Energy Management Performance Contract Installation/Construction Progress Report

January 2014

Johnson Controls

Facilities Included:

Chelmsford, MA
Address Area,sf

Name ofthe Building

Adams Library ByamSchool Central School Admin CommunityEducationSchool DPW Garage FireEast FireNorth FireSouth FireWest HarringtonSchool HighSchool HighwayMaintenance McCarthyMiddleSchool McKayLibrary Parker MiddleSchool PoliceGarage PoliceStation School Center Senior Center SouthRowSchool TownOffice NewDPW ChelmsfordCountryClub ChelmsfordForumIceRink

25BostonRd 25MapleRd. 230 NorthRd. 170 DaltonRd. 54RichardsonRd. 115 RiverneckRd. 35PrincetonBlvd. 295 ActonRd. 260 OldWestfordRd. 120 RichardsonRd. 200 RichardsonRd. 56RichardsonRd. 250 NorthRd. 43NewfieldSt. 75GranitevilleRd. 2AOldeNorthRd. 2 OldeNorthRd. 84Billerica Rd. 75GrotonRd. 250 BostonRd. 50Billerica Rd. 9 Alpha Road 66ParkRoad 2 BrickKilnRd,NBellerica

30,182 60,441 10,192 37,100 11,890 4,226 3,740 2,640 2,796 60,441 285,882 3,300 147,957 4,244 105,400 4,850 26,906 55,562 20,399 42,500 30,912

951,560

Johnson Controls

Baseline Energy Use

Chelmsford, MA
Usage Total (kWh) 426,336 260,240 245,742 212,240 67,090 29,431 26,151 9,988 19,002 263,920 2,043,068 5,787 711,240 8,990 721,440 20,295 579,000 538,350 168,200 198,960 219,800 TotalCost Usage Total (Therms) 15,440 30,995 6,260 27,325 6,144 1,329 2,306 2,101 2,845 29,199 103,936 9,757 59,391 1,484 59,480 7,017 11,453 44,985 6,321 29,623 11,331 0 0 0 TotalCost TotalEnergy Cost $85,577 $77,041 $52,619 $65,343 $21,550 $6,877 $7,519 $4,546 $6,956 $75,240 $427,411 $13,551 $180,870 $3,605 $184,172 $12,658 $99,756 $137,577 $36,392 $66,493 $48,646 $0 $0 $0

Name ofthe Building

Adams Library ByamSchool Central School Admin CommunityEducationSchool DPW Garage FireEast FireNorth FireSouth FireWest HarringtonSchool HighSchool HighwayMaintenance McCarthyMiddleSchool McKayLibrary ParkerMiddleSchool PoliceGarage PoliceStation School Center SeniorCenter SouthRowSchool TownOffice NewDPW ChelmsfordCountryClub ChelmsfordForumIceRink

$65,842 $39,906 $44,571 $32,604 $11,720 $5,084 $4,491 $1,767 $3,251 $40,119 $307,984 $912 $109,534 $1,612 $112,408 $3,485 $85,052 $83,709 $28,313 $30,863 $34,049

$19,735 $37,136 $8,048 $32,739 $9,830 $1,794 $3,027 $2,779 $3,705 $35,121 $119,427 $12,639 $71,336 $1,993 $71,764 $9,173 $14,704 $53,868 $8,079 $35,630 $14,598 $0 $0 $0

6,775,268

$1,047,274

468,716

$567,125

$1,614,399

Johnson Controls

Baseline Energy Use

Chelmsford, MA
kWhUnitCost ($/kWh)Blended $0.154 $0.153 $0.181 $0.154 $0.175 $0.173 $0.172 $0.178 $0.171 $0.152 $0.151 $0.158 $0.154 $0.179 $0.156 $0.172 $0.147 $0.155 $0.168 $0.155 $0.155 UnblendedUnit Cost$/kWh $0.135 $0.135 $0.181 $0.135 $0.175 $0.173 $0.172 $0.178 $0.171 $0.135 $0.138 $0.158 $0.141 $0.179 $0.135 $0.172 $0.135 $0.135 $0.136 $0.136 $0.136 UnitCost ($/Therm) $1.277 $1.198 $1.286 $1.198 $1.601 $1.351 $1.314 $1.324 $1.303 $1.202 $1.148 $1.295 $1.201 $1.345 $1.205 $1.307 $1.284 $1.197 $1.278 $1.203 $1.289 $0.000 $0.000 $0.000

NameoftheBuilding

Adams Library ByamSchool Central School Admin CommunityEducationSchool DPW Garage FireEast FireNorth FireSouth FireWest HarringtonSchool HighSchool HighwayMaintenance McCarthyMiddleSchool McKayLibrary ParkerMiddleSchool PoliceGarage PoliceStation School Center Senior Center SouthRowSchool TownOffice NewDPW ChelmsfordCountryClub ChelmsfordForumIceRink

$0.163

$0.152

$1.117

Johnson Controls

Chelmsford, MA
ECM #1: Lighting Fixture Retrofit
Description: JCI is retrofitting or replacing 1,302 existing lighting fixtures with new high efficiency lighting.
Site/Building Name Lamps Only Retofit Lamps and Ballasts Retofit Fixture Retofits Non Remove Measure

AdamsLibrary ByamElementary CommunityElementary ChelmsfordCountryClub HarringtonElementarySchool ChelmsfordHighSchool ForumIce Arena McKayLibrary McCarthyMiddle School Central School Admin SeniorCenter SouthRowElementary ChelmsfordTownHall Fire DepartmentNorth Fire DepartmentWest Fire DepartmentEast Police Station Police Garage HighwayMaintenance DepartmentofPublicWorks ParkerMiddle School CenterElementary
Totals

14
-

199
-

26
-

52
-

2
-

11
-

14
56

57 13
332

105 21 16 16 14 231 15 69 22 15 19 26 282 3 4 6 278 75 24 8 38 15


1302

34
-

1
-

2 13 2 631
-

20 2
-

1 330
-

1
-

2
-

4 18
1037

5 40
-

10
79

Status ECM: 1 ECM Total $974,559 80% complete $820,075 To date PAC outstanding due to redesign and integration systems into existing, forecast completion February. Various punch list corrections remaining sites, in progress

Johnson Controls

Chelmsford, MA
ECM #2: Lighting Lighting Controls
Description: JCI is installing occupancy controls/sensors to automatically turn off lighting during unoccupied periods. Facilities Included: Status ECM: 2 Chelmsford High School
McCarthy Middle school South Row Elementary School Adams library, DPW Maintenance, Town Hall, Police Station
ECM#2LightingFixture Control Ceiling Wall Total FacilityName Mounted Mounted Photocell Sensors Sensor Sensor ChelmsfordHighSchool 45 113 158 McCarthyMiddle School 14 70 84 SouthRowElementarySchool 3 3 AdamsLibrary 22 5 27 DPWMaintenance 8 8 Police Station 6 7 13 TownHall 13 14 27 Total 108 209 3 320

Total $240,825 100% complete $216,742. To date Various punch list corrections.

Johnson Controls

Chelmsford, MA
ECM #3: Building Envelope - Weatherization
Description:
Doors are being weather-stripped, door sweeps installed / replaced and caulking applied around structural leakage. Window joints being re-caulked around the rough-in perimeter, and locations along the soffit and fascia will sealed. Roof penetrations, wall joints and any other envelope penetrations being properly sealed.

Facilities Included:
All Twenty-three (23) facilities Detailed scope provided in DEA

Status: ECM Total $360,079 100% complete $324,071. to date Various punch list corrections in progress

Johnson Controls

Chelmsford, MA
ECM #4: Building Envelope Roof/Attic Insulation
Description: JCI is installing attic insulation per the below table. Status: Facilities Included:
Byam Elementary School Harrington Elementary School South Row Elementary School Community Education School Adams Library South Fire Station

ECM Total $381,450 100% complete $343,306. to date Various punch list corrections. in progress
Sq.Ft. 1,300 1,300 32,000 1,300 2,400 1,100 RValue 16 16 30 30 60 38

ECM#4AtticInsulation FacilityName ByamElementarySchool HarringtonElementarySchool SouthRowElementarySchool CommunityEducationSchool AdamsLibrary SouthFire

Johnson Controls

Chelmsford, MA
ECM #5: Building Envelope Window Replacement
Description: JCI is replacing the existing windows with new windows per below description. Status: Facilities Included:
South Fire Station Schools Central Administration

ECM Total $9,963 50% complete $4,461. to date Remaining upon mild weather

Central School Administration: Reduce window opening size and install 3 new windows Frame in existing old windows to size for new 5 x 4 2 lite slider vinyl windows, with insulation and drywall above and below on interior and fiberglass on exterior. South Fire Station: Install white vinyl 5 lite bow window to replace old single pane unit u-value of .28 or less

Johnson Controls

Chelmsford, MA
ECM #6 Energy Management System Upgrades
Description: JCI is installing Trend / Novar Building Automation Systems for control of building environments at each location below: Status:
.

Facilities Included:
Chelmsford High School Byam Elementary School Center Elementary School Harrington Elementary School McCarthy Elementary School Parker Elementary School South Row Elementary School Community Education School Adams Library Town Hall Schools Central Administration

ECM Total $3,351,853 44% of upgrades completed $1,466,533 To Date Good working relationship with FMC Technologies (Towns vendor of choice) Complex measure, as varying levels of upgrades are required at each building Project scheduled completion date is late spring 2014

10

Johnson Controls

Chelmsford, MA
ECM #7 Building Controls - Install VFDs on Fans
Description: JCI is furnishing and installing Variable Frequency Drives on existing RTU and AHU Supply and Return Fan Motors. Facilities Included:
Chelmsford High School McCarthy Elementary School Parker Elementary School

Status: ECM Total $165,190 0% To date Detailed survey complete Winter Weather Delay

FacilityName ChelmsfordHighSchool McCarthyMiddle School ParkerMiddle School Total

ECM#7BuildingControlsInstallVFD'sonFans 3HP 5HP 7.5HP 10HP 1 3 11 1 3 2 1 1 6 14 1

15HP 6

20HP 1

Total 23 5 1 29

11

Johnson Controls

Chelmsford, MA
ECM #8 Heating System Furnace / DX Cooling Unit
Description: JCI is providing engineering, material, and labor to replace Furnace (gas fired with split DX Cooling) with new Furnaces (condensing gas fired with split DX cooling) Status: ECM Total $121,267 Facilities Included: $109,140 To date Senior Center Installation of mechanical systems 100% operational
Summary Scope of Work: Remove and dispose existing six (4) gas fired furnaces (with DX split cooling), associated condensing units and refrigerant piping Disconnect existing pipes, electrical wiring, and ductwork, supports etc. to the extent required, and retain for reuse with new system Install six (4) York Series Affinity furnaces (with DX coils) and outside Condensing units. Install refrigerant piping.

12

Johnson Controls

Chelmsford, MA
ECM #9 Air Handling Unit Replacement
Description: JCI is providing engineering, material, and labor to replace AHUs per the below scope. Facilities Included:
Town Hall

Demolition Remove Existing Air Handling Unit located in Gym. Outside air opening to be reused Existing enclosure to remain in place Disconnect gas piping to the extent necessary for new work Disconnect electrical and reserve circuit breakers for new work New Work Furnish and install (2) Reznor gas-fired unit heaters. Heaters to be installed approximately 14 feet above floor. Furnish & install conduit & wiring from nearest available source. Extend existing gas piping and connect to new unit heaters Furnish and install concentric through-wall vent kits for each unit Furnish & Install 2-stage thermostatic control in tamper proof enclosure. Stage 1 to activate one Unit Heater; stage two to activate 2nd . Furnish and install (1) Greenheck wall mount exhaust fan, including electrical. Rework existing outside air openings for new air intake. Provide timer with manual bypass for fan control. Provide manufacturer authorized start-up of new equipment Conduct training for designated personnel in the maintenance, service and operation of the system

Status: ECM Total $41,948 Project scheduled completion date is June 2014, expect to complete early

13

Johnson Controls

Chelmsford, MA
ECM #10 Heating System Boiler Replacements
Description: JCI is providing engineering, material, and labor to replace Boiler per the below scope. Facilities Included:
Town Hall

Status: ECM Total $228,166 $205,349 To date New boilers are in place, and operational New Laars DHW for non-heating season complete and operational Punch list corrections in progress

Scope of Work:
Remove & dispose of existing Weil Mclain HW Boiler.. Install two new Aerco 750,000 BTU gas fired condensing HW boilers, with a combined input rating of 1,500,000 BTU/hr. Boilers will incorporate PVC direct vent systems. Install boiler controller. Install one acid neutralization tank. Connect to boilers and pipe to nearest floor drain. JCI is furnishing and installingone low-loss distribution manifold JCI is furnishing and installingCPVC combustion air and independent exhaust venting per boiler manufacturers instructions. Venting to be routed to building exterior through existing combustion air opening
Johnson Controls

14

Chelmsford, MA
ECM #12: Heating System Pipe and Valve Insulation
Description: JCI is installing insulation on bare pipe and equipment, and replacing damaged existing insulation. Facilities Included: Status: ECM Total $4,650 $4,185. To Date 100% complete Punch list corrections in progress

Byam Elementary School Center Elementary School South Row Elementary School North Fire Station South Fire Station Town Hall

15

Johnson Controls

Chelmsford, MA
ECM #13: Heating System Unit Ventilators
Description: JCI is furnishing and installing all engineering, equipment, and labor for the replacement of existing classroom Unit Ventilators per the below chart. Facilities Included:
Status: ECM Total $2,497,261 $1,400,483 To date Chelmsford High School HS, Harrington, Byam Schools are 90% complete Byam Elementary School Punch list corrections in progress Harrington Elementary School Parker and Comm. Ed. Schools scheduled for Spring Parker Elementary School 2014 Community Education School

ECM#13UnitVentilators FacilityName ChelmsfordHighSchool ByamElementarySchool HarringtonElementarySchool ParkerMiddle School CommunityEducationSchool Total


16 Johnson Controls

Qty. 58 33 33 55 24 203

Chelmsford, MA
ECM #14: Heating System Unit Ventilators W/ DX Cooling
Description: JCI is furnishing and installing all engineering, equipment, and labor for the replacement of existing Unit Ventilators per the below chart. Note added Three Ton DX cooling. Facilities Included:
Chelmsford High School

ECM#13UnitVentilatorsw/DXCooling FacilityName Qty. ChelmsfordHighSchool 10

Status: ECM Total $189,270 90 % Complete $170,343 To date Remaining 10% to be completed during Spring vacation

17

Johnson Controls

Chelmsford, MA
ECM #15: Cooling System Ductless Split System
Description: JCI is providing engineering, material, and labor to install new Ductless Split System per the below scope. Facilities Included:
Town Hall $660,092 ECM Total 20% Complete $132,018 To date

Status: Towns As-built drawings on which project engineering was based were significantly out of date Redesign had to be coordinated with previously planned installation of fire sprinkler system, and New Fire station construction impact. Structural engineer engaged to OK location of roof mounted condenser units found pre-existing damage in roof support joists and leaks Roof joist and leak repairs, Complete Redesigned, stamped construction drawings illustrating new refrigerant piping and sprinkler system, Complete ECM now commencing

Scope of Work:
Removal Existing Through the wall Air Conditioning Units and seal up the openings with proper insulation and cover the interior hole.. Receive & Install new York Split System Units Install indoor units per drawings and install refrigeration piping to condensing units located on the roof. Furnish & install new conduit and wiring to condensing units, including new lockable disconnect for units, suitable for exterior applications. Furnish & install electrical wiring to new indoor units.
18 Johnson Controls

Chelmsford, MA
ECM #17: Cooling System Chiller Replacement
Description: : JCI is providing engineering, material, and labor to replace Chiller per the below scope.
Status: ECM Total $134,353 $40,306 to date Chiller installed, waiting spring startup

Facilities Included:

Center Elementary School

Scope of Work:
Remove and dispose of existing rooftop condenser and indoor chiller barrel and refrigerant piping. Receive & Install new York packaged chiller to be located in place of existing condensing unit Pipe chilled water from previous indoor evaporator to newly installed rooftop chiller Furnish & Install rooftop mounting brackets. Furnish & install new conduit and wiring, including new lockable disconnect for units, suitable for exterior applications.
19 Johnson Controls

Chelmsford, MA
ECM #18: Pumping System - VFDs on Hot Water Pumps
Description : JCI is furnishing and installing Variable Frequency Drives(VFDs) on pumps to control the pump motor speed and thereby control the flow via the hydronic loop. Status: ECM Total $17,714 Facilities Included: 0% To date Center Elementary School Detailed survey complete

FacilityName CenterElementarySchool

ECM#18PumpingSystemInstall VFD'sonHotWaterPumps 3HP 5HP 7.5HP 10HP 15HP 2

20HP

Total 2

20

Johnson Controls

10

Chelmsford, MA
ECM #20: Renewable Energy Photovoltaic Generation Description: JCI is furnishing engineering, materials, and labor to install Solar PV system on school buildings; sizes as shown on below chart. Facilities Included:
Chelmsford High School Byam Elementary School Center Elementary School Harrington Elementary School McCarthy Elementary School Parker Elementary School South Row Elementary School Community Education School

Status: ECM Total $6,563,582 $1,949,807 To date HS 75%,Byam 45%, Harrington 46%, McCarthy, 30% Completion June 2014

21

Johnson Controls

Chelmsford, MA
ECM #20: Renewable Energy Photovoltaic Generation Deliveries: All solar panels, mounting racking delivered to respective sites Construction progress: High School 75% complete Harrington 45% complete Byam 40% complete McCarthy 35% complete Center 30% complete Community Ed. 5% complete Parker 5% complete So. Row 5% complete New DPW 5% complete

22

Johnson Controls

11

Chelmsford, MA
ECM #21: Motors Energy Efficient Motor Replacement
Description: JCI is furnishing and installing supply fan motors for rooftop units per below chart. Status: ECM Total $13,286 Facilities Included: 0$ To date Harrington Elementary School Weather Delay Community Education Center

ECM#21MotorReplacement FacilityName Qty. HarringtonElementarySchool 2 HarringtonElementarySchool 1 HarringtonElementarySchool 1 CommunityEducationSchool 2 Total 6

HP 1.5 2 3 1.5

23

Johnson Controls

Chelmsford, MA
ECM #24: Water Conservation
Description : Existing 3.5 gpf toilets are being replaced with 1.28 gpf fixtures. Existing 2.0 gpf urinals are being retrofitted to 1.0 gpf. Existing 2.2 gpm bathroom sink faucets are being retrofitted to 0.5 gpm. Facilities Included:
Chelmsford High School Harrington Elementary School Senior Center

Status:
ECM Total $144,237 $129, 218 To date Complete
ECM#24WaterConservation ExistingFixture Counts Toilets Sinks Urinals 69 52 73 33 10 29 11 3 11 113 65 113 RetrofitFixture Counts Toilets Sinks Urinals 69 52 26 33 0 29 9 3 11 111 55 66

FacilityName ChelmsfordHighSchool HarringtonElementarySchool SeniorCenter Total

24

Johnson Controls

12

Chelmsford, MA
ECM #25: Vending Machine Controls
Description : JCI is installing Vending Miser controls on all vending machines.. Facilities Included:
Chelmsford High School Byam Elementary School Center Elementary School Harrington Elementary School McCarthy Elementary School Parker Elementary School South Row Elementary School Community Education School

Status: ECM Total $7,567 $6,810 to date Complete 10% retention outstanding
ECM#25VendingMachine Controls FacilityName ChelmsfordHighSchool ByamElementarySchool CenterElementarySchool HarringtonElementarySchool McCarthyMiddle School ParkerMiddle School SouthRowElementarySchool CommunityEducationSchool TownHall Ice Forum Total Qty. 10 2 1 1 1 1 1 1 1 4 23

25

Johnson Controls

Chelmsford, MA
ECM #26: Walk-in Cooler/Freezer Controls
Description : JCI recommends refrigeration controllers on walk-in coolers and freezers and installing electronically commutated (EC) motors on evaporator fans. Facilities Included:
Chelmsford High School Byam Elementary School Center Elementary School Harrington Elementary School McCarthy Elementary School Parker Elementary School South Row Elementary School Community Education School

Status:
ECM Total $78,224 Scheduled for installation March 2014

26

Johnson Controls

13

Chelmsford, MA
ECM #27: Steam to Hot water Conversion
Description: JCI is furnishing and installing all engineering, equipment, and labor for the conversion of existing Steam system to Hot Water system Facilities Included:

Parker Middle School

Status: ECM Total $530,890 $26,545. to date August 2014 Completion Involves asbestos abatement, to be done only during school vacation breaks, In Progress

Complete scope and drawings were included in DEA.


27 Johnson Controls

Chelmsford, MA
ECM #28 Energy Efficient Transformers
Description : JCI is replacing existing transformers with High Efficiency K-Star Harmonic Mitigating Transformers. Facilities Included: Chelmsford High School Parker Middle School Ice Forum Status: ECM Total $179,062 $161,156 to date Complete ahead of schedule

FacilityName ChelmsfordHighSchool ParkerMiddle School Ice Forum Total

ECM#28EnergyEfficientTransformers 20KVA 30KVA 37.5KVA 50KVA 75KVA 2 1 1 1 1 1 2 1 1 4 1 1 3

100KVA 150KVA 225KVA 3 1 3 1 3 3

Total 6 10 1 17

28

Johnson Controls

14

Chelmsford, MA
ECM #29: Street Light Retrofit
Description: JCI is furnishing and installing all engineering, labor, and material for street light retrofit per below schedule. ECM Total $1,230,851 32% To date $393,872 To date
StreetLightingScopeofWorkforTownofChelmsford,MA
ExistingFixtureType
Pole MountedCobra Heads, 100w HPS Pole MountedCobra Heads, 150w HPS Pole MountedCobra Heads, 250w HPS Pole MountedCobra Heads, 400w HPS Pole MountedCobra Heads, 50wHPS Pole MountedCobra Heads, 70wHPS TOTAL
29 Johnson Controls

Qty
27 26 28 14 2073 50 2,218

Existing RecommendedLED Proposed Wattage/Fixture ReplacementfromCREELighting Wattage/Fixture


138 188 295 465 66 95 BXSP2AO2BAUSR (tune to 70watt) BXSP2AO2BAUSR (tune to 90watt) STRLWY2MAA04DULSV700 STRLWY2MAA06DULSV700 BXSPA02AAUSR (tuneto 34watt) BXSPA02AAUSR (tuneto 43watt) 70 90 93 139 34 43

ECM #29: Street Light Retrofit


Towns request to install: CREE BXSPR fixtures in lieu of originally proposed BXSP fixtures. Install 2123 BXSPR low wattage fixtures & 95 BXSP fixtures. Proceed with work until winter conditions necessitate work stoppage. Recommence installation in late March, 2014 or as conditions permit. Estimated substantial completion date of June, 2014 Resulting savings of $173,971.00 for this ECM
Asof011514 Existing 100wattHPSCobraHead 150wattHPSCobraHead 250wattHPSCobraHead 400wattHPSCobraHead 50wattHPSCobraHead 70wattHPSCobraHead Total Proposal New70wattLEDCobraHead New90wattLEDCobraHead New93wattLEDCobraHead New139wattLEDCobraHead New25wattLEDCobraHead(BXSPRTypeII) New25wattLEDCobraHead(BXSPRTypeIII) Revised QTY 27 26 28 14 2,005 30 2,130 Installed QTY 26 10 7 2 700 0 745

30

Johnson Controls

15

Project Financial Summary

Original EPC Contract Approved Changes Contract to Date Completed to Date

$18,126,326 ($159,638) $17,966,698 $7,879,178