Value Concept
Value engineering concentrates on the effectiveness through stating functions, goals, objectives, needs, requirement and desires. Then define the quality features that make the product more acceptable. Finally, generate VE Proposals that meet the requirements at the least possible Life Cycle Cost.
Value Concept
VE is a balance between Function, Quality and Cost as shown in figure :
Function
Value Engineering
Cost
Quality
Value Concept
Function +Performance + Quality Best Value Worth = Cost
Function, Performance and Quality Must Meet the Owners Minimum Requirements
Best Value Worth can be Defined as the Least Cost to Accomplish the Function to an Acceptable Degree
Note that Increased Costs Lowers Best Value Worth - Unless there is an Equal or Greater Increase in Function, Performance or Quality
Value Concept
Function: The specific work that a project must do. Quality : Customer requirements, desires and expectation ,or Fit for Use or the Value-Added benefits Life Cycle Cost (LCC): The initial Cost plus all the associated cost of running the facility. The running cost covers energy, maintenance, repair ,replacement ,staffing ...etc. etc. Over all Expenses = Real Cost + Waste Waste: any process that does not add value to the projects
Value Concept
Value is defined as a fair return or equivalent in goods, services, or money for something exchanged. Value is commonly represented by the relationship: Value Function/Resources where function is measured by the performance requirements of the customer and resources are measured in materials, labor, price, time, etc. required to accomplish that function.
Value Concept
A value methodology focuses on improving value by identifying alternate ways to reliably accomplish a function that meets the performance expectations of the customer.
VE Applicability
VE can be applied during any stage of a projects design development cycle . However , the greatest benefit and resource savings are typically achieved early in the development and conceptual design stages. This is a point in time where the basic information of the intended product is established ,but before major design and development resources are spent .
VE Applicability
VE may be applied more than once during the life of the project. Early application of VE helps to get the project started in the right direction, and repeated applications help to refine the projects direction based on new or changing information. It is important to note that the later that a VE study is conducted, the higher the cost of change will be to implement the improvements.
Detailed Design
Construction
Constructive VE opportunity
Destructive Intervention
VE Job Plan
JOP PLAN
PHASE 1: Information Phase PHASE 2: Function Analysis Phase
VE Job Plan
Information Phase Further familiarization of the project by the team; all team members participate in determine the true needs of the project. Areas of high cost or low worth are identified. The team reviews and defines the current conditions of the project and identifies the goals of the study.
VE Job Plan
Function Analysis Phase The team defines the project functions using a two-word active verb/ measurable noun context. The team reviews and analyzes these functions to determine which need improvement, elimination, or creation to meet the projects goals.
VE Job Plan
Creative Phase: The team lists creative ideas generated from its review of the project with the aim of obtaining a large number of ideas through brainstorming and association of creative proposals. The team employs creative techniques to identify other ways to perform the projects function(s).
VE Job Plan
Evaluation Phase Creative ideas are analyzed , and the team selects the best ideas for further development. The team follows a structured evaluation process to select those ideas that offer the potential for value improvement while delivering the projects function(s) and considering performance requirements and resource limits
VE Job Plan
Development Phase
The team prepares alternative designs with capital and/or life cycle cost comparisons of original designs and proposed alternatives. All recommendations are supplemented with written descriptions, sketches, basic design concepts, technical information and cost summaries. The team develops the selected ideas into alternatives (or proposals) with a sufficient level of documentation to allow decision makers to determine if the alternative should be implemented.
VE Job Plan
Presentation Phase The objective in this phase to present the VE study report to the decisionmakers ,the report includes a statement of the follow-up necessary to ensure implementation ,the presentation may be in written form or both written and oral .
Functionality
Durability Aesthetics Ecology Health Socio-Cultural Sustainability
Information Phase
Gather Information Develop Sustainable Performance criteria Analyze Function Generate Idea Brainstorm Sustainable Targets
Develop & weigh project specific sustainable performance criteria that reflect environment, social and economic issues.
Include Sustainability objectives as functions - encourage alternate modes - reduce waste - conserve energy
Creative Phase
Gather Information Develop Sustainable Performance criteria Analyze Function Generate Idea Brainstorm Sustainable Targets
Analyze Function
Evaluation Phase Develop and Expand Ideas Develop Ideas that improve Sustainability Evaluate and Rank Ideas Consider Sustainability When Ranking Ideas
Consider Sustainability When Ranking Ideas Facilitator ensures some sustainability ideas are carried forward to development
Analyze Function
Development Phase
Present Ideas Consider Sustainability in recommended ideas Develop and Expand Ideas Develop Ideas that improve Sustainability Evaluate and Rank Ideas Consider Sustainability When Ranking Ideas
Develop Ideas that Improve Sustainability Evaluate social, economic, environmental benefits (not just capital cost of idea).
Analyze Function
Presentation Phase
Present Ideas Consider Sustainability in recommended ideas Develop and Expand Ideas Develop Ideas that improve Sustainability Evaluate and Rank Ideas Consider Sustainability When Ranking Ideas
Consider Sustainability in Recommended Ideas Integrate sustainability with project goals and objectives. Show how Value is improved.