You are on page 1of 21

DATA RATES- P AND M WORKS

NIL

0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3

0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day Day

Quantity 0.50 17.00 17.00

Maistry Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 70.75 2244.00 2218.50 4533.25 45.33 453.33 679.99 226.66 5938.56

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 cum Rs: Rate per cum Rs: Rate approved per cum Rs: YEAR: 2010-11

0.00 0.00 5938.56 5938.56 0.00 5938.56 59.00 59.00 ITEM No: 36.b

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Removing and hauling all kinds of soil / soft rock including boulders upto 0.6 m diameter slipped due to natural geological causes and disposing off the same in specified dump

area or as directed including costof all materials, machinery, labour, rampways and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. Note: The rate under this item is for unit quantity of soil / soft rock in slipped condition. The wieghted average rate applicable to entire quantity based on rates provided under items 36.b and 37.b may be considered where the slipped material consists of mixture of soil / soft rock and hard rock. DATA: The quantity assumed for analysis is the volume of soil / soft rock in slipped condition. For soil / soft rock in slipped condition 10 % bulkage is assumed and further bulkage of another 10 % is asssumed on digging / loading the slipped soil / soft rock mass for disposal. Therefore, the measurement for soil / soft rock shall be for the volume in slipped condition and not for the original in-situ condition. Consider 95 % quantity with 1 km lead for disposal by shovel and tipper combination. Consider 5 % quantity ( residual muck at bed ) with 50 m lead for disposal by work force. Capacity of shovel bucket : 0.50 cum Capacity of shovel bucket under heaped condition : 0.58 cum

80

DATA RATES- P AND M WORKS

Capacity of tipper : 5.00 cum Lead for disposal of excavated soil : Upto 1 km Speed for loaded tipper under temperary haul road condition : 15 km / hr Speed for empty tipper under temperary haul road condition : 20 km / hr Turning and unloading time : 2.00 min Shovel digging and loading cycle per bucket : 20 sec Slipped condition quantity / bucket with 10 % bulkage ( 0.58 /1.10 ) : 0.52 cum Slipped condition quantity / load with 10 % bulkage ( 5 / 1.1 ) : 4.54 cum Number of buckets per load ( 4.54 / 0.52 ) say : 9 buckets Corrected Quantity of in-situ soil per load ( 9 x 0.52 ) say : 4.68 cum Ideal cycle time for loading 9 buckets ( 9 x 20 / 60 ) : 3.00 min The ideal cycle time for shovel requires spotting of a tipper within 3.00 minutes near the shovel. However, in practice for removal of slipped soil the space available may not permit positioning of tippers on either side of the shovel. Generally, one tipper has to move after loading to position the next tipper for loading. Assuming one cycle time extra the corrected cycle time for the shovel will be 3.33 minutes. Round trip cycle time for tipper: Corrected cycle time of shovel for digging and loading : 3.33 min Time for 1 km haulage under load ( 60 / 15 ) : 4.00 min Time for turning and un-loading : 2.00 min Time for 1 km return trip ( 60 / 20 ) : 3.00 min Time for turning and spotting : 1.00 min Total : 13.33 min No.of tippers to match corrected cycle time of shovel( 13.33 / 3.33) : 4 Nos Output of tipper / hr with 50 min working / hr ( 50 x 4.68 / 13.33 ) : 17.55 cum Considering use of shovel and tippers for 0.5 hour for rampway formation and other preliminary works the output for 4 tippers per day will be ( 4 x 17.55 x 7.5 ) : 526 cum Further, assuming removal of about 95 percent of slipped muck by deploying shovel and about 5 percent muck by manual labour the daily output will be say : 550 cum Average output of 1 heavy and 1 light mazdoor assumed at 6 cum / day for removing muck. Consider removal of 550 cum slipped soil / soft rock by deploying machinery for rate analysis. 1. Requirement of materials : No materials required.

2. Requirement of machinery : Deploy 1 No. 0.5 cum shovel for 8 hours including time required for forming rampways etc. Deploy 4 Nos. tippers for 8 hours. 3. Requirement of workforce ( Other than machinery crew ) : Maistry : 1 No. Heavy mazdoor : 4 Nos. Light mazdoor : 4 Nos. RATE ANALYSIS A. MATERIALS: Sl No 1 Perticulars NIL Unit Quantity 0.00 0.00 1% 10% UNIT : 550.00 cum Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Amount in Rs. 0.00 0.00 0.00 0.00 0.00

Add for small Tools and Plants @ Add for Contractor's Profit @

81

DATA RATES- P AND M WORKS

Add for Contractor's Overheads @

5% Total cost of Materials :

Rs: Rs:

0.00 0.00

B. MACHINERY: Sl No 1 2

Description

Unit Hour Hour Hour Hour

Quantity 8.00 8.00 32.00 32.00

Shovel 0.5 cum capacity Fuel / Energy charges Tippers 5 cum capacity 4 Nos Fuel / Energy charges

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3 4 5

Rate in Rs. 725.00 330.00 271.00 208.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 5800.00 2640.00 8672.00 6656.00 23768.00 237.68 929.60 1188.40 26123.68

Description

Unit Hour Hour Day Day Day

Quantity 8.00 32.00 1.00 4.00 4.00

Crew for Shovel Crew for Tipper Maistry Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 77.50 56.70 141.50 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 620.00 1814.40 141.50 528.00 522.00 3625.90 36.26 362.59 543.89 181.30 4749.93

ABSTRACT: A. Cost of Materials

Rs:

0.00

B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: TOTAL Rs: 0.00% Rs: 550.00 cum Rs: Rate per cum Rs: Rate approved per cum Rs: YEAR: 2010-11

26123.68 4749.93 30873.61 0.00 30873.61 56.00 56.00 ITEM No: 37.a

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Removing and hauling hard rock of all toughness including boulders above 0.6 m diameter slipped due to natural geological causes including breaking large fragments by blasting if necessary and disposing off the same in specified dump area or as directed including cost of all materials, machinery, labour, rampways and all other ancillary operations etc., complete with initial lead upto 50 m and lift upto 1.5 m. Note: The rate under this item is for unit quantity of hard rock in slipped condition. The rate under this item shall be adopted where the material can be disposed off within 50 m lead or where the slipped zone is inaccessible for disposal of material by mechanical mode.

82

DATA RATES- P AND M WORKS

The wieghted average rate applicable to entire quantity based on rates provided under items 36.a and 37.a may be considered where the slipped material consists of mixture of soil / soft rock and hard rock. DATA: Consider removal of 100 cum slipped hard rock for rate analysis. The quantity assumed for analysis is the volume of rock in slipped condition. Therefore, the measurement of rock shall be for the volume in slipped condition and not for the original in-situ condition. Drilling and Blasting : Quantity of slipped rock requiring blasting assumed : 100 cum As there will be no side and bed tightness for slipped rock mass the spacing of jack hammer holes can be more than the normal spacing of 1 x 1.2 m grid. Consider the spacing of holes at 1.5 times the normal spacing for slipped rock mass. Grid spacing of holes say : 1.5 x 2 m As there will be no bed tightness for slipped rock mass no sub-drilling is necessary. Considering average 0.8 m deep holes. Yeild per hole for 1.5 x 2 m grid spacing ( 1.5 x 2 x 0.8 ) : 2.40 cum Number of holes for 100 cum slipped rock ( 100 / 2.4 ) : 42 holes Depth of drilling for 42 holes at 0.8 m / hole ( 42 x 0.8 ) : 34 m Rate of drilling by jack hammers : 8 m / hour With 50 min / hour working rate of drilling ( 8 x 50 / 60 ) say : 6.5 m / hour Hourly output for 2 jack hammers : 13 m Time required for drilling 34 m ( 34 / 13 ) : 2.60 hours Disposal of muck : Manual labour is proposed for disposal of muck. Output of 1 heavy mazdoor and 1 light mazdoor assumed @ 5.5 cum / day. 1. Requirement of materials : Small dia explosive @ 0.25 kg / cum Number of electric detonators @ 1 / hole Detonating fuse coil @ 1.0 m / hole Jack hammer drill rod

( 100 x 0.25 )

: : : :

25 kg 42 Nos 42 m 34 m drilling

2. Requirement of machinery : Deploy 8.5 cmm air compressor for 2.6 hours. Deploy 2 Jack hammers for 2.6 hours. 3. Requirement of workforce ( Other than machinery crew ) : Maistry Blaster ( licensed ) Helper blasting Stone breaker Heavy mazdoor Light mazdoor 4. Use rate of materials : Cost of drill rod 1.5 m length @ Rs: 3400.00 / No. Life of drill rod with reconditioning Use rate of drill rod per Rm drilling ( cost / life ) Length of air and water hose assumed Cost of 25 mm dia air hose 25 m @ Rs: 150.00 / Rm Life of air hose Use rate of air hose per hour ( cost / life )

: : : : : :

0.5 No. 0.5 No. 0.5 No. 2 Nos. 18 Nos. 18 Nos.

Rs: 3400.00 : 150 m Rs: 22.67 : 25 m each Rs: 3750.00 : 800 hours Rs: 4.69

83

DATA RATES- P AND M WORKS

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Perticulars Unit Rm kg Nos. Rm Hour LS Quantity

UNIT :

100.00 cum Rate in Rs. 22.67 45.00 10.00 8.00 4.69 30.00 Total Rs: Rs: Rs: Rs: Rs: Amount in Rs. 770.67 77.07 1125.00 420.00 336.00 24.38 30.00 2783.11 27.83 278.31 139.16 3228.41

Use rate of drill rod Reconditioning charges @ 10% Explosive small dia. Detonator ( ele ) Detonating fuse coil Use rate of air hose Sundries Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @

34.00 25.00 42.00 42.00 5.20 1.00

1% 10% 5% Total cost of Materials :

B. MACHINERY: Sl No 1 2 3

Description

Unit Hour Hour Hour Hour LS

Quantity 2.60 2.60 5.20 5.20 0.50

Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Jack hammer Fuel / Energy charges Sundries

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery :

Rate in Rs. 202.00 619.00 14.00 5.00 30.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 525.20 1609.40 72.80 26.00 15.00 2248.40 22.48 165.04 112.42 2548.34

C. LABOUR: Sl No 1 2 3 4 5 6 7 8

Description

Unit Hour Hour Day Day Day Day Day Day

Quantity 2.60 5.20 0.50 0.50 0.50 2.00 18.00 18.00

Crew for Air compressor Crew for Jack hammer Maistry Blaster ( Licensed ) Helper blasting Stone breaker Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 72.10 111.90 141.50 147.00 141.50 146.00 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 187.46 581.88 70.75 73.50 70.75 292.00 2376.00 2349.00 6001.34 60.01 600.13 900.20 300.07 7861.76

ABSTRACT: A. Cost of Materials

Rs:

3228.41

84

DATA RATES- P AND M WORKS

B. Hire charges of Machinery C. Cost of Labour Add for other enabling works @ Total cost for

Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 cum Rs: Rate per cum Rs: Rate approved per cum Rs: YEAR: 2010-11

2548.34 7861.76 13638.51 0.00 13638.51 136.00 136.00 ITEM No: 37.b

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Removing and hauling hard rock of all toughness including boulders above 0.6 m diameter slipped due to natural geological causes including breaking large fragments by blasting if necessary and disposing off the same in specified dump area or as directed including cost of all materials, machinery, labour, rampways and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. Note: The rate under this item is for unit quantity of rock in slipped condition. The wieghted average rate applicable to entire quantity based on rates provided under items 36.b and 37.b may be considered where the slipped material consists of mixture of soil / soft rock and hard rock. DATA: The quantity assumed for analysis is the volume of rock in slipped condition. For rock in slipped condition 20 % bulkage is assumed and further bulkage of another 20 % is asssumed on breaking the slipped rock mass for disposal. Therefore, the measurement of rock shall be for the volume in slipped condition and not for the original in-situ condition. Consider 95 % quantity with 1 km lead for disposal by shovel and tipper combination. Consider 5 % quantity ( residual muck at bed ) for disposal by work force. Disposal of muck : Distance of dump yard from slip area : Upto 1 km Haulage of slipped hard rock muck : By tippers

Capacity of shovel bucket : 0.50 cum Capacity of shovel bucket under heaped condition : 0.58 cum Capacity of tipper : 5.00 cum Lead for disposal of excavated rock : Upto 1 km Speed for loaded tipper under moderate site conditions : 15 km / hr Speed for empty tipper under moderate site conditions : 20 km / hr Turning and unloading time : 2.00 min Shovel digging and loading cycle per bucket : 30 sec Slipped condition qty / bucket for 20 % bulkage ( 0.58 / 1.20 ) : 0.48 cum Slipped condition qty per load for 20 % bulkage ( 5 / 1.20 ) : 4.17 cum Number of buckets per load ( 4.17 / 0.48 ) say : 9 buckets Corrected quantity / load for 9 buckets ( 9 x 0.48 ) : 4.32 cum Ideal cycle time for loading 9 buckets ( 9 x 30 / 60 ) : 4.50 min The ideal cycle time for shovel requires spotting of a tipper within 4.50 minutes near the shovel. However, in practice for such excavation works the space available may not permit positioning of tippers on either side of the shovel. Generally one tipper has to move beyond rampway after loading to position next tipper for loading. Assuming one loading cycle extra, the corrected cycle time for shovel will be ( 10 x 30 / 60 ) : 5.00 min Round trip cycle time for tipper: Corrected cycle time of shovel for digging and loading : 5.00 min Time for 1 km haulage under load ( 60 / 15 ) : 4.00 min

85

DATA RATES- P AND M WORKS

Time for turning and un-loading Time for 1km return trip Time for turning and spotting

( 60 / 20 )

Total No.of tippers to match corrected cycle time of shovel ( 14.50 / 5.00 ) Consider 3 tippers for analysis. Output of tipper / hr with 50 min working / hr ( 50 x 4.32 / 14.50 ) : 14.90 cum Output of 2.90 tippers / day ( slipped qty ) ( 14.90 x 2.90 x 8 ) : 346 cum Considering disposal of about 95 % muck by shovel and 5 % at bed by manual labour the total output per day will be ( 346 / 0.95 ) : 364 cum Consider output of 1 heavy mazdoor and 1 light mazdoor at 5 cum / day. Consider removal of 364 cum slipped rock for rate analysis. Drilling and Blasting : Quantity of slipped rock requiring blasting : 364 cum As there will be no side and bed tightness for slipped rock mass the spacing of jack hammer holes can be more than the normal spacing of 1 x 1.2 m grid. Consider the spacing of holes at 1.5 times the normal spacing for slipped rock mass. Grid spacing of holes say : 1.5 x 2 m As there will be no bed tightness for slipped rock mass no sub-drilling is necessary. Considering average 0.8 m deep holes. Yeild per hole for 1.5 x 2 m grid spacing ( 1.5 x 2 x 0.8 ) : 2.40 cum Number of holes for 364 cum slipped rock ( 364 / 2.4 ) : 152 holes Depth of drilling for 152 holes at 0.8 m / hole ( 152 x 0.8 ) : 122 m Rate of drilling by jack hammers : 8 m / hour With 50 min / hr working rate of drilling ( 8 x 50 / 60 ) say : 6.5 m / hour Hourly output for 2 jack hammers : 13 m Time required for drilling 122 m ( 122 / 13 ) say : 9.50 hours 1. Requirement of materials : Small dia explosive @ 0.25 kg / cum ( 364 x 0.25 ) : 91.00 kg

: : : : :

2.00 min 3.00 min 0.50 min 14.50 min 2.90 Nos

Number of electric detonators @ 1 / hole ( 152 x 1 ) Detonating fuse coil @ 1 m / hole ( 152 x 1 ) Jack hammer drill rod 2. Requirement of machinery : Deploy 8.5 cmm air compressor for 9.5 hours. Deploy 2 Jack hammers for 9.5 hours. Deploy Angle dozer for 0.5 hour for formation of approach / rampway etc. Deploy 1 shovel 0.5 cum capacity for 8 hours. Deploy 3 tippers for 8 hours for disposal of muck. 3. Requirement of workforce ( Other than machinery crew ) : Maistry Blaster ( licensed ) Helper blasting Stone breaker Heavy mazdoor Light mazdoor 4. Use rate of materials : Cost of drill rod 1.5 m length @ Rs: 3400.00 / No. Life of drill rod with reconditioning Use rate of drill rod per Rm drilling ( cost / life ) Length of air and water hose assumed Cost of 25 mm dia air hose 25 m @ Rs: 150.00 / Rm

: 152 Nos say : 152 m : 122 m drilling

: : : : : :

1 No. 1 No. 1 No. 1 No. 4 Nos. 4 Nos.

Rs: 3400.00 : 150 m Rs: 22.67 : 25 m each Rs: 3750.00

86

DATA RATES- P AND M WORKS

Life of air hose Use rate of air hose per hour RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 Perticulars Unit Rm kg Nos. Rm Hour LS

( cost / life ) UNIT : Quantity 122.00 91.00 152.00 152.00 19.00 2.00

: 800 hours Rs: 4.69 364.00 cum Rate in Rs. 22.67 45.00 10.00 8.00 4.69 30.00 Total Rs: Rs: Rs: Rs: Rs: Amount in Rs. 2765.33 276.53 4095.00 1520.00 1216.00 89.06 60.00 10021.93 100.22 1002.19 501.10 11625.44

Use rate of drill rod Reconditioning charges @ 10% Explosive small dia. Detonator ( ele ) Detonating fuse coil Use rate of air hose Sundries Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @

1% 10% 5% Total cost of Materials :

B. MACHINERY: Sl No 1 2

Description

Unit Hour Hour Hour Hour

Quantity 9.50 9.50 19.00 19.00

Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Jack hammer Fuel / Energy charges

Rate in Rs. 202.00 619.00 14.00 5.00 Contd

Amount in Rs. 1919.00 5880.50 266.00 95.00

B. MACHINERY ( Contd ) : Sl No Description

Unit

Quantity

3 4 5 6

Angle dozer Fuel / Energy charges Shovel 0.85 cum Fuel / Energy charges Tipper 5 cum ( 3 Nos ) Fuel / Energy charges Sundries

Hour Hour Hour Hour Hour Hour LS

0.50 0.50 8.00 8.00 24.00 24.00 1.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery :

Rate in Rs. Contd 1154.00 423.00 725.00 330.00 271.00 208.00 30.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 577.00 211.50 5800.00 2640.00 6504.00 4992.00 30.00 28915.00 289.15 1363.75 1445.75 32013.65

C. LABOUR: Sl No 1 2

Description

Unit Hour Hour

Quantity 9.50 19.00

Crew for Air compressor Crew for Jack hammer

Rate in Rs. 72.10 111.90

Amount in Rs. 684.95 2126.10

87

DATA RATES- P AND M WORKS

3 4 5 6 7 8 9 10 11

Crew for Dozer Crew for Shovel Crew for Tipper Maistry Blaster ( Licensed ) Helper blasting Stone breaker Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

Hour Hour Hour Day Day Day Day Day Day

0.50 8.00 24.00 1.00 1.00 1.00 1.00 4.00 4.00

1% 10% 15% 5% Total cost of Labour :

77.50 77.50 56.70 141.50 147.00 141.50 146.00 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

38.75 620.00 1360.80 141.50 147.00 141.50 146.00 528.00 522.00 6456.60 64.57 645.66 968.49 322.83 8458.15

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for other enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 364.00 cum Rs: Rate per cum Rs: Rate approved per cum Rs:

11625.44 32013.65 8458.15 52097.23 0.00 52097.23 143.00 143.00

SECTION:PRELIMINARY & MAINTENANCE WORKS

YEAR: 2010-11

ITEM No: 38

ITEM: Cleaning concrete / masonry / rock surface for guniting / shotcreting by sand blasting method as per specifications including cleaning by air and water jets after sand blasting cost of all materials, labour, machinery, scaffolding etc., complete with initial lead for sand upto 1 km and all lifts. DATA: Consider 100 sqm area for cleaning: 1. Requirement of materials : Sand of gradation 2mm to 1mm @ 0.10 cum / sqm Approximately 2 cum natural river sand yeilds 1 cum of sand blasting grade sand after seiving in 2mm and 1 mm sieves. Allowing 10 % extra for undulations etc., the actual area of sand blasting :: 110 sqm Requirement of processed sand ( 110 x 0.10 ) : 11.00 cum Requirement of natural river sand ( 11.00 x 2 ) : 22.00 cum 2. Requirement of machinery : Output of sand blasting per hour : 20 to 25 sqm Considering 50 minutes per hour working, Requirement of 8.5 cmm compressor ( 110 x 60 / 50 / 22.5 ) : 6 hours Requirement of sand blasting equipment : 6 hours 3. Requirement of workforce ( Other than machinery crew ) : Heavy mazdoor: For seiving sand : 4 Nos. For loading sand blast drum : 2 Nos.

88

DATA RATES- P AND M WORKS

For assisting sand blaster Light mazdoor: For seiving sand For cleaning / collection of rebound sand and other works 4. Use rate of materials : Cost of 25 mm dia 50 m air hose @ Rs: 150.00 / Rm Life of air hose Use rate of air hose per hour ( cost / life ) Cost of sand blast gun nozzle @ Rs: 312.00 / Each Life of sand blast gun nozzle Use rate of sand blast gun nozzle per hour ( cost / life ) Cost of 20 mm dia 50 m water hose @Rs: 128.00 / Rm Life of air hose Use rate of air hose per hour ( cost / life ) RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 Perticulars Unit cum Hour Hour Hour LS Quantity 22.00 6.50 6.50 6.00 4.00 UNIT :

: 1 No. : 4 Nos. : 2 Nos. Rs: 7500.00 : 800 hours Rs: 9.38 Rs: 312.00 : 200 hours : 1.56 Rs: 6400.00 : 800 hours Rs: 8.00 100.00 sqm Rate in Rs. 154.00 9.38 8.00 1.56 30.00 Total Rs: Contd Amount in Rs. 3388.00 60.94 52.00 9.36 120.00 3630.30

Natural river sand ( unscreened ) Use rate of air hose Use rate of water hose Use rate of sand blast gun nozzle Sundries( Seive etc )

A. MATERIALS ( Contd ): Sl No Perticulars

Unit

Quantity

Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add for scaffolding etc @

1% 10% 5% 10% Total cost of Materials :

Rate in Rs. Contd Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 36.30 363.03 181.51 363.03 4574.17

B. MACHINERY: Sl No 1 2 3

Description

Unit Hour Hour Hour Hour Hour Hour

Quantity 6.50 6.50 6.50 6.50 6.00 6.00

Air compressor 8.5 cmm diesel Fuel / Energy charges Pump 5 hp ( diesel ) Fuel / Energy charges Sand blasting equipment Fuel / Energy charges

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery :

Rate in Rs. 202.00 619.00 7.00 55.00 84.00 9.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 1313.00 4023.50 45.50 357.50 504.00 54.00 6297.50 62.98 443.50 314.88 7118.85

89

DATA RATES- P AND M WORKS

C. LABOUR: Sl No 1 2 3 4 5

Description

Unit Hour Hour Hour Day Day

Quantity 6.50 6.50 6.00 7.00 6.00

Crew for Air compressor Crew for pump Crew for Sand blasting equipment Heavy mazdoor Light mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @ ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 72.10 35.80 74.40 132.00 130.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 468.65 232.70 446.40 924.00 783.00 2854.75 28.55 285.48 428.21 142.74 3739.72 4574.17 7118.85 3739.72 15432.75 0.00 15432.75 154.00 154.00

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 sqm Rs: Rate per sqm Rs: Rate approved per sqm Rs:

SECTION:PRELIMINARY & MAINTENANCE WORKS

YEAR: 2010-11

ITEM No: 39

ITEM: Providing 40 mm thick shotcreting in layers to concrete / masonry surface in cement concrete 1 : 2 : 2 proportion by weight using 6 mm down size hard graded crushed aggregate including cost of all materials, machinery, labour, cleaning joints / surface, scaffolding wherever required and all other ancillary operations etc., complete with initial lead upto 1 km and all lifts. DATA: Thickness of shotcreting : 40 mm Concrete mix proportion by weight : 1:2:2 Water to cement ratio by weight : 0.35 Unit weight of concrete 1 : 2 : 2 proportion by weight in kg / cum : 2450 Cement per cum of concrete : 455 kg Sand per cum of concrete : 0.55 cum Coarse aggregate per cum of concrete : 0.57 cum During shotcreting a portion of the concrete mix is wasted due to rebounding of mainly sand and coarse aggregate particles. The extend of rebound varies from 30 to 35 percent. For the purpose of data rate the extend of rebound is considered at 32.5 percent. The actual mix proportion in the finished shotcreting will b around 1 : 1.54 : 1.54 by weight. For 40 mm thick shotcreting the rate of progress will be 2 to 3 sqm per hour. For data rate analysis the rate of progress is considered at 2.5 sqm per hour. For shift of 8 hours the progress will be 20 sqm. Consider 20 sqm shotcreting in cement concrete 1 : 2 : 2 propn for rate analysis. 1. Requirement of materials : Qty of concrete for 20 sqm with 32.5 % rebound (20 x 1.325 x 0.04) : 1.06 cum Add concrete for filling depressions / joints / crevices etc @ 5 % : 0.05 cum Total quantity of concrete for 20 sqm : 1.11 cum

90

DATA RATES- P AND M WORKS

2.

3.

4. 5.

Quantity of cement with 1 % wastage ( 1.11 x 455 x 1.01 ) : 510 kg Quantity of sand with 2 % wastage ( 1.11 x 0.55 x 1.02 ) : 0.62 cum Quantity of C. A with 2 % wastage ( 1.11 x 0.57 x 1.02 ) : 0.64 cum Quantity of super plasticiser ( 510 x 0.15 / 50 ) : 1.5 ltr Requirement of machinery : Deploy shotcreting equipment with accessories for 8 hours. Deploy 8.5 cmm air compressor for 8 hours. Deploy 5 hp pump for 8 hour for pumping water to storage tank for mixing and curing. Requirement of workforce ( other than machinery crew ) : Mason Class-I : 1 No. Heavy mazdoor for cement handling : 2 Nos. Heavy mazdoor for sand and C.A handling : 2 Nos. Light mazdoor for curing and miscellaneous works. : 2 Nos. Rehandling / Initial lead for materials: 1 km rehandling lead for cement and 1 km initial lead for other materials considered. Use rate of materials : Cost of grout hose 25 m @ Rs: 150.00 / m Rs: 3750.00 Life of grout hose : 800 hours Use rate of grout hose per hour ( cost / life ) Rs: 4.69 Cost of water hose 25 m @ Rs: 128.00 / m Rs: 3200.00 Life of water hose : 800 hours Use rate of water hose per hour ( cost / life ) Rs: 4.00 Cost of shotcreting nozzle @ Rs: 312.00 / m Rs: 312.00 Life of shotcreting nozzle : 200 hours Use rate of shotcreting nozzle per hour ( cost / life ) Rs: 1.56

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 6 7 8 Perticulars Unit kg cum cum ltr Hour Hour Hour LS Quantity

UNIT :

20.00 sqm Rate in Rs. 4.00 199.00 669.00 75.00 4.69 4.00 1.56 30.00 Total Rs: Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 2040.00 123.38 428.16 112.50 37.50 32.00 12.48 30.00 2816.02 28.16 281.60 140.80 0.00 0.00 3266.58

Cement icluding wastage @1% Sand ( screened ) Coarse aggregate 6 mm down Super plasticiser Use rate of grout hose 25 m Use rate of water hose 25 m Use rate of shotcreting nozzle Sundries Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add for royalty charges on C.A @ Add for royalty charges on sand @

510.00 0.62 0.64 1.50 8.00 8.00 8.00 1.00

1% 10% 5% ( Included in material rate ) ( Included in material rate ) Total cost of Materials :

B. MACHINERY: Sl No 1 2

Description

Unit Hour Hour Hour Hour

Quantity 8.00 8.00 8.00 8.00

Guniting equipment Fuel / Energy charges Air compressor 8.5 cmm ( ele ) Fuel / Energy charges

Rate in Rs. 84.00 9.00 202.00 619.00

Amount in Rs. 672.00 72.00 1616.00 4952.00

91

DATA RATES- P AND M WORKS

3 4

Pump 5 hp ( ele ) Fuel / Energy charges Sundries

Hour Hour LS

8.00 8.00 1.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3 4 5

7.00 55.00 30.00 Total Rs: Rs: Rs: Rs: Rs:

56.00 440.00 30.00 7838.00 78.38 549.40 391.90 8857.68

Description

Unit Hour Hour Hour Day Day Day Day

Quantity 8.00 8.00 8.00 1.00 2.00 2.00 2.00 1%

Crew for Guniting equipment Crew for Air compressor Crew for pump Mason Cl I Heavy mazdoor for cement handling for sand Light mazdoor Add for small Tools and Plants @

Rate in Rs. 74.40 72.10 35.80 159.00 134.00 132.00 130.50 Total Rs: Rs: Contd

Amount in Rs. 595.20 576.80 286.40 159.00 268.00 264.00 261.00 2410.40 24.10

C. LABOUR ( contd ): Sl No Description

Unit

Quantity

Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

10% 15% 5% Total cost of Labour :

Rate in Rs. Contd Rs: Rs: Rs: Rs:

Amount in Rs. 241.04 361.56 120.52 3157.62

ABSTRACT: A. Cost of Materials including royalty charges B. Hire charges of Machinery C. Cost of Labour

Rs: Rs: Rs: TOTAL Rs: Add for scaffolding @ 5.00% Rs: Add for other enabling works @ 0.00% Rs: Total Rs: Add for 1 km rehandling / initial lead including loading / unloading: Cement 510 kg @ Rs: 129.10 / tonne Rs: Sand 0.62 cum @ Rs: 84.90 / cum Rs: C.A 0.64 cum @ Rs: 121.90 Rs: Total cost for 20.00 sqm Rs: Rate per sqm Rs: Rate approved per sqm Rs: SECTION:PRELIMINARY & MAINTENANCE WORKS YEAR: 2010-11

3266.58 8857.68 3157.62 15281.89 764.09 0.00 16045.98 65.84 52.64 78.02 16242.48 812.00 812.00 ITEM No: 40

ITEM: Drilling 25 mm / 32 mm diameter holes vertical or inclined in concrete / masonry / rock by

92

DATA RATES- P AND M WORKS

percussion drilling using jack hammer as directed to specified depth including cost of all materials, machinery, labour, cleaning holes etc., complete. DATA: Diameter of hole Rate of drilling by jack hammer with frequent shifting from hole to hole Consider 100 m drilling for analysis: Consider 2 jack hammer drills for drilling holes. Hourly progress of drilling with 50 min / hr working ( 6 x 2 x 50 / 60 ) Time for drilling 100 m ( 100 / 10 ) 1. Requirement of materials : No materials required. : 25 mm : 6 m / hour

: 10.00 m say : 10 hours

2. Requirement of machinery : Deploy 1 Air compressor 8.5 cmm for 10 hours with 50 minutes per hour working Deploy 2 Jack hammer drills for 10 hours 3. Requirement of workforce ( other than machinery crew ) : Maistry for marking hole locations and supervision of drilling work Heavy mazdoor for assisting maistry and miscellaneous works 4. Use rate of materials: Cost of jack hammer drill rod 1.5m @ Rs:

: 1 No. : 1 No.

3400.00 / Each

Rs:

3400.00

Life of drill rod with reconditioning Use rate of drill rod per m drilling Cost of air hose 25 m @ Life of air hose Use rate of air hose per hour

Rs:

( cost / life ) 150.00 / Rm ( cost / life ) UNIT : Unit Rm Hour LS Quantity 10.00 20.00 2.00

: 150 m Rs: 22.67 Rs: 3750.00 : 800 hours Rs: 4.69 100.00 Rm Rate in Rs. 22.67 4.69 30.00 Total Rs: Rs: Rs: Rs: Rs: Amount in Rs. 226.67 22.67 93.75 60.00 403.08 4.03 40.31 20.15 467.58

RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Perticulars

Use rate of drill rod 1.5 m long Reconditioning charges @ 10% Use rate of air hose 2 Nos Sundries Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @

1% 10% 5% Total cost of Materials :

B. MACHINERY: Sl No 1 2 3

Description

Unit Hour Hour Hour Hour LS

Quantity 10.00 10.00 20.00 20.00 2.00

Air compressor 8.5 cmm ( diesel ) Fuel / Energy charges Jack hammer Fuel / Energy charges Sundries

Rate in Rs. 202.00 619.00 14.00 5.00 30.00 Total Rs:

Amount in Rs. 2020.00 6190.00 280.00 100.00 60.00 8650.00

93

DATA RATES- P AND M WORKS

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2 3 4

Rs: Rs: Rs: Rs:

86.50 635.00 432.50 9804.00

Description

Unit Hour Hour Day Day

Quantity 10.00 20.00 1.00 1.00

Crew for Air compressor Crew for Jack hammer Maistry Heavy mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 72.10 111.90 141.50 132.00 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 721.00 2238.00 141.50 132.00 3232.50 32.33 323.25 484.88 161.63 4234.58

ABSTRACT: A. Cost of Materials

Rs:

467.58

B. Hire charges of Machinery C. Cost of Labour Add for other enabling works @ Total cost for

Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 Rm Rs: Rate per Rm Rs: Rate approved per Rm Rs: YEAR: 2010-11

9804.00 4234.58 14506.15 0.00 14506.15 145.00 145.00 ITEM No: 41

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Providing one coat of painting 40 micron dry film thickness to embedded parts / gates / / hoist components with zinc rich epoxy primer ( zinc content 85 % ) paint of approved quality including removing rust, cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts. DATA: Consider 100 sqm area for painting: 1. Requirement of materials : Coverage of zinc rich epoxy primer paints for one coat Qty of paint 100 sqm 1 coat with 2 % wastage(100 x 1 x 1.02 / 9) 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Painter Class-II for preparing surface @ 30 to 40 sqm / day Painter Class-II for painting @ 15 sqm / day Heavy mazdoor for assisting painter for cleaning and painting RATE ANALYSIS A. MATERIALS: Sl No Perticulars Unit Quantity UNIT :

: 9 sqm / ltr : 11.5 ltrs

: 3 Nos. : 7 Nos. : 3 Nos. 100.00 sqm Rate Amount

94

DATA RATES- P AND M WORKS

1 2

Zinc rich epoxy primer Sundries ( rust remover / brush etc ) Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add for scaffolding / ladder etc @

ltr LS

11.50 4.00

1% 10% 5% 5% Total cost of Materials :

in Rs. 594.00 30.00 Total Rs: Rs: Rs: Rs: Rs: Rs:

in Rs. 6831.00 120.00 6951.00 69.51 695.10 347.55 347.55 8410.71

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery :

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

C. LABOUR: Sl No 1 2

Description

Unit Day Day

Quantity 10.00 3.00

Painter Class-II Heavy mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 132.00 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 1415.00 396.00 1811.00 18.11 181.10 271.65 90.55 2372.41

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 sqm Rs: Rate per sqm Rs: Rate approved per sqm Rs: YEAR: 2010-11

8410.71 0.00 2372.41 10783.12 0.00 10783.12 108.00 108.00 ITEM No: 42

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Providing two coat of painting 40 micron dry film thickness each coat to gate components such as horizontal girders / sector arms /bracings /trunnion assembly / yoke girders / stiffeners/ foot bridge etc., with anti-corrosive bituminous black paint of approved quality including removing rust, cleaning surface, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts. DATA: Consider 100 sqm area for painting:

95

DATA RATES- P AND M WORKS

1. Requirement of materials : Coverage of paints for each coat Qty of paint 2 coats 100 sqm with 2 % wastage( 100x 2x1.02 /12 ) 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Painter Class-II for preparing surface @ 30 to 40 sqm / day Painter Class-II for painting @ 15 sqm / day Heavy mazdoor for assisting painter for cleaning and painting RATE ANALYSIS A. MATERIALS: Sl No 1 2 Perticulars Unit ltr LS Quantity 17.00 4.00 1% UNIT :

: 12 sqm / ltr : 17 ltrs

: 3 Nos. : 7 Nos. : 5 Nos. 100.00 sqm Rate in Rs. 94.00 30.00 Total Rs: Rs: Contd Amount in Rs. 1598.00 120.00 1718.00 17.18

Anti-corrosive bituminous black paint Sundries Add for small Tools and Plants @

A. MATERIALS: Sl No

Perticulars

Unit

Quantity

Add for Contractor's Profit @ Add for Contractor's Overheads @ Add for scaffolding / ladder etc @

10% 5% 2% Total cost of Materials :

Rate in Rs. Contd Rs: Rs: Rs: Rs:

Amount in Rs. 171.80 85.90 34.36 2027.24

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day

Quantity 10.00 5.00

Painter Class-II Heavy mazdoor Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 141.50 132.00 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 1415.00 660.00 2075.00 20.75 207.50 311.25 103.75 2718.25

96

DATA RATES- P AND M WORKS

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 100.00 sqm Rs: Rate per sqm Rs: Rate approved per sqm Rs: YEAR: 2010-11

2027.24 0.00 2718.25 4745.49 0.00 4745.49 47.00 47.00 ITEM No: 43

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Supplying and fixing bulb type uncladded rubber seals and hot dipped G.I bolts / nuts / washers of approved quality including removing existing worn-out / damaged bulb type rubber seals from gates, cleaning surface, making holes in new seals, fixig seals and bolts tightly in position, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts. DATA: Consider replacing 10 m length of worn-out / damaged seals:

Consider spacing of bolt fixing holes at 100 mm. Conside consumption of gas for making holes in seal at 2 minute per hole. Consider consumption of oxygen gas at 1.8 cum and acetylene gas at 0.6 cum / hour. 1. Requirement of materials : Bulb ( music note ) type rubber seal uncladded conforming to IS: 11855 Hot dipped G I bolts / Nuts / Washers @ 2 kg / metre length of seal Quantity of oxygen gas for 100 holes ( 100 x 2 x 1.8 / 60 ) Quantity of acetylene gas for 100 holes ( 100 x 2 x 0.6 / 60 ) 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Marker / Fabricator / Erector Helper marker / fabricator RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 Perticulars Unit Rm kg cum cum LS Quantity 10.00 20.00 2.00 6.00 2.00 UNIT :

: : : :

10 m 20 kg 6.00 cum 2.00 cum

: 2 No. : 4 Nos. 10.00 Rm Rate in Rs. 235.00 95.00 258.00 48.00 30.00 Total Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 2350.00 1900.00 516.00 288.00 60.00 5114.00 51.14 511.40 255.70 102.28 6034.52

Bulb type uncladded rubber seal Hot dipped G I bolts / Nutd / Washers Acetylene gas Oxygen gas Sundries (cutting torch /wire brush etc ) Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add for scaffolding / ladder etc @

1% 10% 5% 2% Total cost of Materials :

B. MACHINERY: Sl No

Description

Unit

Quantity

Rate

Amount

97

DATA RATES- P AND M WORKS

NIL

0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2

in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day

Quantity 2.00 4.00 1%

Marker / Fabricator Helper marker / fabricator Add for small Tools and Plants @

Rate in Rs. 157.50 141.50 Total Rs: Rs: contd

Amount in Rs. 315.00 566.00 881.00 8.81

C. LABOUR ( Contd ): Sl No Description

Unit

Quantity

Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

10% 15% 5% Total cost of Labour :

Rate in Rs. contd Rs: Rs: Rs: Rs:

Amount in Rs. 88.10 132.15 44.05 1154.11

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 10.00 Rm Rs: Rate per Rm Rs: Rate approved per Rm Rs: YEAR: 2010-11

6034.52 0.00 1154.11 7188.63 0.00 7188.63 719.00 719.00 ITEM No: 44

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Supplying and fixing bulb type teflon cladded rubber seals and hot dipped G.I bolts / nuts / washers of approved quality including removing existing worn-out / damaged bulb type rubber seals from gates, cleaning surface, making holes in new seals, fixig seals / bolts tightly in position, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts. DATA: Consider replacing 10 m length of worn-out / damaged seals: Consider spacing of bolt fixing holes at 100 mm. Conside consumption of gas for making holes in seal at 2 minute per hole. Consider consumption of oxygen gas at 1.8 cum and acetylene gas at 0.6 cum / hour. 1. Requirement of materials : Bulb (music note) type rubber seal teflon cladded conforming to IS 11855 Hot dipped G I bolts / Nuts / Washers @ 2 kg / metre length of seal

10 m : 20 kg

98

DATA RATES- P AND M WORKS

Quantity of oxygen gas for 100 holes Quantity of acetylene gas for 100 holes 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Marker / Fabricator / Erector Helper marker / fabricator RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 Perticulars

( 100 x 2 x 1.8 / 60 ) ( 100 x 2 x 0.6 / 60 )

: 6.00 cum : 2.00 cum

: 2 No. : 4 Nos. UNIT : Unit Rm kg cum Quantity 10.00 20.00 2.00 10.00 Rm Rate in Rs. 675.00 95.00 258.00 contd Amount in Rs. 6750.00 1900.00 516.00

Bulb type teflon cladded rubber seal Hot dipped G I bolts / Nutd / Washers Acetylene gas

A. MATERIALS ( Contd ): Sl No Perticulars

Unit

Quantity

4 5

Oxygen gas Sundries (cutting torch /wire brush etc ) Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add for scaffolding / ladder etc @

cum LS

6.00 2.00

1% 10% 5% 2% Total cost of Materials :

Rate in Rs. contd 48.00 30.00 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 288.00 60.00 9514.00 95.14 951.40 475.70 190.28 11226.52

B. MACHINERY: Sl No 1

Description NIL

Unit

Quantity 0.00 0.00

Add for small Tools and Plants @ 1% Add for Contractor's Profit on DPOL / Energy @ 10% Add for Contractor's Overheads @ 5% Total hire charges of Machinery : C. LABOUR: Sl No 1 2

Rate in Rs. 0.00 0.00 Total Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Description

Unit Day Day

Quantity 2.00 4.00

Marker / Fabricator Helper marker / fabricator Add for small Tools and Plants @ Add for Contractor's Profit @ Add for hidden cost on Labour @ Add for Contractor's Overheads @

1% 10% 15% 5% Total cost of Labour :

Rate in Rs. 157.50 141.50 Total Rs: Rs: Rs: Rs: Rs: Rs:

Amount in Rs. 315.00 566.00 881.00 8.81 88.10 132.15 44.05 1154.11

99

DATA RATES- P AND M WORKS

ABSTRACT: A. Cost of Materials B. Hire charges of Machinery C. Cost of Labour Add for enabling works @ Total cost for

Rs: Rs: Rs: TOTAL Rs: 0.00% Rs: 10.00 Rm Rs: Rate per Rm Rs: Rate approved per Rm Rs: YEAR: 2010-11

11226.52 0.00 1154.11 12380.63 0.00 12380.63 1238.00 1238.00 ITEM No: 45

SECTION:PRELIMINARY & MAINTENANCE WORKS

ITEM: Supplying and fixing flat rubber seals and hot dipped G.I bolts / nuts / washers of approved quality including removing existing worn-out / damaged flat type rubber seals from

gates, cleaning surface, making holes in new seals, fixig seals / bolts tightly in position, cost of all materials, labour, scaffolding etc., complete with all leads and all lifts. DATA: Consider replacing 10 m length of worn-out / damaged seals: Consider spacing of bolt fixing holes at 100 mm. Conside consumption of gas for making holes in seal at 2 minute per hole. Consider consumption of oxygen gas at 1.8 cum and acetylene gas at 0.6 cum / hour. 1. Requirement of materials : Flat type rubber bottom seal conforming to IS: 11855 Hot dipped G I bolts / Nuts / Washers @ 2 kg / metre length of seal Quantity of oxygen gas for 100 holes ( 100 x 2 x 1.8 / 60 ) Quantity of acetylene gas for 100 holes ( 100 x 2 x 0.6 / 60 ) 2. Requirement of machinery : No machinery proposed for the work. 3. Requirement of workforce : Marker / Fabricator / Erector Helper marker / fabricator RATE ANALYSIS A. MATERIALS: Sl No 1 2 3 4 5 Perticulars Unit Rm kg cum cum LS Quantity 10.00 20.00 2.00 6.00 2.00 UNIT :

: : : :

10 m 20 kg 6.00 cum 2.00 cum

: 2 No. : 4 Nos. 10.00 Rm Rate in Rs. 147.00 95.00 258.00 48.00 30.00 Total Rs: Rs: Rs: Rs: Rs: Rs: Amount in Rs. 1470.00 1900.00 516.00 288.00 60.00 4234.00 42.34 423.40 211.70 84.68 4996.12

Flat type rubber bottom seal Hot dipped G I bolts / Nutd / Washers Acetylene gas Oxygen gas Sundries (cutting torch /wire brush etc ) Add for small Tools and Plants @ Add for Contractor's Profit @ Add for Contractor's Overheads @ Add for scaffolding / ladder etc @

1% 10% 5% 2% Total cost of Materials :

100

You might also like