INSPECTION AND TEST PLAN

EARTH WORKS

NO 1.0 1.1

List of Inspection Operation SITE PREPARATION Assessment for site condition, checks for obstacles, stocks or equipment

Controlling Document Specification

Frequency Stage Verifying Documents After taking-over notice from the Client Prior to stake out of the work area After stakeout of the work area Prior to start of works Prior to start of works After completion of trial pit Each area as applicable Visual Requirement

Inspection Contr Engr Client SC WP HP

Comments Hand Over Notice from Client

1.2

Issuance of CRFI to Engineer for joint inspection Ms of the site NATURAL GROUND LEVEL CHECKING Additional survey after the initial 20m wide strip, Ms if required EXISTING UTILITIES Locating of identified existing utilities on site Investigation of existing utilities by trial pits. Specific MS to be issued depending on the type of utility observed Survey is carried out on trial pits

Joint Survey

SC

WP

HP

Request for Inspection

2.0 2.1

Approved design drawing

SC

NA

NA

Approved drawing

3.0 3.1 3.2

PDF Editor
3.4 Issuance of drawing by Technical dept. This Site situation takes into account conflicts with other interfaces recorded as applicable. The Technical dept may accept the current drawings, or issue a revision based on actual as-built information
ALIGNMENTS AND LEVELS

3.3

Approved Drawing Approved method statement Survey report

Approved Drawing Approved method statement Survey report

SC SC

WP WP

HP NA

TM
Survey data if applicable

Approved Drawing

SC

HP

HP

4. 4.1 5.0 5.1

Stakeout of site delimitation EXCAVATION Setting out

Approved Drawing Ms and

After approved drawing

SC

HP

NA

Pre excavation

SC

HP

NA

INSPECTION AND TEST PLAN

EARTH WORKS

5.2

Excavation Layout

Approved Drawing Ms and Approved Drawing Ms Ms and Spec Ms, Spec and Drawing Ms and Spec

After completion of Survey Works

SC

HP

HP

At the beginning stage of the project, reference point shall be agreed and joint survey will be done..

5.3 5.4 5.5 6.0 6.1

Calibration of Instruments Classification of Materials Replacement of over excavation Excavation or unsuitable materials revealed BACKFILL MATERIAL Classification of Materials

RFI RFI

SC SC SC

NA WP WP

NA HP NA

RFI

SC

WP

NA

6.2

Processing of Material

Ms and Spec

6.3

Testing Of Material

Ms and Spec

RFI

SC

WP

HP

Suitable material shall be inspected for the suitability will stock at stock pile Gradation and at berg limits shall comply to specification for earthwork Suitable TM excavated material shall comply required specification standard.