1. LOCATION
Off-takes from Left Bank of River Indus up-stream of Guddu Barrage, the project located in Ghotki Sukkur and Khairpur Districts of Sindh Province. PROJECT LOCATION MAP The scheme of the project is shown as under:-
G U D U
KASH MOR
DA R PU R LA M M
RAHIMYAR KHAN
IN
KANDKOT
RI US
VE
R
MUREED SHAKSH
CH
OW
CH
AD
AH
AD
SADIQABAD
RAIN
L AN A EE C
UBAURO RETI
GH OT KI
SHAHPUR
YARO LUND
SALEH PAT
DI K H ST R A I IC T RP UR
R A J P U T A N A
2.
SCOPE OF WORK
The length of Main Canal is 175 Km with capacity of 5,155 cusecs. About 609 Km. of Distributaries will also be constructed. All the distributaries will be lined. 304 major structures and 1318 minor structures are under construction. 3. Objectives / Benefits
The Rainee Canal is a multipurpose project and will afford benefits in the following fields. a. b. c. d. e. f. g. h. i. j. k. 4. 5. 6. Better utilization of flood water ensuring greater supply of water to Sindh. Better flood mitigation and aversion of losses to property. Irrigation of 412,400 acres of barren land. Cropping intensity during Kharif would increase from 0% to 80% in initial five years. Improved Forestry & Fruit Production. Development of cattle breeding, dairy farming. Drinking water for Arid Zone. Social uplift and poverty alleviation. Environmental improvement due to charging of lakes. Development of fish farming to the extent of 258 tons annually. Development of transportation routes in project area. Creation of job opportunity and alleviation of Poverty. October, 2002 June, 2013 (Re-Scheduled) PCI amounting to Rs. 18.862 Billion approved by ECNEC on 18.02.2004.
The Revised PCI amounting to Rs. 42.252 Billion has been forwarded by Secretary, Ministry of Water & Power Islamabad on 20th February, 2010 to Planning & Development Division Islamabad for obtaining approval of ECNEC.
7.
SALIENT FEATURES Main features of the project are as under: a. b. c. d. Canal Capacity Command Area Canal Length Lined Portion of Canal 5155 Cusecs 412,400 Acres 175 KMs 119 KMs
e. f. g. h. g. h. i. j. k. l. m. 8.
Distribution System Lakes Storage Syphon Canal Head Regulator (at Guddu Barrage) Cross Drainage Structures Railway Bridge National Highway Bridge Road Bridges Head Regulators of Distributaries Project Cost EIRR
The details of contracts / packages given below:DESCRIPTION Contract RC-1 Earthwork of Main Canal from RD 18+000 to RD 38+000 Contract RC4 Construction of River Training Works, Head Regulator, Earthwork and Structures of Rainee Canal from Head Regulator to RD 18+000 Contract RC5A (Remaining works of RC-2, 3 & 5) Earthwork & Structures from RD 18+000 to 181+433 V.O No.RC-5A/02 STATUS Work completed on 31.05.2003 Defect Liability Certificate issued w.e.f 01.07.2012 Defect Liability Certificate issued w.e.f 09.02.2011 Taking Over Certificate (TOC) issued w.e.f 20.03.2012. Defect Liability Certificate issued w.e.f. 20.02.2011 Work suspended & Contract Terminated by the Contractor. Amicable settlement through MOU is under process. Taking Over Certificate issued w.e.f. 16.04.2012.
9.
CHIEF ENGINEER & P.D, Rainee Canal Project, WAPDA, Officers Bachelor Hostel T.P.S Colony Guddu 0722578413 / 0723709670
Updated as on 28-02-2013