Professional Documents
Culture Documents
A Gantt chart is a graphical representation of the duration of tasks against the progression of time. It is a useful tool for planning and scheduling projects. A Gantt chart is helpful when monitoring a project's progress. A Gantt chart is a type of bar chart that illustrates a project schedule. Gantt charts illustrate the start and finish dates of the terminal elements and summary elements of a project.
S - Curve
The S Curve is a well known project management tool and it consists in "a display of cumulative costs, labour hours or other quantities plotted against time. The name derives from the S-like shape of the curve, flatter at the beginning and end and steeper in the middle, because this is the way most of the projects look like. The S curve can be considered as an indicator and it's used for many applications related to project management such as: target, baseline, cost, time etc. Variety of S-Curve * * * * * * Man Hours versus Time S Curve Costs versus Time S Curve Baseline S Curve Actual S Curve Target S Curve Value and Percentage S Curves
Cost S - Curve The Costs versus Time S Curve is appropriate for projects that contain labour and non-labour (e.g. material supply / hire / subcontract) tasks. It shows cumulative costs expended over time for the duration of the project, and may be used to assist in the calculation of the project's cashflow, and cost to complete.
Baseline S - Curve
Prior to project commencement, a schedule is prepared outlining the proposed allocation of resources and the timing of tasks necessary to complete the project within a set time frame and budget. This schedule is referred to as the Baseline Schedule. From this schedule, a Baseline S Curve is generated. This S Curve reflects the planned progress of the project. If the project requirements change prior to commencement (eg. change of scope, delayed start), the Baseline Schedule may require revision to reflect the changed requirements.
Target S - Curve
Following project commencement, modification of the Baseline Schedule is usually required. Changes are continually made to the Production Schedule (which is originally the same as the Baseline Schedule). The production schedule reflects the actual progress of the project to date, and any revisions made to tasks yet to commence or not yet completed. From this schedule, a Target S Curve may be generated. This S Curve reflects the ideal progress of the project if all tasks are completed as currently scheduled. In an ideal world, the Target S Curve will meet the Baseline S Curve at the end of the project (On Time, On Budget) or finish below and to the left of the Baseline S Curve (Early, Under Budget). In reality, it is not uncommon for the Target S Curve to finish above and to the right of the Baseline S Curve (Late, Over Budget).
Actual S - Curve
The production schedule is updated on a regular basis throughout the duration of the project. These updates include the revision of percentage complete for each task to date. Using this information, an Actual S Curve may be generated. This S Curve reflects the actual progress of the project to date, and may be compared with the Baseline and Target S Curves to determine how the project is progressing. During the project, the Actual S Curve will terminate at the Cut Off Date. This is the date the Production Schedule was last updated. At the completion of the project, the Actual S Curve will meet the Target S Curve.
Why Use a S Curve? S Curve is an important project management tool. They allow the progress of a project to be tracked visually over time, and form a historical record of what has happened to date. Analysis of S Curves allow project managers to quickly identify project growth, slippage, and potential problems that could aversely impact the project if no remedial action is taken.
% or COST etc.
Planned
Actual ACTUAL
TIME
Construct a Gantt Chart with superimposed S-Curve base from the given data.
NODES
1-2 2-3 2-5 3-4 4-5 4-6 4-7 5-7 5-8 6-7 7-8 7-9 8-9 9-10
Activities
A
B C D E F G H I J K L M N
Work Description
Demolition & Clearing Excavation Underground Installation Foundation & Columns Dummy Construction of 2/F Roof Framing and Flooring G/F Slab Mech. Elect. Services Construction of Exterior Walls Dummy Construction of Interior Partition Mech. & Elect. Equipment Fixture Painting and Finishing Works
Dur.(wks)
8 14 6 5 0 6 6 4 12 12 0 10 12 8 Php Php Php Php Php Php Php Php Php Php Php Php
Cost
21,390.00 22,450.00 56,980.00 70,890.00 100,000.00 150,000.00 90,000.00 120,300.00 90,000.00 90,000.00 140,000.00 80,000.00
Construct a Gantt Chart with superimposed S-Curve base from the given data. ACT A B C D E F G H I PRECEDES C, D, F F, D E, G, I E, G, I H G, I H END END DUR 4 7 5 10 2 6 4 8 9 COST Php 10,000 Php 20,000 Php 15, 000 Php 100,000 Php 45,000 Php 60,000 Php 40,000 Php 40,000 Php 45,000
ACT A B C D E F G H I
DUR 4 7 5 10 2 6 4 8 9
COST Php 10,000 Php 20,000 Php 15, 000 Php 100,000 Php 45,000 Php 60,000 Php 40,000 Php 40,000 Php 45,000
A 4
START
2 J 0
C 5
4 K 0
E 2 G 4
H 8
D 10 F 6
7 I 9
END
B 7
ACT A B C D E F G H I
DUR 4 7 5 10 2 6 4 8 9
COST Php 10,000 Php 20,000 Php 15, 000 Php 100,000 Php 45,000 Php 60,000 Php 40,000 Php 40,000 Php 45,000
0
START
A 4 1
4 2 J 0 4 B 7 7
C 5
9
17
4 K 0
17
E 2
19 21
H 8
29
D 10 F 6
G 4 I 9
7
26
END
13
ACT A B C D E F G H I
DUR 4 7 5 10 2 6 4 8 9
COST Php 10,000 Php 20,000 Php 15, 000 Php 100,000 Php 45,000 Php 60,000 Php 40,000 Php 40,000 Php 45,000
0
START
A 4
4 2
7
12
C 5
9
17
19 17
E 2
19 21
21
H 8
29
29
1
0
J 0 4 B 7 7 3
D 10
7 11
K 0
17
G 4
17 29
7
26
END
F 6
13
20
I 9
ACT A B C D E F G H I
DUR 4 7 5 10 2 6 4 8 9
COST Php 10,000 Php 20,000 Php 15, 000 Php 100,000 Php 45,000 Php 60,000 Php 40,000 Php 40,000 Php 45,000
0
START
A 4
4 2
7
12
C 5
9
17
19 17
E 2
19 21
21
H 8
29
29
1
0
J 0 4 B 7 7 3
D 10
7 11
K 0
17
G 4
17
7
26
END
F 6
13
20
I 9
Project Status: Actual S - Curve Determine the up to date overall status of the project based from the given data below.
Work Description
Demolition & Clearing Excavation Underground Installation Foundation & Columns Construction of 2/F Roof Framing and Flooring G/F Slab Mech. Elect. Services Construction of Exterior Walls Construction of Interior Partition Mech. & Elect. Equipment Fixture Painting and Finishing Works
Dur. (wks)
8 14 6 5 6 6 4 12 12 10 12 8 Php Php Php Php Php Php Php Php Php Php Php Php
Cost
21,390.00 22,450.00 56,980.00 70,890.00 100,000.00 150,000.00 90,000.00 120,300.00 90,000.00 90,000.00 140,000.00 80,000.00
Previous
100% 100% 0% 100% 30% 30% 0 20% 10% 10% 2% 0%
Present
0 0 10% 0 5% 12% 10% 7% 7% 6% 2% 2%