You are on page 1of 7

Personal Details

Name: Address: Paul Eastwood Coleman Lisronagh Clonmel Co. Tipperary UK mobile 07979 300 980 Irish mobile 00353 86 0413769 eastwood.paul@gmail.com 6 November 1970 Irish

Telephone:

E-mail: Date of Birth: Nationality:

Profile: Sixteen years experience involving Design, Planning and Construction supervision in Pharmaceutical, Refinery, Nuclear and Gas Storage Mechanical environments. Design skills include 3D modeling and Layout using Autoplant, Microstation, Autocad Plant. Planning skills include Primavera P6 and Microsoft Project. Education & Training H.N.C. in Mechanical Engineering 1993 O.N.C in Mechanical Engineering 1991 Primavera P6 Planning/Scheduling Nov 09 Process Piping Draughting and Design Certificate Certificate in 2D Autocad, City & Guilds of London Certificate in 3D Autocad, City & Guilds of London JE in-house Autoplant Training JE in-house Navisworks Training Time Served Indentured Apprenticeship in Engineering.

Employment History:
Mar 13 Present : Position Held: Bilfinger Industrial Services., Ineos, Grangemouth, Scotland. Piping Designer
Area 4 Tank farm Remediation Project.

Constructability reviews for new bulk storage tank

Surveying existing plant to generate Plot plans showing new equipment locations and tie-ins.
Producing isometric's for issuing to mechanical contractor.

July 11 Feb 13 : Position Held:

Jacobs., Cork, Ireland. Project Engineer Seconded to MSD Carlow .Responsible for the Drawing office, Owner of the drawing register and equipment register. Issuing contractors up to date information for Projects. As building P&IDs' Approving DCNs, ECNs and project variations. SME point of contact for audits.

July 10 June 11 : Position Held:

M.W Group Ltd., Shanghai, China Lead Engineer Projects worked on: ScinoPharm, Jiangsu, China; Creating level 1-4 Schedules. Preparation of plot plan. Developing new P&IDs for Detail design. Preparation of cost estimate, including bulk M.T.Os. Merial Nanchang, China Maintaining project master schedule Creating micro-schedules to avoid construction delays Commissioning of mechanical equipment. Mechanical completion walkdowns Prochem Engineering Ltd., Kilkenny Project Planner Using Microsoft Project to create detailed WBSs for civil, mechanical and electrical projects. Assigning resources and producing budget details for the projects. Liaising with disciplines and suppliers to gauge time of work for project phases. Reviewing critical path to achieve optimum performance of projects. Radley Engineering Ltd., Dungarvan.

Feb 10 May 10 : Position Held:

Jul 09 Oct 09:

Field / Planning Engineer, Based on site at Merck (Carlow) facility. Producing G.As, Isos, P&IDS. Creating test packs. Ensuring documentation compliance with field installation. Surveying and liaising with consultant/client with regard to equipment location. Updating installation schedule using Primavera 6. Creating Micro schedules to get project back on time Apr 09 July09: Position Held: Prochem Engineering Ltd., Kilkenny Senior Piping Designer Based on site at Schering Plough to prepare a basis of design for a new reactor installation. Reviewing and as- building P&IDs. Updating P&IDs to incorporate modifications Surveying existing plant to generate Plot plans showing new equipment locations and tie-ins. Generating MTOs for pricing estimates. Reviewing vendor equipment details.

Nov 08 March 09 Jacobs International Inc. Ltd, Glasgow. Position Held: Senior Piping Designer Projects worked on: Scottish and Southern Power: Alborough II Underground Gas Storage Facility FEED for the installation of nine new Wellheads. Producing isometric's for hydraulic calculation purposes. Cellar and equipment modelling. Various piping studies to facilitate unidirectional drilling. Reviewing Piping Spec's Generation of project specific M.T.O spreadsheets. British Energy: Hunterston B Nuclear Power Station; FEED for reworking a CO2 storage facility. Producing Layouts on Autoplant, Updating associated P&ID's Generating M.T.O's for cost purposes. Hinckley Point B Nuclear Power Station; Designing a new Boiler house facility Producing Bulk M.T.O's, Updating specifications as required. April 07 Oct 08 Prochem Engineering Ltd. Kilkenny.

Position Held:

Construction Services Engineer . Based on site at Abbott Vascular, Clonmel. Drawing Office co-ordinator, responsible for all site drawings. Involved in the commissioning of the utility plant and associated process infrastructure to support the clean rooms start up and validation. Liaison between Abbott and the various on site contractors / consultants with regards to the Construction of a new manufacturing ,warehousing , clean rooms and office facility. Client side construction supervision of the new facility. As building of P&IDs to ensure compliance for validation purposes. Jacobs International Inc. Ltd, Cork. Senior Piping Designer Projects worked on: Cononco Phillips Ireland Ltd: Design and Installation of a new crude spiking pump Design of a new Bio treatment facility, Isometric production using ACAD / Autoplant Piping studies for Jacobs (Holland) Glaxo Smithkline Beecham: Design of a new Thermal Fluid system. Generating bulk M.T.O.s for Front end studies. NavisWorks presentations for client reviews of the new system. Fluor (Ireland) Ltd. Dublin. Piping Designer Based on site in Wyeth Medica (Newbridge). Responsible for the As Building and updating of GMP critical P&IDs to FDA Audit standard. Power User of the AutoManager Meridian. Assisting the Quality and Validation departments. Prochem Engineering Ltd. Kilkenny. Piping Designer / Planner Based on site in Merck Sharp & Dohme (6years): Planning, Design and Procurement and construction of a new HTHM Storage facility. Planning Emergency scrubbing system, including Front End studies. Installation G.As & I.Q. Documentation for Validation.

Jul 06 April 07 Position Held:

Aug 05 Jun 06 Position Held:

July 98 Jul 05 Position Held:

As Building of P&IDs to ensure consistency and accuracy of plant data management system. Liaison with civil and mechanical contractors to ensure work was completed to Merck Standards. CAD manager, responsible for CAD standards, drawing handover and 12 CAD users. Schering Plough (Avondale):Site based design & installation of a C.I.P system. Material procurement & construction supervision. Barclay Chemicals Relocation & expansion of an existing chemical facility.

May 97 June 98 Position Held:

Callaghan Engineering Ltd. Dublin 2. Piping Designer Allied Signal: Installation of Tray drier, Wastewater treatment plant upgrade. Swords Laboratories: P2 relocation of a solvent manifold to avail the space for further production area. Expansion of wastewater treatment facility. Cytotoxic production facility pilot plant. Pfizer Ltd. Based on site as a material / procurement coordinator for a Pharmaceutical upgrade. Minchem: Front-end study for a bioremediation plant. Project Management Ltd. Dublin 24. Piping Designer. Working on site on a major overhaul of a semi-conductor facility for Intel Ireland (FAB 10 project). Feasibility studies for the replacement of Vertical Diffusion Furnaces. Involved in D.I.W generation & Distribution to clean rooms. Tetra Pak (Irl) Ltd. Dublin 18. Piping Designer. Site based engineering for an upgrade of an existing dairy facility. Duties included G.As for new vats, pumps, heat exchangers & integrated C.I.P system. As build P & ID systems & in house design of material conveying systems. Jacobs International Inc. Ltd.

Jan May 1997 Position Held:

Sept Dec 1996 Position Held:

July Aug 1996

Position Held:

Dublin 4. Piping Designer Front end engineering design, feasibility studies, Piping G.As & other discipline generated drawings. H.D.S. Energy Ltd. Piping Designer Front end study for design & installation of a new steam generation system for Irish Refineries at Whitegate, Co. Cork. Site surveying, interfacing with client for tie-ins, routing studies. Callaghan Engineering Ltd. Dublin 2. Piping Draughtsman. Involved in the design & development of a Bulk Canning Facility for B.C.B Beverages located at Cork. D.I.W distribution system for Proctor & Gamble, Nenagh. Johnston Engineering Ltd. Surrey, England Municipal Vehicle Manufacturers. Time served apprenticeship as Mechanical Engineering Technician. Designing and building specialty vehicles from Precinct Sweepers to custom Airport vehicles. Apprenticeship involved Engineering planning, Time Study, Progress Chasing, and two years in Application Engineering.

Feb June 1996 Kildare. Position Held:

June 95 Jan 96 Position Held:

1989 1993

Position Held:

Referees:
Miguel Rivera Project manager MW Group Shanghai Miguel.rivera@mwgroup.net Mark Anderson,
Principal Piping Engineer

Jacobs Glasgow

mark.anderson@jacobs.com Donal Higgins Director Prochem Engineering Kilkenny Donal_Higgins@prochem.ie

You might also like