Professional Documents
Culture Documents
2 Create new calendar according to the given data.:TOOLS-CHANGE WORKING TIME 3 Specify the start date of the project and calendar.PROJECT MENU- PROJECT INFORMATION 4 Assign the calendar in GANTT area. 5 Add activities.(Copy activities from given excel sheet). 6 Assign the WBS.Your WBS code & given WBS code should match. 7 Link activities.
NFORMATION
4 Prepare the WBS as given below only.The WBS code should match with given WBS code. i.e.A37 to A143 5 Please do not edit the given data.
Outline Code 1 1.1 1.2 1.2.1 1.2.2 1.3 1.3.1 1.3.2 1.3.3 1.3.4 1.3.5 1.3.6 1.3.7 1.3.8 1.3.9 1.3.10 1.3.11 1.3.12 1.3.13 1.3.14 1.3.15 W.B.S 1 1.1 1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.1.7 1.2 1.2.1 1.2.1.1. 1.2.1.2 1.2.1.3 1.2.1.4 1.2.1.5 1.2.1.6 1.2.2 1.2.2.1 1.2.2.2 1.2.2.3 1.2.2.4 1.2.2.5 1.3 1.3.1 1.3.1.1 1.3.1.2
W.B.S. NAME
Level Of WBS 1 2 2 3 3 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
DURATIONS (day)
Project "ABC"
General works Substructure Foundations Basement RCC Superstructure Ground Floor RCC First Floor RCC Second floor RCC Brickworks, door frames Internal Plaster External Plaster Concealed Conduiting & Waterproofing Aluminum Windows & grills Fixing Toilet Dado TILING Flooring & Kitchen Dado Fixing doors shutters Internal Painting External Painting Sanitory Wares & Electrical Fittings Building Services TASK NAMES
1.Project "ABC"
1.1 General
1.2 Substructure
1.3 Superstructur e
PROJECT "ABC"
General works Obtain building permits Install temporary power Install temporary water service Set up site office Prepare site - lay down yard and temporary fencing Clear the site Lineout Substructure Foundations Excavations of foundations Excavations of elevator pit P.C.C. for all footings Reinforcement works for footings and columns Formwork for footings Prepare and pour concrete for basement floor Basement (RCC) Casting of Columns Casting of Lift wall Casting of Staircase Shuttering work for slab Slab casting Superstructure Ground Floor (RCC) Casting of Columns Casting of Lift wall 4 2 2 2 2 3 2 3 3 3 6SS 7SS+1 day 8FS-1 day,4,5,6,7
7 1 2 7 3 3 12 5 7 7 1
9 9 13 14SS+2 days 15SS+6 days,12,14 16FS+1 day 18SS+2 days 18SS+2 days 18SS+6 days 21,18,19,20
12 5
1.3.1.3 1.3.1.4 1.3.1.5 1.3.2 1.3.2.1 1.3.2.2 1.3.2.3 1.3.2.4 1.3.2.5 1.3.3 1.3.3.1 1.3.3.2 1.3.3.3 1.3.3.4 1.3.3.5 1.3.4 1.3.4.1 1.3.4.2 1.3.4.3 1.3.4.4
Casting of Staircase Shuttering work for slab Slab casting First Floor (RCC) Casting of Columns Casting of Lift wall Casting of Staircase Shuttering work for slab Slab casting Second floor (RCC) Casting of Columns Casting of Lift wall Casting of Staircase Shuttering work for slab Slab casting Brickworks, fixing of door frames Basement Ground First Second
7 7 1 12 5 7 7 1 12 5 7 7 1 10 10 10 10
27SS+2 days 25,28,26,27 29 31SS+2 days 31SS+2 days 33SS+2 days 31,34,32,33 35 37SS+2 days 37SS+2 days 39SS+2 days 37,40,38,39 22FS+15 days 29FS+15 days 35FS+15 days 41FS+15 days
1.3.5 1.3.5.1 1.3.5.2 1.3.5.3 1.3.5.4 1.3.6 1.3.6.1 1.3.6.2 1.3.6.3 1.3.6.4 1.3.7 1.3.7.1 1.3.7.2 1.3.7.3 1.3.7.4
Internal Plastering Basement Ground First Second External Plastering Backside surface Left side surface Front side surface Right side surface External Painter Backside surface Left side surface Front side surface Right side surface Concealed Conduiting (Plumbing) & Waterproofing for toilets and bathrooms Basement Ground First Second Aluminum Windows & grills Fixing Basement Ground First Second Toilet Dado Basement Ground First Second TILING Flooring & Kitchen Dado Basement Ground First Second FIXING DOOR SHUTTERS Basement Ground First Second Internal Painting Basement Ground First Second Sanitory Wares & Electrical Fittings Basement Ground First Second Building Services Procurement of lift Lift Installation work Procurement of DG Procurement of Transformor Installation of DG Installation of Transformor
9 9 9 9 10 7 10 7 9 7 9 7
1.3.8 1.3.8.1 1.3.8.2 1.3.8.3 1.3.8.4 1.3.9 1.3.9.1 1.3.9.2 1.3.9.3 1.3.9.4 1.3.10 1.3.10.1 1.3.10.2 1.3.10.3 1.3.10.4 1.3.11 1.3.11.1 1.3.11.2 1.3.11.3 1.3.11.4 1.3.12 1.3.12.1 1.3.12.2 1.3.12.3 1.3.12.4 1.3.13 1.3.13.1 1.3.13.2 1.3.13.3 1.3.13.4 1.3.14 1.3.14.1 1.3.14.2 1.3.14.3 1.3.14.4 1.3.15 1.3.15.1 1.3.15.2 1.3.15.3 1.3.15.4 1.3.15.5 1.3.15.6
7 7 7 7 10 10 10 10 10 10 10 10 7 7 7 7 8 8 8 8 15 15 15 15 7 7 7 7 60 15 15 15 15 15
43,61 44,63 45,64 46 48,88 49,89,68 50,90,69 51,91,70 63 64,73 65,74 66,75 48 49,78 50,79 51 48 49,83 50,84 51,85 78 79,88 80,89 81,90 48 49,93 50,94 51,95 16 56FS+7 days 18SS+2 days,99 18SS+2 days 28 28 61SS+4 days
15 15 3
66SS+5 days
Tips. 1) Select any activity and decide which activity will be predecessors and successors for the current activity. 2) If possible, link activities in parallel 3) Except first and last activity, remaining all activities should not be open ended 4) Try to reduce the total project durations. 5) All relationships between activities shouls be realistic Q.N.1 Find the total durations of the above project.
Strictly follow the following steps to assign the resources 1 Change the existing currency and specify new indian currency INR, sym 2 Copy following resources in the resource sheet
Before assigning any resources please follow next steps 1) Select all activities 2) Right click, task information,select advanced,select task type as fixed durations
W.B.S TASK NAMES DURATION (day)
1
1.1
Project "ABC"
General works Obtain building permits 4
1.2 1.2.1
Install temporary power Install temporary water service Set up site office Prepare site - lay down yard and temporary fencing Clear the site Lineout Substructure Foundations
2 2 2 2 3 2
1.2.2
1.3 1.3.1
1.3.2
1.3.3
Excavations of foundations 7 Excavations of elevator pit 1 P.C.C. for all footings 3 Reinforcement works for footings and columns uptp basement floor 7 Prepare and pour concrete for basement floor 7 Basement (RCC) Casting of Columns 12 Casting of Lift wall 5 Casting of Staircase 7 Shuttering work for slab 7 Slab casting 1 Superstructure Ground Floor (RCC) Casting of Columns 12 Casting of Lift wall 5 Casting of Staircase 7 Shuttering work for slab 7 Slab casting 1 First Floor (RCC) Casting of Columns 12 Casting of Lift wall 5 Casting of Staircase 7 Shuttering work for slab 7 Slab casting 1 Second floor (RCC) Casting of Columns 12 Casting of Lift wall 5 Casting of Staircase 7 Shuttering work for slab 7 Slab casting 1 Brickworks, fixing of door frames
1.3.4
Basement
10
Ground
10
First
10
1.3.5
1.3.6
1.3.7
1.3.8
1.3.9
1.3.10
Second Internal Plastering Basement Ground First Second External Plastering Backside surface Left side surface Front side surface Right side surface External Painter Backside surface Left side surface Front side surface Right side surface Concealed Conduiting (Plumbing) & Waterproofing for toilets and bathrooms Basement Ground First Second Aluminum Windows & grills Fixing Basement Ground First Second Toilet Dado Basement Ground First Second TILING Flooring & Kitchen Dado
10 9 9 9 9 10 7 10 7 9 7 9 7
7 7 7 7 10 10 10 10 10 10 10 10
1.3.11
Basement
Ground
First
1.3.12
1.3.13
1.3.14
1.3.15
Second FIXING DOOR SHUTTERS Basement Ground First Second Internal Painting Basement Ground First Second Sanitory Wares & Electrical Fittings Basement Ground First Second Building Services Procurement of lift Lift Installation work Procurement of DG Procurement of Transformor Installation of DG Installation of Transformor HT & LT Cabling work Fire fighting system Building Finishing
7 8 8 8 8 15 15 15 15 7 7 7 7 15 15 15 15 15 15 15 15 3
ssign the resources ify new indian currency INR, symbol is Rs.
Rs. 25,000 Rs. 10,000 Rs. 25,000 Rs. 15,000 Rs. 5,000 Rs. 35,000
Excavation (125 cum) Excavation (50 cum) P.C.C.(15 cum) Rcc (20 cum) Rcc (35 cum) Rcc (30cum) Rcc (2cum) Rcc (1.5cum) Rcc (90 cum)
Rcc (30cum) Rcc (2cum) Rcc (1.5cum) Rcc (90 cum) Rcc (30cum) Rcc (2cum) Rcc (1.5cum) Rcc (90 cum) Rcc (30cum) Rcc (2cum) Rcc (1.5cum) Rcc (90 cum)
100 mm Thk.wall(280 sqm),150mm thk.wall(480 sqm),200mm thk.wall(240 sqm),FW door Qty(50 sqm),Door frames(sal wood)(210 Rm) 100 mm Thk.wall(280 sqm),150mm thk.wall(480 sqm),200mm thk.wall(240 sqm),FW door Qty(50 sqm),Door frames(sal wood)(210 Rm)
100 mm Thk.wall(280 sqm),150mm thk.wall(480 sqm),200mm thk.wall(240 sqm),FW door Qty(50 sqm),Door frames(sal wood)(210 Rm) 100 mm Thk.wall(280 sqm),150mm thk.wall(480 sqm),200mm thk.wall(240 sqm),FW door Qty(50 sqm),Door frames(sal wood)(210 Rm) Internal Plaster (2849 SQM),celling plaster (964 sqm) Internal Plaster (2849 SQM),celling plaster (964 sqm) Internal Plaster (2849 SQM),celling plaster (964 sqm) Internal Plaster (2849 SQM),celling plaster (964 sqm) External Plaster (500 SQM) External Plaster (500 SQM) External Plaster (500 SQM) External Plaster (500 SQM) External Plaster (500 SQM) External Painting (500 External Painting (500 External Painting (500 External Painting (500 SQM) SQM) SQM) SQM)
Toilet s water Proofing (77 sqm) Toilet s water Proofing (77 sqm) Toilet s water Proofing (77 sqm) Toilet s water Proofing (77 sqm) Aluminium powder coated sliding windows(80 sqm) Aluminium powder coated sliding windows(80 sqm) Aluminium powder coated sliding windows(80 sqm) Aluminium powder coated sliding windows(80 sqm) Cermic- Glazed Tiles (340 sqm) Cermic- Glazed Tiles (340 sqm) Cermic- Glazed Tiles (340 sqm) Cermic- Glazed Tiles (340 sqm)
Virtified Tiles Flooring (495 sqm),Vetrified tiles skirting(566 Rm),Cermic flooring(143 sqm),Cermic tiles skirting(199 Rm),Anti-skid ceramic tiles (165 sqm),black granit platform in kitchen(21 RM) Virtified Tiles Flooring (495 sqm),Vetrified tiles skirting(566 Rm),Cermic flooring(143 sqm),Cermic tiles skirting(199 Rm),Anti-skid ceramic tiles (165 sqm),black granit platform in kitchen(21 RM)
Virtified Tiles Flooring (495 sqm),Vetrified tiles skirting(566 Rm),Cermic flooring(143 sqm),Cermic tiles skirting(199 Rm),Anti-skid ceramic tiles (165 sqm),black granit platform in kitchen(21 RM) Virtified Tiles Flooring (495 sqm),Vetrified tiles skirting(566 Rm),Cermic flooring(143 sqm),Cermic tiles skirting(199 Rm),Anti-skid ceramic tiles (165 sqm),black granit platform in kitchen(21 RM) D1(15 SQM),D2(37 SQM),D3(11 SQM),D4(41 SQM) D1(15 SQM),D2(37 SQM),D3(11 SQM),D4(41 SQM) D1(15 SQM),D2(37 SQM),D3(11 SQM),D4(41 SQM) D1(15 SQM),D2(37 SQM),D3(11 SQM),D4(41 SQM) Internal Painting Internal Painting Internal Painting Internal Painting (2850 sqm) (2850 sqm) (2850 sqm) (2850 sqm)
Sanitary Wares & Electrical Fittings (10156 sqm) Sanitary Wares & Electrical Fittings (10156 sqm) Sanitary Wares & Electrical Fittings (10156 sqm) Sanitary Wares & Electrical Fittings (10156 sqm) Fixed cost Rs.400000 Fixed cost Rs.25000 Fixed cost Rs.300000 Fixed cost Rs.100000 Fixed cost Rs.15000 Fixed cost Rs.300000 Fixed cost Rs.50000 Fixed cost Rs.15000 Total male coolie -15,Total female coolie -15
BALCONY UTILITY
TOILET BEDROOM
LIVING
KITCHEN C. BEDROOM
TOILET
UTILITY
KITCHEN
UTILITY
TOILET BEDROOM
LIVING
KITCHEN C. BEDROOM
TOILET
UTILITY
KITCHEN
LOBBY
C. BEDROOM
TOILET
LIVING
M. BEDROOM BALCONY
BEDROOM BALCONY
UTILITY
UTILITY
TYPICAL
M. BEDROOM
OILET BEDROOM
TOILET KITCHEN KITCHEN KITCHEN TOILET M. BEDROOM DINING TOILET LIVING TOILET TOILET TOILET M. BEDROOM TOILET LIVING LIVING TOILET C. BEDROOM
UTILITY
KITCHEN
UTILITY
BALCONY
BALCONY
UTILITY
UTILITY
BALCONY
M. BEDROOM
OILET BEDROOM
TOILET KITCHEN KITCHEN KITCHEN TOILET M. BEDROOM DINING TOILET LIVING TOILET TOILET TOILET M. BEDROOM TOILET LIVING LIVING TOILET C. BEDROOM
UTILITY
KITCHEN
LIFT
LIFT
LOBBY
LOBBY
HOSP.LIFT
HOSP.LIFT
DINING
DINING
TOILET
BALCONY BEDROOM
OM BALCONY BALCONY
UTILITY
UTILITY
UTILITY
UTILITY
DINING TOILET
TOILET
LIVING
TOILET
C. BEDROOM
DINING TOILET
TOILET
LIVING
TOILET
C. BEDROOM
LIVING
TOILET
C. BEDROOM
TOILET
DINING
TOILET
BEDROOM BALCONY
M. BEDROOM BALCONY