You are on page 1of 33

ENDORSEMENT SHEET FOR QP

REFERENCE / STANDARD / FIELD QUALITY PLAN (RQP / SQP/RFQP/SFQP) TO BE FILLED IN BY SUPPLIER AT TIME OF SUBMISSION
PROJECT NAME CONTRACT NO.: MAIN SUPPLIER MANUFACTURER WORKS & ADDRESS ITEM /EQUIPMENT / SYSTEM/ SUB-SYSTEM DETAILS i.e. MODEL TYPE / SIZE /RATING etc. APPROVED QP NO.: RQP/SQP/RFQP/SFQP DADRI CS-6130-108-2-FC-NOA-4722 BHEL M/S BHEL TRICHY BOILER STRUCTURE

To be filled in by NTPC
REVIEW & ENDORSEMENT BY NTPC PROJECT SPECIFIC QP NUMBER ALLOTTED QP NO.: 6130-108-QVM-G-003-01 REV 01 REV. NO.: DATE:
** The RQP/SQP/RFQP/SFQP once endorsed for a particular contract shall remain valid even though the original QP may have expired or revised, unless / otherwise mutually agreed with the supplier.
(TICK APPLICABLE)

0000-999-QV M-T273

REV. NO.: 00

DATED**:29/07/2003

Confirmation by Main Supplier (TICK WHICHEVER APPLICABLE) I. That the item/ component is identical to that considered for QP approval. OR. II. That there are minor changes in the item/ component with respect to that considered for QP approval, however the same do not affect the contents of QP. OR III. That there are minor changes in the item/ component with respect to that considered for QP approval, however the same affect the QP slightly, as indicated BELOW. 1. Log-sheet no. 01 revised as per boiler layout plan drg. For Dadri 2. Log-sheet no. 02 revised as per boiler layout plan drg. For Dadri 3. Log-sheet no. 08 revised as per Trichy instruction of minimum structure required for Lifting boiler Drum .
Revised Log sheets noted. However, BHEL to ensure that the requirements of Erection manual and Erection drawings are completely converted into Log-sheets.

The QP is endorsed for this project without any change The QP is endorsed for this project with changes as indicated. DISTRIBUTION OF ENDORSEMENT OF A) RQP/SQP: 1. MAIN SUPPLIER (WITH A COPY OF QP) 2. MANUFACTURER 3. RIO 4. CQA-SPL 5. CQA-O/C B) RFQP/SFQP: 1. MAIN SUPPLIER (with a copy of QP) 2. MANUFACTURER 3. NTPC FQA (with a copy of QP) 4. NTPC Erection (with a copy of QP) 5. CQA-SPL 2007.05.2 6. CQA-O/C

( H.M.NAGDHAR ) DGM/Quality SIGN.: (Main Supplier) DATE BHEL/PSNR

3 14:25:42 +05'30'
SIGN.: (Manufacturer) DATE: NTPC (Reviewed /Approved by/ Date & Seal)

FORMAT NO.: QS-01-QAI-P-10/ F5-R1

1/1

ENGG. DIV./ QA&I

FIELD QUALITY PLAN


FOR

BOILER STRUCTURES
(Erection) FOR

DADRI TPP - 2 x 490 MW (M/s. National Thermal Power Corporation Ltd.)

BHARAT HEAVY ELECTRICALS LIMITED POWER SECTOR NORTHERN REGION NOIDA

QP NO. : PN-QPE-BR-100 REV.NO.: R00


FMT-QP-001 Rev.01

FIELD QUALITY PLAN FOR


BOILER STRUCTURES (Erection) DADRI TPP 2 x 490 MW (M/s. National Thermal Power Corporation Ltd.)

APPROVED BY QUALITY PLAN NO. ORIGINAL DATE OF ISSUE REVISION NO. & DATE COPY NO. ISSUED TO DATE OF ISSUE

AGM PSNR Q NOIDA

(S K DUTTA) PN-QPE-BR-100 24-04-2007 R00 Dt. 24-04-2007

CONTROLLED / INFORMATION COPY ISSUED BY (SIGNATURE & DESIGNATION)


( H.M.NAGDHAR ) DGM/Quality BHEL/PSNR

H M NAGDHAR/DGM/QUALITY

BHARAT HEAVY ELECTRICALS LIMITED POWER SECTOR NORTHERN REGION


FMT-QP-002 Rev. 01

QP NO. : PN-QPE-BR-100

CONTENTS
PSNR - Quality

REV.NO.: PAGE 1

R00 OF 1

Sl.No. 1.0 2.0 3.0

Description Status of amendments Authorisation for different categories of checks Field Quality Plan for BOILER STRUCTURES (Erection) For DADRI TPP 2 x 490 MW (M/s. National Thermal Power Corporation Ltd.)

No. of Pages 01 01

3.1 3.2 3.3

Statement of checks Documents referred in Quality Plan Log Sheets : L-00 to L-08

10 01 15

******

FMT-QP-003 Rev.00

QP NO. : PN-QPE-BR-100 STATUS OF AMENDMENTS


PSNR Quality

REV.No.: PAGE 1

R00 OF 1 Remarks

Sl.No.

Reference of Sheet(s) Amended


NIL

Amendment No. & Date

FMT-QP-016 Rev. 00

PSNR - Quality

AUTHORISATION FOR DIFFERENT CATEGORIES OF CHECK

Classification of Check Symbol Description BHEL A Critical NTPC BHEL B Major NTPC BHEL C Minor NTPC -----Erection / Commissioning Head of Section Quality Assurance Engineer Erection / Commissioning Inspection Agency Task performer & surveillance by QAE FQA Task performer Erection / Commissioning Task performer Clearing Agency HOS FQA HOS Erection / Commissioning Incharge Task performer Dispositioning Authority Engg. centre / Head Quality - Region CQA Engg. centre / Head Quality - Region FQA Engg. centre / Head Quality - Region

Legend

HOS QAE

NOTE : 1. Dispositioning Authority in A, B & C classes of checks shall be as under : Product non-conformities Process / system non-conformities 2. : Engineering Centre : Head / Quality - Region

QAE shall witness A Category checks. He is also authorised to carry out surveillance in any of theB and C category of checks at his discretion. In case of non-conformity, before accepting, clearing agency shall ensure dispositioning and the same shall be reflected in log sheets / protocols. Non-conformance Procedure, apart from above shall be in line with clause No. 4.7 of QA co-ordination procedure.

3.

4.

FMT QP 004 REV. 00

QP NO. : PN-QPE-BR-100 STATEMENT OF CHECKS


PSNR Quality

REV.No.: PAGE 1

R00 OF 10

Capacity / Type System Sub-System Area


*

: : : :

2 x 490 MW BOILER STRUCTURES ERECTION

For checks where log sheets are not called for, suitable records shall be maintained in the form of log book / protocols. As an evidence of having carried out the work satisfactorily, a general purpose log sheet L-00 shall be maintained for all the checks. The above sub-system covers Foundations, Boiler supporting structures including ceiling structures and welding. NTPC Technical specification and NTPC approved documents relevant to this product shall be binding and any Non-conformation to this shall be referred to NTPC for disposal as per NTPC-CQA non-conformance disposal procedure. Abbreviations used in the column Type of Check are : R M V : Record Verification

* *

: Measurement : Visual

FMT-QP-005 Rev. 00

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : PSNR-QUALITY, NOIDA

PROJECT : DADRI 2 x 490 MW


PACKAGE : SG CONTRACT NO. : CS-6130-108-2FC-NOA-4722 CONTRACTOR : BHEL, PS-NR
FORMAT OF RECORD REMARKS

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
TYPE OF CHECK INSTRUMENT

QP NO. : PN-QPE-BR-100 REV. : R00 DATE : 24-04-2007 PAGE 2 OF 10


CLASS QUANTUM / FREQUENCY OF CHECK

SL. NO.

CHARACTERISTICS / ITEM

REFERENCE DOCUMENT/ ACCETANCE STANDARD

FOUNDATION : 1. Availability of identified & protected permanent bench mark. Elevation of top of foundation pedestals with reference to permanent bench mark. V B 100%

2.

Dumpy level / Water level / Tape Tape

100%

Drawing / Guidelines for erection

L - 01

3.

Disposition of foundation pedestals with reference to longitudinal axis of boiler and reference axis. Spacing between the foundation pedestals.

100%

-do-

L - 02

4.

Tape

100% -do-

L - 02

5. 6.

Diagonals of the main column foundation pedestals. Pitch distance of foundation pedestal bolts on both the axes and its diagonals.

M M

Tape Tape

B C

100% 100% -do-

L - 03 L - 04

FOR NTPC USE BHEL, PSNR-QUALITY BHEL, PS-NR MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE

DOC. NO.

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

FMT-QP-015 REV.02

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : PSNR-QUALITY, NOIDA

PROJECT : DADRI 2 x 500 MW

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
TYPE OF CHECK INSTRUMENT

: SG QP NO. : PN-QPE-BR-100 PACKAGE REV. : R00 CONTRACT NO. : CS-6130-108-2DATE : 24-04-2007 FC-NOA-4722 PAGE 3 OF 10 CONTRACTOR : BHEL, PS-NR
FORMAT OF RECORD CLASS QUANTUM / FREQUENCY OF CHECK REFERENCE DOCUMENT/ ACCETANCE STANDARD REMARKS

SL. NO.

CHARACTERISTICS / ITEM

STRUCTURES : 1. Preassembly of columns before erection, wherever applicable. V/M Tape / Piano wire / Water level - do C 100% Drawing

2.

Individual column piece camber and sweep (Tolerance : 1 mm / M ; 10 mm max.). Camber and sweep for assembled columns (Tolerance : 1 mm / M ; 18 mm max.). Total length of column before erection (Tolerance : 15 mm max.). Orientation of columns. Check for match mark, elevation mark, column No., splice size etc. Ensure matching of centre line of base plate with pedestal axes.

100%

Drawing / Guidelines for Erection - do -

3.

- do -

100%

4.

Tape

100%

- do -

5.

100%

- do -

6.

100%

- do -

FOR NTPC USE BHEL, PSNR-QUALITY BHEL, PS-NR MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE

DOC. NO.

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

FMT-QP-015 REV.02

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : PSNR-QUALITY, NOIDA

PROJECT : DADRI 2 x 500 MW

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
CHARACTERISTICS / ITEM TYPE OF CHECK INSTRUMENT

: SG QP NO. : PN-QPE-BR-100 PACKAGE REV. : R00 CONTRACT NO.: CS-6130-108-2-FC-NOA-4722 DATE : 24-04-2007 CONTRACTOR : BHEL, PS-NR PAGE 4 OF 10
CLASS QUANTUM / FREQUENCY OF CHECK REFERENCE DOCUMENT/ ACCETANCE STANDARD FORMAT OF RECORD REMARKS

SL. NO.

7.

Elevation of column at 1 metre level with reference to bench mark (Tolerance : 5 mm ). Alignment of first piece of column with horizontal beams and vertical bracings (Tolerance : Position w.r.t. reference axis : 5 mm ; elevation : 5 mm). Completion of boxes with main brace level members (MBL). Grouting gap below the column base (Min. 20 mm ; max. 70 mm ). Verification of test certificates and batch certificates of grout material.

Water level / Tape

100%

Drawing / Guidelines for Erection - do L 06

8.

Theodolite / Tape / Plumb bob

100%

9.

100%

- do -

10.

Tape

100%

- do -

11.

100%

Work Instruction for Grouting

12.

Grouting of column bases.

V/R

100%

Drawing / Grout Manufacturers Recommendation

L - 05

FOR NTPC USE BHEL, PSNR-QUALITY BHEL, PS-NR MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE FMT-QP-015 REV.02

DOC. NO.

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : PSNR-QUALITY, NOIDA

PROJECT : DADRI 2 x 500 MW

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
CHARACTERISTICS / ITEM TYPE OF CHECK INSTRUMENT

: SG QP NO. : PN-QPE-BR-100 PACKAGE REV. : R00 CONTRACT NO. : CS-6130-108-2-FC-NOA-4722 DATE : 24-04-2007 CONTRACTOR : BHEL, PS-NR PAGE 5 OF 10
CLASS QUANTUM / FREQUENCY OF CHECK REFERENCE DOCUMENT/ ACCETANCE STANDARD FORMAT OF RECORD REMARKS

SL. NO.

13.

Alignment of columns at every stage of erection.

Theodolite / Tape / Plumb bob Bolt Tension Calibrator / Torque wrench Piano wire / Tape / Water level - do -

100%

Drawing / Guidelines for Erection Drg. / Guidelines for Erection / HSFG Bolt Tightening Procedure Drawing / Guidelines for Erection

L - 06

14.

Tightening of HSFG bolts for column joints, horizontal beams and vertical bracings.

M/V

100%

15.

Camber and sweep of the individual ceiling girder pieces (Tolerance : 1 mm / M, max. 5 mm).

100%

16.

Camber, sweep, diagonal and overall length before and after welding (Tolerance : 1 mm / M, max. 15 mm). Alignment of ceiling girders.

100%

- do -

17.

Tape / Plumb bob / Water level Bolt Tension Calibrator / Torque wrench

100%

- do -

L - 07

18.

Tightening of HSFG bolts between ceiling girders and welded beams (WBs).

100%

Drawing / Guidelines for Erection / HSFG Bolt Tightening Procedure

FOR NTPC USE BHEL, PSNR-QUALITY BHEL, PS-NR MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE FMT-QP-015 REV.02

DOC. NO.

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : PSNR-QUALITY, NOIDA

PROJECT : DADRI 2 x 500 MW

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
CHARACTERISTICS / ITEM TYPE OF CHECK INSTRUMENT

: SG QP NO. : PN-QPE-BR-100 PACKAGE REV. : R00 CONTRACT NO : CS-6130-108-2-FC-NOA-4722 DATE : 24-04-2007 CONTRACTOR : BHEL, PS-NR PAGE 6 OF 10
CLASS QUANTUM / FREQUENCY OF CHECK REFERENCE DOCUMENT/ ACCETANCE STANDARD FORMAT OF RECORD REMARKS

SL. NO.

19.

Verticality of columns before and after ceiling girder erection, at every 5M and at column erection joints.

Theodolite / Plumb bob / Tape Theodolite / Tape

100 %

Drawing / Guidelines for Erection - do -

L-06

20.

Centre line of ceiling girders marked w.r.t. the longitudinal axis of boiler transferred from ground level to top. Readiness of structure for drum erection. Clearance of mile-stone activity. Verticality of all main columns (wherever possible) immediately after drum lifting and compare with previous values. Removal of temporary supports.

100%

L 07

21. 22. 23.

V V M Theodolite / Plumb bob / Tape

A A A

100% 100% 100%

- do -

L 08

Drawing / Guidelines for Erection

L 06

24.

100%

FOR NTPC USE BHEL, PSNR-QUALITY BHEL, PS-NR MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE FMT-QP-015 REV.02

DOC. NO.

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : BHEL, PSNR -QUALITY, NOIDA

PROJECT : DADRI 2 x 500 MW

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
CHARACTERISTICS / ITEM TYPE OF CHECK INSTRUMENT

: SG QP NO. : PN-QPE-BR-100 PACKAGE REV. : R00 CONTRACT NO.: CS-6130-108-2-FC-NOA-4722 DATE : 24-04-2007 CONTRACTOR : BHEL, PS-NR PAGE 7 OF 10
CLASS QUANTUM / FREQUENCY OF CHECK REFERENCE DOCUMENT/ ACCETANCE STANDARD FORMAT OF RECORD REMARKS

SL. NO.

WELDING & NDE : 1. 2. Qualification of welders. Availability of approved WPS, Heat Treatment Schedule, Erection Manual, Storage Manual, Calibration test certificates of instruments used. Adoption of correct procedure, approved electrodes and methods. V/R R A A 100% 100% Welding Manual

3.

V/R

100%

Drawing / Welding Manual / Heat Treatment Manual Drawing / Guidelines for Erection / Heat Treatment Manual

4.

Pre heating and Post Weld Heat Treatment of weld joints.

V/M

Time Temperature Recorder / Thermal Chalk

As per Reference Document

5.

NDE for welds of structural members : a) Edge Preparation : MPI / LPI for new edges prepared at site after flame cutting / trimming of respective member where t 32 mm. V C 100% NDE Manual

FOR NTPC USE BHEL, PS-NR BHEL, PS-QUALITY MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE FMT-QP-015 REV.02

DOC. NO.

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : PSNR-QUALITY, NOIDA

PROJECT : DADRI 2 x 500 MW

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
CHARACTERISTICS / ITEM TYPE OF CHECK INSTRUMENT

: SG QP NO. : PN-QPE-BR-100 PACKAGE REV. : R00 CONTRACT NO : CS-6130-108-2-FC-NOA-4722 DATE : 24-04-2007 CONTRACTOR : BHEL, PS-NR PAGE 8 OF 10
CLASS QUANTUM / FREQUENCY OF CHECK REFERENCE DOCUMENT/ ACCETANCE STANDARD FORMAT OF RECORD REMARKS

SL. NO.

b) Butt Welds : i. MPI / LPI on all back gouged / ground grooves prior to welding from second side. ii. RT for t 32 mm. iii. MPI / LPI on finished welds for t 25 mm < 32 mm. iv. MPI / LPI on finished welds for t < 25 mm. c) Groove Welds : i. MPI / LPI for back gouged / ground area before second side welding in case of double side welding in case of double side groove joint. ii. MPI / LPI on finished welds for t > 25 mm. iii. MPI / LPI on finished welds for 25 mm. V B 100% NDE Manual V B 100% NDE Manual

V V V

B B B

100% 100% 10% of weld length at random

- do - do - do -

V V

B B

100% 10% of weld length at random


DOC. NO.

- do - do -

FOR NTPC USE BHEL, PSNR-QUALITY BHEL, PS-NR MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE FMT-QP-015 REV.02

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : PSNR-QUALITY, NOIDA

PROJECT : DADRI 2 x 500 MW

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
CHARACTERISTICS / ITEM TYPE OF CHECK INSTRUMENT

: SG QP NO. : PN-QPE-BR-100 PACKAGE REV. : R00 CONTRACT NO : CS-6130-108-2-FC-NOA-4722 DATE : 24-04-2007 CONTRACTOR : BHEL, PS-NR PAGE 9 OF 10
CLASS QUANTUM / FREQUENCY OF CHECK REFERENCE DOCUMENT/ ACCETANCE STANDARD FORMAT OF RECORD REMARKS

SL. NO.

d) Fillet Welds : i. LPI / MPI for welds between flange and web. ii. LPI / MPI for other welds joining plate members in which both plate members are over 25 mm thick. iii. All other welds. 6. NDE FOR CEILING GIRDERS : a) Butt welds : i. MPI / LPI for back gouged / ground area before second side welding. ii. MPI on all butt welds for ceiling girders. iii. For flange - RT iv. For web spot RT of joints, including T / + joints. V B 100% - do V V B B 100% 10% of weld length 100% NDE Manual - do -

- do -

V V V

B B B

100% 100% 10% of weld length


DOC. NO.

- do - do - do -

FOR NTPC USE BHEL, PSNR-QUALITY BHEL, PS-NR MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE FMT-QP-015 REV.02

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

FIELD QUALITY PLAN


MANUFACTURERS NAME & ADDRESS

PREPARED BY : PSNR-QUALITY, NOIDA

PROJECT : DADRI 2 x 500 MW

BHEL, PS-NR,
Noida
PSNR - Quality

ITEM

: BOILER

SUB-SYSTEM : STRUCTURES
CHARACTERISTICS / ITEM TYPE OF CHECK INSTRUMENT

: SG QP NO. : PN-QPE-BR-100 PACKAGE REV. : R00 CONTRACT NO : CS-6130-108-2-FC-NOA-4722 DATE : 24-04-2007 CONTRACTOR : BHEL, PS-NR PAGE 10 OF 10
CLASS QUANTUM / FREQUENCY OF CHECK REFERENCE DOCUMENT/ ACCETANCE STANDARD FORMAT OF RECORD REMARKS

SL. NO.

b) Fillet welds : MPI on fillet welds joining web tension flange. V B 100% NDE Manual

FOR NTPC USE BHEL, PSNR-QUALITY BHEL, PS-NR MANUFACTURER / SUBCONTRACTOR CONTRACTOR SIGNATURE FMT-QP-015 REV.02

DOC. NO.

ERECTION
AREA REVIEWED BY NAME & SIGNATURE, OF APPROVING AUTHORITY & SEAL

QP NO. : PN-QPE-BR-100 DOCUMENTS REFERRED IN QUALITY PLAN


PSNR Quality

REV.NO.: R00 PAGE 1 OF 1

SL.NO.
1.

Reference Document
Guidelines for the Erection of Boiler Supporting Structures Tightening Procedure for HSFG Bolts (Pub. No. 2302-82) Welding Manual (Doc. No. :PS:CMX:001 Rev.No.: 01/12-98) NDE Manual (Doc. No. :PS:CMX:002 Rev.No.: 01/12-98) Heat Treatment Manual (Doc. No. :PS:CMX:003 Rev.No.: 01/12-98) Storage & Preservation Instructions for Boiler & Auxiliaries (Doc. No. : PS:CMX:005 Rev. 00 / 93 )

Issuing Authority
BHEL, Trichy

2.

BHEL, Trichy

3.

BHEL, PS-NR, Noida

4.

BHEL, PS-NR, Noida

5.

BHEL, PS-NR, Noida

6.

BHEL, PS-NR, Noida

FMT-QP-017 REV.00

RECORD OF QUALITY CHECKS


PSNR - Quality

SHEET NO. OF QPI

CHECK NO.

RESULTS ACHIEVED OK / NOT OK

DRAWING / DOCUMENT REFERENCE

FORMAT OF RECORD

CHECKED BY SIGN. & DATE

ACCEPTED BY SIGN. & DATE

REMARKS

Note : Any protocol made is to be numbered & mentioned in Format of Record column. SYSTEM SUB-SYSTEM AREA QP NO. : PN-QPE-BR-100 REV. NO. : R00 LOG SHEET NO. : L-00 PAGE 1 OF 1

PROJECT UNIT NO. RATING


FMT-QP-007 REV. 00

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

BOILER FOUNDATIONS TOP OF PEDESTAL


Top elevation of pedestals as per drawing _______ mm Tolerance : + 30 mm - 20 mm Pedestal Sl, No. Designation
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29.
PROJECT UNIT NO. RATING FMT-QP-008 REV.00

Top Elevation

Sl. No.
30. 31. 32. 33. 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45. 46. 47. 48. 49. 50. 51. 52. 53. 54. 55. 56.

All dimensions are in mm Pedestal Top Designation Elevation


S1R S2R S3R S4R S5R S6R S7R S8R S9R S10R S11R S12R S13R S14R S15R S16R S19R S20R S21R S22R S23R S24R S25R S26R S27R LC1R LC2R

S1L S2L S3L S4L S5L S6L S7L S8L S9L S10L S11L S12L S13L S14L S15L S16L S17 S18 S19L S20L S21L S22L S23L S24L S25L S26L S27L LC1L LC2L
NAME CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE & DATE

QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-01 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION DRAWING / DOCUMENT NO. Power Sector - Quality

BOILER COLUMN FOUNDATION PEDESTALS - SPACING


B 1
S22L

2
S23L

3
S1L S2L

4
S3L

5
S4L

6
S5L

7
S6L S21L

S28L
S27L S24L

8 49 50 A
61

44
S7L S8L

9 45 17
S14L

10 46
S9L

11 47
S10L

12 48
S11L

13
S12L

14
S20L

15 60 C

16 51
S13L

52

18
S15L S16L

53 22
S17

57

58
59 S18 S25R

S21L S25R
64 S19

62 LONGITUDINAL AXIS OF BOILER

19
S13R S14R

20
63

21
64 S15R S16R

65 72

26 66
S7R

67
S8R

27 68 74

69
S9R S3R

28 70 75
S4R

29 71
S10R

30
S11R

31 S21 R
S12R S20R

73
S1R S2R

76
S5R

77
S6R

78
S21R 42 S27R 43 S24R

32

33

34 D

35 38

79
S22R

80
S28R

81
S23R

39

40

41

NAME PROJECT UNIT NO. RATING FMT-QP-007 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE / DATE

PN-QPE-BR-100 REV. NO.: R00 LOG SHEET NO.: L-02 PAGE 1 OF 3

QP NO.:

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

BOILER COLUMN FOUNDATION PEDESTALS - SPACING


Sl.No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. Location 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 As per drawing Actual Sl.No. 28. 29. 30. 31. 32. 33. 34. 35. 36. 37. 38. 39. 40. 41. 42. 43. 44. 45. 46. 47. 48. 49. 50. 51. 52. Location 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 1 mm / M, 5 mm max. 1 mm / M, 15 mm max.
SIGNATURE & DATE QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-02 PAGE

As per drawing

Actual

26. 26 53. 27. 27 54. Tolerances : 1. Between adjacent foundation pedestals centres : 2. Spacing between first and last row of foundation : All dimensions are in mm.
NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

BOILER COLUMN FOUNDATION PEDESTALS - SPACING


Sl.No.
55. 56. 57. 58. 59. 60. 61. 62. 63. 64. 65. 66. 67. 68. 69. 70. 71. 72. 73. 74. 75. 76. 77. 78. 79. 80. 81.

Location
55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81

As per drawing

Actual

Sl.No.
82. 83. 84. 85.

Location
A B C D

As per drawing

Actual

NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.0 CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE & DATE

QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-02 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION DRAWING / DOCUMENT NO. Power Sector - Quality

BOILER COLUMN FOUNDATION PEDESTALS - SPACING


B
S22L S23L

S28L
S1L S2L S3L S4L S5L S6L S21L S27L S24L

S7L

S8L

S9L

S10L

S11L

S12L

S20L

S21L
S13L S14L LONGITUDINAL AXIS OF BOILER 63 S13R S14R 64 S15R S15L S16L

A
S17 S18 S25R S16R

S25R
S19

S21 R
S7R S1R S8R S2R S9R S3R S10R S4R S11R S5R S12R S6R S20R S21R S27R S24R

S22R

S28R

S23R

NAME PROJECT UNIT NO. RATING FMT-QP-007 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE / DATE

PN-QPE-BR-100 REV. NO.: R00 LOG SHEET NO.: L-03 PAGE 1 OF 2

QP NO.:

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

DIAGONAL CHECK BETWEEN MAIN COLUMN FOUNDATION PEDESTALS


Diagonal between
S7L & S8R S7R & S8L S13L & S14R S13R & S14L S8L & S9R S8R & S9L S9L & S10R S9R & S10L S15L & S16R S15R & S16L S10L & S11R S10R & S11L S11L & S18 S17 & S12L S17 & S12R S11R & S18 S11L & S12R S11R & S12L

Sl.No.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18

Measurement

Difference

Sl.No.

Diagonal between

Measurement

Difference

Tolerances : 1. Foundation pedestals diagonal difference 2. Cumulative diagonal difference All dimensions are in mm.
NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

: :

1 mm / M, 10 mm max. 1 mm / M, 25 mm max.
SIGNATURE & DATE QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-03 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

PITCH DISTANCE OF FOUNDATION BOLTS AND DIAGONALS


b3 b4

a2 A a1 D1

D2

a4

a3

b1 B
AS PER DRAWING PEDESTAL DESIGNATION L R L R L R L R L R A B a1 a2 a3

b2

a4

b1

b2

b3

b4

D1

D2

Tolerances: 1. Pitch Distances 2. Diagonal Difference


PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

: 3 mm All dimensions are in mm : 5 mm max.


NAME SIGNATURE & DATE QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-04 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

GROUTING OF COLUMN BASES

1.

Column Numbers

2.

Grout Material Specification

3.

Ratio of proportion of grout mix

4.

Whether any additives added

Yes / No

If yes, details

5.

Date of grouting

6.

Whether test cubes have been taken

Yes / No

If yes, test results

7.

Remarks

The following column bases________________________________________are cleared for further erection after ________ days of curing.

NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE & DATE

QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-05 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

VERTICALITY OF COLUMNS
Tolerance: 1mm / M, 25 mm Max. Column Number All dimensions are in mm Inclined towards East West North South

Elevation

NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE & DATE

QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-06 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

CEILING STRUCTURES ALIGNMENT


P S7L S8L Q S9L R S S10L T S11L S12L

GIRDER A GIRDER B GIRDER C GIRDER D GIRDER E C. L. of boiler axis marked on girders

GIRDER F

S7R P1

S8R Q1

S9R R1

S10R S1

S11R T1

S12R

SPACING BETWEEN CEILING GIRDERS: As per drawing

Tolerance :

5 mm Max.

Location P Q R S T

Actual

Location P1 Q1 R1 S1 T1

As per drawing

Actual

All dimensions are in mm

NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE & DATE

QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-07 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

CEILING STRUCTURES ALIGNMENT


DIAGONAL DIFFERENCE BETWEEN ADJACENT CEILING GIRDERS Tolerance : 25 mm Max. Between Girders AB BC CD DE E-F D1 D2 D1~D2

CEILING GIRDER C. L. VARIATION W.R.T. BOILER AXIS : Tolerance : 12 mm Max. All dimensions are in mm

Girder Designation Girder - A Girder B Girder C Girder D Girder E Girder F

Variation w.r.t. boiler axis Towards Left Towards Right

NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE & DATE

QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-07 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

JOINT INSPECTION PROTOCOL FOR COMPLETION OF STRUCTURE PRIOR TO DRUM ERECTION


Sl.No. 1 2 Activity Completion and verification of all log sheets / records of erection. Erection completion of : a) All columns b) Horizontal beams between columns c) Vertical bracings and tie members d) Horizontal bracing on all main brace levels (MBLs) e) Ceiling girders, welded beams (WBs) & ceiling bracings. 3. 4. 5. 6. 7. Welding completion Completion of HSFG bolts tightening. NDE completion Heat treatment completion Remarks : Observation

Note : Minimum structures required for drum erection are listed in sheets 2 / 3 and 3 / 3. Boiler supporting structure is cleared for drum erection.
NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER SIGNATURE & DATE QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-08 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

MINIMUM STRUCTURES REQUIREMENT FOR DRUMERECTION (LIST OF REVAMPED PG - MA UNDER PG - 35


Sl.No. 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
PROJECT UNIT NO. RATING FMT-QP-008 REV.00 ACCEPTED BY CUSTOMER

MA 4 146 4 196 24 335 010 111 112 121 122 130 140 150 190 211 212 213 214 221 222 231 232 311 312 321 322 331 332 341 342 351 352 361 362

Description Upper Drum Sspn Id 6 17300 DL Upper Drum trans Str 4483 DL Slncr & support starting 3320 DL Foundation Materials Main Columns Left Main Columns Left Main Columns Right Main Columns Right Main Columns Middle, except S14 L & S14 R and S17 Auxiliary Columns Left Auxiliary Columns Right Girder Pin Connection Ceiling Girder (fabricated) Ceiling Girder (fabricated) Cross Girder Cross Girder Ceiling Rolled shapes Ceiling Rolled shapes Ceiling Bracing Ceiling Bracing Floor Bracing I MBL Floor Bracing I MBL Floor Bracing II MBL Floor Bracing II MBL Floor Bracing III MBL Floor Bracing III MBL Floor Bracing IV MBL Floor Bracing IV MBL Floor Bracing V MBL Floor Bracing V MBL Floor Bracing VI MBL Floor Bracing VI MBL

1st Pass 2nd Pass 1st Pass 2nd Pass

1st Pass 2nd Pass 1st Pass 2nd Pass 1st Pass @ 2nd Pass @ 1st Pass 2nd Pass 1st Pass 2nd Pass 1st Pass 2nd Pass 1st Pass 2nd Pass 1st Pass 2nd Pass 1st Pass 2nd Pass 1st Pass 2nd Pass
QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-08 PAGE

OF

INSTRUMENT REGN.NO. DATE OF INSPECTION


PSNR - Quality

DRAWING / DOCUMENT REF.

MINIMUM STRUCTURES REQUIREMENT FOR DRUMERECTION (LIST OF REVAMPED PG - MA UNDER PG - 35


Sl.No. MA Description

33 381 Landing Platforms - 1st tier * 34 382 Landing Platforms - 2nd tier * 35 383 Landing Platforms - 3rd tier * 36 390 Drum Floor * 37 441 Main Beams - Lower - 1st Pass 38 442 Main Beams - Middle - 1st Pass 39 443 Main Beams - Upper - 1st Pass 40 451 Main Beams - Lower - 2nd Pass 41 452 Main Beams - Middle - 2nd Pass 42 453 Main Beam - Upper - 2nd Pass 43 511 Front Bracing - Lower 44 512 Front Bracing - Middle 45 513 Front Bracing - Upper 46 521 Side Bracing - Lower 47 522 Side Bracing - Middle 48 523 Side Bracing - Upper 50 531 Rear Bracing - Lower 51 532 Rear Bracing - Middle 52 533 Rear Bracing - Upper 53 700 Fasteners 54 811 Floor grills & Guard Plate * 55 821 Main Stairs - Lower 56 822 Main Stairs - Middle 57 823 Main Stairs - Upper 58 851 Handrails & Posts * @ - Rolled shapes which are required for drum lifting are to be erected and others as and when requirements arises. - These items are not mandatory for drum lift, but may be important from statutory regulation, operation / erection and health / safety point of views.

NOTE : For details refer applicable PGMA list.

NAME PROJECT UNIT NO. RATING FMT-QP-008 REV.00 CHECKED BY ACCEPTED BY CUSTOMER

SIGNATURE & DATE

QP NO.:PN-QPE-BR-100 REV.NO.: R00 LOG SHEET NO.: L-08 PAGE

OF

You might also like