Professional Documents
Culture Documents
Jordan Hamid
Block A13-1-10, Vista apartment seri alam jalan
Persiaran seri alam, bdr seri alam masai 81750 Johor Bahru Malaysia
E-mail : jordan_hamid@hotmail.com
jhpowers88@gmail.com
Supplemental Information
Objective
JORDAN Cv Page 1/7
Challenging and rewarding upper-level position in a growth-oriented organization,
which offers diverse job responsibility in Construction Piping Supervisor and QA/QC-
Inspector and will fully, utilize both my technical and managerial abilities.
Experience Classification
Piping Supervisor 14
QA/QC-Piping Inspector 11
QA/QC- hull 2
Line Checker 11
Commissioning 2
Piping Foreman 2
Employment History
Germanischer Lloyd/STR
○ To assist the Certifiying Authority/ QA/QC Engineer responsible for the piping
inspection, erection and installation of piping system.
○ To check the variable for Welder Qualification certificate and position limits and
the history of employment to avoid time laps.
○ To check and monitor the joint preparation suck as per requirement of WPS and
also the jig and fixtures for distortion control.
○ To check the material size, dimension, pipes rout as per isometric drawing,
collect the data and result and submit to higher authorities.
Respect and apply HSE rules, to assist the lead QA/QC head. Marine Conversion
Depatment, responsible for the erection structural block and installation of piping
system for T-10 drilling tender bardge, assign.
○ Ensure all Fabrication spool (pipe’s), structure block correctly as per drawing
and welding activities are strictly comply with code, standards and client
specification.
○ To check the variable for Welder Qualification certificate and position limits and
the history of employment to avoid time laps.
○ To check the material size, dimension, pipes rout as per isometric drawing,
collect the data and result and submit to higher authorities.
○ Primarily responsible for all construction activities at site and to ensure that the
contractors executes the daily activities as planned and completed on desired
date.
○ To ensure the contractor carries out the works safely and apply safety
conditions and practices prevail at work site.
○ To resolve any relevant technical querries and liase with client senior inspector.
If not direct to superintendent or discipline engineer.
Respect and apply HSE rules, responsible for the fabrication and installation of piping
system for N’KOSSA-1 FSO-YOHO. Conversion project / MISC- Bunga Kertas, FPSO-
Conversion project ( Onshore/ Offshore).MOAB Talisman Energy Project(Dynac Eng.).
On shipbuilding and operation department, assign to
○ Field control
○ Responsible for reviewing the entire piping system to make sure that it meets all
required codes and its safe and adequate facilities are provided.
○ Handle special tools and equipment for maintenance, inspection, and repair.
○ Perform punch listing and coordinate punch list work items in preparation for
handover of test packages.
○ conduct roll out meeting and clinics to designer to minimize and control error
and promote lesson learnt on previous project.
○ Assign for the revision and modification of P&ID as required by process and
clients comments using intelligent PDS-2D intergraph system.
○ Conduct line check create punch list A,B,C, submit the report to planning
coordinator and contractor for killing( Clearing).
Kertih, Terengganu
○ Check isometric base on P&ID, project specification, equipment report and plot
plan.
○ Check pipe system design and operating condition on project data sheet.
○ Check conduct inspection and monitor test preparation prior testing activities,
○ Conduct line check and create punlist submit the report to planning coordinator
○ Direct reports to the Lead Construction Engineer and performs the following
functions:
○ Interprets piping drawings and specifications for contractor use.
○ Verifies correct installation of piping with all components (supports, hangers,
valves, etc.).
○ Monitors physical installations to ensure that work is installed in accordance
with drawings, specifications, and applicable codes.
○ Assign to supervised at workshop fabrication,fabricated pipes spool and pipes
support
○ Coordinates his discipline(s) with others, when conflicts arise, to resolve
problems and prevent delays.
○ Assists contractor in planning and scheduling work to obtain maximum
efficiency.
○ Check ,conduct inspection and monitor test preparation prior testing activities,
prepare test schedule base on contruction schedule
○ Witnesses all piping construction verifications, including P&ID checks and
hydrostatic testing.
○ Collect revision of project isometric drawingas per field change, site instruction
and as-builts.
○ Compilation of completed check sheets, test sheets in a book called Dossier and
check it’s completion prior to hand-over to Commissioning group or Client.
○ Supervise and Line check the Piping and Mechanical installation and make sure
if conforms to P&ID and prepare as-built drawing if necessary. Preserve &
Maintain all Equipment once received in Fabrication yard, Compile all Punch-list
generated by all Departments, Client, and Vendor & Commissioning and prepare
consolidated Punch-list and monitor status.
○ Provide calculation and detailed drawing for revised piping routes and design.
Engage in punch killing supervision prior testing.
○ Reports to the Lead Construction Engineer and performs the following functions
Assign to
○ supervise, check and monitor all piping activities collect data testing activities.
○ package and document. Check ,conduct inspection and monitor test preparation
prior
testing activities.
Supervisor Jan.
1995 - Sept. 1995
○ Checking all the existing pipe line for lay out in good alignments and in proper
elevation as per isometric is concerned.
○ Check &fit-up of spools along pipe rack, furnace, different kinds of materials
steel, carbon steel, alloy.
○ Supervised and monitor of fabrication of pipe spool on site & fabrication shop
and non-destructive test qualification results
○ Checking of line schedule for testing and installation of manifold and vent valve.
○ Check the entire installed pipeline according to the given code name and
number for priority for hydro testing schedule.
○ Check all weld joint and inspection of all valves are installed correctly and tightly
closed
○ Provide detail drawing, and technical information base on project scope and
standards.
Education
BsME.-Diploma-WMSU- 1993
Safety Induction And Health for construction Conducted by: NIOSH / CIDB
Confined Space Aweareness: MSTS ASEA SDN. BHD. Pasir Gudang J.B.
API 570 Pressure Piping Inspector: Inspection, Repair, Rerating & Alteration, API
RP 571,
API RP 574, API RP 578, ASME B31.3 Piping Design, ASME B16.5 Flanges, ASME
Section IX Welding ASME Section V NDE. ( Jan 2008)
Safety Training Courses: Offshore Passport Certification For 3 Year - Until 2012
Basic Offshore Safety Induction & Emergency Training With HUET EBS (Including
Additional OLP Modules)
Award
Improbing Safety Award: SBM / Exxon Mobil, FSO YOHO Project 2004
References Salary
Personal Information
I hereby certify that the above information is true and correct to the best of my
knowledge.