Professional Documents
Culture Documents
Table of Contents 1. Planning Considerations 1.1 Statutory Obligation 1.11 1.12 1.1 1.1! Licensing Arrangements for Contractors Building Products Requiring Product Certification Cost of time of getting Product Certification A""ro#al and Consent by Building $e"artment
2.
%ntroduction of t&e Project '&e Building 'eam C&art Site Layout Plan
(eneral %nformation of Planning .1 Pre)start %n#estigations .2 Site Logistics . Site *anagement 'eam +stablis&ment . 1 Site *anagement C&art
.! Security and site office +stablis&ment ., Site Access and $eli#eries .- .oise Control ./ 'em"orary 0acilities .1 Signage Board .2 Storage of *aterial requirement Table of Contents P.1
!.
Construction *et&od Statement !.1 Preliminary 4or5 !.2 Construction of Pre)Bored 6)Piles !. Sub)Structure !. 1 !. 2 '&e Ris5 of Common *al"ractice and *ista5es Problems sol#ing
!.! Su"er Structure !.!1 !.!2 '&e Ris5 of Common *al"ractice and *ista5es Problems sol#ing
!., Pouring Concrete !.,1 !.,2 '&e Ris5 of Common *al"ractice and *ista5es Problems sol#ing
,.
*aster Programme C&art ,.1 Precedence Relations ,.121 ,.122 Combined $iagram Resource Programme C&art
,.2 Re"orting Procedures of *aster7 Recourse Programme ,.21 '&e Ris5 of Common *al"ractice and *ista5es
-.
Construction *aterial of Precast Concrete 9nit -.1 Rele#ant Regulations -.11 -.12 -.1 (eneral (uidelines of Rele#ant 'erms and Requirements '&e Ris5 of Common *al"ractice and *ista5es Problems sol#ing
/.
Conclusion
1.
References
1.
Planning Considerations P.
1.11
(eneral Requirements Our construction contractors &a#e to obtain a Registered Contractor status to be eligible to carry out construction 8or5s under t&e Building Ordinance ;Ca" 12 <. A"art from Registered (eneral Building Contractor7 our contractors s&ould register as s"ecialist contractors in t&e areas of ;1< foundation7 ;2< site formation7 ; < demolition7 ;!< #entilation and ;,< ground in#estigation 8or5s.
Our Project is under '&e 4or5s Bureau in c&arge of 6ong :ong "ublic 8or5s. %t &as its o8n list of a""ro#ed contractors classified into t&e follo8ing categories=
Category Buildings Port 4or5s Road and $rainage Site 0ormation 'erritory 4ater8or5s
Administrative Departments in Charge Arc&itectural Ser#ices $e"artment Ci#il +ngineering $e"artment 6ig&8ays $e"artment $e#elo"ment $e"artment 4ater Su""lies $e"artment P.!
'o be able to submit tenders for s"eciali>ed construction 8or5s7 our contractors need to obtain "rior a""ro#al from t&e aut&orities. '&ere are o#er ,3 categories of construction 8or5s including ground in#estigation field8or57 land "iling7 air)conditioning and refrigeration installations t&at require "rior a""ro#al.
4e 8ill ensure t&at t&e tests conducted by '&e Building Aut&ority?s recogni>e t&ose laboratories accredited by t&e 6ong :ong Laboratory Accreditation Sc&eme ;6O:LAS< or by ot&er laboratory accreditation bodies 8&ic& &a#e reac&ed mutual recognition agreements 8it& 6O:LAS.
'&e building "roducts requiring "roduct certification ado"ted are= Building Products Product ;PCCS< 'imber $oor sets ;fire rated doors< Panel 4all for Partitions Cement Products 'ile Ad&esi#es Ceramic 'iles Re"air *ortars Aluminum 4indo8s 6eat Soa5ed 'em"ered (lass Concrete cube and core Production and Su""ly of Concrete Steel reinforcement Reinforcement s"licesAcou"lers Curtain 8all systems 0ire resisting "roducts Standard sands "roduction
.otes 1< 2< PCCS "ublis&ed by t&e 6ong :ong %nstitute of Steel Construction PCCS "ublis&ed by t&e 6ong :ong Concrete %nstitute
Conformity
Certification
Sc&emes
Passi#e 0ire Protection Products ;PCCS)P0PP<1 Cement Products ;PCCS)CP<2 'ile Ad&esi#es ;PCCS)'A<2 Ceramic 'iles ;PCS)C'<2 Re"air *ortars ;PCCS)R*<2 Aluminum 4indo8s ;PCCS)A4<1 6eat Soa5ed 'em"ered (lass;PCCS)'(< 6O:LAS @SPSC 6O:LAS 6O:LAS 6O:LAS 6O:LAS @uality Sc&eme for Standard Sands P.,
1.1$
1.1(
4e need com"lete t&e form BA! to inform Buildings $e"artment ;B$<. All dra8ings are fulfilled t&e legal requirement 8it& B$ a""ro#al c&o". B$ 8ill gi#e t&e a""ro#al letter 8&ic& document mentioned in letter of a""ro#al ;e.g. concrete record7 cantile#er re"ort ;P.AP 1/ <7 ins"ection form for foundation ;P.AP2!2<< and as)built dra8ings also to inform B$. 4e need to inform B$ t&e 8or5s 8ill start in / days ad#ance and submit a form BA13. After t&e 8or5s start7 B$ 8ill carry out a safety ins"ection and audit to ensure t&e tas5s fulfilled t&e design assum"tion. P.-
1.
Contractual Obligation
Bet8een t&e contractor and t&e em"loyer in deli#ering ser#ices under t&e terms and conditions is laid out in t&e contract. 4e ordinate all "arties concentrate critical acti#ities during t&e "roject are identified in t&e im"ortation "rogress of "lanning.
1.$ Social Obligation 4or5er on site7 neig&bors outside 8ill affect our "lanning control to sustainability is one of t&e u"coming 5ey issues in construction. Our site is near Euen Long (o#ernment Primary Sc&ool so t&at 8e 8ill #ery force on t&e noise control7 $ust and $ebris and traffic jam.
)ntroduction of the Pro*ect P./ '&is building "roject called FBloc5 A F 8&ic& located at 3 Eau S&in Street7 Euen Long. '&is is a One Concord Bloc5 forty)t&ree ;! < floor "ri#ate residential building "roject ;see t&e floor "lan<.
Concord Bloc5 design is cross)s&a"ed7 t&e building consists of a floor area 8it& four 8ings t&at eac& floor &as eig&t units7 and eac& 8ing &as t8o units. $emand in eac& 8ing 8&ic& t8o 8ings or 8&ole floor &as t8o 2)room or )bedroom units. '&e com"leC consists of four lifts and t8o emergency fire esca"e stairs. '&ere &a#e Lift motor room7 fres& 8ater tan57 flus& 8ater tan5 and fire ser#ices tan5 on t&e roof. Ot&er "lant rooms7 including "um" rooms7 transformer rooms7 8ater G electric meter rooms7 mec&anical #entilation and air)conditioning system are also included.
'&e Building 'eam of t&is building "roject 8it& c&art is s&o8n t&eir relations=
P.2
P.13
'&e lifting of materials of t&e u""er floor and roofs 8ill be underta5en by to8er cranes. '&e for5lift truc5 8ill used for t&e required off loading7 &ori>ontal material mo#ement facilities7 transfer concrete bloc5s. P.11
P.12
Project Sur#eyor
(eneral StaffsAAssistant
Safety *anagers
+ngineer
SubcontractorA S"ecialist
P.1
P.1!
P.1As our tender require our "ro"osed timing and sequencing of o"erations to ac&ie#e "roject com"letion in satisfaction.
'&e "re)bored 6)"ile is a small diameter "ile -13mm7 equi""ed 8it& an H6? steel section and filled 8it& cement grout. +ac& "ile &as a minimum soc5et into good quality roc5 ;(rade %%% or better 8it& 'CR J 1,K<.
'&e drilling tools for t&e installation of t&ese "iles com"rise= O$+L7 SymmetriC or equi#alent system to install a tem"orary casing -13mm diameter P.1/ 8it&in t&e soft ground abo#e t&e roc5 &ead. $o8n)t&e)6ole ;$'6< &ammer to form t&e roc5 soc5et ,,3mm diameter. $rilling 6ead
*aterial S"ecifications a""ro#ed as BS ! -3 ! A ;121-<7 BS +. 1332,)2 S2/,DR ;233!< Conformity= Code of Practice for t&e Structural 9se of Steel 233, M 6ong :ong SAR (o#ernment Building $e"artment Publication. (.$ Sub,Structure Resource requirements for bloc5 foundations7 in "lacing concrete bloc5 foundation 8alls7 a ty"ical cre8 8ill consist of t&ree bric5layers and t8o bric5layer &el"ers. 4e find t&at sufficient s"ace 8as a#ailable on t&e siteN se#eral cre8s 8ill 8or5 on t&e same job at t&e same time to s"eed u" com"letion of t&e acti#ity in "ro"ortion to t&e number of cre8s. %nstallation of under floor drainage bet8een t&e foundations 8ill be underta5en. '&e ground floor slab 8ill be cast once t&e under floor drainage &as been com"leted and "assed t&e test. (.$1 The ris7 of Common -alpractice and -ista7es
P.11 Su""liers in liability for negligence "ro#ide t&e rust in steel 8it& "oor corrosion "rotection. Poor quality control 8it&out ins"ection of site is 6uman factors negligence. (.$ Problems solving
9nclear t&e region is s&o8n on dra8ing. '&e 8or5ers destroy t&e frames and loose t&e "arts are disassembled. '&e duration of acti#ities #aries due to factors suc& as a su""ly of materials7 s5ill of 8or5ers7P.12 8eat&er and efficiency of "lant and equi"ment is de#iated. (.( Problems solving
4e 8ill "ro#ide training t&e "rocess and "ractice before early stage. Sufficient time s&all be allo8ed for fabrication7 factory "re)assembly of frames and learning "eriod for ado"ting t&e cycle.
P.1!
(./
Problems solving
4e 8ill get t&e "roduct certification from PCCS before deli#ery. Setting times of Cement s&all be seriously controlled as %nitial setting time !, minutes for trans"ortation and com"action7 and t&en 0inal setting time 13 &ours for OPC reduce t&e effect t&e construction "rogress. (ood "um"ing o"eration control and test t&e "i"elines e#ery day.
P.21
P.22
P.2
P.2!
P.2,
Acti#ity of 3 Eau S&in Street7 Euen Long7 ..'. Acti#ity A. B. C. $. +. 0. ( 6. %. D. $escri"tion 'o8er Crane and Su""ort Pre"aration 8or5s 0oundation Substructure 4or5s Su"erstructure 4or5s *oc5u"Asam"le flats %nternal 0inis&ing Lift %nstallation Plant Room 0inal %ns"ection Before Com"letion $uration ;*ont&< ! 3 , 13 11 12 , 2
L0)+S)$ Acti#ity +stimated $uration ;mont&< A)B A)C B)C C)0 C)$ $)+ $)0 +)6 +)( 0)( P.2()D 6)% %)D 3 3 2 , 13 13 11 12 , +arliest Start 'ime ;+S< 3 ! 3 ! ! 13 13 1112/ 21 O$ +arliest 0inis& 'ime ;+0< 3 ! 2 2 13 11222/ 2 1 ! )$ Latest Start 'ime ;LS< 3 ! 2 11 ! 11 13 21 1/ 11, 1 Latest 0inis& 'ime ;L0< 3 ! ! 113 1/ 11 2/ 2/ 2 2 ) )$ 'otal 0loat ;'0< 3 3 2 13 3 1 3 , 1 3 3 , , Critical Acti#ity
P P P P P
P.2/
3 B
3
13
2
1 3 -
1+
$ 1, 2 0
1 -
2 1 2
13
26
1 2
, %
! D : 2
3 A ! 2
13 2( 2/
2 /
12
11
C !
!
The critical path is A,C,D,3,+,& The e;pected pro*ect duration is $5 months /.1 :esource Programme Chart P.21
P.22
'&is 8ill in#ol#e liaison bet8een site management and t&e "lanner "re"aring t&e net8or5 t&at t&is liaison facility is rarely a#ailable. .e8 %nformation not a#ailable to t&em for "re"aring t&e net8or57 t&en may initiate "rogram u"dating by itself. /. Problems solving
4e acce"t to be de#elo"ed by our site foreman7 contractors and subcontractors in more detail to allo8 t&eir o8n draft reser#e critical "at& under t&eir construction "roblems in t&e "ast. %t 8ill be a li#e document t&at it s&ould be continually re#ie8ed7 re#ised and re)sc&eduled ta5ing into consideration all a#ailable information ;&tt"=AAen.8i5i#ersity.orgA8i5iAConstructionQ"lanning<. '&is let "rocessing more efficiently and fleCibility to meet t&e target "eriod 8it& bot& original and reser#e critical acti#ities. '&e draft reser#e critical "at& 8ill "re"are after "re"aration 8or5s 8it& ne8 reser#e Program=
Acti#ity
+stimated $uration
+arliest Start
+arliest 0inis&
Latest Start
Latest 0inis&
'otal 0loat
Critical Acti#ity P. 3
;mont&<
'ime
'ime
'ime ;LS< 3 1 2 ! , ! / / 1! 1 1, 1! / 1 1/ 1/ 2 3
'ime ;L0< 2 , / 1, 1 1, 1! / 1/ 1/ 1/ 1/ 2 2 3 2
;'0< 3 1 3 3 1 3 / / 13 3 / 3 / / 3 3 3 3 3 3 P P P P P
ID $ ' 3 ) + . 0 1 $0 $$ $' $3 $) $+ $$. $0 $1 '0 '$ '' '3 ') '+ ''. '0 '1 30 3$ 3' 33 3) 3+ 33. 30 31 )0 )$ )' )3 )) )+ )). )0 )1 +0 +$ +' +3 +) ++ ++. +0 +1 -0 -$ -' -3 -) -+ --. -0 -1 .0 .$ .' .3 .) .+ ... .0 .1 00 0$ 0' 03 03
P P P P P P P P
;.
4.
I.
P. 1
?.
L.
".
N.
Acti#ity $escri"tion %tem A. B. C. $. +. 0. (. 6. %. D. :. L. *. .. Pre"aration 8or5s Site 0acilities 0oundation Substructure 8or5 +Cca#ation for utility trenc&es Placing form8or5 and reinforcement for concrete %nstalling se8er lines %nstalling ot&er utilities Pouring concrete slabs %nstalling Precast Concrete Lift Plumbing +lectric 4ater"roof
P. 2
2 B /
1 3 /
3 A 2
13 /
1/ :
1 / /
2 1 1 2 3 C ,
1
1 /-
2 / L
3 *
3
% 1 0
1
1 / 6
1 !
13
1 2 2 ! ,
1 , ,
1/ 13 D 13
2 !
1, 2, .
+ 3 ( 1
1 ,
The reserve critical path is A,!,C,D,.,3,),&,>,L,-,1 and the e;pected pro*ect duration is $ months. P.
'&e design of "recast concrete s&all be under t&e 6ong :ong Building ;Construction< Regulations and BS1113. A tailor)made steel lifting frame s&all be designed 8it& BS,2,3 for lifting "recast units. Access suc& as gang8ay7 ladder s&all be "ro#ided from t&e building or ground to t&e location of t&e "recast yard. All lifting gear suc& as steel lifting frame7 c&ain slings7 &oo5 to8er crane and "ulley bloc5 s&all be eCamined and ins"ected by com"etent "ersons. +Camination results s&all be entered in t&e a""ro#ed from under t&e 0G%9 ;LAL(< Regulation. '&e su""ly of form release agent s&all conform to t&e rele#ant regulations. '&e su""lier or manufacturer s&all submit t&e *aterial Safety $ata S&eet for conducting &ealt& ris5 assessment. 0.1 The ris7 of Common -alpractice and -ista7es
Poor treatment to construction joints 8ill be affected "oor 8ater"roof. 'em"orary 8or5s installationAerection does not strictly com"ly 8it& t&e a""ro#ed design t&at P. , t&is mista5e 8ill be caused t&e accident.
4e &a#e built a $ model for its inno#ati#e design of Precast 8it& connection details. By simulating and animating t&e series of installation 8or5s7 "articularly t&e jointing 8or5s7 "otential construction difficulties could be identified in early stage 8it& a #ie8 to im"ro#ing t&e build ability "rior to any site moc5 u" or mass "roduction in t&e "recast factory. Steel structures 8ill be "refabricated7 assembled on ground and t&en lifted to "osition for installation. '&e cutting of steel members 8ill be done off)site under controlled conditions to reduce t&e dust created. Connections 8ill be designed to minimi>e ris5 of incorrect assembly suc& as unique bolt layout for eac& connection and clear instructions "ro#ided on dra8ings 8it& color. @uality Assurance systems and inde"endent quality audit s&all be a""ro#ed all eCamination before deli#ery to t&e construction site for installation P. '&e P&oto of %nstallation of Precast "rocessing
2.
Conclusion
(ood construction "lanning and met&od are is "re)requisite for a successful "roject. FPlan7 $o7 C&ec57 ActI "rocess and F"artneringI a""roac& s&ould be ado"ted. ;$a#id C. 4. :8o5< F%nformation is "o8erI and effecti#e communication is to transfer t&e idea and information for all "arties in t&e "roject. Planning is to forecast t&e "roblems on eac& construction "rocess and "redict t&e met&od to sol#e. Successful Programme is to control t&e time cost and monitor on a regular basis for eac& ste" and any correcti#e action a""lied t&us increase t&e "rofit. '&e abo#e met&od statement &as been eC"loited s"ecifically to demonstrate our understanding of t&e "roject requirements. %t 8ill foresee t&e "roblem and "re#ie8 t&e sol#ing solution. Pre"are tas5s 8ill arrange in early stage smoot&ly.
8.
References P. /
Coo5e B and 4illiams P ;2332< Construction Planning, Programming and Control, 3rd Edition, Wiley-Blackwell . Hong Kong Construction Industry Study !!", #arc$ !! $tt%&''www.$ousingaut$ority.go(.$k'tc'common'%d)'*usiness-%artners$i%s'resources'*uildingin)ormation-modelling'userguide%artI.%d)
CD .nclosed
P. 1