Project Name Customer Drawing Reff. / Rev Single Line No. / Rev Location / Area
: WORTEL FIELD DEVELOPMENT PROJECT : SANTOS (Sampang) Pty. Ltd. : : : E/I Building System / Sub No. System Desc. Sub System Desc. : 9820-U-009 : Control Room Building System : 9820-U-009-1 Tag No. E03MC
No.
1 2 3 4 5 6 7 8 9 10 11 12
Check frame material have correct specifiction and size Check frame design accordance with design drawing Check frame have correct dimension accordance to design drawing Check that frame have completed fabrication work Check that MCT frame location refer to layout Check that support have completed finishing work Check MCT specification refer to MTO and company specification Check that MCT installed at correct location refer to layout Check that MCT installation arrangement refer to installation detail Check that MCT accessories are installed correctly
Notes :
Description Company
Performed by
Witnessed / Approved by
Witnessed / Approved by
Signature
Project Name Customer Drawing Reff. / Rev Single Line No. / Rev Location / Area
: WORTEL FIELD DEVELOPMENT PROJECT : SANTOS (Sampang) Pty. Ltd. : 9820-64-352-2 : : E/I Building System / Sub No. System Desc. Sub System Desc. : 9820-U-009 : Control Room Building System : 9820-U-009-1 Tag No.
9820-MCT-E01 INDOKOMAS
E03MC
No.
SANTOS
PAL
1 2 3 4 5 6 7 8 9 10
Check frame material have correct specifiction and size Check frame design accordance with design drawing Check frame have correct dimension accordance to design drawing Check that frame have completed fabrication work Check that MCT frame location refer to layout Check that support have completed finishing work Check MCT specification refer to MTO and company specification Check that MCT installed at correct location refer to layout Check that MCT installation arrangement refer to installation detail Check that MCT accessories are installed correctly
Notes :
Description Company
Performed by
Witnessed / Approved by
Witnessed / Approved by
Signature
Project Name Customer Drawing Reff. / Rev Single Line No. / Rev Location / Area
: WORTEL FIELD DEVELOPMENT PROJECT : SANTOS (Sampang) Pty. Ltd. : 9820-64-352-2 : : E/I Building System / Sub No. System Desc. Sub System Desc. : 9820-U-009 : Control Room Building System : 9820-U-009-1 Tag No.
9820-MCT-E02
E03MC
No.
SANTOS
1 2 3 4 5 6 7 8 9 10
Check frame material have correct specifiction and size Check frame design accordance with design drawing Check frame have correct dimension accordance to design drawing Check that frame have completed fabrication work Check that MCT frame location refer to layout Check that support have completed finishing work Check MCT specification refer to MTO and company specification Check that MCT installed at correct location refer to layout Check that MCT installation arrangement refer to installation detail Check that MCT accessories are installed correctly
Notes :
Description Company
Performed by
Witnessed / Approved by
Witnessed / Approved by
Signature
Project Name Customer Drawing Reff. / Rev Single Line No. / Rev Location / Area
: WORTEL FIELD DEVELOPMENT PROJECT : SANTOS (Sampang) Pty. Ltd. : : : System / Sub No. System Desc. Sub System Desc. : : : Tag No.
9820-MCT-E03 INDOKOMAS
E03MC
No.
SANTOS
PAL
1 2 3 4 5 6 7 8 9 10
Check frame material have correct specifiction and size Check frame design accordance with design drawing Check frame have correct dimension accordance to design drawing Check that frame have completed fabrication work Check that MCT frame location refer to layout Check that support have completed finishing work Check MCT specification refer to MTO and company specification Check that MCT installed at correct location refer to layout Check that MCT installation arrangement refer to installation detail Check that MCT accessories are installed correctly
Notes :
Description Company
Performed by
Witnessed / Approved by
Witnessed / Approved by
Signature
Project Name Customer Drawing Reff. / Rev Single Line No. / Rev Location / Area
: WORTEL FIELD DEVELOPMENT PROJECT : SANTOS (Sampang) Pty. Ltd. : : : E/I Building System / Sub No. System Desc. Sub System Desc. : 9820-U-009 : Control Room Building System : 9820-U-009-1 Tag No.
9820-MCT-E06 9820-MCT-101 9820-MCT-102 9820-MCT-103
E03MC
No.
1 2 3 4 5 6 7 8 9 10 11 12
Check frame material have correct specification and size Check frame design accordance with design drawing Check frame have correct dimension accordance to design drawing Check that frame have completed fabrication work Check that MCT frame location refer to layout Check that support have completed finishing work Check MCT specification refer to MTO and company specification Check that MCT installed at correct location refer to layout Check that MCT installation arrangement refer to installation detail Check that MCT accessories are installed correctly
Notes :
Description Company
Performed by
Witnessed / Approved by
Witnessed / Approved by
Signature