AIN El KEBIRA - ALGERIA CEMENT PRODUCTION LINE, 6.

000 TPD

LIST OF EXCLUSIONS The following are excluded from Contractor scope of work 1. 2. 3. 4. 5. 6. 7. Any Design for Permanent Structure Site preparation and site leveling, permanent fence and Gate Excavation in Rock and/or Dewatering Reallocation of existing utilities Demolition and removal of existing buildings Furnishing (furniture and Equipment) of all buildings except the laboratory building and up to 100,000USD ONLY. Raw water wells, water treatment plant and the water tanks, water from the existing plant is considered usable without any form of treatment. 8. 9. Water and electricity consumptions for construction, by Client. Permanent special protection and measures against floods.

10. Raw Materials, Spare Parts, Supplies and Consumables required during Pre-commissioning and Commissioning periods 11. Power, and Power Consumption During Pre-commissioning and Commissioning 12. Follow-up and obtaining of any kind of licenses/approvals and authorizations from local authorities which may be required for engineering design and supplies construction and operation of the plant. 13. Staff and personnel required for the commissioning, operation and maintenance of the plant 14. Overall Site and Camp Security. 15. Any services / accommodation for PLS staff other than the site office (Equipment and running by PLS) 16. Kiln brick-laying machine for erection for factory and the Belt Vulcanizing Machine for welding the conveyors. 17. Operation and Maintenance activities. 18. Main Electrical Supply network to plant Site. 19. Height to medium voltage substation, transformers, etc and all related work 20. Roads network outside the plant fence, including road from crusher to plant. 21. CTC approval and its related cost. 22. We have not allowed in our prices for VAT 23. Our price does not include any cost related custom duties and all associated charges for permanent material / equipments 24. Our offer does not include the provision of building permits and its associated fees, Environmental Permits, Construction Permits, Occupancy Permits, we have assumed such permits shall be issued by the client free of charge and in a timely manner. 25. Our price exclude any repair modification in existing structure for the new installation and tie in 26. Our price exclude any clearance from material 27. Our offer does not include the FOLLOWING All Risk Insurance Professional Indemnity Insurance Third Party Liability Insurance

Page 1/1

You might also like