2011-02-23 Thomas Bernt, Facilities Project Director - Mariner Hege Blom, Procurement Manager
1Classification: Internal 2011-02-22
Mariner: Statoil (65 (65,11%), 11%) Eni (28 (28,89%), 89%) Nautical Petroleum (6%) Bressay: Statoil (81,6%) (81 6%) and Shell (18 (18,4%) 4%)
2Classification: Internal 2011-02-22
Operations in Aberdeen, UK
3-
Classification: Internal
2011-02-22
M i Mariner Overview O i
4-
Classification: Internal
2011-02-22
Well layout
Maureen Main 16 Producers 6 Water Injectors Heimdal 44 Dual MLTs 3 Single Producers 32 Water Injectors
5-
Classification: Internal
2011-02-22
Twin-rig setup
PDQ
FSU
Shuttle
Diluent
ESP
6Classification: Internal 2011-02-22
7-
Classification: Internal
2011-02-22
PDQ Platform
60 well slots 2 drilling rigs Living Quarter for 190 people Gas system for import of fuel gas Process Capacities: Reservoir liquid 300 kbl/sd Reservoir oil 60 kbbl/sd Res. Gas 0.34 MSm3/sd Diluent
8-
Classification: Internal
2011-02-22
30000Te
9-
Classification: Internal
2011-02-22
10 - Classification: Internal
2011-02-22
Steel jacket
8 legs Spacing p g at mud line: 62m x 88m Spacing at topside: 28m x 95m, cantilevered 7m to west Five p pile cluster ( (96) ) in each of the four corners Operation Jacket Weight: Launch weight: Pile weight 20 x 96: 17 918t 19 797t 6 800 t
11 - Classification: Internal
2011-02-22
Flare 203Te
12 - Classification: Internal
2011-02-22
Storage capacity: 1 mm bbls (75%crude//25% dil ent) diluent) Export diluent to the PDQ at a rate of up to 20 000 bbls/day) Receive diluted crude oil from the PDQ at a rate of up to 80 000 bbls/day Export the diluted crude oil to North Sea Shuttle Tanker via a Stern Discharge System (SDS)
13 - Classification: Internal
2011-02-22
Bridge connection
Telescopic p bridge g on PDQ to compensate for the FSU movement relative to PDQ A cantilevered truss work bridge on the FSU (45 m)
14 - Classification: Internal
2011-02-22
Development p schedule
Mariner Development Project
Overall Master Schedule
2011 Q1 DG2 Key Milestones Q2 Q3 Q4 Q1 2012 Q2 Q3 Q4 DG3 Q1 2013 Q2 Q3 Q4 Q1 2014 Q2 Q3 Q4 Q1 2015 Q2 Q3 Q4 Q1 2016 Q2 Q3 Q4 2017 Q1 DG4
Study Phase
Definition (FEEDs)
ITT / TEA / CA
PDQ
Fam.
ITT / TEA / CA
FSU Construction
HU /Com
Pre-Drilling
15 - Classification: Internal
2011-02-22
Procurement
17 - Classification: Internal 2011-02-22
Procurement philosophy
All procurement will be according to the European Economic Act (EEA) Qualification through FPAL Global competition Final contract split/strategy will be settled through the FEED phase (2011) Most likely major contracts huge global companies Optimal split based on market opportunities, interface handling, risk sharing, and company organisational strategy Final procurement strategy to be approved by Statoil management and the partners
18 - Classification: Internal
2011-02-22
19 - Classification: Internal
2011-02-22
20 - Classification: Internal
2011-02-22
21 - Classification: Internal
2011-02-22
Market communication
A supplier conference was arranged in London summer 09 to inform about the projects Statoil, Statoil UK is presently evaluating to join the Supply Chain Code of Practice Statoil to be represented on OE2011 (and Share Fair 2011) Ongoing communication with potential FEED contractors Dialogue meetings with potential major EPC (FC) contractors in 2011 Communication strategy gy to be established within 1Q2011 Q International UK - regional/local companies UK seminars are foreseen from 2011 ( (arranged g by y Statoil or applicable pp networks) Generally major Statoil projects establish a project specific web site, incl procurement issues e issues, e.g. g strategies strategies, plans plans, contact persons persons, awarded contracts etc etc.
22 - Classification: Internal
2011-02-22
H How t to prepare ?
Qualified/register in FPAL As a supplier: What is my core business, contribution, level who is my partner ? To be qualified with respect to: HSE References Financial situation Capacity Necessary approvals from UK authorities if applicable
23 - Classification: Internal
2011-02-22
24 - Classification: Internal
2011-02-22
25 - Classification: Internal
2011-02-22
Thank you y