Baseline Constraint Date Construction Planning Construction schedule EPC planning Excel Tutorial Lookahead Schedule Maintenance Planning Maintenance schedule Planner's Resources Primavera P6 Primavera P6 Tutorial Progress Calculation/Measurement Sample Layout Sample WBS Sample Work Activity Schedule Control schedule design Schedule development Schedule Options Schedule Report

Tut ori al H ow t o gener at e S curve/ hi st ogram f r om Pri m avera,P6 -PartI


The following steps should be done before S curve is generated. 1. Establish WBS 2. Adding activities, Activity codes, Activity sequencing 3. Define resource dictionary 4. Assign activity resource and budgeted man hour 5. Save as a baseline schedule 6. Record the actual status when the actual works are done and schedule it based on report date Plan data can be produced if the steps 1 to 5 are done. The Actual data can also be exported if all the steps are done. Suppose you have already done all these steps as we are learning how to generate Scurve/ Histogram chart from P6 in this post. There is more than one method to generate the time-based S curve and histogram chart from P6. The related posts you might be interested are How to Get Resource Loading Histogram/S Curve in Primavera P6 and Creating discipline wise manpower histogram using Primavera P6 export data. This post demonstrates how these curves are produced by using Excel export data from Primavera, P6. Use the following procedures;

Mindjet Mind Mapping


www.mindjet.com Free 30 Day Trial - Leading Mapping Software for Business & Individuals

Open the Assignment window Bring out the columns that you want to export to excel Group/Organize the column data Set the Timescale format Export to Excel

Easy Value Stream Maps


www.SmartDraw.com Make Value Stream Maps Fast See Examples, Free Download!

Open the "Assignment" window


You must be at resource assignment window when you are preparing to export S curve/histogram data to excel. To view "Assignment" window 1. Open the selected project 2. On the menu bar, go to View >> Toolbars >> Directory to see Assignments tag

PO PU LAR PO STS
How to Get Resource Loading Histogram/S Curve in Primavera P6

Tutorial-How to generate S curve/histogram from Primavera, P6 - Part I

WBS ( Work Breakdown Structure ) for Engineering and Construction

3. Click on Assignments tap, then you will see Resource Assignments window

Primavera P6 Software Excel Planning Primavera Scheduling

http://www.toolboxforplanning.com/2010/12/tutorial-generate-s-curvehistogram-from... 17/06/2013

Toolbox4Planning: Tutorial-How to generate S curve/histogram from Primavera, P6 - ... Page 2 of 5

Primavera P5 Primavera Tutorial Excel Video Tutorial

CATEG O RI ES

Planner's

Resources

Primavera P6 Tutorial Construction Progress Planning


Calculation/Measurement Sample WBS EPC planning Excel Tutorial Schedule development Schedule Report Baseline
Primavera P6 Sample Layout Maintenance Planning Sample Work Activity Constraint Date
Construction schedule Lookahead Schedule Maintenance schedule Schedule Control Schedule Options schedule design

Bring out the Columns that you want to export to excel


The first thing you need to find out yourself is which columns are required to be reported and how do you want to analyze the data after exported. Suppose you want to view Overall Budgeted Units and Actual Units that can be used to analyze overall progress. And you might need to look at spreadsheet information such as Cum Budged Units and Actual Units in order to analyze periodic data (i.e weekly budgeted unit, weekly actual units, weekly manpower, etc). That means Cum Budgeted Units and Actual Units from the Spreadsheet Fields are also displayed to calculate weekly or monthly progress S curve/histogram data. To View Overall Budgeted Units and Actual Units Columns 1. Go to View on the menu bar >> Columns >> Customize. 2. And then you will see the Columns window. In the selected options box, Activity ID, Activity Name, Resource ID Name, Start and Finish columns are shown by default.

Enter your email address:

Subscribe
Delivered by FeedBurner

ARCH I VES
ARCHIVES

U SEFU L LI N KS
EngineeringToolbox Maintenance planning and scheduling planningplanet.com PMsite.com Projectcontrolsonline.com Turnaround and shutdown planning professional

3. Select Actual Units and Budgeted Units from units group in the available options box, then click the forward arrow diagram to show actual units and budgeted units as shown in figure below.

39
Like Send

4. After Actual and Budgeted Units are selected, hide Start and Finish by clicking backward arrow if you don't want to see it. And Click OK Then resource assignments window can be viewed as shown in figure below.

Continue Reading Tutorial-How to generate S curve/histogram from Primavera, P6 - Part II


A 5 personas les gusta esto. Regstrate para ver qu les gusta a tus amigos.

Me gusta

You might also like:

http://www.toolboxforplanning.com/2010/12/tutorial-generate-s-curvehistogram-from... 17/06/2013

Toolbox4Planning: Tutorial-How to generate S curve/histogram from Primavera, P6 - ... Page 3 of 5

Tutorial-How to generate S curve/histogram from Primavera, ...

Tutorial-How to generate S curve/histogram from Primavera, ...

How to Get Resource Loading Histogram/S Curve in Primavera ...


LinkWithin

+2 Recommend this on Google

0 com m ent s: Posta Com m ent

Comment as: Select profile...

Publish

Preview

Li nks t ot hi s post
Create a Link

Newer Post
Subscribe to: Post Comments (Atom)

Home

Older Post

Primavera

Primavera 5 P6 Software

Histogram

W ELCO M E
Hi, I'm Min Oo. Thanks for visiting my site and I would like to welcome to my blog. I have been working as a project engineer, project control engineer, planner, planning engineer, cost & schedule control engineer and mechanical engineer in Oil,Gas & Petrochemical Industry. The greatest value of Toolbox4Planning is sharing planning resources, tools and techniques applied to any industries which involved in all aspects of engineering, construction, manufacturing, maintenance and research. You can find some tutorials and templates related to planning, scheduling and project control at Toolbox4Planning which would help you improving your planning knowledge and skills. Grab a seat, share your thoughts and leave the comments. Contact:admin@toolboxforplanning.com

FO LLO W ERS
Join this site
with Google Friend Connect

Members (72) More

Already a member?Sign in

2013 Toolbox4Planning. All rights reserved.. Powered by Blogger.

http://www.toolboxforplanning.com/2010/12/tutorial-generate-s-curvehistogram-from... 17/06/2013

Toolbox4Planning: Tutorial-How to generate S curve/histogram from Primavera, P6 - ... Page 4 of 5

http://www.toolboxforplanning.com/2010/12/tutorial-generate-s-curvehistogram-from... 17/06/2013

Toolbox4Planning: Tutorial-How to generate S curve/histogram from Primavera, P6 - ... Page 5 of 5

http://www.toolboxforplanning.com/2010/12/tutorial-generate-s-curvehistogram-from... 17/06/2013

You might also like