You are on page 1of 58

PETRONAS TECHNICAL STANDARDS

DESIGN AND ENGINEERING PRACTICE

TECHNICAL SPECIFICATION

WELDABLE MARTENSITIC STAINLESS STEEL LINE PIPE FOR USE IN OIL AND GAS OPERATIONS (AMENDMENTS/SUPPLEMENTS TO API SPEC 5LC)

PTS 31.40.20.36 DECEMBER 2009

2010 PETROLIAM NASIONAL BERHAD (PETRONAS) All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

Revision History Rev No.


1

Reviewed by
Noor Syamiza Abdul Malik Syahrizad Mohd Yunus

Approved by
Abu Bakar Mohd Arif

Date

PREFACE PETRONAS Technical Standards (PTS) publications reflect the views, at the time of publication, of PETRONAS OPUs/Divisions. They are based on the experience acquired during the involvement with the design, construction, operation and maintenance of processing units and facilities. Where appropriate they are based on, or reference is made to, national and international standards and codes of practice. The objective is to set the recommended standard for good technical practice to be applied by PETRONAS' OPUs in oil and gas production facilities, refineries, gas processing plants, chemical plants, marketing facilities or any other such facility, and thereby to achieve maximum technical and economic benefit from standardisation. The information set forth in these publications is provided to users for their consideration and decision to implement. This is of particular importance where PTS may not cover every requirement or diversity of condition at each locality. The system of PTS is expected to be sufficiently flexible to allow individual operating units to adapt the information set forth in PTS to their own environment and requirements. When Contractors or Manufacturers/Suppliers use PTS they shall be solely responsible for the quality of work and the attainment of the required design and engineering standards. In particular, for those requirements not specifically covered, the Principal will expect them to follow those design and engineering practices which will achieve the same level of integrity as reflected in the PTS. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal or its technical advisor. The right to use PTS rests with three categories of users : 1) PETRONAS and its affiliates. 2) Other parties who are authorised to use PTS subject to appropriate contractual arrangements. 3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) and 2) which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said users comply with the relevant standards. Subject to any particular terms and conditions as may be set forth in specific agreements with users, PETRONAS disclaims any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person whomsoever as a result of or in connection with the use, application or implementation of any PTS, combination of PTS or any part thereof. The benefit of this disclaimer shall inure in all respects to PETRONAS and/or any company affiliated to PETRONAS that may issue PTS or require the use of PTS. Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, PTS shall not, without the prior written consent of PETRONAS, be disclosed by users to any company or person whomsoever and the PTS shall be used exclusively for the purpose they have been provided to the user. They shall be returned after use, including any copies which shall only be made by users with the express prior written consent of PETRONAS. The copyright of PTS vests in PETRONAS. Users shall arrange for PTS to be held in safe custody and PETRONAS may at any time require information satisfactory to PETRONAS in order to ascertain how users implement this requirement.

TABLE OF CONTENTS PART I INTRODUCTION 1.1 SCOPE

1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS 1.3 DEFINITIONS 1.4 ABBREVIATIONS 1.5 CROSS-REFERENCES 1.6 ITEMS TO BE SPECIFIED/AGREED BY THE PRINCIPAL

PART II AMENDMENTS/SUPPLEMENTS TO API SPEC 5LC 1. SCOPE

1.1 COVERAGE 1.2 METRIC UNITS 1.3 MEASURING DEVICES 1.4 SPECIAL PROCESSES 1.5 CERTIFICATION 1.6 QUALITY SYSTEM 2. REFERENCED STANDARDS

2.1 GENERAL 2.3 3. 3.1 3.4 3.5 4. 5. 5.1 5.2 5.3 5.4 EQUIVALENT STANDARDS DEFINITIONS AND TERMS HEAT INSPECTION LOT INSPECTION LOT SIZE MISCELLANEOUS - RETENTION OF RECORDS PROCESS OF MANUFACTURE AND MATERIAL PROCESS OF MANUFACTURE COLD EXPANSION HEAT TREATMENT TRACEABILITY

6. 6.1 6.2 6.3 6.6 7. 7.1 7.2 7.3 7.4 7.5 7.6 7.13 7.15 7.17 7.19 7.20 7.21 7.22 7.23 8. 8.1 8.2 9. 9.1 9.3 9.4 10. 10.1 10.2

CHEMICAL PROPERTIES AND TESTS COMPOSITION HEAT ANALYSES PRODUCT ANALYSES CHEMICAL ANALYSES PROCEDURE MECHANICAL PROPERTIES AND TESTS MECHANICAL PROPERTIES TENSILE TESTS - GENERAL TENSILE TESTING LONGITUDINAL TENSILE TESTS TRANSVERSE TENSILE TESTS WELD TENSILE TESTS FLATTENING TESTS GUIDED-BEND TEST WELD DUCTILITY TEST FOR ELECTRIC-WELDED PIPE CENTRIFUGALLY-CAST HOMOGENEITY TEST HARDNESS TESTS RETESTS (HARDNESS) CHARPY IMPACT TESTING CHARPY RETESTS SPECIAL TESTS CTOD TESTING RESIDUAL MAGNETISM HYDROSTATIC TESTS INSPECTION HYDROSTATIC TEST TEST PRESSURES SUPPLEMENTARY HYDROSTATIC TESTS DIMENSIONS, WEIGHTS, AND LENGTHS DIMENSIONS AND WEIGHTS DIAMETER

10.3 10.5 10.7 10.8 11. 11.1 11.2 11.3 11.4 11.5 11.6 11.7 11.8 11.9

WALL THICKNESS LENGTH JOINTERS PIPE ENDS NON-DESTRUCTIVE INSPECTION INSPECTION METHODS FOR WELDED PIPE INSPECTION METHODS FOR SEAMLESS PIPE INSPECTION METHODS FOR CENTRIFUGALLY-CAST PIPE RADIOLOGICAL INSPECTION EQUIPMENT FLUOROSCOPIC OPERATOR QUALIFICATION OPERATOR CERTIFICATION REFERENCE STANDARD ISO WIRE PENETRAMETER FREQUENCY

11.10 PROCEDURE FOR EVALUATING IN-MOTION OPERATION OF THE FLUOROSCOPE 11.11 ACCEPTANCE LIMITS 11.12 IMPERFECTIONS 11.13 DEFECTS 11.14 WELD REPAIR 11.15 ULTRASONIC AND ELECTROMAGNETIC INSPECTION OF WELDED PIPE 11.16 ULTRASONIC AND ELECTROMAGNETIC INSPECTION OF SEAMLESS PIPE 11.17 ULTRASONIC INSPECTION OF CENTRIFUGALLY-CAST PIPE 11.18 TESTING OF BEVEL FACES 11.19 NDT PERSONNEL QUALIFICATION 12. 12.2 12.4 12.5 12.6 12.7 WORKMANSHIP, VISUAL INSPECTION, AND REPAIR OF DEFECTS PURCHASER INSPECTION VISUAL INSPECTION DEFECTS REPAIR OF DEFECTS PROCEDURE FOR REPAIR OF WELD SEAMS OF SUBMERGED-ARC WELDED PIPE

12.8 12.9

PROCEDURE FOR REPAIR OF WELD SEAMS OF ELECTRIC-WELDED AND INDUCTIONWELDED PIPE PROCEDURE FOR REPAIR OF WELD SEAM OF GAS METAL-ARC WELDED PIPE

12.10 GAUGE PIG 13. 13.1 13.2 13.3 13.5 13.6 14. 14.1 14.2 14.3 14.4 15. 15.1 15.2 15.3 16. 16.1 16.2 16.3 16.4 16.5 MARKING AND SURFACE TREATMENT MARKING - GENERAL LOCATION OF MARKINGS SEQUENCE OF MARKINGS DIE STAMPING SURFACE TREATMENT STORAGE, HANDLING, AND PACKING HANDLING STORAGE PACKAGING TRANSPORTATION DOCUMENTATION LANGUAGE PRE-MANUFACTURING DOCUMENTATION SHIPPING DOCUMENTATION FIRST-DAY-PRODUCTION TESTS GENERAL NON-DESTRUCTIVE TESTING CHEMICAL COMPOSITION MECHANICAL TESTING SPECIAL TESTS

APPENDIX A REPAIR WELDING PROCEDURE A.1 A.2 GENERAL REPAIR WELDING PROCEDURE QUALIFICATION

APPENDIX F PURCHASER INSPECTION PART III REFERENC

PART I INTRODUCTION 1.1 SCOPE This new PTS specifies requirements and gives recommendations for the purchase of both seam-welded and seamless weldable martensitic stainless steel (known generically as weldable 13Cr and weldable Super 13Cr) line pipe for use in oil and gas operations. The requirements are considered necessary to maintain technical integrity of pipelines and to ensure that a suitable specification exists in the absence of standardised grades of these materials.
NOTE: This PTS applies under non-sour conditions. The PETRONAS definition of sour service is given in PTS 31.22.20.31, however, as the application limits of these materials have not yet been determined, qualification testing in project-specific environments may be required even when the expected H2S is insufficient to give a sour service definition.

Part II of this PTS gives amendments and supplements to API Spec 5LC Third Edition July 1998 (Reaffirm 2006) and shall be read and used in conjunction with that document. The section numbering in Part II follows that of API Spec 5LC. Where sections of API Spec 5LC are not amended or supplemented by this PTS, they shall apply as written.
NOTE: Both API Spec 5LC and this PTS adopt sampling as a method to determine batch compliance. Nevertheless, all pipes supplied shall meet all requirements of this PTS.

1.2

DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS Unless otherwise authorised by PETRONAS, the distribution of this PTS is confined to companies forming part of the PETRONAS Group or managed by a Group company, and to Contractors and Manufacturers/Suppliers nominated by them. This PTS is intended to be used for the purchase of line pipe for the construction of oil and gas production flowlines and related facilities. If national and/or local regulations exist in which some of the requirements may be more stringent than in this PTS, the Contractor shall determine by careful scrutiny which of the requirements are the more stringent and which combination of requirements will be acceptable as regards safety, environmental, economic and legal aspects. In all cases the Contractor shall inform the Principal of any deviation from the requirements of this PTS which is considered to be necessary in order to comply with national and/or local regulations. The Principal may then negotiate with the Authorities concerned with the object of obtaining agreement to follow this PTS as closely as possible.

1.3 1.3.1

DEFINITIONS General definitions

The Contractor is the party, which carries out all or part of the design, engineering, procurement, construction, commissioning or management of a project, or operation or maintenance of a facility. The Principal may undertake all or part of the duties of the Contractor. The Manufacturer/Supplier is the party, which manufactures or supplies equipment and services to perform the duties specified by the Contractor. The Principal is the party, which initiates the project and ultimately pays for its design and construction. The Principal will generally specify the technical requirements. The Principal may also include an agent or consultant authorised to act for, and on behalf of, the Principal. The word shall indicates a requirement. The word should indicates a recommendation.

1.3.2 Specific definitions Defect (in NDT) A discontinuity or group of discontinuities whose indication(s) do not meet specified acceptance criteria. Term used in API 5LC, which shall be understood to mean HFW. An interruption, which may be either intentional or unintentional, in the physical structure or configuration of a pipe. Evidence of an imperfection that requires interpretation to determine its significance. Complete pipe segment of 100 mm length measured from the end face of the finished pipe. The flat starting material for welded pipe before forming into the shape of a pipe. Term used in API Spec 5LC, which has the same meaning as Principal. A Manufacturer whose product has been previously demonstrated to be suitable for the intended service, and formally accepted by the Principal. Term used in API Spec 5LC which has the same meaning as radiographic. The term radiographic is used in this PTS.

Electric welded Imperfection (in NDT)

Indication (in NDT)

Pipe end

Plate or strip

Purchaser

Qualified Manufacturer

Radiological

1.4

ABBREVIATIONS CTOD -Crack Tip Opening Displacement DN -Nominal Diameter FL -Fusion Line GTAW -Gas Tungsten Arc Welding HAZ -Heat Affected Zone HFW -High Frequency Welded ID -Internal Diameter KV -Charpy V-notch impact energy LBW -Laser Beam Welded MT -Magnetic particle testing NDT -Non-destructive testing OD -Outside Diameter PAW -Plasma Arc Welded PT -Liquid penetrant testing RT -Radiographic Testing SAW -Submerged Arc Welding SMAW -Shielded Metal Arc Welding UT -Ultrasonic Testing WCL -Weld Centreline WPS -Welding Procedure Specification

1.5

CROSS-REFERENCES Where cross-references to other parts of this PTS are made, the referenced section is shown in brackets. Other documents referenced by this PTS are listed in (Part III).

1.6

ITEMS TO BE SPECIFIED/AGREED BY THE PRINCIPAL The following information should be provided by the Principal at the enquiry stage of the order: -Nominal ID (and whether constant ID is required); -Minimum design temperature; -Maximum design temperature; - Design pressure; -Service environment (gas, oil, water, multiphase, sour, non-sour); -End preparation required if different from the standard API bevel; -Whether pipe is to be used as mother pipe for induction bends; -Whether mechanical property restrictions for reeling are to be applied; -Whether elevated temperature tensile testing is required and the acceptance criteria; -Requirement for mechanical tests in simulated post-weld heat-treated condition; -Length requirements if different from (Part II - 10.5) of this PTS; -Whether supply of jointers is acceptable and the welding requirements if different from this PTS; -Whether the passage of a gauge pig is necessary; -Which of the Manufacturer/Suppliers quality control procedures are to be submitted for agreement; -Time period for submission of contract quality plan; -Level of inspection to be deployed by the Principal; -Whether inspection reports in accordance with ISO 10474 type 3.2 are required instead of inspection certificates in accordance with ISO 10474 type 3.1.B; -Specific marking requirements; -Specific packaging requirements; -Other specific requirements amending or supplementing this PTS.

PART II AMENDMENTS/SUPPLEMENTS TO API SPEC 5LC 1. 1.1 SCOPE COVERAGE Delete this section and replace with the following: This specification covers the supply of proprietary grades of welded and seamless martensitic stainless steel line pipe by qualified Manufacturers/Suppliers. The primary product is bevelled pipe having a standard API bevel. Should a different end finish be required, it shall be clearly stated by the Principal in the contract document. Manufacturers/Suppliers should have satisfactorily qualified their products in accordance with the upstream qualification requirements detailed in report SIEP 975763. Alternative data may also be considered by the Principal for qualifying a Manufacturer/Supplier. 1.2 METRIC UNITS Replace first paragraph with the following: Metric units are used throughout this specification. 1.3 MEASURING DEVICES Delete this section and replace with the following: The Manufacturer/Supplier shall control measuring devices within the requirements of ISO 10012-1. 1.4 SPECIAL PROCESSES Delete the part of the table pertaining to centrifugally-cast pipe. Delete reference to repair welding procedures and add the following text: Applicable special processes shall also include those identified and documented in the quality assurance system of the Manufacturer/Supplier. Procedures for all special processes shall be produced by the Manufacturer/Supplier and supplied to the Principal (see Part II Section 15) when requested. 1.5 CERTIFICATION Delete this section and replace with the following: Inspection certificates in accordance with ISO 10474 type 3.1.B shall be supplied unless the Principal specifies inspection reports in accordance with ISO 10474 type 3.2., in which case the Manufacturer/Supplier shall issue and validate the inspection reports and they shall be counter-validated by the Principals authorised representative. The Manufacturer/Supplier shall provide a listing of all pipes supplied detailing for each pipe the unique pipe number, heat number, test number,

certificate number, length and weight. These data shall also be supplied to the Principal on a computer disc in an agreed format. Add new section: 1.6 QUALITY SYSTEM The Manufacturer/Supplier should maintain and operate a quality management system in accordance with ISO 9001 or ISO 9002 or an alternative standard if approved by the Principal. The quality assurance system shall employ statistical process control and have documented procedures for its application.

2. 2.1

REFERENCED STANDARDS GENERAL Add the following: See also (Part III) of this PTS.

2.3

EQUIVALENT STANDARDS Delete this section.

3. 3.1

DEFINITIONS AND TERMS HEAT Add to the existing section: Where the size of the secondary refining vessel is less than that of the primary steel producing vessel, the heat shall be considered to be the metal produced by a single cycle of the secondary refining vessel.

3.4

INSPECTION LOT Delete this section and replace with the following: A unit of pipes from the same heat and, for batch heat treatment, heat treatment batch, having the same dimensions.

3.5

INSPECTION LOT SIZE Delete this section and replace with the following: For pipes with OD < 508 mm, the maximum lot size shall be 100 pipes. For other sizes, the maximum lot size shall be 50 pipes.

4.

MISCELLANEOUS - RETENTION OF RECORDS Amend the second sentence of the first paragraph as follows: Contract records, and any others requiring retention by the Manufacturer/Supplier's quality assurance system, shall be retained by the Manufacturer/Supplier and shall be made available to the Principal upon request for a period of five years after completion of the order.

5.

PROCESS OF MANUFACTURE AND MATERIAL PROCESS OF MANUFACTURE Delete the first paragraph and replace with the following: Pipe furnished to this specification shall be seamless or welded manufacture as defined below. Welded pipe shall be welded using the processes described below. Combination welded pipe shall be subject to the limitations given in item 6. The manufacturing process shall be described in accordance with the requirements of (15.2.2) and the material produced by the process shall have been prequalified in accordance with SIEP 97-5763. Plates or strip shall be formed into pipe at ambient temperature. a. Seamless and Centrifugally-Cast. 1. Seamless is defined as wrought tubular product made without a welded seam. It is manufactured by hot working steel or, if necessary, by subsequently cold finishing the hot worked product. b. Welded processes 1. Without filler metal Place the existing text under a new sub-heading: a. High Frequency Welding The HFW process shall employ a minimum frequency of 150 kHz. b. Laser beam welding A welding process that produces coalescence with the heat from a laser beam focussed on the joint. The beam provide a concentrate heat source for narrow , deep welds and high welding rates.
NOTE process. Some Manufacturer/Suppliers may use HFW equipment to provide preheating for the laser welding

2. With filler metal Delete sub-section (b) relating to Gas Metal-Arc Welding. c. Pipe making processes 2. Centrifugally cast Delete this sub-section.

4. Submerged-arc. Submerged-arc welded pipe is defined as having one longitudinal seam produced by the automatic submerged-arc welding process as defined in 5.1.b.2.a. At least one pass shall be deposited on the inside and one pass on the outside. The full length of the weld seam shall be made by the automatic submerged-arc process, using run-on and run-off tabs. 6. Combination welding Delete or double and add the following to this section: Only PAW/GTAW combination welded joints are permitted by this specification. 7.0 Double seam Double seam welded pipe is not permitted. Add new sub-section 8. as follows: 8. Laser beam welding. Laser beam welded pipe is defined as having one longitudinal seam produced by the LBW process as defined in (5.1.b.1.b). d. Tack welding Add the following: Tack welding shall be continuous. Add new item as follows:. e. Jointer weld A jointer weld is a circumferential seam weld that joints two piece of pipes together f. Strip end weld A strip end weld is a weld that joins strip ends together thus permitting continuous longitudinal welding of the strip. Strip end welds shall not be included in the final pipe length. Table 2 Delete this table.

5.2

COLD EXPANSION Delete this section and replace with the following: Where appropriate, welded pipe shall be subjected to cold mechanical expansion. Expansion shall be maintained between 0.8 % and 1.5 %. The % expansion is defined as follows:

Da = OD (ID) after expansion Db = OD (ID) before expansion Sizing of seamless and welded pipe by cold reduction shall be limited to 1.5 %. 5.3 HEAT TREATMENT Delete this section and replace with the following: All pipe shall be supplied in the quenched and tempered condition. The coiled strip and/or pipe shall be heat treated in accordance with the Manufacturer/Supplier's documented heat treatment procedure. Pipe temperatures shall be verified by recorded measurement and the measurements shall be included in the quality records. The coiling temperature shall be agreed between the Principal and the Manufacturer. The tolerance on the tempering soaking temperature shall be 15 C. 5.4 TRACEABILITY Add the following: The Manufacturer/Supplier's procedure shall be documented and shall ensure that any length of pipe can be traced to the correct heat/lot and the associated inspection certificates. Each pipe shall be assigned a unique identification number, which shall either be stamped at both ends with low stress die stamps or stencilled onto the pipe as specified by the Principal.
NOTE: Attention is drawn to clause 4 of ISO 10474 regarding supply of certificates by an intermediary processor.

6. 6.1

CHEMICAL PROPERTIES AND TESTS COMPOSITION Delete this section and replace with the following: The composition of the pipe determined by heat and product analysis shall be in accordance with that specified by the Principal in the contract document. The Principal shall specify a composition previously qualified by the Manufacturer/Supplier in accordance with SIEP 97-5763. The primary elements, which shall be determined, are: C, Mn, P, S, Si, Ni, Cr, Mo, N, Cu, intentional additions.

6.2

HEAT ANALYSES Delete first sentence and replace with the following: The Manufacturer/Supplier shall furnish a certificate giving the heat analysis for each heat of material applied to the order.

6.3

PRODUCT ANALYSES Delete this section and replace with the following: Product analyses shall be provided to the Principal in the inspection document. The frequency shall be two pipes per heat. Samples shall be taken from formed pipe or tensile tests specimens extracted from formed pipe. In addition to the base metal chemical analyses, an analysis shall be performed on the weld metal of pipe welded with filler metal. This test shall be performed on the first-dayproduction test pipes and once every 100 pipes during production. The composition shall comply with that specified by the Principal in the contract document within the permissible variations in product analysis given in (Table 3).

Table 3 Delete existing Table 3 and replace with the following: Table 3. Permissible variations for product analysis of 13 % Cr line pipe Element C Mn Si P S Cr Ni Mo N Other alloying elemens Permissible variation 0.01 0.04 0.05 0.005 0.005 0.15 0.10 0.10 0.03 0.02

6.6

CHEMICAL ANALYSES PROCEDURES Methods of Analysis methods and practices relating to chemical analysis shall be performed in accordance with ASTM A751, Standard Methods, Practices and Definitions for Chemical Analysis of Steel Products .Calibrations performed shall be traceable to established standards.

7. 7.1

MECHANICAL PROPERTIES AND TESTS MECHANICAL PROPERTIES Delete this section and replace with the following: The pipe material shall conform to the following mechanical property requirements at room temperature: Tensile requirements Yield strength (Rt0.5) range 550 - 700 MPa Tensile strength minimum MPa 700 Elongation minimum % 20 Yield-to-tensile ratio maximum 0.90

NOTE: Rt0.5 is the yield strength for 0.5 % total elongation.

7.2

TENSILE TESTS - GENERAL Add the following: Where guaranteed elevated-temperature properties are required, the Principal shall state the test temperature and the property requirements in the contract document. If post-weld heat treatment of field welds will be performed, additional specimens shall be tested in the simulated post-weld heat-treated condition. The acceptance criteria shall be as specified in (7.1). The Principal shall indicate whether post-weld heat treatment is to be performed in the contract document. The Manufacturer/Supplier shall advise the Principal of the correct post-weld heattreatment thermal cycle to maintain the required properties, including elevatedtemperature properties, of the pipe material.

7.3

TENSILE TESTING a. Frequency Delete this sub-section including Table 7, and replace with the following: One transverse and one longitudinal tensile test from each first-day-production test pipe and one pipe per lot shall be performed at room temperature. In addition, if elevated-temperature testing is specified by the Principal, one elevated-temperature transverse tensile test shall be performed on each first-dayproduction test pipe and on one pipe per lot.

7.4

LONGITUDINAL TENSILE TESTS Delete this section and replace with the following: Longitudinal tensile test specimens shall be either non-flattened strip or round bar.

7.5

TRANSVERSE TENSILE TESTS Delete first paragraph and items a. and b. and replace with the following: Transverse tensile properties shall be determined by flattened strip specimen. Where pipe dimensions preclude the use of a strip specimen, round bar specimens may be used with the agreement of the Principal.

7.6

WELD TENSILE TESTS Delete "as specified in Table 7" from the first sentence.

Delete the second sentence and replace with the following: All weld reinforcement shall be removed. 7.13 FLATTENING TESTS Add the following to the second paragraph: The acceptance criterion for the second stage flattening shall be no evidence of lamination or other imperfections. 7.15 GUIDED-BEND TEST Amend the equation in Figure 5 as follows:

7.17

WELD DUCTILITY TEST FOR ELECTRIC-WELDED PIPE Delete section from the start of the 4th sentence and replace as follows: No cracks or breaks shall occur in the weld or parent material during flattening of the test specimen to 50 % of its original OD. Liquid Penetrant or microscopic examination shall be used to confirm the absence of cracking. Cracks which originate from the edge of the specimen and which are less than 6 mm long shall not be cause for rejection. The test frequency shall be once per lot of pipes.

7.19

CENTRIFUGALLY-CAST HOMOGENEITY TEST Delete this section.

7.20

HARDNESS TESTS Delete this section and replace with the following:

7.20.1 Seamless pipe A full circumferential section shall be taken as a sample from each first-dayproduction test pipe and from one pipe representing each lot. Hardness measurements shall be performed in accordance with ISO6507-1 on three polished and etched specimens taken at 120 intervals around the circumference of the sample. Traverses shall be as shown in Figure 6 of API Spec 5LC. For pipe with wall thickness of 8 mm and greater, three hardness traverses shall be made on each specimen: 2 mm from the outer surface; mid-thickness; and 2 mm from the inner surface. Each traverse shall contain three readings spaced at 5 mm intervals. The average of each of the three readings shall be the hardness value. For pipe with wall thickness less than 8 mm only two traverses, each 2 mm from the surfaces shall be required. The acceptance criterion shall be a maximum hardness value of 325 HV10. 7.20.2 Longitudinally welded pipe a. Macrographic examination Two full thickness transverse samples shall be extracted from the longitudinal weld from each first-day-production test pipe and from one pipe representing each lot. Test pieces from the samples shall be polished and etched for macro-examination in accordance with ASTM E 340. The examination shall be performed at a minimum magnification of x5. The acceptance criterion shall be no defects as defined by this PTS. Photomacrographs shall be included in the inspection documents. b. Hardness testing A series of Vickers HV10 hardness indentations shall be made in accordance with EN 1043-1 on one of the test pieces prepared for macro-examination from each of the first-day-production test pipes and from one pipe representing each lot. The hardness indentation locations shall be agreed by the Principal. The indentations shall be visible in the photomacrographs. For pipe with wall thickness of 8 mm or greater, three traverses shall be made, one 2 mm from the outer surface, the second across the centreline of the weld and the third 2 mm from the inner surface. The centreline traverse may be omitted for pipe
o

of wall thickness less than 8 mm. The indentations shall be visible in the photomacrographs. No individual hardness value shall exceed the following: Base material 325 HV10 Weld metal and HAZ 350 HV10. Add new section: 7.21 RETESTS (HARDNESS) Should a maximum of one hardness value per pipe exceed 325 HV10, a further three indents shall be made in the proximity of the original indents so that there is no interference between them. All three extra readings shall have a hardness value less than 325 HV10. Should any of these extra readings exceed 325 HV10 then a further test ring shall be cropped from the pipe for hardness testing and, in addition, two further pipes from the heat shall be hardness-tested. Should any of these further readings exceed 325 HV10, then the heat shall be rejected or all individual pipes shall be tested for acceptance. Add new section: 7.22 CHARPY IMPACT TESTING One pipe per lot shall be subjected to Charpy impact testing in accordance with ISO 148-2. Both absorbed energy and percentage shear area shall be measured. The test specimens may be extracted from the test rings taken for tensile and hardness testing. If stress relieving of the pipe is required by the Principal, the tests shall also be performed on pipe in the stress-relieved condition. Tests shall be performed on specimens taken from the mid-thickness position at the locations shown in the following table: Pipe type Base meta l X X X X X WCL Location FL FL+2 FL+5

Seamless SAW HFW (1) PAW & GTAW LBW (1)

X X X X

X X

X X X X

(1) For HFW and LBW pipe, the FL+2 tests may be replaced by tests taken from the WCL+2 position

A set of three specimens from each pipe shall be tested at the following test temperature: Nominal Pipe Wall Thickness t Mm t < 16 16 < t < 25 25 < t < 32 t > 32 Test Temperature oC T T-10 T-20 T-30 Max Test Temperature oC 0 0 0 0

If T is not specified by the Principal in the contract document, the test temperature shall be taken as 0 C. The descending hierarchy of specimen size and orientation shall be as follows: Choice 1 2 3 4 5 6 Orientation Transverse Transverse Transverse Longitudinal Longitudinal Longitudinal Size mm 10 x 10 10 x 7.5 10 x 5 10 x 10 10 x 7.5 10 x 5

Lower choice specimens shall only be used when the higher choice is impractical. For pipe of wall thickness less than 5 mm, Charpy testing may be omitted. The acceptance criteria for the different specimen sizes and orientations shall be as follows: Size mm 10 x 10 10 x 7.5 10 x 5 10 x 10 10 x 7.5 10 x 5 Orientation Min. average Min. individual absorbed energy absorbed energy J J 60 45 48 33 90 72 50 36 25 68 54 38

Transverse Transverse Transverse Longitudinal Longitudinal Longitudinal

The individual minimum shear area for base metal shall be 100 %. For weld metal and HAZ specimens, the individual minimum shear area shall be 50 %. Add new section: 7.23 CHARPY RETESTS If tests fail to meet the specified requirements, the sampled pipe shall be rejected. Two further pipes from the lot shall then be tested. If the results of both of these further tests are satisfactory no further testing is required and the lot shall be accepted. Should one or both pipes be unsatisfactory, the lot of pipes shall be rejected.

8.

SPECIAL TESTS Delete this section and replace with the following:

8.1

CTOD TESTING If the pipe wall thickness exceeds 12.5 mm, CTOD testing shall be performed on the three pipes selected for first-day-production tests. The test method shall be in accordance with BS 7448 Parts 1 and 2. Rectangular Bx2B specimens shall be used where B shall be as close to the full wall thickness as possible allowing for machining requirements. The specimen orientation shall be NP. One set of three test pieces shall be cut from each pipe with the notches placed at the weld centreline. A further set of three specimens shall be cut with the notch placed in unaffected base material. If the pipe diameter prevents the extraction of 10 mm thick specimens, the requirement for CTOD testing shall be waived. The test temperature shall be T or 0 C whichever is lower. The acceptance criterion shall be a minimum CTOD value of 0.15 mm.

8.2

RESIDUAL MAGNETISM Three pipes per heat shall be tested for residual magnetism in their final delivery condition. The maximum value of residual magnetism shall be 20 Gauss. Where the residual magnetism of any sampled pipe exceeds 20 Gauss, the pipe shall be subjected to degaussing operations and all remaining pipes from the heat shall then be checked and degaussed as necessary. The results of residual magnetism checks shall be recorded and included as part of the inspection documentation.

9. 9.1

HYDROSTATIC TESTS INSPECTION HYDROSTATIC TEST Delete this section and replace with the following: Each length of pipe shall withstand, without leakage, an inspection hydrostatic test to at least the pressure specified in (9.3). The test pressure shall be held for a minimum of 15 seconds for all pipes. For all pipes, hydrostatic testing shall take place after sizing operations and final heat treatment. For welded pipe, hydrostatic testing shall be performed before non-destructive testing. The water used for hydrostatic testing shall have a maximum chloride ion concentration of 50 ppm. The Manufacturer/Supplier shall include the details of monitoring and control of hydrotest water in a documented hydrotest procedure.

9.3

TEST PRESSURES Delete this section and replace with the following: The test pressure for all sizes of pipe shall be such that the hoop stress calculated on the basis of the minimum allowable wall thickness and including stresses from end loading is at least 95 % of the specified minimum yield strength at room temperature. The Manufacturer/Supplier shall define the end load compensation factor in the hydrotest procedure.

9.4

SUPPLEMENTARY HYDROSTATIC TESTS Delete this section.

10. 10.1

DIMENSIONS, WEIGHTS, AND LENGTHS DIMENSIONS AND WEIGHTS Modify Note 2 as follows: The Manufacturer/Supplier shall state the plain-end weight correction factor in the weighing procedure. Add the following: Dimensional and weight inspection shall be performed on pipes after all other operations have been performed.

10.2

DIAMETER Delete this section and replace with the following: The diameter of the pipe shall be within the tolerances specified in Table 9 as amended below. Table 9 TOLERANCES ON DIMENSIONS AND WEIGHTS

Outside Diameter D Pipe body Delete the existing text and replace with the following: For welded pipe, the outside diameter of the pipe body, as determined by taping the circumference, shall not deviate by more than 0.75 % or 3 mm, whichever is less, from the value given in Metric Table C-1 in Appendix C. For seamless pipe, the OD tolerance shall be 3 mm. Pipe ends Delete the existing text and replace with the following: For welded pipe of diameter greater than DN 200 (8 inch), the average internal diameter shall not deviate from the nominal internal diameter by more than 0.5 % or 2.0 mm, whichever is less. For seamless pipe, the tolerance on average ID shall be 2.0 mm. The nominal internal diameter is defined as the outside diameter D, given in Metric Table C-1, minus twice the nominal wall thickness. The internal diameter shall be measured using an internal gauge or a measuring tape inside the pipe. For pipe of DN 200 (8 inch) and below, the diameter tolerance may apply to the outside diameter.

Out-of-roundness Delete the existing text and replace with the following: The ends of each pipe shall be tested for out-of-roundness using an internal ring gauge of diameter 4.0 mm less than the nominal internal diameter. The gauge shall pass freely into each end of the pipe for a distance of 100 mm when held normal to the pipe axis. Out-of-roundness of the pipe body shall be determined from measurement of the maximum and minimum OD at the same pipe cross-section. The acceptance criterion shall be: ODmax - ODmin < 3 mm Add the following to Table 9: Local irregularity of seam welds The pipe ends and three positions equidistant along the pipe length shall be checked for non-circularity at the position of the longitudinal weld using a template gauge to be agreed with the Principal. The chord length of the template shall be a minimum of 25 % of the OD or ID as applicable, up to a maximum of 300 mm. At the pipe ends, the gauge shall be located internally. The local irregularity in profile shall not exceed 1.5 mm measured between the gauge and the pipe. 10.3 WALL THICKNESS Delete the second sentence and replace with the following: The tolerance on the nominal wall thickness shall be: Seamless pipe -10 % +15 % Welded pipe -5 % +10 % 10.5 LENGTH Delete this section and Table 10 and replace with the following: Onshore lines: 95 % of shipped pipes for the order shall be between 11 and 12.2 m long. No pipe shall be shorter than 8 m. No pipe shall be longer than 12.5 m. Offshore lines: The average length of shipped pipes for the order shall be 12.2 m. 95 % of shipped pipes shall be between 11.9 and 12.5 m long. No pipe shall be shorter than 11.6 m. No pipe shall be longer than 12.8 m.

10.7

JOINTERS Delete first two sentences and replace with the following: Jointers shall only be supplied when specified by the Principal.

10.8

PIPE ENDS Add to this section: The pipe shall be supplied with pipe ends cut perpendicular to the pipe axis. The maximum deviation from the perpendicular shall be 0.5 % of the nominal outside diameter, with a maximum of 1.5 mm. The entire end bevel shall be machined and root faces shall not be brought into tolerance by filing and/or grinding.

11. 11.1

NON-DESTRUCTIVE INSPECTION INSPECTION METHODS FOR WELDED PIPE Add the following to the first paragraph: Non-destructive inspection for acceptance purposes shall be performed after hydrostatic testing of the pipe. Delete items a. and b. and replace with the following: Welded pipe shall be inspected full length in accordance with the standards nominated in (Table A). Where the system leaves untested portions at the pipe ends, these portions shall be subjected to a manual or semi-automatic UT examination based on the same technique, test sensitivity, and test parameters as used for the main test. For manual scanning, the scan speed shall not exceed 100 mm/s. For HFW and LBW pipe, the shear wave probe angle shall be 45 3 and the number and arrangement of probes shall be in accordance with the following:

Wall thickness range mm inner zone


11.9

Number of probes for zone of weld (at both sides of the longitudinal weld)

mid portion none one pair in tandem centered at midwall position two pairs in tandem centered at 40 % and 60 % of thickness tandem 3.0 mm flat bottom hole

outer zone One One

one one

12.0 to 17.9 18.0 to 23.9

one

one

mode of operation reference reflector

pulse echo N10 notch

pulse echo N10 notch

For SAW pipe, the number and arrangement of probes shall be in accordance with the following: Wall thickness range mm
11.9

Number of probes for zone of weld (at both sides of the longitudinal weld) inner zone one one one mid portion none one centered at midwall position two centered at 40 % and 60 % of thickness three centred at 30 %, 50 %, and 70 % of thickness pulse echo
(NOTE 1)

outer zone one one one

12.0 to 17.9 18.0 to 23.9 24.0 to 29.9 mode of operation reference reflector

one

pulse echo N10 notch

pulse echo N10 notch

3.0 mm flat bottom hole

NOTE 1: The angle of the mid portion probes shall be perpendicular to the weld bevel with a tolerance of 3. Where the weld bevel is less than 15 (half aperture), the probes shall be used in the tandem arrangement. For these steep angles, the probe angle shall be 45 3. Probe angle requirements are also shown in the standards listed in Table

11.2

INSPECTION METHODS FOR SEAMLESS PIPE Delete this section and replace with the following: Seamless pipe shall be inspected full length in accordance with the standards nominated in (Table A). Where the system leaves untested portions at the pipe ends, these portions shall be subjected to a manual or semi-automatic UT examination based on the same technique, test sensitivity, and test parameters as used for the main test. For manual scanning, the scan speed shall not exceed 100 mm/s.

11.3

INSPECTION METHODS FOR CENTRIFUGALLY-CAST PIPE Delete this section.

11.4

RADIOLOGICAL INSPECTION EQUIPMENT Delete this section and replace with the following: Radiographic testing of welds shall be performed with X-ray equipment using finegrain type film and lead intensifying screens. The radiographic technique shall be in accordance with ISO 12096. The image quality class shall be R1.

11.5

FLUOROSCOPIC OPERATOR QUALIFICATION Delete this section. Table A Standards for non-destructive inspection
Non-destructive inspection Specification Crossreference Notes

All pipe Ultrasonic testing for imperfections at pipe ends Magnetic Particle or Penetrant testing of bevel faces laminar Liquid ISO 11496 ISO 13664 ISO 12095 Seamless pipe Ultrasonic testing imperfections Ultrasonic testing imperfections for for longitudinal transverse ISO 9303 ISO 9305 ISO 10543 ISO 10124 Welded pipe (except HFW) Ultrasonic testing for longitudinal and ISO 9765 transverse imperfections in the weld seam (11.15) 1.4 (11.15) & (11.16) (11.15) & (11.16) (11.15) & (11.16) (11.15) & (11.16) or (11.15) (11.18)

Ultrasonic testing of wall thickness Ultrasonic testing for imperfections in the pipe body laminar

Ultrasonic testing for imperfections in the pipe body Ultrasonic testing for

laminar laminar plate/strip

ISO 12094 ISO 13663

(11.15) (11.15)

2.5 3.5

imperfections in the edges adjacent to the weld

Testing of the weld seam at pipe ends ISO 9765 or ISO not covered by automatic testing: manual 12096 UT or RT HFW pipe Ultrasonic testing for longitudinal imperfections in the weld seam Ultrasonic testing for imperfections in the pipe body Ultrasonic testing for laminar laminar plate/strip ISO 9303 ISO 9303 or ISO 9764 ISO 12094 ISO 13663

(11.15) or (11.4) and (11.11)

(11.15) (11.15) (11.15) 2 3

imperfections in the edges adjacent to the weld

Ultrasonic testing for longitudinal imperfections in the pipe body

(11.15)

NOTES:

1. Full length RT of the weld seam in accordance with this PTS may be substituted. 2. The test may be performed on the plate/strip body prior to forming into pipe with a minimum coverage of 25 %. 3. The test may be performed on the plate/strip edges in accordance with ISO 12094 prior to forming into pipe.
o

4. Angle beam shear wave as follows: for longitudinal defect detection 50 to 70 ; for transverse defect
o

detection, X or K transmission, one pair of 50 to 70 probes up to 11.9 mm thickness, two pairs of probes
o

for greater wall thickness. For on-bead scanning, the probe angle shall be 45 3 . 5. Using a twin crystal probe with a focal length of between 25 % and 75 % of the thickness. The dead zone shall be less than 25 % of the thickness at operational amplification.

11.6

OPERATOR CERTIFICATION Delete this section.

11.7

REFERENCE STANDARD Delete this section and replace with the following: The reference standard shall be a wire penetrameter in accordance with ISO 1027.

11.8

ISO WIRE PENETRAMETER Delete this section and replace with the following: The penetrameter shall be selected in accordance with the requirements of ISO 12096 Table 1. Image class R1.

11.9

FREQUENCY Delete this section.

11.10 PROCEDURE FOR EVALUATING IN-MOTION OPERATION OF THE FLUOROSCOPE Delete this section. 11.11 ACCEPTANCE LIMITS Delete this section and replace with the following: Acceptance criteria shall be as specified in ISO 12096. The test report shall contain the details specified in ISO 12096. If the Principal specifies that the radiographic test procedure is to be agreed, items a to i of clause 9 of ISO 12096 may be stated in the procedure and only items j to l included in the test report. Item k in the test report shall include the actual sensitivity and density achieved.

11.12 IMPERFECTIONS Delete this section including Tables 12 and 13 and Figures 8 and 9. 11.13 DEFECTS Delete this section. 11.14 WELD REPAIR Delete this section and replace with the following: Any weld repairs shall be performed in accordance with the requirements of section 12.6 and shall be examined using the same technique used for examining the weld seam. 11.15 ULTRASONIC AND ELECTROMAGNETIC INSPECTION OF WELDED PIPE a. Equipment

Add the following: Automatic ultrasonic equipment shall incorporate: i. A facility for registration and recording of indications on paper and/or on a retrievable medium without intervention by the operator; ii. An automatic weld tracking system for correct positioning of the probes with respect to the weld centreline without operator intervention. To allow alternative systems, the Manufacturer/Supplier shall demonstrate that complete coverage is achieved even when the probe drifts away from the weld seam; iii. A device which monitors the effectiveness of the coupling. A deviation in excess of 10 dB from the acceptable coupling situation shall indicate a loss of coupling; iv. An audible warning/paint spray system that operates when the coupling is unsatisfactory; v. An automatic paint-marking device that activates when the ultrasonic echo received exceeds the trigger/ alarm level. From each pipe under test, an automatic "on-line" record shall be made without operator intervention. For every pipe, a summary record shall be made showing pipe identification number, time, examination results (including re-examinations) and effectiveness of acoustic coupling. b. Reference standards Delete this item, including Figure 10, and replace with the following: Reference standards and calibration shall be as specified in the appropriate ISO specification and this PTS. For automatic UT, calibration shall be performed using a reference standard and shall also be checked dynamically.

Specific requirements for each NDT standard shall be as follows: ISO Standard ISO 9764 ISO 10124 ISO 11496 Specific requirements N10 notch shall be on both internal and external surface and at both sides of the weld. Reference standard shall be a flat-bottomed round Tested band shall be a minimum of 50 mm and recess. shall overlap automatic tested pipe body area by a minimum of 25 mm. Reference standard shall be a flat-bottomed round shall recess. Minimum coverage be 25 %. Edge band shall be 25 mm from final plate/strip edge. Reference standard shall be a 6 mm flat-bottomed round recess positioned mid Reference standard shallat be a wall. flat-bottomed round recess. c. Acceptance limits Delete this item, including Table 14, and replace with the following: ISO Standard ISO 9303 ISO 9764 ISO 10124 ISO 11496 ISO 12094 ISO 13663 L2C L3 ISO 3183-3, Table D.2, sour No trigger/alarm B1 (body). E1 (edge) ISO 3183-3, Table D.2 Acceptance limit

ISO 12094

ISO 13663

11.16 ULTRASONIC AND ELECTROMAGNETIC INSPECTION OF SEAMLESS PIPE Delete this section and replace with the following: a. Equipment See (Part II 11.15a). b. Reference standards

See (Part II 11.15b) and the following: ISO Standard ISO 9305 Specific requirements Notch shall be on both internal and external surface

c. Acceptance limits See (Part II - 11.15c) and the following: ISO Standard ISO 9305 ISO 10543 L2C As per ISO 10543 Acceptance limit

For ISO 9303 and ISO 9305, full coverage shall be achieved at the examination sensitivity level and under all scanning speeds. 11.17 ULTRASONIC INSPECTION OF CENTRIFUGALLY-CAST PIPE Delete this section. Add new sections: 11.18 TESTING OF BEVEL FACES Testing of bevel faces shall be performed using MT in accordance with ISO 13664. When agreed by the Principal, PT in accordance with ISO 12095 may be used. The acceptance criterion shall be no linear indications 11.19 NDT PERSONNEL QUALIFICATION NDT personnel shall be qualified and certificated in accordance with ISO 11484 or an equivalent standard agreed by the Principal. The Manufacturer/Supplier's NDT operations shall be managed by personnel certificated to NDT Level 3 (UT being the main method). All NDT procedures shall show the approval and qualification number/expiry date of the NDT Level 3. Shift supervision and calibration activities shall be undertaken by personnel certificated to NDT Level 2 or higher in all of the methods being used by the Manufacturer/Supplier. All other personnel performing NDT operations shall be certificated to NDT Level 1 in the relevant method(s).

12. 12.2

WORKMANSHIP, VISUAL INSPECTION, AND REPAIR OF DEFECTS PURCHASER INSPECTION Delete this section and replace as with the following: The requirements of Appendix F shall apply.

12.3

WORKMANSHIP a. Dents Delete third sentence of this sub-section and replace with the following: All cold-formed dents with a sharp bottom gouge and all sharp gouges (without dents) deeper than 1.0 mm shall be considered as defects. b. Offset of plate edges Delete this sub-section and replace with the following: The maximum permitted radial offset shall be as follows: Wall thickness, t, mm Maximum radial offset mm HFW
10

0.5 0.05 t -

Other welding processes 1.0 0.1 t 2.0

10 < t 20 >20

d. Height of outside and inside weld beads - except ERW Delete tabulation after first paragraph and replace with the following: The bead height shall not lie outside the ranges specified below: -Outside: - 0, + 3 mm -Inside: - 0, + 2.5 mm The inside weld bead shall be ground flush with the parent material over the full length of the pipe end. e. Height of flash of electric-welded pipe Delete second paragraph and replace with the following: The inside flash of HFW pipe shall not extend beyond the prolongation of the original inside surface by more than 0.5 mm plus 5 % of the nominal wall thickness.

12.4

VISUAL INSPECTION Delete this section and replace with the following: The full internal and external surface of each finished pipe shall be visually examined for surface defects. For internal examination of pipe DN 600 and larger, the inspector shall pass through the bore of the pipe. The Manufacturer/Supplier shall control the visual inspection process with a documented procedure. The procedure shall be qualified in accordance with ASME Section V - Article 9.

12.5

DEFECTS b. Laminations and inclusions Delete this sub-section and replace with the following: The complete internal and external pipe surface and bevel faces shall be free of surface breaking laminations and inclusions. Note : A lamination is defined as an internal metal separation creating layers generally parallel to the surface f. Disposition 1. Add the following to this item: In all cases where repair by grinding has been carried out, the length of pipe containing each grinding repair shall be re-inspected after the grinding operation by the same inspection methods as the original inspection and by MT. The inspection shall confirm freedom from defects and that the wall thickness is not less than the minimum specified. Where manual ultrasonic testing for wall thickness is performed it shall be in accordance with ASTM E 797. 2. Amend this item as follows: Repaired in accordance with 12.6. 3. Add the following to this item: Where surface breaking defects are found in the pipe bevel, the pipe shall be cut back and rebevelled. The new bevel shall be subjected to visual inspection and NDT in accordance with this PTS.

12.6

REPAIR OF DEFECTS b. Weld seam of welded pipe Delete this sub-section and replace with the following: Defects in the weld seam of SAW pipe and pipe welded by GTAW or PAW using a filler metal may be repaired. Repair of defects in the weld seam of other forms of welded pipe shall not be permitted.

Repair welding is not acceptable within 200 mm of the ends of the seam weld. Repair welds shall be subjected to radiographic testing in accordance with (section 11). No weld-repaired area shall be subjected to further repair. c. Heat-treated pipe Delete this sub-section and replace with the following: All repair welding (where permitted) shall be performed prior to final pipe heat treatment. Table 15 Delete this table. 12.7 PROCEDURE FOR REPAIR OF WELD SEAMS OF SUBMERGED-ARC WELDED PIPE Delete this section and replace with the following: PROCEDURE FOR REPAIR OF ARCWELDED PIPE The defect shall be completely removed and the cavity thoroughly cleaned. The cavity shall be inspected by MT, or PT, to ensure that no remnants of the defect remain. The minimum length of the repair weld shall be 50 mm. The repair weld shall be made by either SMAW or GTAW. The welding procedure shall be qualified in accordance with Appendix A. Shielding gas containing hydrogen shall not be used. 12.8 PROCEDURE FOR REPAIR OF WELD SEAMS OF ELECTRIC-WELDED AND INDUCTIONWELDED PIPE Delete this section. 12.8 PROCEDURE FOR REPAIR OF WELD SEAM OF GAS METAL-ARC WELDED PIPE Delete this section. Add new section: 12.10 GAUGE PIG If specified by the Principal, a gauge pig shall be passed through the following pipes in their supply conditions: i. All first-day-production test pipes. ii. Two pipes from each working shift, one at the beginning and one at the end. iii. First two pipes immediately after any adjustment or maintenance is carried out on the mechanical expander.

The gauge shall consist of two parallel, 6 mm thick circular plates each at least 98 % of minimum pipe ID separated by a rigid bar of which the length is twice the pipe ID. In order to pass the test, the gauge shall be passed through the pipe without damaging the gauge plates. The material of the gauge plates shall be 316L or duplex stainless steel or other material agreed by the Principal.

13. 13.1

MARKING AND SURFACE TREATMENT MARKING - GENERAL b. Delete this sub-section and replace with the following: Marking of test pressure, sizes and weights shall be in metric units. Add new sub-section: c. For pipes of DN 100 and above, stencil markings shall be block capitals of minimum height 19 mm. For smaller pipe diameters, the character height shall be 10 mm or more. The stencil colour shall be white and the stencil fluid shall be free from chlorides.

13.2

LOCATION OF MARKINGS b. Delete this sub-section and replace with the following: For pipe up to DN 400, paint stencilling shall be on the outer surface starting at a point between 450 mm and 750 mm from the end of the pipe. For larger pipe, the paint stencilling shall be on the inside surface, facing the pipe end, and finish 150 mm or more from the pipe end. In both cases the marking sequence shall be as defined in (13.3). c. Delete this sub-section.

13.3

SEQUENCE OF MARKINGS i. Supplementary requirements Delete this sub-section. Add the following new sub-sections: PTS 31.40.20.36 Principal-specified markings Additional marking requirements if specified by the Principal.

13.5

DIE STAMPING Delete this section and replace with the following: If specified by the Principal, the unique pipe identification number shall be diestamped or vibro-etched on the bevel face at each end of the pipe. Low stress die stamps shall be used.

13.6

SURFACE TREATMENT Delete this section and replace with the following: The pipe shall be pickled or gritblasted in accordance with the Manufacturer/Supplier's documented procedure. Add new section:

14. 14.1

STORAGE, HANDLING, AND PACKING HANDLING During manufacture, storage and transportation, the pipes shall not come into contact with loose carbon steel (e.g. swarf, filings etc.). Nylon slings or rubbercoated hooks/supports etc. shall be used for all handling operations.

14.2

STORAGE All pipe shall be stored and packed in accordance with the Manufacturer/Supplier's documented procedure which shall show calculations for stacking height and arrangement. The pipe shall be fitted with end caps and shall have a dedicated storage area fully segregated from other materials.

14.3

PACKAGING Packaging shall be as specified by, or agreed with the Principal.

14.4

TRANSPORTATION The transportation of pipe shall be as specified in the following: i. API RP 5LW for marine transportation ii. API RP 5L1 for railroad transportation The pipe shall not be transported by sea as deck cargo. Add new section:

15. 15.1

DOCUMENTATION LANGUAGE All documentation submissions required by this PTS shall be in the English language.

15.2

PRE-MANUFACTURING DOCUMENTATION The Manufacturer/Supplier shall submit to the Principal within the time period specified in the contract document, a contract-specific quality plan and procedures detailing all special processes, as described in (Part II 1.4).
NOTE: Review of this documentation at the enquiry stage of the contract may assist this process.

15.2.1 Content of the quality plan The format and issue of the quality plan shall be consistent with the document control element of the Manufacturer/Supplier's quality system. The content of the quality plan should be based on ISO 10005 and shall include the following: 1. 2. 3. 4. 5. 6. 7. 8. Identification of the product and contract to which the plan is to be applied; Reference to API Spec 5LC and this PTS; Location of steel making and pipe production; Identification of the individuals responsible for controlling the activities defined in the plan; Identification of the individuals with the authority to interface directly with the Principal; Identification of all subcontractors; The quality plans of all subcontractors; All sequenced activities for the contract and references to the quality system procedures and work instructions which will be applied to these activities; Copies of all the quality system procedures and work instructions covering manufacturing production, test and inspection, special processes, control of nonconforming product, handling, storage, packing, and shipping as requested by the Principal; Test and inspection frequency and acceptance criteria including the upper and lower process control limits where statistical process control is employed;

9.

10.

NOTE: Process control for chemical composition and dimensional parameters is generally based on upper and lower control levels.

11. 12.

The location of each inspection and test point in the process sequence; Points where the Principal has established its witnessing or verification requirements.

15.2.2 Special processes The Manufacturer/Supplier shall provide procedures for those manufacturing activities determined to be special processes and critical to the final mechanical and dimensional integrity of the pipe. This shall include the following: Seamless pipe -pipe forming procedure; -pipe heat treatment procedure; -hydrostatic test procedure; - NDT procedures HFW pipe -Strip manufacturing procedure including details of rolling and any specialised cooling or coil heat treatment. -Strip NDT procedures. -Pipe making method including details of methods for preparing the edges of the strip for welding and for control of misalignment of edges and pipe shape. Details of the sizing operation should also be given. -A detailed welding procedure specification which shall include the following: methods for automatic control of welding parameters; electrical or induction frequency; details of welding power unit; welding speed; welding temperature; shielding method/arrangement; weld profiling. -Weld seam (or full body) heat treatment procedure. Hydrostatic test procedure. NDT procedures.

LBW pipe -Strip and pipe manufacturing procedure as required above for HFW pipe. -A detailed welding procedure specification in accordance with ISO 9956-11. This shall include all details of the methods used for automatic control and monitoring of the welding parameters, gas shielding method/arrangement and weld profiling. -Pipe heat treatment procedure. -Hydrostatic test procedure. - NDT procedures. Arc welded pipe -Strip and pipe manufacturing procedure as required above for HFW pipe. -Plate rolling details for pipe to be supplied in the as-rolled condition. -Heat treatment procedure for plate heat treated before forming. -Pipe manufacturing procedure. -For SAW, GTAW and PAW pipe, a detailed welding procedure specification in accordance with ISO 9956-2. -Hydrostatic test procedure. - NDT procedures. The manufacturing procedures shall correspond with those used previously for the manufacturing qualification tests (in accordance with SIEP 97-5763). 15.3 SHIPPING DOCUMENTATION Each shipment shall be accompanied by a packing list; a pipe tally list; and, where applicable, an original or certified copy of the Principal's inspection release note. The pipe tally list shall show the pipe numbers with their corresponding heat number, length, weight, and end dimensions. Add new section:

16. 16.1

FIRST-DAY-PRODUCTION TESTS GENERAL At the commencement of production, three completely finished pipes of the first day's production shall be selected at random for testing to verify that the proposed manufacturing procedure results in fully acceptable pipe. If more than one cast is used or pipes of more than one dimension are produced then the three pipes shall be taken from different heats or size range. For pipe made from coiled strip, the test pipes shall include pipes taken from each end of the coil. The Principal shall make the selection when a representative is deployed. The selected pipes shall be considered to be the production test pipes per lot as required in this PTS. These tests shall be repeated upon any change in manufacturing procedure or significant interruption to the production programme.

16.2

NON-DESTRUCTIVE TESTING a. Visual examination All test pipes shall be examined visually for dimensional tolerances, and for surface defects, in accordance with (Part II 10, 11 and 12) respectively. b. Magnetic particle testing For seamless pipe only, each test pipe shall be submitted to magnetic particle testing over the entire pipe body in accordance with ISO 13665. For welded pipe, the weld seam shall be submitted to magnetic particle testing along its entire length. Acceptance of indications shall be in accordance with test category M1 of ISO 13665 with the exception that linear indications, other than acceptable undercut in welded pipe, shall be considered as defects. c. Ultrasonic testing The body of each pipe used for first-day production tests shall be examined by ultrasonic testing in accordance with (Part II 11). d. Radiographic testing For welded pipe, except HFW, the entire weld seam shall be inspected in accordance with (Part II 11).

16.3

CHEMICAL COMPOSITION The chemical composition of each test pipe and weld (if applicable) shall be determined in accordance with (Part II 6).

16.4

MECHANICAL TESTING Mechanical tests shall be carried out on each test pipe as required by (Part II 7). In addition, for each first-day-production test pipe, a full Charpy impact transition curve shall be produced, showing impact energy in joules and percentage shear (fibrous) of the fracture surface, plotted against temperature, over a temperature range sufficient to produce fracture appearance from 10 % to 100 % fibrous shear.

16.5

SPECIAL TESTS CTOD tests in accordance with (Part II - 8.1) and residual magnetism checks in accordance with (Part II 8.2) shall be performed on each test pipe.

APPENDIX A REPAIR WELDING PROCEDURE A.1 GENERAL Delete sub-sections a., b., and c. and replace with the following: Shielded metal-arc using low-hydrogen electrodes. Gas tungsten-arc. Add the following: The composition of the repair weld metal shall match that of the weld seam.

A.2

REPAIR WELDING PROCEDURE QUALIFICATION Delete this section and replace with the following: A repair welding procedure specification shall be prepared in accordance with ISO 9956-2. A fully simulated repair weld shall be made on a pipe piece of sufficient length to accommodate extraction of all the required test specimens. Qualification shall be by the visual, non-destructive, and destructive testing of the test weld seam as specified in this PTS for the original seam weld. Repair weld metal shall not be exposed on the inner surface of the pipe unless it has been heat-treated.

A.2.2

Mechanical testing Delete this section and replace with the following: The repair welding procedure shall be subject to the same testing required for the original weld by (Part II - 7 and 8).

APPENDIX F PURCHASER INSPECTION F.1 INSPECTION NOTICE Delete this section and replace with the following: The Manufacturer/Supplier shall give five working days' notice to the Principal of the production run or inspection or test, which is to be witnessed. Add the following: F.5 SUMMARY OF PRINCIPAL'S INSPECTION PROFILES The Principal shall indicate the type of inspection to be performed in the contract document.
SEQUENCE NO 1.0 2.0 3.0* 4.0 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 5.0 5.1 5.2 5.3 5.4 6.0 INSPECTION ACTION ATTENDANCE IN THE MILL DURING CONTRACT QUALITY PLAN PRODUCTION PREMANUFACTURING MILL PRODUCTION MEETING Pipe rolling Heat treatment Sampling test pieces Physical properties Hydrostatic test NDT for acceptance Dimensional inspection Marking Packing DOCUMENT REVIEW Production records Tally lists Inspection reports Release note FIRST DAY PRODUCTION RR RR RC E W/RC RR RR RC E W/RC RR RR RC E RC RR RR RC E RC FULL RUNNING Yes RA E* LIMITED RUNNING Spot RA E* FULL FINAL No RA E* LIMITED FINAL No RA

SWA FW/RR E FW/RC FW/RC FW/RR SW/SE/RR SW SW

SWA FW/RR E FW/RC FW/RC FW/RR SW/SE/RR SW SW RC RC SE/RR SW SW RC RC SE/RR SW SW RR RR

RR/RC RR/RC

Abbreviations and notes: TESTS E Execution by Principal's Inspector. FW Witness first operation for compliance, including check of calibrations; subsequently random inspection, review document and endorse for acceptance. RA Review document and endorse for acceptance. RC Review certificate and endorse for acceptance. RR Review production records and endorse for acceptance. SE Random execution by Principal's Inspector. SW Random witness by Principal's Inspector. SWA Random witness applicable when pipe forming is part of finishing line (e.g. there is no additional heat treatment on a different line).

W Full witness. *If specified in the contract document.

PART III REFERENCES In this PTS, reference is made to the following publications:
NOTE: Unless specifically designated by date, the latest edition of each publication shall be used, together with any amendments, supplements, or revisions thereto.

PETRONAS STANDARDS Index to PTS publications and standard specifications PTS 00.00.05.05 Pressure vessels (amendments/supplements PTS 31.22.20.31 ASME Section VIII, Division 1 and Division 2) Qualification test requirements for weldable 13Cr line pipe SIEP 97-5763, September 1997

AMERICAN STANDARDS Specification for CRA line pipe API Spec 5LC, 3rd July 1998, Reaffirm Aug 2008

Recommended practice for railroad transportation of line pipe Recommended practice for transportation of line pipe on barges and marine vessels
Issued by: American Petroleum Institute Publications and Distribution Section 1220 L Street, Northwest Washington, DC 20005 USA.

API RP 5L1 API RP 5LW

Boiler and pressure vessel code, Section V, nondestructive examination


Issued by: American Society of Mechanical Engineers 345 East 47th Street New York NY 1001USA

ASME V

Standard test mthod for macro-etching metals and alloys Standard practice for measuring thickness by manual ultrasonic pulse-echo contact method
Issued by: American Society for Testing and Materials 100 Bar Harbor Drive, West Conshohocken, PA 19428-2959 USA

ASTM E 340 ASTM E 797

BRITISH STANDARDS Fracture mechanics toughness tests - Part 1. Method for determination of KIC, critical CTOD and critical J values of metallic materials Fracture mechanics toughness tests - Part 2. Method for determination of KIC, critical CTOD, and critical J values of welds in metallic materials
Issued by: British Standards Institution 389 Chiswick High Road London W4 4AL UK

BS 7448 Part 1

BS 7448 Part 2

EUROPEAN STANDARDS Destructive tests on welds in metallic materials. Hardness testing Part 1: Hardness tests on arc welded joints
Issued by: Comit Europen de Normalisation Rue de Stassart 35 1050 Brussels Belgium Copies can also be obtained from national standards organizations.

EN 1043-1

INTERNATIONAL STANDARDS Steel Charpy impact test (V-notch) Radiographic image quality indicators for non destructive testing principles and identification Petroleum and natural gas industries Steel pipe for pipelines Technical delivery conditions Part 3: Pipes of requirement class C Metallic materials - Vickers hardness test - Part 1: Test method Quality systems - Model for quality assurance in design, development, production, installation and servicing Quality systems - Model for quality assurance in production, installation and servicing Seamless and welded (except submerged arc-welded) steel tubes for pressure purposes - Full peripheral ultrasonic testing for the detection of longitudinal imperfections Seamless steel tubes for pressure purposes Full peripheral ultrasonic testing for the detection of transverse imperfections ISO 148 ISO 1027

ISO 3183-3

ISO 6507-1 ISO 9001

ISO 9002

1SO 9303

1SO 9305

Electric resistance and induction welded steel tubes for pressure purposes - Ultrasonic testing of the weld seam for the detection of longitudinal imperfections Submerged arc-welded steel tubes for pressure purposes Ultrasonic testing of the weld seam for the detection of longitudinal and/or transverse imperfections Specification and approval of welding procedures for metallic materials Part 2: Welding procedure specification for arc welding, Amendment 1 Specification and approval of welding procedures for metallic materials Part 11: Welding procedure specification for laser beam welding Quality management - Guidelines for quality plans Quality assurance requirements for measuring equipment Part 1:Metrological confirmation system for measuring equipment

ISO 9764

ISO 9765

ISO 9956-2

ISO 9956-11 ISO 10005 ISO 10021-1

Seamless and welded (except submerged arc-welded) steel tubes for ISO 10124 pressure purposes Ultrasonic testing for the detection of laminar imperfections Steel and steel products Inspection documents Seamless and hot-stretch-reduced welded steel tubes for pressure purposes - Full peripheral ultrasonic thickness testing Steel tubes for pressure purposes - Qualification and certification of non-destructive testing (NDT) personnel Seamless and welded steel tubes for pressure purposes Ultrasonic testing of tube ends for the detection of laminar imperfections Welded steel tubes for pressure purposes Ultrasonic testing for the detection of laminar imperfections in strips/plates used in the manufacture of welded tubes Seamless and welded steel tubes for pressure purposes Liquid penetrant testing Submerged arc-welded steel tubes for pressure purposes Radiographic testing of the weld seam for the detection of imperfections Welded steel tubes for pressure purposes Ultrasonic testing of the area adjacent to the weld seam for the detection of laminar imperfections Seamless and welded steel tubes for pressure purposes Magnetic particle inspection of the tube ends for the detection of laminar imperfections ISO 10474 ISO 10543

ISO 11484

ISO 11496

ISO 12094

ISO 12095

ISO 12096

ISO 13663

ISO 13664

Seamless and welded steel tubes for pressure purposes ISO 13665 Magnetic particle inspection of the tube body for the detection of surface imperfections Issued by: International Organisation for Standardisation 1, rue de Varemb CH-1211 Geneve 20 Switzerland Copies can also be obtained from national standards organizations

You might also like