0.5 for concrete and bricks). L is the length in meter, along the air-termination or down conductor, from the point being considered to the closest equipotential bonding point [1]. The values of k i , and k c are given in Tables 1.1 and 1.2.
Table 1.1) Values of k i

Table 1.2) Values of k c

1.3 Conclusion At present, photo voltaic cells have a growing demand as a renewable energy source. For the roof-top installation, PV panels are integrated to the new buildings and new constructions. This integration raise challenges in designing the building and also the PV system. A major issue arises in this case is the lightning protection of the building and PV system [1]. A single lightning stroke can damage the panels and cause substantial loss of money. Hence, available protection techniques for safeguarding the buildings against direct strikes are necessary to be evaluated to provide a safe location to install the PV system.

Dept. of EEE

TEC, Vellarakkad

CHAPTER 2 EXTERNAL LPS


2.1 Introduction External protection system of a building intercepts the direct lightning strikes by air termination system, conducts the lightning current through a low impedance path to the earth termination system, and disperses this high current to a low resistance earth. In following the challenges in designing these three components are discussed [1]. 2.2 Air termination system The role of an air termination system is to capture the lightning discharge current and dissipate it harmlessly to earth via the down conductor and earth termination system. Therefore it is vitally important to use a correctly designed air termination system [4]. The type of air termination system installed on the roof depends on the shape and materials of the roof and usage of the building. Also, the type of protection and the area which is critical to be protected influence the selection of air termination system. Considering these factors, the following in any combination can be used for the design of air termination, Air rods (or finials) whether they are free standing masts or linked with conductors to form a mesh on the roof. Catenary (or suspended) conductors, whether they are supported by free standing masts or linked with conductors to form a mesh on the roof. Meshed conductor network that may lie in direct contact with the roof or be suspended above it, so that the roof is not exposed to a direct lightening discharge. Positioning of the air termination system is of paramount importance. The air termination components should be installed on corners, exposed points and edges of the structure [4]. Three basic methods recommended for determining the optimum location of the air termination systems are, The rolling sphere method (RSM) The protection angle method (PAM) The mesh method (MM)

Dept. of EEE

TEC, Vellarakkad

2.2.1 The Rolling Sphere Method The rolling sphere method is a simple means of identifying areas of a structure that need protection, taking into account the possibility of side strikes to the structure. In this method, an imaginary sphere is rolled over the surface of the structure. Where the sphere touches the structure, this point is vulnerable to a lightning flash and airtermination(s) are required. The air-termination system is placed such that the sphere only touches the air-terminations, and not the structure [4][6]. Corresponding to the class of LPS, radius of the rolling sphere is different.
Table 2.1) Rolling sphere radius and class of LPS

Fig. 2.1) Rolling sphere method

For structures less than 60 m high the risk of flashes to the sides of the building is low, and therefore protection is not required for the vertical sides directly below protected areas.

Fig. 2.2) RSM for buildings less than 60 m high

Dept. of EEE

TEC, Vellarakkad

In the IEC standards, for buildings above 60 m, protection is required to the sides of the upper 20% of height.

Fig. 2.3) RSM for buildings greater than 60 m & less than 120m high.

Fig. 2.4) RSM for buildings greater than 120 m high

This method is suitable for defining zones of protection for all types of structures especially those of complex geometry [6].

Dept. of EEE

TEC, Vellarakkad

2.2.2 The Protective Angle Method The protective angle method is a mathematical simplification of the rolling sphere method. The protective angle (a) is the angle created between the tip (A) of the vertical rod and a line projected down to the surface on which the rod sits.

Fig. 2.5) PAM for a single air rod

Fig. 2.6) Effect of height of the reference plane on protection angle

Air-terminations (rods/masts and catenary wires) are located so the volume defined by the protection angle covers the structure to be protected. The height of the airtermination is measured from the top of the air-termination to the surface to be protected. The protective angle varies with the height of the air termination and the class of the LPS. The protection angle method is limited in application to heights that are equal to or less than the corresponding rolling sphere radius [4][6]. The protection angle method can be used on inclined surfaces, where the height of the rod is the vertical height, but the protection angle is referenced from a perpendicular line from the surface to the tip of the rod [6].
Fig. 2.7) PAM applied to an inclined surface.

Dept. of EEE

TEC, Vellarakkad

Where the protection angle method alone is employed, multiple rods are generally required for most structures. However the protection angle method is most commonly used to supplement the mesh method, providing protection to items protruding from the plane surface.

Fig. 2.8) Combination protection

2.2.3 The Mesh Method For protection of a plane (flat) surface, the mesh method is considered to protect the whole bound surface if meshed conductors are: Positioned on the edges (perimeter) of the surface The mesh size is in accordance with Table 2.2
Table 2.2) Mesh size for mesh method

No metallic structures protrude outside the volume (consider air-terminals and RSM/PAM method to protect these)

Dept. of EEE

TEC, Vellarakkad

From each point, at least two separate paths exist to ground (i.e. no dead ends), and these paths follow the most direct routes

Fig. 2.9) Protection via mesh method

The mesh method should not be used on curved surfaces, but can be used on nonhorizontal plane surfaces and compound surfaces [6]. For example on the vertical sides of tall buildings, for protection against flashes to the side, or on compound surfaces such as industrial roofs. For compound surfaces, conductors should be placed on the roof ridge lines if the slope exceeds 1/10.

Fig. 2.10) Mesh method for compound shapes

Dept. of EEE

10

TEC, Vellarakkad

The protective area provided by the mesh method is the area bounded by the mesh. The protection to areas adjacent to the mesh (e.g. building sides and lower structural points) is determined by the protection angle method or rolling sphere method. The protection provided by meshed conductors not placed in full accordance with the mesh method, e.g., those raised above the building surface, should be determined with an alternative design method, i.e., PAM or RSM, applied to the individual conductors.

Fig. 2.11) Volume protected by meshed conductors according to PAM & RSM method

2.3 Down conductor system The down conductor system is the electrically conductive connection between the air termination system and the earth termination system. The function of down conductor systems is to conduct the intercepted lightening current to the earth termination system without intolerable temperature rises to damage the structure. It can be implemented by separate conducting tapes/wires or natural components of the building such as reinforcing rods of walls or concrete columns and steel structured frames.

Dept. of EEE

11

TEC, Vellarakkad

To avoid damage caused during the lightening current discharge to the earth termination system, the down conductor systems must be mounted to ensure that from the point of strike to the earth, Provide multiple paths for lightning current. Be a direct continuation of the air-termination system. The length of the current paths is kept as short as possible (straight, vertical, no loops). Not be installed in gutters or down-spouts (even if PVC covered). The connections to conductive components of the structure are made wherever required (distance < s; s= separation distance). Connect via a test joint to the earth termination network. The general requirements for down-conductors on non- isolated LPS are: At least two down-conductors should be used. Down-conductors should be equally distributed around the perimeter of the structure (within practical and aesthetic reasons). Down-conductor should be located at exposed (external) corners of the structure where possible (within 300 mm). Attempt to locate down-conductors (using separation distance requirements) away from doors, window frames, railings etc. that would be subjected to human touch during thunderstorms periods. The typical values of the distance between down conductors are shown in Table 2.3. In case of tall structures bonding all down conductors at regular vertical intervals (say 20 m) may keep the system at equipotential [7].
Table 2.3) Typical spacing of down-conductors & equipotential bonding rings

Dept. of EEE

12

TEC, Vellarakkad

The general requirements for down-conductors in an isolated LPS are: For rod air-terminations, one down-conductor is required per mast. If the mast is metallic or interconnected reinforcing steel, then no additional down-conductor is required. For catenary air-terminations (one or more wires), at least one down-conductor is required per support. It should be noted that, down conductors must be installed straight and vertical, and they should not be installed in loops or as over hangs. If loops cannot be avoided, the separation distance across the gap must be greater than minimum separation, s. 2.4 Earth termination system The surge current flows through the down conductors will be dispersed to the soil by the earth termination system. Since the reliable performance of the entire lightning protection system is dependent upon an effective earthing system, it should possess the following characteristics, Low electrical resistance between the electrode and the earth. The lower the earth electrode resistance the more likely the lightening current will choose to flow down that path in preference to any other, allowing the current to be conducted safely to and dissipated in the earth. The general requirement is that the lightning protection earthing system must have a resistance of less than 10 ohms Good corrosion resistance. The choice of material for the earth electrode and its connections is of vital importance. It will be buried in soil for many years so has to be totally dependable. Design details are given on two methods: Type A Vertical and/or horizontal electrodes installed outside the structure footprint. Type B Ring electrode, installed outside the structure footprint (at a distance of about 1 meter from the structure walls. In a given ring conductor 80% of its length should be in contact with soil) or natural earth electrode within footprint (e.g. footing reinforcing).

Dept. of EEE

13

TEC, Vellarakkad

Fig. 2.12) Type A & B earthing systems

In type A system, there must be earth electrodes installed at the base of each downconductor. A minimum of two electrodes must be used. Depending on the class of the LPS, the minimum total length of electrode at each down-conductor is, (l 1 ) for horizontal electrodes and (0.5l 1 ) for vertical electrodes.

Fig. 2.13) Minimum length of electrodes, l1, for type A & B earthing systems

In type B system, a ring electrode around the perimeter of the structure, or natural elements within the foundation is used. A ring conductor should have a mean radius of distance r e l 1 .
Dept. of EEE 14 TEC, Vellarakkad

Where the distance r e would require the ring to be installed at a distance greater than 1 m from the structure, then it is recommended that the ring be installed at 1 m and additional supplemental horizontal or vertical electrodes are added per the following requirements. At least two equidistant supplemental electrodes should be installed and ideally connected at the each point where the down-conductors connect to the ring electrode. Additional horizontal electrode length at each down-conductor = l 1 - r e Additional vertical electrode length at each down-conductor = (l 1 - r e ) / 2

Fig. 2.14) Type B earthing system with additional elements

Type B is recommended for bare solid rock and for structures with extensive electronic systems or great risk of fire. Type B is preferential from the point of view of providing equipotential bonding between the down-conductors (assuming no ground level equipotential ring is used) and providing better potential control in the vicinity of conductive building walls. For structures with non-conducting walls (brickwork, wood, etc.), and no interconnection to foundation reinforcing, a type B system or earth equipotential bonding ring is highly recommended. 2.5 Conclusion An external LPS consists of Air termination system, Down conductor system and Earth termination system. These individual elements of an LPS should be connected together using appropriate lightning protection components satisfying the lightning protection standards. This will ensure that in the event of a lightning current discharge to the structure, the correct design and choice of components will minimize any potential damage.

Dept. of EEE

15

TEC, Vellarakkad

CHAPTER 3 INTERNAL LPS


3.1 Introduction In the event of lightning, the danger of direct strikes to the protected building is reduced by external lightning protection system, which facilitates the high inrush current to flow through multiple down conductor system and then disperse to the soil through the earth termination system. Apart from the direct strikes nearby strikes of lightning can also affect the electrical systems inside the building. This is due to surges that are generated by inductive coupling (rarely capacitive coupling as well). 3.2 Lightning protection zones The protection of electrical and electronic systems in buildings and structures against surges resulting from the lightening electromagnetic pulse (LEMP) is based on the principle of Lightening Protection Zones. According to this principle, the building or structure to be protected must be divided into internal Lightening Protection Zones according to the level of threat posed by LEMP. The zones may not necessarily be physical boundaries (e.g. structure walls). The zones are areas characterized according to threat of direct or indirect lightning flashes and full or partial electromagnetic field. The occurrence of lightning flashes, the lightning current or induced current and the electromagnetic field are varied in these different LPZs [2][6][7]. LPZ 0 (Zero) is considered the lowest zone, LPZ 1, 2n being respectively higher. In general the higher the number of zone the lower the electromagnetic effects expected. It is the design and placement of the LPS that ensures the structure and internal contents are within an LPZ 0B zone.
Table 3.1) Lightning protection zones

Dept. of EEE

16

TEC, Vellarakkad

Internal systems are required be located within an LPZ 1 (or higher) zone. As seen from Figure 3.1, electrical/electronic equipment located in LPZ 1 (or higher) and connecting to external services such as power lines, data lines and water and gas pipes (located in LPZ 0B or LPZ 0A) require transient protection devices (TPD) or Surge Protective Device (SPD) and spatial shielding or shielding cables, to limit energy being conducted from zones exposed to direct lightning or full/partial electromagnetic fields or surge current. Non electrical services (e.g. water, gas, etc.) meet this requirement by equipotential bonding [7].

Fig. 3.1) Lightning protection zone concept

At the boundary of each internal zone, the equipotential bonding must be carried out for all metal components and utility lines entering the building or structure. This is done directly or with suitable SPDs.

Dept. of EEE

17

TEC, Vellarakkad

3.3 Equipotential bonding Equipotential bonding is simply the electrical interconnection of all appropriate metallic installations/parts, such that in the event of lightening currents flowing, no metallic part is at a different voltage potential with respect to one another. If the metallic parts are essentially at the same potential then the risk of sparking or flashover is nullified. This electrical interconnection can be achieved by natural bonding or by using specific bonding conductors. Bonding can also be accomplished by the use of Surge Protective Devices (SPDs) where the direct connection with bonding conductors is not suitable.

Fig. 3.2) Example of main equipotential bonding

Figure 3.2 shows a typical example of an equipotential bonding arrangement. The gas, water and central heating system are all bonded directly to the equipotential bonding bar located inside but close to an outer wall near ground level. The power cable is bonded via a suitable SPD, upstream from the electric meter, to the equipotential bonding bar. This bonding bar should be located close to the Main Distribution Board (MDB) and also closely connected to the earth termination system with short length conductors [4][5].

Dept. of EEE

18

TEC, Vellarakkad

In larger or extended structures several bonding bars may be required but they should all be interconnected with each other. The screen of any antenna cable along with any shielded power supply to electronic appliances being routed into the structure should also be bonded at the equipotential bar [4]. 3.4 Conclusion The fundamental role of the internal LPS is to ensure the avoidance of dangerous sparking occurring within the structure to be protected. This could be due to following a lightning discharge, to lightning current flowing in the external LPS or indeed other conductive parts of the structure and attempting to flash or spark over to internal metallic installations. Carrying out appropriate equipotential bonding measures or ensuring there is a sufficient electrical insulation distance between the metallic parts can avoid dangerous sparking between different metallic parts.

Dept. of EEE

19

TEC, Vellarakkad

CHAPTER 4 LIGHTNING PROTECTION FOR ROOF-TOP PV SYSTEMS


4.1 Introduction Building Integrated Photo Voltaic (BIPV) system as a type of implementation of solar energy has a high demand at present. The assessment of risk of damage due to lightning for these systems is necessary as the systems are installed at significantly large heights and extended surface at such heights make these systems vulnerable to be intercepted with lightning stepped leaders. Therefore, the external LPS of BIPV systems must be designed by considering the PV panel on the roof top as well. 4.2 Design of Lightning Protection System To design suitable air termination system which is capable of protecting PV panels from direct strikes and induced effects several extra precautions should be taken by the designer. The roof should be protected considering the PV panel as an isolated system from the LPS. In this case extra care should be taken regarding the shape, height, and total configuration of panels. In addition, the separation distance of panels to the LPS is another specified issue. In designing the air termination system which consists of rods on the flat surface roofs by the protection angle method can be seen in Figure 4.1, the angle of the PV panels or the maximum angle of the moving panels should be taken into consideration; the protected area by the rod must cover the panel when the panel surface is rotated. In Figure 4.1, it can be observed that by the rolling sphere method the distance between each two rods in a row, also the distance between the rods in one row to the other row can be obtained. Further, in designing LPS, care should be taken to minimize the shadow effect of finials on panels which may reduce the efficiency of system [1].

Fig. 4.1) Protection of PV panels applying RSM and PAM Dept. of EEE 20 TEC, Vellarakkad

As shown in Figure 4.2, at least the minimum separation s should be kept between LPS and the panels frame (isolated LPS). Separation s should also be kept between the bonding conductor and PV panels mounting structure unless the LPS is bonded to the frames (non-isolated LPS) to be protected. The requirement of an isolated or nonisolated LPS depends on the sensitivity of the PV system for the stray lightning currents that will be diverted into the metal framework of the panel. Depending on the requirement of isolation or non-isolation of external LPS, other necessary components of the LPS (such as SPD) may be determined.

Fig. 4.2) Applying protection angle method for PV panels

An important aspect of external LPS in the presence of roof top PV system that has not been properly addressed in the LP standards is the mechanical stability of the vertical air-terminations. In the event of a mechanical failure of vertical air-termination (such as the whole rod being enrooted from the base or part of the upper segment detached from the main rod), the cost of damage may be highly enhanced if the fallen part lands on the PV system [1]. Damage may be even worse in the case of mechanical failure of early streamer emission (ESE) type air terminations (recommended in French Standards NF C 17-102 and Spanish Standards UNE-21186) where a heavy metal part is most often connected at the pinnacle of the rod. Authors have observed such damage to the roof of buildings in several countries including India and Malaysia.

Dept. of EEE

21

TEC, Vellarakkad

Hence, more stringent conditions should be introduced into the standards (or guidelines) on the mechanical strength of vertical air-terminations of LPS for buildings with roof top PV systems. These recommendations should cover the fixing strength of the base plate, material strength, weight of the rod etc. On the other hand, mesh type (horizontal tapes or wires) air-termination systems can strongly be recommended for such structures instead of vertical metal rods. Such design will also reduce the shadoweffect problem as well. The selection of SPDs for roof-top PV systems depends on the class of LPS for building and the isolation of PV panels frames from LPS, unless bonding the panel frames to the LPS makes the system non-isolated which changes the SPD type applicable for that PV system and sizes of earthing conductors that carry the lightning induced currents. DC wires are used to connect the output of PV panels to the inverter inside. Protection of DC wires in the LPZ1 is performed by SPDs that are connected before the inverter in DC side. If the separation distance between panels on the roof and inverter is more than 10 m, two sets of SPDs are required, one close to the PV modules and another one close to the inverter. Furthermore, one set of SPD is essential in the AC side. Also, if the distance between the inverter and load center is more than 10 m, one SPD is needed in the load center as well [1]. Figure 4.3 shows a roof top PV system with all components, the internal and external LPS.

Fig. 4.3) SPD connection for roof top PV system

Dept. of EEE

22

TEC, Vellarakkad

The types of SPDs applicable for the PV system can be selected according to the situation between the panels and LPS. For a roof-top PV system in a building without the external LPS, two sets of SPD type 2 are needed in the DC side and two sets of SPD type 2 in the AC side and load center (distance more than 10 m). In the roof-top PV system with external LPS, if the distances between air terminations and bonding conductors on the roof to the panels frame and mounting system are more than the separation distance S, the PV system can be kept isolated, in this case, two sets of SPD type 2 are required in the DC side and one SPD type 2 in the AC side close to the inverter, but the SPD in the AC load center should be selected from type 1. For the non-isolated PV system where the LPS is connected to the panels frames with a distance less than the separation distance S, two sets of SPDs type 2 are required in the DC side, but in the AC side of inverter one SPD type 1 must be installed close to the inverter and one SPD type 1 is also needed in the AC load center [1]. In order to reduce the dangerous sparking between the PV system components and to make the PV system equipotentialized, all SPDs and inverter equipment grounding must be bonded to the Equipotential bonding bar. This bonding bar should be connected to the main earthing bar close to the earth termination system. Also the panels frame must be connected directly to both the equipotential bonding bar and the main earth bonding bar. The sizes of earthing conductors which connect the components to the bonding bar are different depending on the volume of the induced current that may be carried through the conductor. Also, different dimensions of conductors are employed when the LPS is connected to the panel [1][7]. 4.3 Conclusion BIPV system is becoming an emerging trend in India. The PV panels are usually placed in the roofs of tall buildings so the chance of lightning strikes is large. To protect the panels, available protection techniques for safeguarding the buildings against direct strikes are to be evaluated to provide a safe location to install the PV system.

Dept. of EEE

23

TEC, Vellarakkad

CHAPTER 5 BIPV CASE STUDIES IN INDIA


5.1 Introduction The solar PV technology involves direct conversion of available solar energy into some useful electrical energy. It can realistically contribute to greater global sustainability in the medium to long term. PV is becoming more and more accessible both in urban and rural areas due to declining costs. Recently, there has been a worldwide focus on the architectural integration of PV modules in the building envelope. Such type of modules can effectively replace conventional building materials like roof tiles, shingles, facades, and normal glazing. PV building materials can be manufactured in a manner that they are quite similar to the conventional building products, blending well with the surrounding environment. 5.2 BIPV systems in India India with a tropical climate with sunny weather condition is a suitable area for installing PV systems. Rabi Rashmi Abasan (meaning a solar housing complex) is Indias first solar complex. This complex conceived by WBREDA (West Bengal Renewable Energy Development Agency) is located at New Town Kolkata and is spread over an area of 1.76 acres. There are 25 independent apartments in the complex, each of which has been provided with a rooftop solar PV system of 2 KWP capacity. Sixteen single crystal silicon modules of 125 WP have been put up in each case. Each house owner within the complex will produce his own power for domestic use and feed any surplus power into the local grid. He can also draw power from the grid as and when needed. The utility will pay the house owner and vice-versa on net monthly metering. Also great numbers of bungalows constructed in the country side provide opportunities to install the rooftop PV systems. The preference of bungalows instead of tall buildings normally with flat surface roofs are the lower height of the building and slopped roof. By installing PV panels on the bungalows roofs, the danger of lightning strikes shall be much less than tall apartments.
24

Dept. of EEE

TEC, Vellarakkad

Also the shading effects in most cases can be reduced because the panels are mounted above a height that is taller than trees or any other equipment on the ground. Furthermore, in the rooftop PV systems most of the wirings and all other equipments except panels can be imbedded inside the building with the separation distance to the LPS which can be protected against lightning [1]. Figure 5.1 and 5.2 show two BIPV projects in India, the slopped roof and the flat roof respectively.

Fig. 5.1) Slopped roof BIPV system

Fig. 5.2) Flat roof BIPV system

5.3 Conclusion Two types of BIPV projects in India are slopped roof and flat roof projects. The panels on the slopped roof are mounted directly on the roof without any mounting structure while in flat surfaced roofs the panels are mounted on bars with certain height fixed to structure; therefore, the height of the structure to be protected in the flat surface is higher. Hence, in such cases vertical type air-terminations become a must.

Dept. of EEE

25

TEC, Vellarakkad

CHAPTER 6 CONCLUSION
An efficient design of the LPS with a well-located PV panel provides high efficiency of power generation with minimized lightning risk. To design the external LPS, the type of PV system and the configuration of PV panel should be taken into account. The shape of the roof and location of the panel are also important factors in optimizing the LPS. It is recommended to design the required LPS for the PV system during the construction or pre-construction stage of the building, so that the efficiency of the protection system could be maximized. Wherever it is possible, mesh type air terminations are preferred over vertical rods to minimize mechanical damage in the case of air-termination failure and also to avoid shadow effect.

Dept. of EEE

26

TEC, Vellarakkad

CHAPTER 7 REFERENCES
[1] Narjes Fallah, Chandima Gomes, Mohd Zainal Abidin Ab Kadir, Ghasem Nourirad, Mina Baojahmadi, and Rebaz j.Ahmed Lightning Protection Techniques for RoofTop PV Systems IEEE 7th International Power Engineering and Optimization Conference (PEOCO2013), Langkawi, Malaysia June 2013. [2] IEC 62305-1: Protection against lightning Part 1: General principles, 2010. [3] IEC 62305-2: Protection against lightning Part 2: Risk management, 2010. [4] IEC 62305-3: Protection against Lightning Part 3: Physical damage to structures and life hazard, 2010. [5] IEC 62305-4: Protection against lightning Part 4: Electrical and electronic systems within structures, 2010. [6] Erico international corporationERITECH-Lightning Protection Handbook Designing to the IEC 62305 Series of Lightning Protection Standards. , 2010 [7] DEHN Lightning protection guide revised 2nd edition., 2007