Professional Documents
Culture Documents
BASEMENT
Application for a Building Permit can be made the Customer Service Representative will refer
between the hours of 8:00 am and 4:30 pm at: you to a Safety Codes Officer to ensure your
application complies with the Alberta Building
The City of Calgary
DEVELOPMENT Development & Building Approvals
Customer Advisory Services Counter
Code. Providing you have brought all the
information required, and it is correct, the only
delay may be having to wait your turn if there are
3rd Floor, Calgary Municipal Building other customers ahead of you.
800 Macleod Trail S.E.
Calgary Alberta T2P 2M5 FEES
A schedule of permit fees is available at the
For inquiries, call (403) 268-5311 Customer Service Counter.
Dimension 'A' x Dimension 'B' cannot be less than 0.35 m2 (3.8 ft2). One dimension
of the unobstructed opening must be no less than 380 mm (15"); therefore, the other
dimension of unobstructed opening must be no less than 920 mm (36.2").
b. The minimum dimension requirement is g. The chimney flue for a decorative log Floor Plan Example (reference only)
fireplace has to be sized for 5 times the
FURTHER INFORMATION
waived where a bedroom door provides
access directly to the exterior. gas input rating shown on the appliance. If you require further information, the Customer
Advisory Services Division of Development &
c. Where a window with the minimum h. The heating and ventilation system shall Building Approvals is located on the third floor
dimension is required and that window be installed by a Heating Contractor of the Municipal Building at 800 Macleod Trail SE.
opens into a window-well, a clearance licensed with The City of Calgary.
of at least 550 mm (22 inches) shall be We can be reached at:
4. Additional Dwelling Units (403) 268-5311 or
provided in front of the window.
Refer to the “Additional Dwelling Units” Website: www.calgary.ca/dba
Where the sash swings towards the pamphlet if you intend to create another
dwelling unit. The City of Calgary
window-well, the operation of the Development & Building Approvals
sash shall not reduce the clearance in a 5. Electrical Customer Advisory Services Counter
manner that would restrict escape in an 3rd floor, Calgary Municipal Building
emergency. Development & Building Approvals has
800 Macleod Trail SE
a booklet entitled “Guide for Homeowner
3. Heating & Ventilation Calgary, Alberta T2P 2M5
Permit and Electrical Wiring” which provides
a. Maintain proper clearances of 600 mm (24 guidelines for planning a residential wiring
system. It does not, however, tell you how to Inspections:
inches) in front and 150 mm (6 inches)
at the sides and back to combustible install wiring. • Building
construction when furnaces and other • Electrical
311
gas-burning appliances are enclosed. Note: • Heating & Ventilation
b. Provide outside air for combustion to all If you are building/renovating in an infill area, • Plumbing & Gas
natural gas-fired appliances. your sewer/water service may have to be upgraded.
For verification and/or further information call the
c. When adding a new furnace, a supply of Waterworks/Sewer Division at (403)268-5710.
fresh air shall be introduced into the cold
This series is published by The City of Calgary,
air plenum directly from the outside. WARNING!! Development & Building Approvals, as part of a public
d. Insulate the ducts carrying outside air for All gas installations and piping must be carried information service.
combustion and keep the ducts away from out by a qualified licensed contractor.
water pipes to prevent them from freezing. These pamphlets have no legal status and cannot be
used as an official interpretation of the various bylaws,
Insulate the fresh air intake to the return SAMPLE PLAN codes and regulations currently in effect. The City of
air plenum. The following sample plan is for information and Calgary accepts no responsibility to persons relying
e. Install cold air return at floor level of guidance only and will not be accepted as a plan solely on this information.
developed room(s). for a Building Permit Application.
Pamphlets are updated periodically. Contact the
f. When additional gas appliances (e.g., Planning Services Support Centre at (403)268-5311
decorative gas log fireplaces) are installed, to determine if you have the most recent edition.
vent them separately to the outside. The
existing furnace vents usually do not have
the additional capacity required (see “Gas
Appliances” pamphlet). Revised 2007 April basement_development.indd