You are on page 1of 77

Work Description AIR CONDITIONING DUCTWORK CARPENTRY

Activity FABRICATION INSTALLATION BATTENS

CAULKING TO OPENINGS

DECKING TIMBER

DOOR/WINDOW OPENING FRAME

FIXINGS

GROUNDS/FURRING

INSTALATION

INTERIOR TRIM

REVEAL LININGS

ROOF FRAMING

SHELVING

SIGNS

WALL FRAMING

Also refer Wall Internal Dry

CLEARING SITE

CLEAR TREES & BRUSH

REMOVE TREES STUMPS

REMOVE TREES

TURF CONCRETE
Rule of thumb:

BLINDING

CONCRETE JOINT

CONCRETE POURS

CONCRETE FINISHING

HARDENER - Liquid Chemical -clean old surface -one coat hardener HARDEBER - Metallic Grout Hardener -clean old surface -one coat hardener PLASTIC PROTECTION -after pour & trowel POLISH SURFACE -after rubbing down with stone & sand REMOVE FINS OR TIES, POINTS & PATCH SCRABBLING SLABS SCRABBLING SOFFITS SCRABBLING WALLS SCREEDING OFF TROWEL

COOL ROOM / FEEZER

DEMOLITION

FLOORING

INTERNAL WALLS

MASONRY

PAVING

REINFORCED CONCRET

ROOFING

DOORS/DOOR FRAMES

B1-FOLD DOOR FRAMES

ENTERIOR DOORS

DOORS/DOOR FRAMES

HARDWARE

HUFCOR DOORS

ROLLER SHUTTERS

SCREEN DOOR STRONGROOM DOORS

ELECTRICAL

AUDIO

CABLE

-150mm2 4 CORE MIMS/PVC ON TRAY -4mm2 -6mm2 -10mm2 -16mm2 -25mm2 SINGLE CORE MIMS/PVC ON TRAY -6mm2 -10mm2 -25mm2 -50mm2 -70mm2 -120mm2 TPI CABLE IN CONDUIT -2.5mm2

CABLE TRAY COMMUNICATIONS

CONDUIT

FIT OUT

EXCAVATION

BACKFILL ONLY NO COMPACTION BACKFILL, SPREAD & LEVEL

BACKFILL.REFILL & COMPACT

BULK EXCAVATION

DETAILED EXCAVATION

OVER AREA

FENCHING

FORMWORK

Rule of thumbs:

CONVETIONAL

CRANEABLE SHUTTERS

PAN FORMS

PREFABRICATED

STRIP & CLEAN

GLAZING

CLEAN GLASS

ENTRANCE/SHOPFRONTS

MIRRORS PANES

GRANOLITHIC TOPPING

COVING DIVISION STRIP FLOOR

MATWELL FRAME STAIR TREADS & RISERS

HYDRAULICS

DRAINAGE

PLUMBING

SOIL WASTE & VENT PIPES (Cast Iron) -100mm bend -100mm junction -100mm pipe -150mm bend

-150mm junction -150mm pipe -225mm bend -225mm junction -225mm pipe SOIL WASTE & VENT PIPES (Copper) -32mm bend -32mm junction -32mm pipe -40mm bend -40mm junction -40mm pipe -50mm bend -50 junction -50mm pipe -65mm bend -65mm junction -65mm pipe -80mm bend -80mm junction -80mm pipe -100mm bend -100mm junction -100mm pipe -150mm bend -150mm junction -150mm pipe SOIL WASTE & VENT PIPES (PVC0 -32mm bend -32mm junction -32mm pipe -40mm bend -40mm junction -40mm pipe -50 mm bend -50mm junction -50mm pipe -65mm bend -62mm junction -62mm pipe -80mm bend -80mm junction -80mm pipe -100mm bend -100mm junction -100mm pipe

TAPS & OUTLET


-basin combnation set -laundry combination set -pillar tap

-shower combination set -sink combination set

TRAPS
-40mm -50mm

WATER PIPES (Copper


-15mm pipe -20mm pipe -25mm pipe

IRRIGATION SYSTEMS

LEAKY PIPE MICRO SPRAY SYSTEM

LIFT & ELEVATORS

LINE MARKING RUBBERISED

LINOLEUM

NEOPARIES OPALISED GLASS

MASONRY

BLOCK

CLEANING WALLS

BLOCK WALLS

BRICK

COPING
LINTEL

RANDOM RUBBLE WALLING

SILL

METALWORK
CASTIN

DUCT FRAME & COVERS

GRATING

HANDRAILS STAIR

LADDER (fix only) TOILET ACCESSORIES

TRENCH COVER GRANATING

PAINT/WALLPAPER

REMOVE

PAINT EXTERNAL

PAINT/WALLPAPER
PAINT INTERNAL

PARQUETRY

PAVING
ASPHALT

BRICK

CONCRETE

CONCRETE BLOCK CRAZY PAVING

PILING
BEAMS STEEL

DRIVEN FRICTION GRIP PILES END BEARING SHORT BORED PILES

HOLLOW STEEL CASSION

POLE CONCRETE

POLE WOOD

PRECAST CONCRETE

REINFORCEMENT

CALCULATION

BARS

FABRIC WRAP

MESH

RENDER/PLASTER
PLASTER

RENDER

ROOFING

DOWNSPOUTS

FLASHINGS

GUTTERS

SAFETY MESH WIRE

SHEET

SHEET FLASHING

SINGLES

TILE BODY

SANDBLASTING SCAFFOLDING

SHORING

PLANKT & STUTT

BASEMENTS

SHAFITS

TRENCHES

STRUCTURAL STEEL

0 20 TONNE

20 100 TONNE

100 - 500 TONNE

500 1000 TONNE

1000 5000 TONNE

5000 TONNE+

DOCK & CANOPY FRAMING

FLOORS & PLATFORMS

FRAMING & BRACING

HOLLOW SECTIONS

OVERHEAD PIPE, BRIDGES

PURLINS & CLEATS SURFACE TREATMENT

TRUSSES & CONNECTIONS

QUARRY

VINYL/RUBBER FLOORING

WALL INTERNAL DRY

STUD FRAME

VENEERED PARTICLE BOARD VERMICULITE SPRAY


WATER/DAMP PROOFING

WINDOW/WINDOW FRAMES

Type/Method
SHEET DUCT SHEETMETAL DUCT

Productivity rates
0.56 hrs/m2 0.88 hrs/m2

Nailed to partitions Nailed to rafters and studs Plugged to walls With pressure gun Without pressure gun - 100 x 50mm closed nailed - 100 x 50mm with 25mm gaps Frame - 100 x 50mm nailed to grounds Frame 150 x 50mm plugged to walls

0.44 hrs/m2 0.02 hrs/m2 0.23 hrs/m2 0.05 hrs/m2 0.08 hrs/m2 1.75 hrs/m2 1.50 hrs/m2

BRICK WALL
Drill for 12mm diam masonry anchor CONCRETE WALL Drill for 12mm diam masonry anchor STEEL ANGEL Drill for 6 12mm bolt TIMBER Drill for 6 12mm diam bolt DOUBLE -nailed to partitions & studs -plugged to walls DOUBLE FRAMED -nailed to partitions & studs -plugged to walls SINGLE -nailed tp partitions & studs -plugged to walls ALUMINIUM FOIL Over steel or timber framing BATT INSULATION Between steel or timber framing FLEXIBLE ROLL FOAM GLASS GRANULAR MATERIAL INSULATING LATH ROCKWOOL - LOOSE ROCKWOOL STRIP VAPOR SEAL BARRIER ARCHITRAVE TO BRICK

15 0.32 0.1 0.1

hrs/m hrs/m hrs/each hrs/each

0.13 hrs/each 0.13 hrs/each 0.05 hrs/each

0.07 hrs/m 0.4 hrs/m 0.15 hrs/m 0.53 hrs/m 0.05 hrs/m 0.18 hrs/m

0.05 hrs/m2 0.11 0.12 0.17 0.11 0.09 0.1 0.1 0.02 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2

- 100 x 25mm plugged (including plugging) ARCHITRAVES TO TIMBER FRAMING - 100 x 75mm BEAM CASING CHAIR RAIL PICTURE RAIL - 50 x 25mm fixed to brick walls - 50 x 25mm fixed to timber SKIRTIN - 150 x 25mm fixed to brick wall - 150 x 25mm fixed to timber - 75 x 25mm fixed to brick wall - 75 x 25mm fixed to timber TIMBER HANDRAIL 19mm thick fixed to frame (including plugging)

0.3 hrs/m 0.12 0.13 0.1 0.1 0.19 0.09 0.24 0.14 0.22 0.12 0.45 hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/mm hrs/m hrs/m

0.3 hrs/m

CEILING HANGERS Timber Softwood 200 x 38mm fixed to ceiling joists CEILING JOISTS Timber Softwood 100 x 50mm @ 450 ctrs CEILING BEAMS 150 x 75mm COLLAR TIES 75 x 50mm 125 x 50mm FASCIAS & BARGES -Timber Softwood - 200 x 25mm fixed to rafters PURLINS 100 X 75mm RAFTERS 100 x 50mm RIDGE BOARDS 175 x 25mm STRUTS 150 x 50mm TRUSSES - Fabricated up to 6m span TRUSSES - Fabricated up to 12m span WALL PLATES 100 x 50mm METAL Brownbuilt 2.1m high x 0.42m deep x 0.4m wide TIMBER 25mm thick fixed to ladder brackets (incl fixing) Bank of shelves Single shef

0.21 hrs/m 0.1 hrs/m 0.2 hrs/m 0.13 hrs/m 0.12 hrs/m

0.3 hrs/m 0.26 hrs/m 0.17 hrs/m 0.19 hrs/m 0.12 hrs/m 0.9 hrs/each 1.4 hrs/each 0.13 hrs/m

0.17 hrs/unit 4.25 hrs/m2 elev 4.24 hrs/m2 elev 0.17 hrs/m

SMALL -Internal door name/number

0.25 hrs/each

TIMBER Softwood 100 x 50mm @ 450 ctrs Heavy timbered area with dozer (incl pile & burn) Medium timbered area with dozer (incl pile & burn) Light timbered area with dozer (incl pile & burn) Light timbered area with tractors & cable 200 350mm diam -blast & pull with tractors -grub & remove by hand 350 450mm diam -blast & pull with tractors -grub & remove by hand 450 600mm diam -blast & pull with tractors -grub & remove by hand 200 350mm diam -by hand -with chainsaw 350 450mm diam -by hand -with chainsaw 450 600mm diam -by hand -with chainsaw BY HAND -cut/strip/stack
Concrete pours should not normally exceed 150m3 per day. Discharge times for this amount of concrete with 1 pump is Large pours than 150m require 2 gangs and two pumps. Concrete should be laid by 1pm at latest to permit power floating. -50mm thick -75mm
3

0.14 hrs/m2 27 16.2 11.85 0.65 hrs/hectare hrs/hectare hrs/hectare hrs/hectare

0.83 hrs/each 6 hrs/each 1.5 hrs/each 9 hrs/each 2.5 hrs/each 12 hrs/each

7.88 hrs/each 1.97 hrs/each 10.5 hrs/each 2.5 hrs/each 16.5 hrs/each 3 hrs/each 0.25 hrs/m2

20 30m3 per hour.

0.22 hrs/m2 0.25 hrs/m2 0.06 hrs/m2

EXPANSION JOINT & FELT MEMBRANE WATERSTOP


-metal -rubber -mass concrete in unreinforced footings -Reinforced concrete footings (ie 300mm thick) -Group beams reinforced

0.06 hrs/m2
0.13 hrs/m2 0.1 hrs/m2

0.33 hrs/m3 0.43 hrs.m3 0.5 hrs/m3

-Columns reinforced -Strip footings -Slab on ground (average 150mm thick) -Suspended slab s & beams (screeded from rool over hopper/hoist) -Suspended slab & column (screeded from pump) BROOM FINISH BUSH HAMMER BUSH HAMMER CEMENT WASH EXPOSED AGGREGATE (while green) HARDENER - Liquid Chemical -clean old surface -one coat hardener HARDEBER - Metallic Grout Hardener -clean old surface -one coat hardener PLASTIC PROTECTION -after pour & trowel POLISH SURFACE -after rubbing down with stone & sand REMOVE FINS OR TIES, POINTS & PATCH SCRABBLING SLABS SCRABBLING SOFFITS SCRABBLING WALLS SCREEDING OFF TROWEL

0.7 hrs/m2 0.6 hrs/m3 1.25 hrs/m3 1.5 hrs/m3 1.25 hrs/m3 0.03 hrs/m2 1.5 hrs/m2 2 hrs/m2 0.12 hrs/m2 0.62 hrs/m2 0.32 hrs/m2 0.1 hrs/m2 0.32 hrs/m2 0.21 hrs/m2 0.02 hrs/m2 1.93 hrs/m2 0.32 hrs/m2 0.45 hrs/m2 1.2 hrs/m2 0.62 hrs/m2 0.32 hrs/m2 0.24 hrs/m2 0.12 hrs/m2 0.1 hrs/m2

-Hand Steel
-Machine JOINT FILLING

-Mastic Compound

SMALL COOL ROOM / FREEZER 3m x 3m plan x 2.4 height ASBESTOS -Remove fire spray -Remove sheet -Removes tiles -Removed ceramic/quarry tile -Remove cork tile -Remove linoleum sheet -Remove terrazzo -Remove timber -Remove viny/rubber tiles -Removes plasters from masonry -Remove plaster/fibre board

5 hrs/m2

10 hrs/m2 0.7 hrs/m2 1 hrs/m2 0.08 0.08 0.02 0.07 0.08 0.08 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2

0.11 hrs/m2 0.11 hrs/m2

-Remove plywood -Remove timber frame -Removes hollow block wall by hand -Removes hollow block wall by pneumatic pick -Remove solid by hand -Remove solid by pneumatic pick -Break up brick paving by hand -Break up concrete paving/floor slabs by hand -Break up tarmac surfacing by hand -Columns -slabs on ground -suspended slab -walls -Remove built up roofing -Remove corrugated metal

0.12 hrs/m2 0.11 hrs/m2 1.71 0.23 1.7 0.3 hrs/m2 hrs/m2 hrs/m2 hrs/m2

0.09 hrs/m2 0.5 hrs/m2 0.25 hrs/m2 16 16 16 16 hrs/m3 hrs/m3 hrs/m3 hrs/m3

0.08 hrs/m3 0.14 hrs/m3

Track/doors/hardware SETOUT & STAND -for block/brick walls HOLLOW METAL DOUBLE SWING -incl frame, door, trim, transom HOLLOW METAL SINGLE SWING -incl frame, door, trim, transom PRESSED STEEL DOUBLE SIDED -incl frame, track, hangars, doors, hardware PRESSED STEEL DOUBLE SWING -incl frame, doors, hardware PRESSED STEEL SINGLE SIDED -incl frame, track, hangars, doors, hardware BARREL BOLTS (150mm) CHECK OR SPRING HINGE DOOR CLOSER FULL MORTICED BUTT HINGES HALF MOTICED BUTT HINGES KICKPLATE LOCK & FURNITURE -Exterior -Interior MORTICED LOCK PANIC BOLTS/PUSH BARS

1.3 hrs/m

0.5 hrs/each

15.6 hrs/each 9.5 hrs/each 32 hrs/pair 20.1 hrs/pair 16 hrs/each 0.5 1.8 1 0.15 0.1 1.25 hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each

0.75 hrs/each 1.6 hrs/each 3.2 hrs/each

DOORS & HARDWARE Operable walls TRACK - Operable walls DOMESTIC -2.1 high x 2.4m wide INDUSTRIAL -3.0 high x 3.0 wide -Door & hardware - FIREPROOF

0.66 hrs/m 0.25 hrs/m 4.00 hrs/each 6.00 hrs/each 2.25 hrs/each 0.5 hrs/each

AUDIO CABLE -in conduits -on cable trays in ceiling space HORNS ON WALL SPEAKER IN CEILING 4 CORE & EARTH PVC CIRCULAR ON TRAY -2.5mm2 -6mm2 -16mm2 -35mm2 -95mm2 -150mm2 4 CORE MIMS/PVC ON TRAY -4mm2 -6mm2 -10mm2 -16mm2 -25mm2 SINGLE CORE MIMS/PVC ON TRAY -6mm2 -10mm2 -25mm2 -50mm2 -70mm2 -120mm2 TPI CABLE IN CONDUIT -2.5mm2 -6mm2 -25mm2 -95mm2 CABLE TRAY TO CEILINGS COMMUNICATIONS OUTLETS OPTICAL FIBRE -Jointing CAST INTO SUSPENDED CONCRETE SLAB -20mm

0.08 hrs/m 0.1 hrs/m 1.25 hrs/each 1 hrs/each 0.08 0.11 0.17 0.23 0.42 0.59 0.19 0.21 0.25 0.29 0.35 0.11 0.13 0.17 0.23 0.25 0.32 0.03 0.04 0.05 0.09 hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m

0.65 hrs/m 0.25 hrs/m 0.66 hrs/m

0.05 hrs/m

-25mm -32mm FIXED TO MASONRY -20mm -32mm -50mm FIXED WITHIN SUSPENDED CEILING SPACE -20mm -32mm -50.00mm ELECTRIC CLOCK GENERAL POWER OUTLETS LIGHT SWITCHERS TV OUTLETS

0.06 hrs/m 0.08 hrs/m 0.15 hrs/m 0.18 hrs/m 0.22 hrs/m 0.11 hrs/m 0.12 hrs/m 0.15 hrs/m 0.25 0.25 0.25 0.25 hrs/each hrs/each hrs/each hrs/each

-By hand -By hand -average soil -gravel -sand -By machine (bulldozer) -gravel -By hand -in clay surface -in gravel surface -in loam surface -in 1m deep clay trench -in 1m deep gravel trench -in 1m deep loam trench -in 4m deep clay trench -in 4m deep gravel trench -in 4m deep loam trench -By hand (pneumatic) -in clay surface -in gravel surface -in loam surface RETURN & FILL TO TRENCHES -Backhoe JCB -Bulldozer D4 -Bulldozer D7 SPREAD & LEVEL SPOIL -Bulldozer D4 -Bulldozer D7 BY MACHINE TRACTOR & SCRAPER, BULLDOZER

0.65 hrs/m3

1 hrs/m3 0.52 hrs/m3 0.46 hrs/m3 0.04 hrs/m3

1.6 1.33 1.5 3.45 3.03 2.79 3.84 3.45 3.21

hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3

0.88 hrs/m3 0.72 hrs/m2 0.8 hrs/m3

0.09 hrs/m3 0.05 hrs/m3 0.04 hrs/m3 0.03 hrs/m3

BY MACHINE BULLDOZER (D7/D8) -gradient 1 in 7 down -gradient 1 in 7 up -level BY MACHINE TRACTORS & SCRAPER -haul 100m -haul 500m BY HAND -average soil -hard rock -soft rock

0.01 hrs/m3 0.02 hrs/m3 0.01 hrs/m3 0.01 hrs/m3 0.02 hrs/m3 1.6 hrs/m3 7.33 hrs/m3 4.67 hrs/m3

BY HAND -average soil -hard rock -soft rock BY MACHINE (BACKHOE 0.4m3) -trenches (1m deep) in clay -trenches(1m deep) in gravel -trenches (1m deep) in loam -trenches (4m deep) in clay -trenches (4m deep) in gravel -trenches(4m deep) in loam BY HAND -average soil -hard rock -soft rock BY MACHINE -Trim & grade -D4 bulldozer -D7 bulldozer CHAINLINK 1.8m high including posts 2.4m high including posts MESH 50mm mesh including posts 1m high TIMBER Post & Rail 18m high WIRE Barbed single strand fixed to metal, timber or concrete posts Smooth single strand foxed to metal, timber or concrete posts 2 men for 2 columns in hours Beam and flat slab (simple) 9m2/manday Beam and flat slab (complex) 8m2/manday This is a general guide and will vary for beam /slab ratio for each project.

3 hrs/m3 13.6 hrs/m3 8.5 hrs/m3 0.11 0.10 0.09 0.13 0.11 0.10 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3 hrs/m3

1.81 hrs/m3 8.8 hrs/m3 5.6 hrs/m3 150 hrs/m3 250 hrs/m3

1.25 hrs/m 1.47 hrs/m 1.17 hrs/m 1.27 hrs/m 0.11 hrs/m 0.04 hrs/m

BEAMS -up to 0.6m deep at heights to 3.6m -up to 0.6 deep at heights 3.6m 4.2m -up to 0.6m deep at heights 4.2 4.8m -up to 0.6m deep at heights 4.8m 5.4m -up to 0.60m deep at heights 5.4 6.0m COLUMNS -general -columns base -column head CURB -on slab (i.e upstands) EDGE BOARDS -75mm to 100mm depth -100mm 150mm depth SLAB FLAT (height 0m 3m) 18mm ply deck with shore load supports SLAB FLAT ( height 3m- 3.6m) 18mm ply deck with shore load supports SLAB FLAT (height 3.6m 4.2m) 18mm ply deck with shore load supports SLAB FLAT (height 4.2m 4.8m) 18mm ply deck with shore load supports SLAB FLAT (height 5.4m 6.0m) 18mm ply deck with shore load supports STAIR SOFFITS -incl ply, steel props, landing & risers STAIRS -risers only STRIP FOOTINGS/GROUND BEAM TRENCH FORMS WALLS -vertical face (one side) 0m 1.5m -vertical face (one side) 3m 4.5m -vertical face (one side0 4.5 6m CORE WALLS (ie Lift shafts) -up to 4.0m in height STRAIGHT WALLS -up to 4.0m in height PLACE ONLY, EXCLUDING FALSEWORK -500mm x 500mm -1000mm x 1000mm COLUMN TUBE ROUND (also called fibertube) -300mm diameter -600mm diameter -750mm diameter -900mm diameter

1.80 1.90 2.00 2.20 2.40 2 2 3 0.36

hrs/m2 hrs/m2 jhrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2

0.25 hrs/m2 0.35 hrs/m2

1 hrs/m2 1.1 hrs/m2 1.2 hrs/m2 1.26 hrs/m2 1.43 hrs/m2 2 0.3 0.3 0.8 1 0.60 0.84 0.96 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2

1.60 hrs/m2 1.20 hrs/m2

0.13 hrs/each 0.26 hrs/each

0.16 0.17 0.18 0.18

hrs/m hrs/m hrs/m hrs/m

BONDECK TO SLABS -up to 6m lenghts COLUMN -conventional SLAB -conventional flat -conventional slab & beam STAIRS -conventional STRIP FOOTINGS.GROUND BEAMS -conventional TRENCH -conventional

0.20 hrs/m2 0.31 hrs/m2 0.27 0.44 0.66 0.1 0.1 hrs/2 hrs/m2 hrs/m2 hrs/m2 hrs/m2

-Polish -wash only GLAZING CHANNEL & PLATE GLASS PLATE GLASS (excluding channels -6.5m thick Average only METAL WINDOWS (average 1m x1m) TIMBER WINDOWS (average 1m x 1m) 50mm radius (15 20 thick) Brass angle or flat fix only ENDINGS & JOINTS -trowel into surface INCL PREP OF SLAB, MIXING & APPLICATION -10mm -20 25mm 50mm -brass angle 1m x 1m (fix only) SCREED TO STAIRS & RISERS -including round nosing and return

0.47 hrs/m2 0.1 hrs/m2 3.02 hrs/m2 2.02 hrs/m2 1.53 hrs/m2 0.9 hrs/m2 0.9 hrs/m2 0.3 hrs/m 0.1 hrs/m 0.1 hrs/m 0.25 hrs/m 0.30 hrs/m 0.4 hrs/m 0.50 hrs/m 0.25 hrs/m

AGGREGATE DRAINAGE LINES


-100mm hessian/blue metal 0.07 hrs/m 1.8 hrs/m 2.15 hrs/m 2.8 hrs/m 2.5 hrs/each 0.25 hrs/each 0.25 hrs/each

CONCRETE
-450mm with mortar joints -600mm with mortar joints -900mm with mortar joints

CONCRETE PITS & GULLIES


-precast, place only

EARTHENWARE BEND/JINCTIONS
-100mm with rubber joints -150mm with rubber joints

-225mm with rubber joints

0.5 hrs/m 0.65 hrs/m 0.85 hrs/m 1.1 hrs/m 0.33 hrs/m 0.4 hrs/m 0.53 hrs/m 0.25 hrs/each 0.33 hrs/each 0.55 hrs/m 0.65 hrs/m 0.2 hrs/m 0.4 hrs/m

EARTHENWAREV SEWER
-100mm with rubber joints -150mm with rubber joints -225mm with rubber joints

EARTHENWARE STORMWATER
-100mm with rubber joints -150mm with rubber joints -225mm with rubber joints

PVC BENDS & JUNCTIONS


-90mm/100mm -150mm/160mm

PVC SEWER
-90mm/100mm -150mm/16m

PVC - STORMWATER
-90mm/100mm -150mm/160mm

COCKS & VALVE


-15mm to 20mm -32mm -40mm 0.25 hrs/each 0.3 hrs/each 0.4 hrs/each 0.66 hrs/m 0.82 hrs/m 3.00 hrs/each 1.5 hrs/each

GALVANED PIPE
-32mm straight tube excluding fittings -50mm straight tube excluding fittings HOT WATER UNITS -160 litre pressure glass lined -instantaneous multi point SANITARY FITTINGS -bath pressed steel -bidet (excluding heater) -cistern wall type -cleaners sink -kitchen sink -laundry trough -slop hopper -urinal 180mm long -urinal single stall -vanity basin -wc pan floor mounted -wc pan wall mounted -wc suite -wall basin SOIL WASTE & VENT PIPES (Cast Iron) -100mm bend -100mm junction -100mm pipe -150mm bend

1.5 2.75 1 2 0.75 0.75 2.75 4.00 3.5 0.75 1.5 2.75 2.75 2 0.4 0.45 1.15 0.5

hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/each hrs/m hrs/each

-150mm junction -150mm pipe -225mm bend -225mm junction -225mm pipe SOIL WASTE & VENT PIPES (Copper) -32mm bend -32mm junction -32mm pipe -40mm bend -40mm junction -40mm pipe -50mm bend -50 junction -50mm pipe -65mm bend -65mm junction -65mm pipe -80mm bend -80mm junction -80mm pipe -100mm bend -100mm junction -100mm pipe -150mm bend -150mm junction -150mm pipe SOIL WASTE & VENT PIPES (PVC0 -32mm bend -32mm junction -32mm pipe -40mm bend -40mm junction -40mm pipe -50 mm bend -50mm junction -50mm pipe -65mm bend -62mm junction -62mm pipe -80mm bend -80mm junction -80mm pipe -100mm bend -100mm junction -100mm pipe

0.5 1.35 1.25 1.35 1.5 0.15 0.22 0.37 0.18 0.27 0.4 0.25 0.30 0.47 0.3 0.35 0.53 0.35 0.4 0.6 0.45 0.5 0.75 0.65 0.8 1 0.16 0.18 0.27 0.18 0.2 0.32 0.22 0.24 0.37 0.27 0.3 0.45 0.33 0.35 0.5 0.42 0.45 0.65

hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/m hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/each hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m

TAPS & OUTLET


-basin combnation set -laundry combination set -pillar tap 0.5 hrs/set 1 hrs/set 0.25 hrs/set

-shower combination set -sink combination set

1.5 hrs/set 1 hrs/set 0.25 hrs/each 0.33 hrs/each 0.22 0.24 0.26 0.3 0.34 0.6 hrs/m hrs/m hrs/m hrs/m hrs/m hrs/m

TRAPS
-40mm -50mm

WATER PIPES (Copper


-15mm pipe -20mm pipe -25mm pipe -32mm pipe -40mm pipe -100mm pipe

WATER PIPES (PVC)


-15mm elbow -15mm pipe -15mm tee -20mm elbow -20mm pipe -20mm tee -25mm elbow -25mm pipe -25mm tee -32mm elbow -32mm pipe -32mm tee -40mm elbow -40mm pipe -40mm tee -50mm elbow -50mm pipe -50mm tee -65mm elbow -65mm pipe -80mm pipe -80mm tee -100mm elbow -100mm pipe -100mm tee 0.1 0.13 0.12 0.1 0.13 0.12 0.1 0.16 0.13 0.12 0.18 0.14 0.15 0.2 0.17 0.18 0.23 0.2 0.2 0.26 0.3 0.27 0.33 0.35 0.35 hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/each hrs/each hrs/m hrs/m hrs/each hrs/each hrs/m hrs/each

-Pipe installation

PASSENGER 1 LIFT SERVICING 6 FLOORS -2m x 2m approx 2 QUICK LIFTS SERVICING 15 FLOORS -2m x 2m approx 8 LIFTS SERVICING 24 FLOORS -2.5m x 2.5m approx ROPED HYDRAULIC LOW RISE

15 weeks 19 weeks 22 weeks

-install Lift Motor Room & commission -procurement UNDERSLUNG LIFT LOW RISE -install LMR & commission -procurement SHAFT & PIT -size pit and fabricated cast ins -install door frames & doors

8 weeks 12 weeks 12 weeks 18 weeks 4 weeks 1.5 manday/week

Machine laid including setout

0.05

hrs/m

-facings columns -facing - walls

4.2 hrs/m2/crew 2.75 hrs/m2/crew

Rule of thumb: 1 Labourer can support 1 2 bricklayers concrete blockwork =12 block/m2 all block rates are for ground to 2.4m high allow additional scaffold time for higher work. Rates indicated do not allow for setout and Standing door frames etc. 0.21 hrs/m2 CONCRETE -hollow 75mm -hollow 100mm -hollow 150mm -hollow 200mm threaded over bar reinf. -hollow 100mm -solid 100mm -solid 150mm -solid 200mm CONCRETE BREEZEBLOCK (ice screen walls) GLASS BLOCK -196 x 196 x 98mm STONE BLOCK WALLS 0.79 hrs/m2 0.55 0.69 0.96 0.67 0.67 0.83 1.25 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2

2.44 hrs/m2 4 hr/m2

Rule of thumb: 1 trowel lays 50 brick (common) per hour on 1m2/hr 1 Labourer can support 2 3 bricklayers Single skin brickwork = 50 bricks/m2 Double skin brickwork = 100 bricks/m2 1 brick wall (ie double skin & single skin) = 150 bricks/m2

All brick rates are for ground to 2.4m high allow additional Scaffold time higher work. CAULK WITH COMPOUND CLEANING WALLS COMMONS -1 brick wall (150 bricks m2) -brick on edge partition (38 brick m2) -brick on edge partition (small quantities) -double skin arches -double skin curved in plan -mass brickwork -single skin -single skin curved in plan -solid 215mm wall FACE -1 brick wall (150 bricks m2) 1 side only face -double skin 1 side only face -single skin -single skin for segmented or semi arc -single skin curved in plan POINT WITH MORTAR STONE -35 x 125mm STONE STONE -300mm thick -600mm thick -750mm thick -900mm thick STONE WALL POINTING -flus joint STONE 125mm x 200mm

0.05 hrs/m2 0.23 hrs/m2

2.14 1.08 1.52 16 2.5 80 1 1.5 1.66 2.78 2.23 1.25 13 1.76

hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 brick/hr hrs/m2

0.23 hrs/m2

2.4 2.9 3.7 4.3

hrs/m2 hrs/m2 hrs/m2 hrs/m2

0.5 hrs/m2 0.24 hrs/m

-Anchor slot & Unistrut -Pipe sleeve -300mm diam -900mm diam -300mm wide -450mm wide CAST IRON or GALVANISHED -250mm x 5mm -320mm x 5mm -500 x 5mm

0.5 hrs/m 0.7 hrs/m2 0.85 hrs/m 0.6 hrs/m 1 hrs/m 0.45 hrs/m 0.55 hrs/m 0.65 hrs/m

38/50mm pipe with balusters or wall fixing -at 1.5m centres

0.66 hrs/m

LARGE -fixed to brick/block walls SMALL -fixed to brick/block walls

1 hrs/item 0.4 hrs/item 0.45 hrs/m2

GRANOSITE PAINTED ON -Grano impact stipple TROWELLED ON PAINT -by hand -by sandblasting TO CEMENT RENDER -1 coat sealer, 2 coats oil paint (3 coats) -2 coats water paint TO COMPRESSED FIBROUS CEMENT -1 coat sealer, 2 coats oil paint (3 coats) -2 coats water paint TO METAL WORK - coat zinc primer, 1 undercoat, 1 enamel (3 coats) TO METAL WORK NARROW WIDTHS - coat zinc primer, 1 undercoat, 1 enamel coat (3 coats)

0.2 hrs/m2 0.32 hrs/m2 0.4 hrs/m2 0.05 hrs/m2

0.40 hrs/m2 0.20 hrs/m2 0.36 hrs/m2 0.15 hrs/m2 0.33 hrs/m2 0.10 hrs/m2

STRUCTURAL STEEL TO CEMENT RENDER -2 coats PVC TO FRESSED TIMBER -1 coat satin, 2 coats vanish on frames & sashes -1 coat satin, 2 coats vanish on flat surfaces -prime stop, 2 coats oil paint (3 coats) -prime, stop, 2 coats oil paint on frames & sashes ( 3 coats) -prime, stop, 3 coats oil paint (4coats) -prime, stop, 3 coats oil paint on frame & sashes (4 coats) TO PLASTERBOARD -1 coat sealer, 2c oats oil paint (3 coats) -2 coats PVC TO TIMBER & METAL -0 200mm -200 300m

1.3 hrs/m2

0.50 0.30 0.36 0.54 0.60 0.80

hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2

0.30 hrs/m2 0.15 hrs/m2 0.04 hrs/m 0.05 hrs/m

IN MASTIC OVER CONCRETE FLOOR

0.8 hrs/m2

OVER TIMBER SUB FLOOR

0.8 hrs/m2

MACHINE PREPARATION FOR HOT MIX -bituminous prime coat -bituminous tack coat Note: average rate MACHINE SINGLE COAT HOT MIX -12 25mm thick -50mm thick MANUAL SINGLE COAT -25mm thick -50mm thick MANUAL 2 COAT -37mm thick -62mm thick

0.01 hrs/m2 0.01 hrs/m2 150 hrs/m2 100.00 m2/hr 50 m2/hr 0.14 hrs/m2 0.19 hrs/m2 0.22 hrs/m2 0.27 hrs/m2

BASKET WEAVE PATTERN HERRINGBONE PATTERN ON EDGE -on 25mm thick sand bed (incl cutting) PLAIN STEPS

1.5 1.8 1.00 0.9 2.2

hrs/m2 hrs/m2 hrs/m2 hrs/m2 hrs/m2

PATHS -100mm thick

0.3 hrs/m2 Note:

-incl pointing & cutting PEBBLECRETE FINISH -15 30mm EXPOSED AGGREGATE FINISH

1.5 hrs/m2 0.40 hrs/m2

H or I section -driving -trim top after driving -(Frankipile 10m long) -450 diam x 2m long (no belling) drill, reo & pour -make up & drive

0.23 hrs/m 1.1 hrs/each 8.00 No/day/rig 10.00 No/day/rig

0.16 hrs/m

-Drive battened or angled -drive straight -trim top after driving

hrs/m hrs/m hrs/each

-drive battened or angled -drive straight -trim top after driving -by hand -power tool SHEET STEEL 0.6m length -placing -removing 0.9m length -placing -removing 1.2m length -placing -removing SHEET WOOD HAND PLACED Basements & piles -placing -removing Trenches over 2.5m deep -placing -removing Trenches to 2.5m deep -placing -removing PNUEMATIC DRIVEN Basement & pits -placing -removing Trenches over 2.5m deep -placing -removing Trenches to 2.5m deep -placing -removing WITH PILE DRIVER 6m or deeper -pull or remove EITH PILE HAMMER 6m or deeper -place and drive

0.2 hrs/m 0.16 hrs/m 0.75 hrs/each 0.5 hrs/each

0.75 hrs/each 0.6 hrs/each 0.9 hrs/each 0.8 hrs/each 1 hrs/each 0.9 hrs/each

0.72 hrs/m2 0.46 hrs/m2 0.59 hrs/m2 0.34 hrs/m2 0.53 hrs/m2 0.26 hrs/m2

0.3 hrs/m2 0.43 hrs/m2 0.22 hrs/m2 0.32 hrs/m2 0.19 hrs/m2 0.29 hrs/m2 0.21 hrs/m2 0.21 hrs/m2

ARCHITECTURAL FACADES FLOOR UNITS TRANSFLOOR 8 panels and crane/per hour (excl falsework)

8 units/day

WALL PANELS PRE-STRESSED

6.6mm high x 2.4 wide at ground floor

10 unirs/day

If column or beam steel is prefabricated before installation, allow approx 2/3 of the work content for prefabricated and 1/3 of the work content for installation. Rule of thumb: Average all in output 0.75 tonnes per man (8hr) day or 10.75 Manhours/tonne. Large areas/all inclusive:-1m concrete = 200kg reinforcement average.

CALCULATION OF REO RATE FROM CONCRETE VOLUME Rule of thumb: Slabs Beams Walls Columns Footings BEAM PLACE & FIX -light density -normal density COLUMN PLACE & FIX -normal density 25mm SLAB PLACE & FIX -average density WALL PLACE & FIX -flight density or simple -normal density or normal -heavy density or complex

-100 120 -200 300 -100 -150 400 -80

kg/m3 kg/m3 kg/m3 kg/m3 kg/m3

9 hrs/tonne 15 hrs/tonne 16.00 hrs/tonne 11.5 hrs/tonne 13 hrs/tonne 20 hrs/tonne 26 hrs/tonne

TO STRUCTURAL STEEL BEAMS & COULMNS -beams & column cut, transport & wrap HEAVY GAUGE -place & fix -place & fix

0.1 hrs/m2 0.06 hrs/m2 0.04 hrs/m2

BEAMS -2 coats 16mm COLUMNS -2 coats 16mm SOFFIT -2 coats 16mm -3mm thick skrim coat and polish off WALL -2 coats 16mm -3mm thick skrim coat BEAMS -1 coat 13mm

0.50 hrs/m2 0.55 hrs/m2 0.50 hrs/m2 0.3 hrs/m2 0.40 hrs/m2 0.21 hrs/m2 0.45 hrs/m2

COLUMNS -1 coat 13mm SOFFIT -1 coat 12mm on reveals trowelled or wood float WALL EXTERNAL -1 coat 13mm -2 coats 19mm WALL INTERNAL -1 coat 13mm -1 coat 13mm for wall tile -2 coats 19mm

0.45 hrs/m2 0.62 hrs/m2 0.30 hrs/m2 0.52 hrs/m2 0.30 hrs/m2 0.25 hrs/m2 0.52 hrs/m2

CPMPRESSED FIBROUS CEMENT GAL VANISHED STEEL PVC LEAD -stepped -straight BOX STEEL -average size EAVES -compressed fibrous cement -metal Place before CFC sheet -300 x 300mm fixed to timber

0.4 hrs/m2 0.3 hrs/m2 0.25 hrs/m2 0.54 hrs/m2 0.3 hrs/m2 0.5 hrs/m 0.35 hrs/m 0.33 hrs/m 0.03 hrs/m2

COMPRESSED FIBROUS CEMENT -corrugated METAL GALVANISED CORRUGATED -fixed to steel purlins -fixed to timber purlins METAL RIBBED INTERLOCK -fixed to steel purlins clipped -fixed to timber purlins clipped METAL COVER OR APRON FLASING -200 500mm COMPRESSED FIBROUS CEMENT WOOD CONCRETE/CLAY on battens EXTERIOR WORK PATENT TYPE (1 2 SECTIONS LONG) -erect for 1 2 sections high

0.2 hrs/m2 0.25 hrs/m2 0.22 hrs/m2 0.25 hrs/m2 0.2 hrs/m2

0.45 hrs/m 0.3 hrs/m2 0.37 hrs/m2 0.25 hrs/m2 0.07 hrs/m2

1.40 hrs/section

Note: Rates are for 2 man crew carpenter & labrourer Rule of thumb: Rates are given for average ground For firm ground use Rate x 0.25 For loose ground use Rate x 2.0

-0m 3 deep -place -remove -3m 9m deep -place -remove -9m 15m deep -place -remove -0m 3m deep -place -remove -3m 9m deep -place -remove -9m 15m deep -place -remove -0m 1mm deep -place -remove -1m 3m deep -place -remove -3m 6m deep -place -remove ERECT, PLUMB & TEMPORILY BOLT FSTENING -bolting by hand -riveting -welding ERECT, PLUMB & TEMPORARILY BOLT FASTENING -bolting by hand -riveting -welding ERECT, PLUMB & TEMPORARILY BOLT

0.64 hrs/m2 0.4 hrs/m2 0.88 hrs/m2 0.56 hrs/m2 1.24 hrs/m2 0.86 hrs/m2

0.26 hrs/m2 0.16 hrs/m2 0.38 hrs/m2 0.25 hrs/m2 0.51 hrs/m2 0.33 hrs/m2

0.33 hrs/m2 0.2 hrs/m2 0.35 hrs/m2 0.23 hrs/m2 0.51 hrs/m2 0.34 hrs/m2 4.43 hrs/tonne 5.9 hrs/tonne 6.15 hrs/tonne 5.9 hrs/tonne 3.93 hrs/tonne 3.93 hrs/tonne 5.9 hrs/tonne 4.43 hrs/tonne 3.84 hrs/tonne

FASTENING -bolting by hand -riveting -welding ERECT,PLUMB & TEMPORARILY BOLT FASTENING -bolting by hand -riveting -welding ERECT, PLUMB & TEMPORARILY BOLT FASTENING -bolting by hand -riveting -welding ERECT, PLUMB & TEMPORARILY BOLT FASTENING -bolting by hand -riveting -welding ERECT, PLUMB & TEMPORARILY BOLT FASTENING -bolting by hand -riveting -welding CATWALK & FRAMING -erect & fasten CHECKERED FLOOR PALTE -erect & fasten PLATFORM FRAMING -erect & fasten HEAVY SECTION (UB, UC, RSJ, RSC) -fabrication -fabrication LIGHT SECTION (ANGLES etc) -fabrication LARGE SECTIONS -fabrication SMALL SECTIONS -fabrication ERECT, PLUMB & TEMPORARILY BOLT FASTENING -bolting by hand -riveting -welding -up to 150mm high -over 150mm high SANDBLASTING & PAINT -heavy sections 0.08 1.97

3.44 hrs/tonne 5.19 hrs/tonne 3.93 hrs/tonne 3.35 hrs/tonne 2.45 hrs/tonne 4.92 hrs/tonne 3.44 hrs/tonne 2.95 hrs/tonne 1.47 hrs/tonne 4.33 hrs/tonne 2.46 hrs/tonne 2.95 hrs/tonne 0.98 3.94 1.79 4.43 hrs/tonne hrs/tonne hrs/tonne hrs/tonne

1.43 hrs/tonne 8.12 hrs/tonne 2.07 hrs/tonne 29.52 hrs/tonne 2 hrs/tonne 30.51 hrs/tonne

23 hrs/tonne 30 hrs/tonne 30 hrs/tonne 35 hrs/tonne 5.9 hrs/tonne 1.97 hrs/tonne 2.95 hrs/tonne 2.46 hrs/tonne hrs/tonne hrs/tonne

5 hrs/tonne

-light sections UP TO 10m SPAN -fabrication -erection OVER 10m SPAN -fabrication -erection FLOOR -75 x 75mm on screed bed including clean & grout -100 x 100mm on screed bed including clean & grout -150 x 150mm on screed bed including clean & grout 225 x 225mm on screed bed including clean & grout

8 hrs/tonne

50 hrs/tonne 5 hrs/tonne 35 hrs/tonne 8 hrs/tonne

1.85 hrs/m2 1.50 hrs/m2 1.45 hrs/m2 1 hrs/m2

ASPHALT FLOOR TILE -150 x 150mm -300 x 300mm COVE MASONITE UNDERLAY -Floor RUBBER TILE -100 x 100mm -300 x 300mm VINYL SHEET FLOOR -antistatic -normal VINYL SKIRTING - 75 100mm VINYL TILES COVE -150mm FLOOR -300 x 300mm STAIRS THREADS WALL -300 x 300mm

0.21 0.12 hrs/m2 0.05 hrs/m2 0.12 hrs/m2 0.33 hrs/m2 0.12 hrs/m2

0.16 hrs/m2 0.14 hrs/m2 0.08 hrs/m 0.1 hrs/m 0.21 hrs/m2 0.22 hrs/m2

PROPRIETRY PARTITITON SYSTEM 1.2m 1.2m high pre finished SHEET COMPRESSED FIBROUS CEMENT HARDBOARD -32mm PLASTERBORAD -100mm incl tape & set -direct stick to block/walls PLYWOOD -60mm 0.3 hrs/m2 0.28 hrs/m2 0.25 hrs/m2 0.3 hrs/m2 0.33 hrs/m2 0.77 hrs/m2

STUD METAL -incl studs, top & bottom plates STUDS TIMBER -incl studs, top & bottom plates -100 x 150mm -75 x 50mm SHEET -16mm thick fixed to timber frame 2 COATS -approx 9mm thick

0.22 hrs/m2

0.40 hrs/m2 0.36 hrs/m2 0.5 hrs/m2 1.20 hrs/m2

FOUNDATION/BASEMENT WALLS DAMP RESISTANT PAINT MASTIC TYPE COATING -3mm approx SILICONE or METAL COATING 0.1 hrs/m2 0.53 hrs/m2 0.21 hrs/m2

METAL ALUMINIUM PREFABRICATED


-casement sash -fixed -fixed sash -sliding 1.25 hrs/m2 1.65 hrs/m2 1.25 1.06 1.06 1.65 hrs/m2 hrs/m2 hrs/m2 hrs/m2 1.35 hrs/m2 1.06 hrs/m2

SKYLIGHTS PREFABRICATED TIMBER PREFABRICATED


-awning double hung -fixed -fixed sash -sliding

NOTE In shop conditions. Using 20 gauge duct = 8kg/m 2 Does not include for fire dampers, volume dampers or coils . Add 5% additional time for the above. Using 20 gauge duct = 8kg/m2

See doors/door frame & windows frames.

Note: Allow 4 weeks for procurement

Note: Includes plates, studs, noggings & trimming

Note: See also Granolithic Topping

Note: See also Sandblasting for cured surface

2 man crew. This unit is built freestanding within an existing Room. Includes walls, concrete scared floor, Compressor, condensor, electric and test.

Note: Rate is for first metre. Add 0.30 hours for each additional metre.

2man crew. Delivery 8 10 weeks

Note: additional work required b Electrician If power operated.

These times are indicative only, compaction specifications should be consulted, where available, for special conditions.

Bulk excavation rates are given for firm sand

Multipliers: Gravel 1.25; Loam 1.25 Clay 1.50; Soft rock 4.00

Additional 30% per meter of bracing and for corner bracing.

Rate is erection rate only. Add 5% for fabricated & erect

Rates do not include for support framing (refer METAL WORK)

To calculate lineal metres add number of threads and number of risers and multiply by stair width. for landing refer Granolithic Topping Floor

Includes digging into topsoil (50mm) and connection to pipe and re-cover with soil.

Installation & commission are taken from lift shaft & permanent power available.

Refer to Viny/Rubber Flooring

2 man crew

See also Masonry Random Rubble Walling

Note: For frames and sashes at flat glass

over large open area 300/800m2 with 12 15 men for small areas as per brick paving

Note: does not allow for reinforcing and concrete

Note: Add driving time@0.10 hrs/m for length of pile

Average 8 units/crew and crane/day

For falsework times see Formwork rates Transfloor sequence beams positioned then infill panel placed 4 man transfloor and crane crews

Similar to propriety brand EPM Stresswall Average 10 units.crew and crane/day

Fixing rates will vary as for beam steel Outputs will decrease for complex stirrups or abnormally long stater bars. Outputs do not allow for welding Columns with large bars up to 40mm will require less manhours

Rule of thumb: 1 labourer supports 2 renderes/plasterers

(incl laps, bracing etc)

(incl doors etc but excl glass & ducted skirting) Rate does not include for studs refers Stud Frames

See also GLAZING

You might also like