You are on page 1of 13

12/9/2013

Week 12,1-2 dan 13


Capacity Planning

Capacity definition
2

Capacity is the amount of work that can be done in a specified time period. capacity is defined as the capability of a worker, machine, work center, plant, or organization to produce output per time period. Capacity is a rate of doing work, not the quantity of work done.

12/9/2013

Basic Capacity Definitions

produce a desired output in a given time period Capacity Planning determining the resources and methods needed to meet the priority plan Capacity Control monitoring production, comparing with the capacity plan, and taking appropriate corrective actions Capacity Management determining capacity needed as well as providing, monitoring, and controlling the capacity

Capacity Required capacity needed to

Capacity versus Load

12/9/2013

Capacity Planning Levels

Resource Planning Long range resource


requirements linked to the production plan

Rough-cut Capacity Planning Used to check


feasibility of MPS

Capacity Requirements Planning Detailed


work center capacity plans linked to MRP

Capacity Planning Levels

12/9/2013

Capacity Requirements Planning (CRP) Inputs

Open Order File found as scheduled receipts on


MRP

Planned order releases from MRP Potential


future orders

Work Center file


Information

on capacity in the work center Move, wait, and queue time information

Capacity Requirements Planning Inputs - Continued

Routing file the path that the work will follow


Operations

to be performed Operation sequence Work centers used Potential alternative work centers Tooling needed Standard setup times and run times

12/9/2013

Sample Routing File

Figure 5.3 Routing file

Capacity Available

Impacted by:
Product

specification Product mix Methods used to make product Pace of work

12/9/2013

Planning calender
11

Finding Capacity Available

Rated Capacity = (available time) x (utilization) x (efficiency)


Available

time number of hours a work center can be

used Utilization = [(hours worked)/(available hours)] x 100% Efficiency = [(actual production rate)/(standard production rate)] x 100%

12/9/2013

Soal (rated capacity)


13

A work center consists of 4 machines and is operated 8 hours per day for 5 days a week. Historically, the utilization has been 85% and the efficiency 110%. What is the rated capacity?

Demonstrated capacity
14

Over the previous 4 weeks, a work center produced 120, 130, 150, and 140 standard hours of work. What is the demonstrated capacity of the work center?

12/9/2013

Capacity required (load)


15

Capacity required (load)


16

12/9/2013

Capacity Load Sum of all time required for orders on a work center - Example

Example Load Profile

12/9/2013

Scheduling Orders

Back scheduling (the typical approach) Start


with the due date, use lead time to find the proper start date for each operation

Forward scheduling Launch the order into


the first (gateway) work center, then use the lead times to find when the order will be completed at each work center

Back Scheduling Example

An order for 150 of a component is due on day 135 An order starts at the beginning of a day and finished at the end of a day Operation times for the 150 ordered:

Operation 10 4 days in work center 12 Operation 20 5 days in work center 14 Operation 30 1 day in work center 17 Operation 40 2 days in work center 03

10

12/9/2013

Data from the work center file

The resulting work schedule

11

12/9/2013

The work schedule shown graphically

Making the plan

12

12/9/2013

Managing the Plan Adjusting Capacity


Use Overtime or Undertime Adjust the number of workers Shift workers from other work centers Use alternative work centers to shift load Subcontract work

26

13

You might also like