Reference:C:\Users\Bong\Desktop\01 MathCad\Utilities.mcd(R)
DESCRIPTION This section provides the design of ISOLATED FOOTING PAGE 2 2 4 5 11 13 22 25 CONTENTS A. B. C. C. D. E. F. G. DIMENSIONS MATERIAL PROPERTIES DESIGN LOADS ANALYSIS RESULTS FACTORED SOIL BEARING PRESSURE CHECK SHEAR REINFORCEMENT DESIGN SUMMARY/DETAILS
Footing F-4.xmcd
LNT - Page 1 of 41
Calculation Sheet
SATORP JUBAIL EXPORT REFINERY (PACKAGE-8) KFIP BERTH-22 MAINTENANCE BUILDING \ENG\ST\CA\References\MB\MATHCAD\
04811179 SA-JER-PI903-GCCC-070113
Page Date
2 By
of
26 Checked
Date Jun 11
FOOTING DATA
Footing Length, L = Footing Width, B = Footing Thickness, T = Concrete Unit Wt., Yc = Soil Depth, D = Soil Unit Wt., Ys = Pass. Press. Coef., Kp = Coef. of Base Friction, = Uniform Surcharge, Q = Net Allow. SB Pressure, qs = 5.000 m 6.000 m 0.500 m 24.000 kN/m 0.800 m 18.000 kN/m 3.000 0.400 0.000 kPa 100 kPa
PIER DATA
Number of Piers = Pier #1 Xp (m) = Zp (m) = Lpx (m) = Lpz (m) = h (m) =
B.
3 Nomenclature Pier #2 0.000 0.000 0.500 0.500 1.000 Pier #3 0.000 2.000 0.500 0.500 1.000
MATERIALS PROPERTIES B.1 CONCRETE Compressive Strength Modulus of Elasticity Concrete strain Concrete Protection B.2 REBARS Yield Strength of Steel fy := 414MPa Modulus of Elasticity fc := 30MPa E c := 4700 c := 0.003 cov := 75mm fc MPa E c = 25743 MPa
5 E s := 2 10 MPa
Footing F-4.xmcd
LNT - Page 2 of 41
Calculation Sheet
2 8 50
3 10 79
4 12 113
5 16 201
6 20 314
7 22 380
8 25 491
9 28 616
10 32 804
SKETCH PLAN
cL X-AXIS
cL Z-AXIS
Footing F-4.xmcd
LNT - Page 3 of 41
Calculation Sheet
C.
DESIGN LOADS
10
11
12
13
14
15
k := 0 .. Npier 1
Node_No := k 9 8 10
N LC := rows( ASD_Comb)
( )
( )
( ) ( )
( ) ( )
FX1 :=
FY1 :=
FZ1 :=
( )
( )
( )
MX1 :=
MY1 :=
MZ1 :=
( )
( )
( )
LOAD1 :=
NODE1 :=
Footing F-4.xmcd
LNT - Page 4 of 41
Calculation Sheet
KN METER MOM-X
-7.62 -5.24 79.41 -4.95 58.54 -3.31 81.35 -12.30 -5.53 71.80 -7.98 50.01 -3.35 73.98 16.41 11.70 85.73 16.52 72.04 7.09 81.12
LOAD
100 101 102 103 104 105 106 100 101 102 103 104 105 106 100 101 102 103 104 105 106
FORCE-Y
441.82 406.58 386.44 420.57 405.46 235.58 215.43 799.73 640.25 647.81 719.18 724.85 352.34 359.89 574.79 472.30 499.49 539.38 559.77 274.88 302.06
FORCE-Z
-2.75 -2.33 32.87 -2.12 24.28 -1.48 33.72 -5.24 -2.57 21.87 -3.75 14.58 -1.55 22.89 8.52 5.80 35.73 8.25 30.70 3.52 33.46
MOM-Y
-2.30 -0.97 -1.18 -1.18 -1.33 -0.39 -0.59 -0.35 -0.14 0.38 -0.18 0.21 -0.06 0.46 -0.82 -0.62 0.85 -0.65 0.46 -0.41 1.07
MOM-Z
0.30 28.40 -1.16 20.75 -1.42 29.01 -0.55 -4.44 28.06 -4.01 18.68 -5.37 29.49 -2.58 -1.42 28.63 -1.00 20.66 -1.57 29.41 -0.22
10
Footing F-4.xmcd
LNT - Page 5 of 41
Calculation Sheet
LRFD COMBINATIONS
0 r := matchNode_No , LRFD k k FXU := LRFD_Data 2 , r kN k k FYU := LRFD_Data 3 , r kN k k FZU := LRFD_Data 4 , r kN k k
( )
( ) ( ) ( )
( )
( )
FXU1 :=
FYU1 :=
FZU1 :=
( )
MXU1 :=
MYU1 :=
MZU1 :=
LOAD1 :=
NODE1 :=
LRFD COMBINATIONS
Footing F-4.xmcd LNT - Page 6 of 41
Calculation Sheet
SUPPORT REACTIONS NODE 9 LOAD 200 201 202 203 204 205 206 207 200 201 202 203 204 205 206 207 200 201 202 203 204 205 206 207 FORCE-X -0.55 0.48 7.95 0.62 15.06 0.40 14.59 -0.07 -3.16 -3.80 3.82 -3.85 11.84 -3.49 13.20 -2.14 -0.95 -0.58 7.12 -0.33 14.74 -0.17 14.79 -0.11 ALL UNITS ARE IN -FORCE-Y 598.50 535.91 519.17 503.05 493.84 461.61 351.27 319.04 1007.71 991.65 928.02 934.07 816.43 828.52 520.55 532.64 691.00 722.24 705.23 726.97 639.48 682.97 410.19 453.68 FORCE-Z -2.98 -3.55 -3.71 24.45 -3.50 52.82 -2.24 54.07 -3.55 -7.36 -7.39 12.17 -5.80 33.31 -2.34 36.77 7.96 11.36 11.46 35.40 9.84 57.74 5.30 53.19 KN METER MOM-X -6.78 -10.26 -10.58 57.14 -9.23 126.21 -5.00 130.45 -7.61 -17.50 -17.58 44.29 -13.53 110.20 -5.04 118.69 16.15 21.64 21.78 81.00 18.99 137.43 10.65 129.09 MOM-Y -2.04 -3.10 -2.71 -2.88 -1.81 -2.14 -0.53 -0.86 -0.29 -0.48 -0.43 -0.01 -0.29 0.54 -0.08 0.75 -0.75 -1.09 -1.16 0.02 -1.06 1.30 -0.62 1.74 MOM-Z -2.14 1.09 25.03 1.39 47.88 0.58 46.51 -0.78 -5.00 -5.67 19.63 -6.02 45.45 -5.86 47.39 -3.92 -2.73 -1.49 22.98 -0.73 47.13 -0.29 47.18 -0.23
10
Footing F-4.xmcd
LNT - Page 7 of 41
Calculation Sheet
D.
FOUNDATION, SOIL AND SURCHARGE: Base weight: Soil weight: Surcharge wt: Total wt: Wtbase := L B T c Wtsoil := L B D s Wtsurc := L B Q WTotal := Wtbase + Wtsoil + Wtsurc Wtbase = 360.0 kN Wtsoil = 432.0 kN Wtsurc = 0.0 kN WTotal = 792.0 kN
( ) if hn D Lpx Lpz D ( c s) + ( h D) c n n n
Lpx Lpz h c s n n n
otherwise
T ExcessPier_wt = ( 2.4 2.4 2.4 ) kN Applied load + Excess pier weight TOTAL VERTICAL LOAD: P Total := WTotal + Pty := Py + ExcessPier_wt n n n
Ptyn
n
( Kp ) s ( D + T) ( Kp ) s ( D + T)
+ Kp s ( D) 0.5 + Kp s ( D) 0.5
otherwise
FSSL.x := j
Fxn n j
Fxn j n
1 ,3 0kN kN
"INFINITY" otherwise
Footing F-4.xmcd
LNT - Page 8 of 41
Calculation Sheet
Check_FS SLx := j
"N.A." if FSSL.x = "INFINITY" j otherwise "OK,Safe against sliding @ X" if FSSL.x 1.5 j "N.G. Redesign" otherwise
SLIDING ALONG X-DIRECTION Comb 100 101 102 103 104 105 106 Passive + Ff 1216.32 1097.43 1103.28 1161.43 1165.81 834.90 840.73 Sum FX 3.27 -25.16 2.91 -17.15 3.90 -26.48 1.58 FS Sliding 371.96 43.62 379.13 67.72 298.93 31.53 532.11 Remarks OK,Safe against OK,Safe against OK,Safe against OK,Safe against OK,Safe against OK,Safe against OK,Safe against sliding @ X sliding @ X sliding @ X sliding @ X sliding @ X sliding @ X sliding @ X
FSSL.z := j
Passivez + Frictionz j
Fzn n j
if round
Fz n j n
1 kN
,3 0kN
"INFINITY" otherwise Check_FS SLz := j "N.A." if FSSL.z = "INFINITY" j otherwise "OK,Safe against sliding @ Z" if FSSL.z 1.5 j "N.G. Redesign" otherwise
SLIDING ALONG Z-DIRECTION Comb 100 101 102 103 104 105 106
UPLIFT CHECK: Upward Loads P y.up := n for j 0 .. 6
Remarks OK,Safe against sliding @ Z OK,Safe against sliding @ Z OK,Safe against sliding @ Z OK,Safe against sliding @ Z OK,Safe against sliding @ Z OK,Safe against sliding @ Z OK,Safe against sliding @ Z
( )
( )
Pty.uplift := j
P y.upn n j
Footing F-4.xmcd
LNT - Page 9 of 41
Calculation Sheet
Downward Loads
Pty.down := P Total + j j
P y.upn Wtsurc n j
"INFINITY" otherwise Check_FS UL := j "N.A." if FSUL = "INFINITY" j otherwise "> 1.2, OK,Safe against sliding @ X" if FSUL 1.2 j "< 1.2, N.G. Redesign" otherwise
UPLIFT Comb 100 101 102 103 104 105 106 Downward F 2615.54 2318.33 2332.94 2478.33 2489.28 1662.00 1676.58 Uplift F 0.00 0.00 0.00 0.00 0.00 0.00 0.00 FS Uplift INFINITY INFINITY INFINITY INFINITY INFINITY INFINITY INFINITY Remarks N.A. N.A. N.A. N.A. N.A. N.A. N.A.
OVERTURNING ABOUT X-AXIS CHECK: Moment due to Py: Due to Fz and Mx: Mex := Pty Z p n n n Mox := Fz h + T + Mx n n n n
Eccentricity:
ez := j
Mexn + Moxn n j n j
P Total j
( Ptyn) j < 0 kN
OT Pty j n j
B 2
Zp
if Z p < 0 m n
OT Pty j n j if Z p = 0m n
B 2
Zp if Z p > 0m n n
OT Pty j n j OT Pty j n j
B 2
if ez < 0m j if ez > 0m j
B 2
OT 0 kN m otherwise j OT
Footing F-4.xmcd
LNT - Page 10 of 41
Calculation Sheet
MOT.x :=
Moxn + Mot.xn
n n for j 0 .. 6 if
Mrm.x := n
( Ptyn) j > 0 kN
OT Pty j n j OT Pty j n j
( (
) )
B 2 B 2
+ Zp
if MOT.x > 0 kN m j
Z p if MOT.x < 0 kN m n j
OT 0 kN m otherwise j OT 0 kN m otherwise j OT B
MRM.x :=
Factor of Safety:
FSOT.x := j
MRM.x MOT.x
if
MOT.x
"INFINITY" otherwise Check_FS OTx := j "N.A." if FSOT.x = "INFINITY" j otherwise "> 1.5, OK,Safe against overturning @ X" if FSOT.x 1.5 j "< 1.5, N.G. Redesign" otherwise
OVERTURNING MOMENT ABOUT X Comb 100 101 102 103 104 105 106 RM 8112.56 6823.55 6772.72 7197.37 7159.22 4907.40 4856.48 OM 2.72 -2.28 -372.65 -7.16 -284.93 -1.17 -371.56 FS OT 2988.05 2992.79 18.17 1005.22 25.13 4212.36 13.07 > 1.5, > 1.5, > 1.5, > 1.5, > 1.5, > 1.5, > 1.5, Remarks OK,Safe against overturning @ X OK,Safe against overturning @ X OK,Safe against overturning @ X OK,Safe against overturning @ X OK,Safe against overturning @ X OK,Safe against overturning @ X OK,Safe against overturning @ X
OVERTURNING ABOUT Z-AXIS CHECK: Moment due to Py: Due to Fx and Mz: Mez := Pty Xp n n n Moz := Fx h + T + Mz n n n n
Eccentricity:
ex := j
Mezn + Mozn n j n j
P Total j
Footing F-4.xmcd
LNT - Page 11 of 41
Calculation Sheet
Mozn + Mot.zn
n n
L 2
Xp
if Xp < 0 m n
L 2
Xp if Xp > 0m n n
L 2
if ez < 0m j if ez > 0m j
L 2
OT 0 kN m otherwise j OT Resisting Moment about Z-axis due to Py: Mrm.z := n for j 0 .. 6 if Total Resisting Moment about X-axis: MRM.z :=
( Ptyn) j > 0 kN
OT Pty j n j OT Pty j n j
( (
) )
L 2 L 2
Xp if MOT.z > 0 kN m n j + Xp n
if MOT.z < 0 kN m j
FSOT.z := j
if
MOT.z 0 kN m j
Check_FS OTz := j
"N.A." if FSOT.z = "INFINITY" j otherwise "> 1.5, OK,Safe against overturning @ Z" if FSOT.z 1.5 j "< 1.5, N.G. Redesign" otherwise
"INFINITY" otherwise
OVERTURNING MOMENT ABOUT Z Comb 100 101 102 103 104 105 106 CALCULATE FOOTING STABILITY RM 6538.85 5795.83 5832.35 6195.83 6223.20 4155.00 4191.45 OM -0.66 47.35 -1.81 34.37 -2.51 48.19 -0.98 FS OT 9982.98 122.40 3231.22 180.29 2479.36 86.22 4276.99 > 1.5, > 1.5, > 1.5, > 1.5, > 1.5, > 1.5, > 1.5, Remarks OK,Safe against overturning @ Z OK,Safe against overturning @ Z OK,Safe against overturning @ Z OK,Safe against overturning @ Z OK,Safe against overturning @ Z OK,Safe against overturning @ Z OK,Safe against overturning @ Z
Footing F-4.xmcd
LNT - Page 12 of 41
Calculation Sheet
MAX NET SOIL BEARING PRESSURE Comb 100 101 102 103 104 105 106 P Total (kN) 2615.54 2318.33 2332.94 2478.33 2489.28 1662.00 1676.58 ex (m) 0.000 0.020 -0.001 0.014 -0.001 0.029 -0.001 ez (m) 0.101 0.058 0.257 0.099 0.238 0.048 0.325 K Coeff 1.10 1.08 1.26 1.12 1.24 1.08 1.33 P max (kPa) 95.99 83.63 97.80 92.14 102.86 59.99 74.09 P max.net (kPa) 72.59 60.23 74.40 68.74 79.46 36.59 50.69 Remarks < qs = 100 kPa, < qs = 100 kPa, < qs = 100 kPa, < qs = 100 kPa, < qs = 100 kPa, < qs = 100 kPa, < qs = 100 kPa, O.K.! O.K.! O.K.! O.K.! O.K.! O.K.! O.K.!
ASD_Comb = 104 SL
Pier #1 Py (kN) = Fx (kN) = Fz (kN) = Mx (kNm) = Mz (kNm) = -405.5 0.3 24.3 -58.5 -1.4
Footing F-4.xmcd
LNT - Page 13 of 41
Calculation Sheet
BEARING AREA: Dist x Dist z Brg. L1 Brg. L2 %Brg. Area d x = "N.A." d z = "N.A." L1 = 5.000 m L2 = 6.000 m Brg_Area = 100.00 %
Biaxial Case
Case = "N.A."
GROSS SOIL BEARING CORNER PRESSURES: P = 63.09 kPa 1 P = 102.66 kPa 2 P = 102.86 kPa 3 P = 63.29 kPa 4
MAXIMUM NET SOIL PRESSURE: P max.net := max ( P ) s ( D + T) P max.net = 79.46 kPa Check_qs := if P max.net q s , "OK, q max < q allowable" , "N.G. Redesign" Check_qs = "OK, q max < q allowable"
E.
Putyn
n
Muexn + Muoxn n j n j
PuTotal j
Footing F-4.xmcd
LNT - Page 14 of 41
Calculation Sheet
Moment due to Py: Due to Fx and Mz: Muez := Puty Xp n n n Muoz := Vux h + T + Muz n n n n
Eccentricity:
eux := j
Muezn + Muozn n j n j
PuTotal j
MAX NET ULTIMATE SOIL BEARING PRESSURE Comb 200 201 202 203 204 205 206 207 Pu Total (kN) 3416.09 3368.68 3271.30 3282.97 3068.63 3091.98 2400.89 2424.24 e ux (m) -0.001 0.000 0.012 0.000 0.025 0.000 0.032 -0.001 e uz (m) 0.055 0.109 0.112 0.225 0.094 0.334 0.050 0.356 K Coeff 1.06 1.11 1.13 1.22 1.12 1.33 1.09 1.36 Pu max (kPa) 120.28 124.54 122.82 134.04 115.02 137.51 87.10 109.65 Pu 1 (kPa) 107.46 100.04 98.41 84.82 95.80 68.63 79.13 51.96 Pu 2 (kPa) 120.05 124.52 122.82 134.04 115.02 137.45 87.10 109.54 Pu 3 (kPa) 120.28 124.54 119.68 134.04 108.78 137.51 80.93 109.65 Pu 4 (kPa) 107.69 100.06 95.26 84.82 89.56 68.68 72.96 52.08
LRFD_Comb = 205 FL
Pier #1 Puy (kN) = Vux (kN) = Vuz (kN) = Mux (kNm) = Muz (kNm) = -461.6 -0.4 52.8 -126.2 0.6
Footing F-4.xmcd
LNT - Page 15 of 41
Calculation Sheet
P u = 68.63 kPa 1 P u = 137.45 kPa 2 P u = 137.51 kPa 3 P u = 68.68 kPa 4 F. CHECK SHEAR F.1 FOOTING ANALYSIS ALONG X-DIRECTIONS
L = 5m
q uL :=
Pu + Pu 3 4 2
q uR :=
Pu + Pu 1 2 2
q uL = 103.1 kPa
q uR = 103.0 kPa
qx CALCULATIONS
Effective length of bearing: Brgx := 2 PuTotal FL if min
Pu3 + Pu4
2
Pu + Pu 1 2 2
= 0kPa
Brgx = 5m
2 PuTotal FL
if min
Pu1 + Pu4
2
Pu + Pu 3 2 2
= 0kPa
Brgz = 6m
q :=
q = 0.011
Footing F-4.xmcd
LNT - Page 16 of 41
Calculation Sheet
q ( x) := if q uR = 0kPa q uL 1
Brgx
if x Brgx
)
otherwise
( Brgx x)
if q uL > q uR
x otherwise
qx CALCULATIONS
q at critical sections:
q d1 = n
( )
kPa
q d6 = n
( )
kPa
q d2 = n
( )
kPa
q d5 = n
( )
kPa
q d3 = n
( )
kPa
q d4 = n
( )
kPa
Footing F-4.xmcd
LNT - Page 17 of 41
Calculation Sheet
Diagrams
L 2 L 2 xp ( n ) := L 2 L 2 L 2
+ Xp n + Xp + n + Xp + n + Xp n + Xp n
0m L xf := L 0m 0m
0m 0m yf := T T 0m
T T T + hn yp ( n ) := T + hn T
Mp_ ( x , n ) :=
0kN m if x <
+ Xp L
( Putyn) FL
Vp_ ( x) := Vp 0kN
otherwise
x + Xp n Muozn ) ( Putyn) FL 2 ( F
Mp_ ( x) := Mp 0kN m for i 1 .. Npier Mp Mp + Mp_ ( x , i 1)
Vssf ( x) :=
Mssf ( x) :=
Vsbp ( x) :=
if q uR = 0 kPa 1 ( q uL + q ( x) ) x Brgz if x Brgx 2 1 Brgx q uL Brgz otherwise 2 if q uL = 0 kPa 1 Brg q ( x) z x ( L Brgx) 2 0 kN otherwise if x L Brgx
Msbp ( x) :=
1 2
Footing F-4.xmcd
( quL + q( x) ) x Brgz
0 kN m otherwise otherwise
1 3
2 1 2 q uL x + q ( x) x Brgz othe 6
LNT - Page 18 of 41
Calculation Sheet
a := 1000 Let x := 0m , L .. L a
M1 :=
for i 0 .. a
V1 :=
for i 0 .. a
i L M1 M i a
M1 M
i L M V i a
X( c ) := match
max ( c ) 1 c , 0 L mm a mm
M( X( M1) ) kN m
M( X( M1) ) kN m
m1 = 0
v1 = 0
max yp ( 0) , yp ( 1) , yp ( 2) mm
0.25m1 y1 := 0.25m1
L 2 x1 := L 2
m1 = 1.7 10
q x.5 := q d 5 n n
( )
q x.2 := q d 2 n n
( )
Diagrams
Footing F-4.xmcd
LNT - Page 19 of 41
Calculation Sheet
Soil Bearing Pressure Diagram
q uL = 103.1 kPa
qu (kPa)
q uR = 103.0 kPa
2 10
3 L (mm)
4 10
6 10
Footing F-4.xmcd
LNT - Page 20 of 41
Calculation Sheet
Shear Diagram
Vu (kN)
2 10
3 L (mm)
4 10
6 10
Footing F-4.xmcd
LNT - Page 21 of 41
Calculation Sheet
Moment Diagram
Mu (kN-m)
2 10
3 L (mm)
4 10
6 10
Footing F-4.xmcd
LNT - Page 22 of 41
Calculation Sheet
( )
kN
V d6 = n
( )
( )
kN
kN m
M d4 = n
( )
kN m
( )
VuRz = 727.6 kN
( )
MuRz = 1003.7 kN m MuLz := VuLz := for i 0 .. Npier 1 v V d6 i i max ( v) VuLz = 728.0 kN for i 0 .. Npier 1 m M d4 i i min( m) MuLz = 1004.3 kN m Muneg.z := if min MuLz , MuRz 0kN m , 0kN m , min MuLz , MuRz
( )
( )
))
VuLz = 728.0 kN
VuRz = 727.6 kN
Mupos.z = 0.0 kN m
F.2
Footing F-4.xmcd
LNT - Page 23 of 41
Calculation Sheet
B = 6m
q uL :=
Pu + Pu 1 4 2
q uR :=
Pu + Pu 3 2 2
q uL = 68.7 kPa
q uR = 137.5 kPa
qz CALCULATIONS
q :=
q = 11.471
q ( x) :=
if q uR = 0kPa q uL 1
x if x Brgz Brgz
x B Brgz
if x B Brgz
)
otherwise
( Brgz x)
if q uL > q uR
x otherwise
B d 6 := max + Z p n n 2 B d 5 := max + Z p n n 2
Lpz n 2 Lpz n 2
d e , 0m
de 2
, 0m
Footing F-4.xmcd
LNT - Page 24 of 41
Calculation Sheet
B d 4 := max + Z p n n 2 B d 3 := min + Z p + n n 2 B d 2 := min + Z p + n n 2 B d 1 := min + Z p + n n 2
b oz := d 2 d 5 Lpz n 2 Lpz 2 Lpz 2 Lpz 2 n n n
, 0 m
, B
de 2 , B
+ d e , B
WzR := Brgx d 1
WzL := d 6
azL := d 4
azR := Brgz d 3
qz CALCULATIONS
q at critical sections: q d1 = n
( )
kPa
q d6 = n
( )
kPa
q d2 = n
( )
kPa
q d5 = n
( )
kPa
q d3 = n
( )
kPa
q d4 = n
( )
kPa
Footing F-4.xmcd
LNT - Page 25 of 41
Calculation Sheet
Diagrams
B 2 B 2 xp ( n ) := B 2 B 2 B 2
+ Zp n + Zp + n + Zp + n + Zp n + Zp n
0m B xf := B 0m 0m
0m 0m yf := T T 0m
(
Vp_ ( x) :=
Puty n
) FL
otherwise
Shear due to Soil Pressure: Vsbp ( x) := if q uR = 0 kPa 1 ( q uL + q ( x) ) x Brgx if x Brgz 2 1 Brgz q uL Brgx otherwise 2 if q uL = 0 kPa 1 Brg q ( x) x x ( B Brgz) 2 0 kN otherwise if x B Brgz
x Brgz otherwise
( q uL + q ( x) ) x Brgx 2
Footing F-4.xmcd
LNT - Page 26 of 41
Calculation Sheet
a := 1000
Let
x := 0m ,
B .. B a
B = 6 mm a
B 2 x1 := B 2
M1 :=
for i 0 .. a M1 M i a M1
V1 :=
for i 0 .. a
i B
M
i B M V i a
X( c ) := match
max ( c ) 1 c , 0 B mm a mm
q z.5 := q d 5 n n
( )
q z.2 := q d 2 n n
( )
Diagrams
Footing F-4.xmcd
LNT - Page 27 of 41
Calculation Sheet
Soil Bearing Pressure Diagram
q uL = 68.7 kPa
qu (kPa)
q uR = 137.5 kPa
2 10
3 B (mm)
4 10
6 10
Footing F-4.xmcd
LNT - Page 28 of 41
Calculation Sheet
Shear Diagram
Vu (kN)
2 10
3 B (mm)
4 10
6 10
Footing F-4.xmcd
LNT - Page 29 of 41
Calculation Sheet
Moment Diagram
Mu (kN-m)
2 10
3 B (mm)
4 10
6 10
Footing F-4.xmcd
LNT - Page 30 of 41
Calculation Sheet
( )
kN
V d6 = n
( )
( )
kN
kN m
M d4 = n
( )
kN m
VuRx :=
( )
)
MuRx := for i 0 .. Npier 1 m M d3 i i min( m)
VuRx = 389.3 kN
( )
VuLx :=
( )
MuRx = 276.5 kN m MuLx := for i 0 .. N pier 1 m M d4 i i min( m) MuLx = 189.8 kN m Muneg.x := if min MuLx , MuRx 0kN m , 0kN m , min MuLx , MuRx
VuLx = 109.5 kN
( )
))
F.4
PUNCHING SHEAR Capacity reduction factor Shear strength provided Vc := v 0.33 v := 0.85
fc MPa b ox + b oz d e
) (
T Vc = ( 1167 1167 1167 ) kN Punching Shear Perimeter around column/pier: Along x-direction Along z-direction Area of Punching Shear: T b ox = ( 0.915 0.915 0.915 ) m T b oz = ( 0.915 0.915 0.915 ) m
Footing F-4.xmcd
LNT - Page 31 of 41
Calculation Sheet
Ap := b ox b oz n n n Total force from column/pier: P uy := Puty + LF Ap T c + D s + Q n n FL n T P uy = ( 495.9 862.8 717.3 ) kN q at d/2 distance from supports: Along x-direction T q x.2 = ( 103.1 103.1 103.1 ) kPa T q x.5 = ( 103.1 103.1 103.1 ) kPa Along z-direction T q z.2 = ( 85.4 108.3 131.3 ) kPa T q z.5 = ( 74.9 97.8 120.8 ) kPa Total force acting on punched area Rq := n 1 2 max q x.5 + q x.2 , q z.5 + q z.2 Ap n n n n n T 2 Ap = ( 0.837 0.837 0.837 ) m
T Rq = ( 86.3 86.3 105.5 ) kN Net punching shear: Vup := P uy Rq n n n T Vup = ( 409.6 776.5 611.8 ) kN
Check if shear strength provided by concrete is greater than the maximum shear force. ACI31811.3.1.1.Eq.11.3.p := if min( Vc ) > max Vup , "OK,shear strength provided > Vu." , "NG!" ACI31811.3.1.1.Eq.11.3.p = "OK,shear strength provided > Vu." F.5 WIDE BEAM SHEAR Wide-beam shear along Z direction VuLz = 728.0 kN Shear strength provided VuRz = 727.6 kN Vn b := v 0.17
) )
fc MPa B d e
Vn b = 1970.7 kN
Check if shear strength provided by concrete is greater than the maximum shear force. ACI31811.3.1.1.Eq.11.3.bsz := if Vn b > max VuLz , VuRz , "OK,shear strength provided > Vu." , "NG!" ACI31811.3.1.1.Eq.11.3.bsz = "OK,shear strength provided > Vu." Wide-beam shear along X direction VuLx = 109.5 kN VuRx = 389.3 kN
) )
(
Footing F-4.xmcd
)
LNT - Page 32 of 41
Calculation Sheet
Shear strength provided Vn b := v 0.17
fc MPa L d e
Vn b = 1642.3 kN
Check if shear strength provided by concrete is greater than the maximum shear force. ACI31811.3.1.1.Eq.11.3.bsx := if Vn b > max VuLx , VuRx , "OK,shear strength provided > Vu." , "NG!" ACI31811.3.1.1.Eq.11.3.bsx = "OK,shear strength provided > Vu." G. REINFORCEMENT DESIGN G.1 DESIGN MOMENT FOR BOTTOM BARS Capacity reduction factor Moment at face of pedestal X-direction Moment at face of pedestal Z-direction G.2 BOTTOM REINFORCEMENTS Temp steel reinforcement ratio temp := 0.0018 min := temp [ACI 318 7.12.2] f := 0.90 Muneg.z = 1004.3 kN m Muneg.x = 276.5 kN m
min = 0.0018 Bars in X-direction Factored resistance Mr := max Muneg.z , 0.001 kN m Reinforcement provided Size of bar barx 6 Bar diameter dia = 20 mm barx Mr = f As fy d s
1 2
As fy 0.85 fc b
b := B
Mr = 1004.3 kN m
Bar area
Area of steel provided Distance from extreme compressive fiber to centroid of reinforcing steel Solve the quadratic equation for the area of steel required
As :=
1 2
As fy 0.85 fc b
2
As.reqd := Find As Minimum reinforcement Temperature reinforcement Reinforcing steel required Check As provided Bars in Z-direction
( )
4 As.reqd 3
2 2
As.temp := temp b
T 2
As.temp = 2700 mm
As.reqd = 6638 mm
Footing F-4.xmcd
LNT - Page 33 of 41
Calculation Sheet
Mr = f As fy d s
Factored resistance Mr := max Muneg.x , 0.001 kN m Reinforcement provided Size of bar Proposed bar spacing
1 2
As fy 0.85 fc b
b := L
Mr = 276.5 kN m
Area of steel provided Distance from extreme compressive fiber to centroid of reinforcing steel Solve the quadratic equation for the area of steel required
As :=
1 2
As fy 0.85 fc b
2
( )
4 3 As.reqd
As.reqd = 1893 mm
Minimum reinforcement Temperature reinforcement Reinforcing steel required Check As provided G.3 TOP REINFORCEMENTS Bars in X-direction Factored resistance Mr := max Mupos.z , 0.001 kN m Reinforcement provided Size of bar Proposed bar spacing
As.min = 2525 mm
2 2
As.temp = 2250 mm
As.reqd = 2525 mm
Mr = f As fy d s
1 2
As fy 0.85 fc b
b := B
Mr = 0.0 kN m
Area of steel provided Distance from extreme compressive fiber to centroid of reinforcing steel Solve the quadratic equation for the area of steel required
As :=
1 2
As fy 0.85 fc b
2
( )
4 3 As.reqd
As.reqd = 0 mm
As.min = 0 mm
2 2
As.temp = 2700 mm
As.reqd = 2700 mm
Footing F-4.xmcd
LNT - Page 34 of 41
Calculation Sheet
Check As provided Bars in Z-direction Factored resistance Mr := max Mupos.x , 0.001 kN m Reinforcement provided Size of bar Proposed bar spacing barz.top := 5 S z.top := 300mm As b barz.top S z.top Bar diameter Bar area dia = 16 mm barz.top As = 201 mm barz.top As = 3350 mm 2 2 Mr = f As fy d s As >=? As.reqd = "YES!.. SATISFACTORY"
1 2
As fy 0.85 fc b
b := L
Mr = 34.1 kN m
As :=
d = 401 mm
Mr = f As fy d
1 2
As fy 0.85 fc b
2
( )
4 As.reqd 3
2 2
As.temp := temp b
T 2
As.temp = 2250 mm
As.reqd = 2250 mm
H.
SUMMARY/DETAILS
PLAN REINFORCEMENTS
Bot_BarsParallel.L := concatnum2str
diabarx S x.bot , "mm at " , num2str , "mm O.C." mm mm diabarx.top S x.top , "mm at " , num2str , "mm O.C." mm mm
Top_Bars Parallel.L :=
concatnum2str
if S x.top 0mm
Bot_BarsParallel.B := concatnum2str
Footing F-4.xmcd
LNT - Page 35 of 41
Calculation Sheet
Top_Bars Parallel.B :=
concatnum2str
if S z.top 0mm
Center lines:
0m y1 := 0m
1.2 B 2 y2 := 1.2 B 2
x2 :=
0m 0m
B 2cov 4 y4 := up m up m
Footing:
L 2 L 2 L xf := 2 L 2 L 2
B 2 B 2 B yf := 2 B 2 B 2
Rebars:
Footing F-4.xmcd
LNT - Page 36 of 41
Calculation Sheet
Xp n Xp + n xp ( n ) := X p + n Xp n Xp n 2 Lpx n 2 Lpx n 2 Lpx n 2 Lpx n 2
Lpx n
Columns/pedestal:
Zp n Zp n yp ( n ) := Z p + n Zp + n Zp n
Lpz n 2
PLAN REINFORCEMENTS
L = 5.000 m
B = 6.000 m
cL X-Axis
Footing F-4.xmcd
LNT - Page 37 of 41
Calculation Sheet
cL Z-Axis
SUMMARY OF REINFORCEMENTS: Bot_BarsParallel.L = "20mm at 200mm O.C." Top_Bars Parallel.L = "16mm at 300mm O.C." FOOTING DIMENSIONS: L = 5.000 m B = 6.000 m Bot_BarsParallel.B = "20mm at 200mm O.C." Top_Bars Parallel.B = "16mm at 300mm O.C." T = 0.500 m
Center lines:
y1 :=
0m 0m
1.2 L 2 x1 := 1.2 L 2
Footing F-4.xmcd
LNT - Page 38 of 41
Calculation Sheet
1.2 max ( h + T)
y2 :=
T 2
x2 :=
0m 0m
Footing:
L 2 L 2 L xf := 2 L 2 L 2
0m 0m yf := T T 0m
Rebars:
L 2cov 2 x1rebar := L 2cov 2 cov + 0.5 diabarx y1rebar := cov + 0.5 dia barx
y2rebar :=
cov + diabarx + 1 diabarz cov + dia + 1 dia barx barz cov + dia + 1 dia y3rebar := T barx barz T cov + dia + 1 dia barx barz cov + dia + 1 dia barx barz
Footing F-4.xmcd
LNT - Page 39 of 41
Calculation Sheet
Columns/pedestal:
Xp n Xp + n xp ( n ) := X p + n Xp n Xp n
T T T + hn yp ( n ) := T + hn T
T = 0.500 m
Footing F-4.xmcd
LNT - Page 40 of 41
Calculation Sheet
Footing F-4.xmcd
LNT - Page 41 of 41