The proven, fast slab formwork made of high-strength aluminium

product range 8.10

Edition 01/2007 PERI GmbH P. O. Box 12 64 89259 Weissenhorn Tel.: 0 73 09 / 9 50-0 Fax: 0 73 09 / 9 51-0 info@peri.de www.peri.de

Important notes: Our products are to be used in accordance with the relevant national and european safety regulations. The illustrations in this brochure are photographs of real site situations. Safety or formwork anchor details are therefore not to be taken as a definitive guide to the way the equipment is to be used. Safety precautions and allowable loads are to be strictly observed. Separate structural calculations are required for any deviations from the standard design data. The information contained herein is subject to technical change in the interests of progress.

Contents
The proven aluminium slab formwork system The cost-effective slab formwork with many advantages for the user Forming with drophead SKYDECK infills Detailed solutions with system components Even the logistics have been rationalised Design tables Range PERI International

Page

2-3 4-5 6-7 8-9 10 11 12-19 20-33 36-37

PERI SKYDECK The proven aluminium slab formwork system for sensationally fast formwork erection

SKYDECKs main beam reduces the number of props You only need 0.29 props per square meter of slab. This corresponds to a grid rectangle of 2.30 x 1.50 m (3.45 m2) supported by just one prop. Fewer props save time and leave more space. Formwork materials can be transported across the site, or building materials such as bricks easily stored between these widely spaced props ready for subsequent use. SKYDECK has a drophead that allows you to strike after only 1 day (depending on the depth of the slab and concrete strength). This allows you to reduce formwork stock levels on site, since the beams and panels are than available for the next concreting cycle. Striking after a short time means striking and cleaning is also much easier, since the panels separate from the concrete effortlessly. The drophead principle enables you to work more flexibly, for instance by striking early during poor weather, or when you have labour free.

The large prop spacing of 1.50 x 2.30 m means time saving and more space for moving materials.

Erected

The panels and cover strips form the soffit of the concrete.

Drophead lowered 60 mm

The cover strips and dropheads remain while the panels and beams are struck.

SKYDECK minimises cleaning costs The SKYDECK panels and main beams have self-draining edges, and the edges of the panels are undercut. This keeps the side surfaces clean and reduces cleaning to a minimum. The SKYDECK main beam with powder coating and plastic rack is designed to minimise cleaning, and is therefore an important factor in the speed achieved with this system.

The main beam lies protected under the panels. This reduces cleaning.

so be
Di e

n de

re Pulverbe

sc

hi c

SKYDECK components are made of aluminium to make them very light. No part weighs more than 15 kg. Thanks to the low individual weights PERI SKYDECK enables easy and tireless erection and striking.

PERI ECC
Easy Clean Coating

un ht
gv
on PERI

The ECC powder coating prevents concrete adhering to SKYDECK.

schn

el

le

r saube

SKYDECK has manageable parts. The largest part measures only 1500 x 750 x 120 mm. This allows optimum transport between the rows of props and through door and window openings.

Working with SKYDECK means easy and tireless erection and striking the whole day.

The cost-effective slab formwork with many advantages for the user

SKYDECK forms slab thicknesses of up to 950 mm. See design tables.

The outward projecting teeth "catch" the panels. The panels clip in and lie securely in the rack. The SKYDECK system provides working safety during erection.
3.45 m2 are erected with one standard field. Using main beam SLT 225 means only 0.29 props per m2.

SKYDECK panels positioned from above.

1,50 m

2,30 m

SKYDECK offers a systematic erection sequence and safety features that rule out erection errors. Handling is quickly mastered, even by personnel unfamiliar with this system.

SKYDECK systematization means you no longer have to set out props don't have to determine primary and secondary beam spacings do not have to take account of the load capacity of the formlining

The panels are secured automatically by the lugs on the main beam.

The main beam is mounted rigidly on the drophead or prophead and cannot tilt.

Mounting SKYDECK head The SKYDECK drophead and prophead are fitted with the new type of self-locking coupling. This allows you to mount the head without laborious bolting or pinning and wedging. Simply place it and allow it to engage thats all there is to it! The head is now securely mounted. Removal is simply a matter of releasing the coupling and taking the head off. Self-locking coupling = time saving.

SKYDECK speeds up formwork to reduce your costs. SKYDECK provides: Main beams that save on props Drophead principle ECC powder coating self-draining edges, plastic profiles Individual components made of alum. and weighing less than 15 kg Straight formwork line Structurally optimised system Systematic erection sequence New type of self-locking coupling Benefit to you: Fewer props Earlier, easier striking Less cleaning Easy erection and striking without fatigue Simple perimeter adjustment Very accurate surfaces Operating errors ruled out Quick mounting on the prop without screws or bolts.
Works with all standard props. Diameter of hole 40 mm.

Formwork with drophead

Gives you the advantage of rapid concreting cycles with small stock of equipment. The drophead principle allows striking after 1 day, depending on slab depth and concrete strength. Striking is easier, since the panels release from the concrete more readily after a shorter time. The possibility of striking after a shorter time allows you to work more flexibly (eg during bad weather or when personnel have free capacity). The main beam cuts the number of props. You only need 1 prop for a 2.30 x 1.50 = 3.45 m2 bay. This corresponds to 0.29 props per square meter of slab.

SKYDECK standard grid panel with drophead system

Typical application with wall return, angled wall junction and column to be formed.

B 6

Cross section A-A The design principle with the panels lying on top of the main beam makes the wall junction possible as the main beam can be set back, along the panel.

Longitudinal section B-B Wall junction with prophead set back. The prophead is held on the beam automatically.

drophead

prophead

drophead

An important advantage in application: The extended length of the prop remains the same, irrespective of whether you are working with drophead or the prophead drawn back at the wall junction. Striking with drophead The drophead is released with a hammer blow, causing all of the formwork to drop 60 mm. Panels and main beams can then be taken off. The drophead props with cover strips remain in the grid rectangle. Props in the edge or infill areas can be removed. You will therefore only need about 70% extra drophead props for your new cycle.

Prophead set back at the wall junction 0,41

Drophead

0,41

Only the props with drophead and cover strip remain after striking.

SKYDECK infills

Longitudinal infilling For infilling up to 1.50 m, formwork is simply continued with panels and prophead until the gap left can be closed with filler timbers.

Infilling lengths: 2.25 m with main beam SLT 150 and appropriate infill 1.50 m with 1 panel 750 mm wide and appropriate infill 750 mm panel with appropriate infill or with infill panel 375 mm wide and appropriate infill (see SKYDECK Poster for detailed infilling)

Transition from standard grid rectangle to infilling with the end support

Infill length L

SLT 225 edge beam drophead SFK

SLT 225 drophead SFK

end support SSL

Transverse infilling Transverse infilling or adaptation for angled walls is carried out in the same way as longitudinal infilling, using panels and prophead until the gap left can be closed with a filler plate. The panels can be turned in the other direction to achieve this.

Transverse infilling with 150 x 75 panel, SPH filler timber and filler plate.

max. 1.50 m

filler timber

drophead

Formwork around a column With the secondary or edge beam in one direction. primary beam
Transverse infilling with drophead system with 150 x 75 panel, edge beam and filler

Edge beams turned sideways can be used for formwork around columns.

Formwork is taken around columns with a maximum edge length of 1.38 m in this way. When the edge beam SRT-2 75 is being used the maximum edge length is 630 mm.

Detailed solutions with system components The SKYDECK Platform on the edge of the building saves a safety scaffold

Edge of slab with safety handrail system Slab edges are formed with the cantilevered SLT 375 slab edge beam and the SKYDECK Platform.

The SKYDECK platform saves construction time. Even 1 day after concreting it serves as a safety scaffold for work on the columns and breast walls (parapets).

SKYDECK platform

SAO tension sleeve SLT 375 main beam

anchor chain and M 12 anchor coupler

No safety scaffold necessary

After the simple positioning the platform is immediately fixed against tipping or moving.

Safety scaffold at the cycle joint

Plan

Side elevation

handrail post handrail holder

10

Even the logistics have been rationalised

Formwork erection will be even faster if there is order on site and as few crane lifts as possible.

Pallet lifting truck Item no.: 061510

The SKYDECK pallet can be shifted with the crane or moved with a pallet truck. The pallet is equally suitable for forklift trucks when dispatching, or in the builder's yard. All SKYDECK pallets are hot-dip galvanised and can be stacked.

Large SKYDECK pallet with 48 panels 150 x 75 = 54 m2 of formwork surface

SKYDECK Pallet SD filled with 14 panels 150 x 75 = 15.75 m2 of formwork surface. RP 80 x 120 filled with 25 MULTIPROP Props corresponding to 86 m2 of formwork surface.

11

SKYDECK With prophead SFK, Main beam SLT 225, SLT 150
Main beam SLT 225 Slab thickness d [m] Panel span c 1,50 m Load q* [kN/m2] Prop load [kN]
with SSk centre support

Main beam SLT 150 Panel span c 1,50 m Prop load [kN]
with SSk centre support

Panel span c 0,75 m Prop load [kN]


with SSk centre support

Panel span c 0,75 m Prop load [kN]


with SSk centre support

Deflection line**
with SSk centre support

Deflection line**
with SSk centre support

Deflection line**
with SSk centre support

Deflection line**
with SSk centre support

0.14 0.16 0.18 0.20 0.22 0.24 0.26 0.28 0.30

5.19 17.9 5.71 19.7 6.23 21.5 6.75 23.3 7.27 25.1 7.79 26.9 8.31 28.7 8.83 30.5 9.40 32.4 17.8

7 7 7 7 7 7 7 7 7 6 6 7 7 6 6 6

9.0 9.8 10.7 11.6 12.5 13.4 14.3 15.2 16.2 18.9 21.5 24.2 25.7 26.8 29.5 32.1 19.3 34.7 20.8 37.4 22.4 40.0 24.0 42.7 25.6 27.2 28.8 30.4

7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 7 7 7 7 7 7 7 6

12.1 13.3 14.5 15.7 16.9 18.1 19.3 20.5 21.9 25.4 29.0 32.6 34.7

7 7 7 7 7 7 7 7 7 7 6 6 6 18.1 19.8 21.6 23.4 25.2 27.0 28.8 30.5 32.3 34.1 7 7 7 7 7 7 7 6 6 6

0.35 10.94 37.7 20.8 0.40 12.47 43.0 23.7 0.45 14.01 0.48 14.93 0.50 15.54 0.55 17.07 0.60 18.61 0.65 20.14 0.70 21.68 0.75 23.21 0.80 24.74 0.85 26.28 0.90 27.81 0.95 29.35 * Load to DIN 4421 : Dead load Concrete load Live load Total load 26.6 28.3

g = 0.20 kN/m2 b = 26 kN/m3 x d (m) p = 0.20 x b 1.5 p 5.0 kN/m2 q = g + b + 0.9 x p

** Deflection to DIN 18202 assuming perfect levelling. When calculating the prop load, the actual extension length may be used. The exact extension length of the prop when using the SKYDECK drophead: clear height minus 0.41 m. From a prop load of over 33.3 kN bolting on the Drophead (2 bolts M12x40 mm Mu DIN 601) can only be omitted when using MULTIPROP props.

12

SKYDECK With prophead SSK, Main beam SLT 225, SLT 150
Main beam SLT 225 Slab thickness d [m] Panel span c 1.50 m Load q* [kN/m2] Prop load [kN]
with SSk centre support

Main beam SLT 150 Panel span c 1.50 m Prop load [kN]
with SSk centre support

Panel span c 0.75 m Prop load [kN]


with SSk centre support

Panel span c 0.75 m Prop load [kN]


with SSk centre support

Deflection line**
with SSk centre support

Deflection line**
with SSk centre support

Deflection line**
with SSk centre support

Deflection line**
with SSk centre support

0.14 0.16 0.18 0.20 0.22 0.24 0.26 0.28 0.30

5.19 17.5 5.71 19.3 6.23 21.0 6.75 22.8 7.27 24.5 7.79 26.3 8.31 28.0 8.83 29.8 9.40 31.7 17.8

7 7 7 7 7 7 7 7 7 6 6 7 7 6 6 6 6

8.8 9.6 10.5 11.4 12.3 13.1 14.0 14.9 15.9 18.5 21.0 23.6 26.2 26.7 28.8 31.4 19.2 34.0 20.7 36.6 22.3 39.2 23.9 41.8 25.5 27.0 28.6 30.2

7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 7 7 7 7 7 7 7 6

11.7 12.8 14.0 15.2 16.4 17.5 18.7 19.9 21.2 24.6 28.1 31.5 35.0 35.7

7 7 7 7 7 7 7 7 7 7 6 6 6 6 19.2 20.9 22.7 24.4 26.1 27.8 29.6 31.3 33.0 7 7 7 7 7 7 6 6 6

0.35 10.94 36.9 20.7 0.40 12.47 42.1 23.6 0.45 14.01 0.50 15.54 0.51 15.85 0.55 17.07 0.60 18.61 0.65 20.14 0.70 21.68 0.75 23.21 0.80 24.74 0.85 26.28 0.90 27.81 0.95 29.35 * Load to DIN 4421 : Dead load Concrete load Live load Total load 26.5 29.4 30.0

g = 0.20 kN/m2 b = 26 kN/m3 x d (m) p = 0.20 x b 1.5 p 5.0 kN/m2 q = g + b + 0.9 x p

** Deflection to DIN 18202 assuming perfect levelling. When calculating the prop load, the actual extension length may be used. The exact extension length of the prop when using the SKYDECK Prophead: clear height minus 0.33 m.

13

SKYDECK Panel system

Panel system **Deflection to DIN 18202 line 0.75 m

Slab thickn. d [m]

UDL q* [kN/m2]

Prop load [kN]

0.14 0.16 0.18 0.20 0.22 0.24 0.26 0.28 0.30 0.35 0.40 0.45 0.48 0.50 0.51

5.19 5.71 6.23 6.75 7.27 7.79 8.31 8.83 9.40 10.94 12.47 14.01 14.93 15.54 15.85

5.8 6.4 7.0 7.6 8.2 8.8 9.3 9.9 10.6 12.3 14.0 15.8 16.8 17.5 17.8

7 7 7 7 7 7 7 7 7 7 6 6 6 6 6
* Load to DIN 4421 : Dead load Concrete load Live load Total load

g = 0.20 kN/m2 b = 26 kN/m3 x d (m) p = 0.20 x b 1.5 p 5.0 kN/m2 q = g + b + 0.9 x p

** Deflection to DIN 18202 assuming perfect levelling.

14

1.50 m

SKYDECK Filler timbers, striking time guidelines

1. Permissible width B [m] of the plywood filler Plywood Slap depth [m] used 0.20 0.30 0.40 0.50 0.60 0.70

0.80 0.15 0.40 0.38 0.64


B max. 100 mm

Case 1

3-ply transversely Spruce, Finply, 3-ply longitudinally 3-ply transversely Spruce, Finply, 3-ply longitudinally

0.24 0.67 0.47 0.90


B

0.21 0.58 0.44 0.81

0.19 0.18 0.54 0.49 0.42 0.41 0.76 0.72

0.17 0.16 0.47 0.43 0.40 0.39 0.69 0.67


Case 2

Case 1

Case 2

Filler timber SPH or Edge beam SRT-2

Combihead SCK Filler timber SPH or Edge beam SRT-2

2. Permissible span L [m] of the edge main girders

Girders used GT 24 VT 20 K KH 10/16

0.20 3.51 2.85 2.64

0.30 3.15 2.56 2.37

Slab depth [m] 0.40 0.50 0.60 0.70


2.88 2.68 2.34 2.18 2.17 2.02 2.52 2.40 2.05 1.91 1.90 1.81

0.80 2.29 1.67 1.73

Width of load carried by plywood 400 mm

Minimum concrete strength and guide values* for striking with drophead system
Slab thickness d [m] Concrete strength required fck [N/mm2] *Guide values for the striking time [days] for panels and beams at average curing temperature [C] of

0.14 0.16 0.18 0.20 0.22 0.25 0.30 0.35 0.40-0.95

15 13 11 9 8 7 6 5 5

5 10 8 6 5 4 4 3 3 2

10 6 5 4 3 3 2 2 2 1

20 5 4 3 2 2 2 2 1 1

The necessary concrete strength at the time of striking is important. This can be calculated by suitable methods. Account must also be taken of DIN 1045, e.g. curing. At least 1.31 cm2/m(Q 131) is necessary as lower reinforcement. For systems without centre support of the main girders. A live load of 100 kg/m2 is to be taken into account for the early struck slab. *Guide values after Leonhard for Z 35 cement, CEM I 32,5 R.

15

Props PEP 20
Permissible prop load [kN] according to type inspection

PEP 20 N 260*
Extend. L = 1.51 - 2.60 m length Outer tube Inner tube [m] bottom bottom

PEP 20-300 PEP 20 N 300*


L = 1.71 - 3.00 m Outer tube Inner tube bottom bottom

PEP 20-350 PEP 20 N 350*


L = 1.96 - 3.50 m Outer tube Inner tube bottom bottom

PEP 20-400 PEP 20 G 410*


L = 2.21 - 4.00 m Outer tube Inner tube bottom bottom

PEP 20-500
L = 2.71 - 5.00 m Outer tube Inner tube bottom bottom

1.60 1.70 1.80 1.90 2.00 2.10 2.20 2.30 2.40 2.50 2.60 2.70 2.80 2.90 3.00 3.10 3.20 3.30 3.40 3.50 3.60 3.70 3.80 3.90 4.00 4.10 4.20 4.30 4.40 4.50 4.60 4.70 4.80 4.90 5.00

35.0 35.0 35.0 35.0 33.5 31.9 30.9 29.8 28.6 27.1 24.8

35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 32.9 29.4

35.0 35.0 35.0 32.2 30.5 29.0 27.8 26.9 26.1 24.9 23.3 21.6 20.0

35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 31.7 28.5 25.7 23.2

35.0 35.0 35.0 35.0 35.0 35.0 33.8 32.4 31.2 30.2 29.2 27.5 25.7 24.1 22.4 20.7

35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 34.6 31.5 28.8 26.4 24.1

35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 33.6 32.5 31.2 29.6 27.8 26.1 24.5 23.0 21.6 20.1

35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 33.9 31.2 28.9 26.8 24.8 22.8

35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 34.2 32.3 30.6 28.9 27.4 26.0 24.6 23.4 22.1 20.9 20.0

35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 35.0 34.0 31.9 29.9 28.1 26.4 24.9 23.4 21.8

All PEP 20 props conform with DIN EN 1065 class D. The perm. load for the entire extension range is min. 20 kN. All PEP 20 props clamped in the table swivel head or UNIPORTAL head fitted to PERI tableforms have a permissible load of 30 kN over the entire extension range. *Application Inner Tube at bottom only possible with PERI Slab Tables or SKYDECK (Head bolted).

16

Props PEP 30
Permissible prop load [kN] according to type inspection

PEP 30-150
Extend. L = 0.96 - 1.50 m length Outer tube Inner tube [m] bottom bottom

PEP 30-250
L = 1.46 - 2.50 m Outer tube Inner tube bottom bottom

PEP 30-300 PEP 30 G 300*


L = 1.71 - 3.00 m Outer tube Inner tube bottom bottom

PEP 30-350 PEP 30 G 350*


L = 1.96 - 3.50 m Outer tube Inner tube bottom bottom

PEP 30-400
L = 2.21 - 4.00 m Outer tube Inner tube bottom bottom

1.00 1.10 1.20 1.30 1.40 1.50 1.60 1.70 1.80 1.90 2.00 2.10 2.20 2.30 2.40 2.50 2.60 2.70 2.80 2.90 3.00 3.10 3.20 3.30 3.40 3.50 3.60 3.70 3.80 3.90 4.00

35.0 35.0 35.0 34.9 34.2 33.5

35.0 35.0 35.0 35.0 35.0 35.0

40.0 40.0 40.0 40.0 38.5 36.8 35.3 34.4 33.3 32.1 30.1

40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 37.6 34.8

40.0 40.0 40.0 40.0 40.0 40.0 40.0 39.9 38.8 37.4 35.8 33.2 30.4

40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 37.2 33.8

40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 37.6 35.0 32.3 30.0

40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 37.6 34.6 31.6

40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 37.4 34.8 32.2

40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 40.0 37.0 33.9

All PEP 30 props conform with DIN EN 1065 class E. The perm. load for the entire extension range is min. 30 kN. All PEP 30 props clamped in the table swivel head or UNIPORTAL head fitted to PERI tableforms have a permissible load of 40 kN over the entire extension range. *Application Inner Tube at bottom only possible with PERI Slab Tables or SKYDECK (Head bolted).

17

Props MULTIPROP 250, 350, 480, 625


Permissible prop load [kN] according to type inspection

MP 250
Extend. length [m] l = 1.45 - 2.50 m Outer tube at bottom Inner tube at bottom

MP 350
l = 1.95 - 3.50 m Outer tube at bottom Inner tube at bottom

MP 480
l = 2.60 - 4.80 m Outer tube at bottom Inner tube at bottom

MP 625
l = 4.30 - 6.25 m Outer tube at bottom Inner tube at bottom

1.45 1.50 1.60 1.70 1.80 1.90 1.95 2.00 2.10 2.20 2.30 2.40 2.50 2.60 2.70 2.80 2.90 3.00 3.10 3.20 3.30 3.40 3.50 3.60 3.70 3.80 3.90 4.00 4.10 4.20 4.30 4.40 4.50 4.60 4.70 4.80 4.90 5.00 5.10 5.20 5.30 5.40 5.50 5.60 5.70 5.80 5.90 6.00 6.10 6.20 6.25

73.3 73.3 73.3 73.3 71.7 68.6 67.0 65.4 63.8 62.2 61.1 60.6 60.0

76.2 76.2 76.2 76.2 76.2 76.2 76.2 76.2 74.6 73.0 70.5 67.0 63.6

88.3 88.3 83.0 77.7 72.9 68.6 64.4 61.9 59.3 57.5 55.7 54.3 52.9 51.4 49.8 46.4 42.9

87.4 87.4 87.4 87.4 86.6 85.1 83.5 80.7 77.8 74.9 71.9 68.3 64.6 60.0 55.4 50.3 45.1

85.9 81.2 76.5 71.8 67.1 63.0 58.9 54.8 52.5 50.2 47.9 46.0 44.2 42.3 40.4 38.5 36.6 34.8 32.9 31.1 29.3 27.4 25.6

71.4 71.1 70.8 70.4 70.1 69.4 68.6 67.9 66.2 64.5 62.8 58.6 54.4 50.2 46.9 43.7 40.4 38.2 36.0 33.7 31.5 29.3 27.1

MULTIPROPs are classified according to official approval as follows: MP 250 = T 25 MP 480 = D 45 MP 350 = R 35 MP 625 = D 60 NB: We recommend using the HD spanner, Item no 022027, to release loads > 60 kN. All MULTIPROPs clamped in the table swivel head or UNIPORTAL head fitted to PERI tableforms have a permissible load of MP 350 min. 56 kN, MP 480 min. 36 kN over the entire extension range.

56.2 54.7 53.1 50.9 48.8 46.4 43.8 41.2 38.6 36.1 33.8 31.9 29.9 28.4 26.9 25.5 24.3 23.1 22.0 20.9 20.4

44.6 44.6 44.6 43.8 43.0 42.1 41.2 40.3 38.8 37.3 35.9 34.5 33.1 31.6 30.1 28.6 27.0 25.4 24.1 22.8 22.1

18

19

SKYDECK and Accessories


Weight kg Panel SDP, Alu Powder-coated. Formlining: 9mm Finply (100% Fin. birch) SDP 150x75 = 1,13m2 Filler panels: SDP 150x50 = 0,75m2 SDP 150x37,5 = 0,56m2 SDP 75x75 = 0,56m2 SDP 75x50 = 0,37m2 SDP 75x37,5 = 0,28m2 Item no.

15,50 11,70 10,60 8,60 6,37 5,04

061000
120

061011 061020 061010 061013 061030

99

21

1500

750

375

500

750

750

500

375

Cover Strip SAL Plastic. For use with drophead. Plywood thickness 21mm. SAL 150 SAL 75 SAL 50 SAL 37,5

1500

1,55 0,77 0,55 0,38

061026 061027 061024 061038

300

275

350

400

175

750

300

275

175

500

200

300

*Plywood thickness 27mm SAL 150/27 SAL 75/27 SAL 37,5/27

78

1,65 0,84 0,45

061028 061029 061039

375

20

82

22 27*

Weight kg Main Beam SLT Alu, powder-coated. With rack made of highly impact-resistant plastic. SLT 225 Standard beam SLT 150 For filler areas SLT 375 For tables and overhangs

Item no.

1494

15,40 10,30 25,50

061100 061110 061160

Bracket axis 1500

225

Detail x 187 1120 187

120 72

190

2244 Bracket axis 2250

275

Detail x

13

70 13 24

240

Detail x 300 450 375 375 450 300

161

3744 1042 Bracket axis 3750 1042

240

161 13

Detail x

300 82

450 266

750

375

375

750

450

300

Edge Beam SRT-2, Alu Powder-coated. For longitudinal and transverse filling, for shuttering around columns. Plywood thickness 21mm SRT-2 75 SRT-2 150

745 49 595

2,86 6,16

061046 061045

93* 98

43 68

660 610

1495 1345

43

1410 1360

*Plywood thickness 27mm (yellow) SRT-2 75/27 SRT-2 150/27 Filler Timber SPH For longitudinal and transverse filling, individually adaptable. Plywood thickness 21mm SPH 150 SPH 225

68

2,86 6,16

061048 061047

14
49

4,00 6,00

061049 061036
93* 98

35

1500

2250

*Plywood thickness 27mm SPH 150/27 SPH 225/27

3,38 5,07

061050 061040

21

Weight kg Grid Beam SRO, Alu* Powder-coated. For use in the grid beam system. Plywood thickness 21mm
* is no longer produced

Item no. 061041 061042

SRO 150 SRO 75

5,96 3,03

750 720

100

62
1500 1470

100

*Plywood thickness 27mm (yellow) SRO 150/27 SRO 75/27 Prophead SSK Powder-coated. With self-locking coupling. Supports panels, main beams, secondary beams, edge beams and filler timber.

6,18 3,14 3,92

061043 061044 061200

62

93* 98

259

160

50

93* 98

80

250

72

Drophead SFK Powder-coated. With self-locking coupling. Supports main beams as well as cover strip or formlining. Lowers 60mm.

6,08

061210
40 250

253* 258

18 4

60 Lowering

390

80

*Drophead SFK/27 Plywood thickness 27mm (yellow)

6,07

061035

22

80

550

80

Weight kg Tension Sleeve SAO Powder-coated. Locking device to prevent grid beams from lifting off. For anchoring cantilevers. 1,00

Item no. 061310


63

149 F

Permissible Load (F): 3kN End Support SSL Powder-coated. For the transition from beam to panel without beam, or edge beam or secondary beam when filling gap. 2,10 061023
102 160 85

70

165

Wall Holder SWH-2, Alu Powder-coated. For anchoring the formwork to the wall horizontally. Attach to every second beam or panel.

5,56

061051
37

140

270

245

100

adjustment range 1050

1490

DW 15

202

275

30 100

23

Weight kg Combi-Head SCK Powder coated. With self-locking coupling. Supports main beams, panels, edge beams and Filler Timber. 5,33

Item no. 061180


50 259
250

Handrail Holder SGH, Alu Powder-coated. With quick locking device for mounting on the main beam.

5,03

061250

305

1605

300

305

70

161

1500

Accessorie: Handrail Post SGP Handrail Post SGP Powder-coated. For use with SGH Handrail Holder. Height of handrail above top of panel = 1,40m

5,82 5,82

061260 061260

35 65

1416

1750

425

425

120

10

44

24

15

245
112

368

Weight kg Panel Clip SPK, galv. Fixes panels on main beam. 0,13

Item no. 061290


121
50 43

Panel Wedge Clip SPKK Powder-coated.

0,75

061280

78

80

115

116

Applications 1. Panel joint in middle of main beam Panel/Panel connection with main beam

2. Projecting panel Panel/Panel connection with main beam

125

Side view

Triangular Frame SDR, Alu Powder-coated. For non-right angled filler applications.

93* 98

1500

750

93* 98

750

*Plywood thickness 27mm (yellow) SDR 150x75/27 SDR 75x75/27 Shuttering Aid SSH, Alu Powder-coated. Adjustable in 75mm increments.

7,54 4,68 2,32

061015 061016 061300

750
min. 2325-max. 3750

Plywood thickness 21mm SDR 150x75 SDR 75x75

8,79 5,45

061021 061022

25

Weight kg Transportation Fork SKYDECK SUG, galv. For moving SKYDECK tables with a crane. Comply with the instructions for use given on the type plate. 403,00

Item no. 061520

3240

type plate

1434

3900

1224

1040 14
2500 min. 220 max. 300 60 21 13 21

2800

Lifting device to BGR 500 Permissible load: 1000kg Anchor Chain 3,0kN L = 2,5m Galvanized. 1,37 065073

Permissible Tension Load: 3kN. Turnbuckle 3,0kN, M12 Galvanized. 0,45 065074
16

Permissible Tension Load: 3kN. Base Plate for RS Complete with: Pin 16x65/86 and Cotter Pin 4/1 (1x). 1,86 028100

80

90

65

40 150

10

40 55 30

25

Anchor Bolt PERI MMS 20x130 For erecting push-pull props without plugs, tension cables etc. Use drill 18mm to DIN 8035

0,33

103606
SW 30

20

26

drilling depth min 140

130

60

80

Weight kg Platform SDB SDB 300 SDB 225 SDB 150 For work and protective access to DIN 4420. Scaffold width 1,30m. With continuous 39mm thick staging and folding handrail frame for easy transporting. Platform SDB 225 cantilevers by 750mm to the left or right. 185,00 153,00 108,00

Item no. 061062 061061 061060


1220
1288

1448

2990

2240

1000

1300

2250

SDB 300

1500

1000

SDB 225

1500

1500

750

750

Spare Parts: Handrail Frame SDB, galv. Foldable. SDB 300 SDB 225 SDB 150 Plywood Planking SDB With continuous 39mm thick staging. SDB 300 SDB 225 SDB 150 33,30 25,90 18,50 061065 061064 061063

73,10 54,50 35,90

061068 061067 061066

1500

SDB 150

1500

SDB 225

2250

2250

3000

27

1490

Weight kg Hex. Bolt M12x140 DIN 6914-10.9 0,14

Item no. 061230


SW 22

Accessories: Hex. Nut ISO 4032 M12-8, galv. Washer ISO 7089-12-200HV, galv. Table Connector STV For connecting SKYDECK tables. Also used for setting props at any location at the Main Beams. Complete with: Ring screw M12 DIN 582

140

0,017 0,006 2,56

710330 780702 061052


330 74

23

85

Pallet SD 150x75, galv. For stacking and transportation of 14 SKYDECK Panels 150x75.

77,80

061500

! Important safety note! When stacking light, large surface items outdoors the maximum stacking height must be reduced.

70

1720 120
60 580 1630 60

640

Lifting device to BGR 500 Permissible load: 1000kg Max. stacking height: 2 Min. length of rope: 3,0m

28

760

1970

Weight kg Pallet SD 150x225, galv. For stacking and transportation of 48 SKYDECK Panels 150x75. Complete with: 5 tension straps 83,60

Item no. 061530

1550

250

2310

120

Lifting device to BGR 500 Permissible load: 750kg Pallet Lifting Trolley Length of Forks: 1550mm Support Width of Forks: 520mm Lifting Range: 85 to 195mm 110,00 061510

Lifting appliance to BGV D8 Permissible load: 2000kg

2110

190

120

29

Weight kg Stripping Cart ASW 465 Complete with: 1 Steel traverse 140/220 ASW (1x) consisting of 3 parts 2 Folding base unit 160/190 ASW (1x) 3 Vertical frames 70/90 ASW (6x) 4 Vertical frames 70/120 ASW (6x) 5 Entry platforms 190 ASW (2x) 6 Toe-board set 70/190 ASW (1x) 7 Double handrails 190 ASW (4x) 8 Diagonal braces 210 ASW (3x) 9 Horizontal braces 190 ASW (2x) 10 Wind security clip 60 ASW (8x) 11 Ballast 10kg ASW (12x) Packed in: Ring pallet USP 104, galvanized Complete with: Lashing strap 25x5750mm (1x) Scaffold Tube steel 48.3x3.2, L = 1,0m as Ring extensions (6x) Max. platform height = 4,65m Max. working height = 6,65m Platform height alterations = 300mm 363,00 32,60 18,60 4,40 4,90 14,80 8,00 5,30 2,40 2,30 0,06 10,00 65,60 0,50 3,55

Item no. 102031 102033 102025 102035 102034 102026 102030 102027 102028 102029 102037 102807 100678 100707 026411
1150
2360 1100

4 3

8 6 9 Ring pallet USP 104, galv. Observe operating instructions! Lifting device to BGR 500 Permissible load: 1200kg Stripping Cart, Alu Platform height: up to 2,00m Permissible load: 100kg/m2 77,00 035500 10 11

handrail height 980

3035

250
750

48

1800

30

platform height 2000

PERI BIO Clean, PERI Clean


Weight kg PERI Bio Clean Release Agent for all types of formwork. - Rapidly biologically degradeable. - Based on mineral oils. - Class 1 on German water pollutant scale. (WGK 1) Release Agent Bio Clean 20L Release Agent Bio Clean 208L Item no.

0,91/L 0,91/L

031440 031455

For further information see product information PERI Bio Clean.

Consumption: 1 litre covers 50 to 90m2 of formwork (depending on formwork surface) PERI Clean Release Agent for all types of formwork. Based on mineral oils. Cleans and protects. Can be used down to -15C degree. Class 1 on German water pollutant scale. Release Agent PERI Clean 20L Release Agent PERI Clean 208L 0,92/L 0,92/L 031420 031435

For further information see product information PERI Clean.

Consumption: 1 litre covers 50 to 90m2 of formwork (depending on formwork surface) Pressure Sprayer For spraying formwork surfaces evenly with PERI BIO Clean or PERI Clean. Capacity: 5 litre 4,44 031520

Spare Part: Spray Nozzle (0,1F 110)

0,064

031530

31

MULTIPROP and Accessories


Weight kg MULTIPROP MP, Alu Can be used individually, as well as in combination with MULTIPROP MRK Frames tableforms or shoring towers. MULTIPROP MP 120 (0,80-1,20m) MULTIPROP MP 250 (1,45-2,50m) MULTIPROP MP 350 (1,95-3,50m) MULTIPROP MP 480 (2,60-4,80m) MULTIPROP MP 625 (4,306,25m) 10,40 15,00 18,80 23,80 33,60 027288 027289 027290 027291
150 120 17 10 75

Item no.

End Plate 027305

80 64

40 14

64 80 120 150

L min L max

Section

64

L min. MP 120 MP 250 A MP 350 MP 480 MP 625 800 1450 1950 2600 4300

L max. 1200 2500 3500 4800 6250

A 715 1365 1865 2515 4211

B 421 1071 1571 2221 1975

17 10 75

Base MP 50 With quick action clamp coupling.

8,81

027310

150

500

12,5 80 42 200

For mounting props with 6 to 10mm thick end plates.

89

32

10 0

87

PEP 20, PEP 30 Props


Weight kg Props PEP 20, galv.
6

Item no.

PEP 20-300 PEP 20-350 PEP 20-400 PEP 20-500

L = 1,71-3,00m L = 1,96-3,50m L = 2,21-4,00m L = 2,71-5,00m

15,70 19,20 22,70 30,50

103058 103059 103060 103061

End Plate
14

B
100

84

80 D2 100

120

D1

20-300 A B D1 D2 1602 143 66.0 54.0

20-350 1852 93 71.5 59.5

20-400 2102 143 75.5 63.5

40 20-500 2602 143 84.0 72.0

For load capacity refer to PERI Formwork Design Tables. Props PEP 30, galv.
8

PEP 30-150 PEP 30-250 PEP 30-300 PEP 30-350 PEP 30-400

L = 0,96-1,50m L = 1,46-2,50m L = 1,71-3,00m L = 1,96-3,50m L = 2,21-4,00m

10,40 15,00 18,70 22,70 27,20

103066 103067 103062 103063 103065

End Plate
14 9

B 100

82

80 D2 100

120

D1 A

30-150 A B 852 93 66.0 54.0

30-250 1352 93 66.0 54.0

30-300 1602 143 71.5 59.5

30-350 1852 93 75.5 63.5

40 30-400 2102 143 84.0 72.0

For load capacity refer to PERI Formwork Design Tables.

D1 D2

33

PERI International

1 PERI GmbH Rudolf-Diesel-Strasse 89264 Weissenhorn Phone 07309/950-0 Telefax 07309/951-0 info@peri.de www.peri.de

42 20 22 19

32 34 18 44 38 52 11 11 6 17 5 1 16 2 3 29 53 48 9 41 30 13 28 21 46

4 24
33

12

2 France PERI S.A.S. Zone Industrielle Nord 34-36 rue des Frres Lumire 77109 Meaux Cedex Tel.: +33 /1/ 64 35 24 40 Fax: +33 /1/ 64 35 24 50 peri.sas@peri.fr www.peri.fr 3 Switzerland PERI AG Aspstrae 17 8472 Ohringen Tel.: +41 /52/ 3 20 03 03 Fax: +41 /52/ 3 35 37 61 info@peri.ch www.peri.ch

7 USA PERI Formwork Systems, Inc. 7135 Dorsey Run Road Elkridge, MD 21075 Tel.: +1 /4 10/ 7 12-72 25 Fax: +1 /4 10/ 7 12-70 80 info@peri-usa.com www.peri-usa.com 8 Indonesia PT Beton Perkasa Wijaksana P.O. Box 3737 Jakarta 10210 Tel.: +62 /21/ 5 71 26 44 Fax: +62 /21/ 5 73 85 64 beton@cbn.net.id

9 Italy PERI S.p.A. 4 Spain Via G. Pascoli, 4 PERI S.A. Sociedad Unipersonal 20060 Basiano (MI) Ctra. Paracuellos - Fuente el Saz km. 18,9 Tel.: +39 /02/ 9 50 78-1> Camino de Malatones, km. 0,5 Fax: +39 /02/ 95 76 19 14 28110 Algete / Madrid info@peri.it Tel.: + 34 / 91 / 6 20 48 00 www.peri.it Fax: + 34 / 91 / 6 20 48 01 10 Japan info@peri.es www.peri.es PERI Japan K.K. 7F 314 Hakozaki Building, 5 Belgium /Luxemburg 31-4 Hakozaki-cho, N.V. PERI S.A. Nihonbashi Chuo-ku Industriepark Tokyo 103-0015 Nijverheidsstraat 6 PB 54 Tel.: +81 / 3 / 56 42 / 61 00 1840 Londerzeel Fax: +81 / 3 / 56 42 / 61 Tel.: +32 /52/ 31 99 31 01frbk6541@mb.infoweb.or.jp Fax: +32 /52/ 30 08 30 11 United Kingdom/Ireland info@peri.be www.peri.be PERI Ltd. Market Harborough Road 6 Netherlands Clifton upon Dunsmore PERI B.V. Rugby, CV23 0AN v. Leeuwenhoekweg 23 Tel.: +44 /17 88/ 86 16 00 Postbus 304 Fax: +44 /17 88/ 86 16 10 5480 AH-Schijndel info@peri.ltd.uk Tel.: +31 /73/ 5 47 91 00 www.peri.ltd.uk Fax: +31 /73/ 5 49 36 51 info@peri.nl www.peri.nl

16 Austria 12 Turkey PERI Ges.mbH PERI Kalp ve skeleleri Industriegelnde 152 San. Tic. Ltd. Sti. Postfach 1 akmakl Ky Kars 3131 Getzersdorf Sanbir Bl. 4.Blge 9.Cadde No: 133 Tel.: +43 /27 83/ 41 19 Bykekmece / Istanbul Fax: +43 /27 83/ 41 19-20 Tel.: +90 /2 12/ 8 86 74 01(02)-(09) office@peri.at Fax: +90 /2 12/ 8 86 74 15 www.peri.at periist@peri.com.tr www.peri.com.tr 17 Czech Republic PERI spol. s r.o. 13 Hungary P.O. Box 3 PERI Kft. 252 42 Jesenice / Prahy Zdor u. 4. Tel.: +420 /241 090 311 1181 Budapest Fax: +420 /241 090 315 Tel.: +36 /1/ 2 960 960 info@peri.cz Fax: +36 /1/ 2 960 950 www.peri.cz info@peri.hu www.peri.hu 18 Denmark PERI DANMARK A/S 14 Malaysia forskalling og stillads PERI Formwork Malaysia Greve Main 26 Sdn. Bhd. 2670 Greve Unit 19-04-7, Level 7 Tel.: +45 /43/ 45 36 27 PNB Damansara Fax: +45 /43/ 45 36 87 19 Lorong Dungun peri@peri.dk Damansara Heights www.peri.dk 50490 Kuala Lumpur Tel.: + 60 / 3 / 20 93 68 23 Fax: + 60 / 3 / 20 92 58 76 19 Finland PERI Suomi Ltd Oy info@perimalaysia.com Hakakalliontie 5 www.perimalaysia.com 05460 HYVINK Tel.: +358 /19/ 26 64 600 15 Singapore Fax: +358 /19/ 26 64 666 PERI-HORY ASIA www.perisuomi.fi Formwork Pte. Ltd. No. 1 Sims Lane # 06-10 Singapore 387355 20 Norway PERI NORGE AS Tel.: +65 / 67 44 29 89 Industrigata 11 Fax: +65 / 67 44 36 93 3400 Lier pha@periasia.com Tel.: +47 /32/ 24 17 00 www.periasia.com Fax: +47 /32/ 24 17 01 info@peri.no www.peri.no

21 Poland PERI Polska Sp. z o.o. ul. Stoeczna 62 05-860 Pochocin Tel.: +48 /22/ 72 17 400 Fax: +48 /22/ 72 17 401 info@peri.pl.pl www.peri.pl.pl 22 Sweden PERIform SVERIGE AB Montrgatan 4-6 Box 9073 30013 Halmstad Tel.: +46 /35/ 17 46 60 Fax: +46 /35/ 17 46 78 peri@periform.se www.periform.se 23 Korea PERI (Korea) Ltd. 9thFl., Yuseong Bldg. 830-67 Yeoksam-dong, Kangnam-ku, Seoul 135-080 Tel.: +82 /2/ 5 50 22 00 Fax: +82 /2/ 5 57 53 82 info@perikorea.com www.perikorea.com 24 Portugal PERIcofragens Lda. Rua Cesrio Verde, n 5 - 3 Esq. Linda-a-Pastora 2790-326 QUEIJAS Tel.: +3 51 /21/ 4 25 38 90 Fax: +3 51 /21/ 4 25 39 46 info@peri.pt www.peri.pt 25 Argentina PERI S.A. Ruta Nacional No. 9, km 47,5 (Panamericana Ramal Escobar) (1625) Escobar / Prov. Bs. As. Tel.: +54 /34 88/ 42 81 00 Fax: +54 /34 88/ 42 30 21 info@peri.com.ar www.peri.com.ar

36

44 36 52 43

7 39 47 49 37 40

50

51 23 54 35 10

14 15 8 26

45 27 25

31

26 Brazil 31 Australia PERI Australia Pty. Ltd. PERI Formas e 116 Glendenning Road Escoramentos Ltda. Rodovia Raposo Tavares, km 41 Glendenning NSW 2761 Colinas Bandeirante Tel.: +61 /2/ 88 05 23 00 CEP 067300-000 Fax: +61 /2/ 96 75 72 77 Vargem Grande Paulista info@periaus.com.au So Paulo www.periaus.com.au Tel.: +55 / 11 / 41 58 81 88 Fax: +55 / 11 / 41 58 81 88 32 Estonia info@peribrasil.com.br PERI AS www.peribrasil.com.br Valdme 8 Tnassilma Tehnopark 76401 Saku vald 27 Chile PERI Chile Ltda. Harjumaa C /Jos de San Martin 104 Tel.: + 3 72 / 6 / 77 11 00 Fax: + 3 72 / 6 / 77 11 22 Parque Industrial Los Libertadores peri@peri.ee Colina, Santiago de Chile www.peri.ee Tel.: +56 /2/ 4 44 60 00 Fax: +56 /2/ 4 44 60 01 perich@peri.cl 33 Greece PERI Hellas Ltd. www.peri.cl Sokratous Str. 5th kil. Koropi-Varis Ave. 28 Romania P. O. Box 407 PERI Romnia SRL Calea Bucureti nr. 2B 194 00 Koropi 077015 Baloteti - ILFOV Tel.: +30 /210/ 66 20 895-8 Tel.: +40 /21/ 3 51 19 73 (75) Fax: +30 /210/ 66 28 416 Fax: +40 /21/ 3 51 19 74 info@perihellas.gr www.perihellas.gr info@peri.ro www.peri.ro 34 Latvia PERI SIA 29 Slovenia Granita 26 Goran Opali s. p. 1057 Riga technologije in storitve Tel.: +371 / 7 13 41 11 Obrena 137 Fax: +371 / 7 13 41 15 2000 Maribor info@peri-latvija.lv Tel.: +386 /2/ 4 21 52 40 www.peri-latvija.lv Fax: +386 /2/ 4 21 52 41 30 Slovakia PERI spol. s r.o. Pribylinsk 10 831 04 Bratislava Tel.: +421 /2/ 4 92 09-1 11 Fax: +421 /2/ 4 92 09-1 10 info@peri.sk www.peri.sk

36 Canada 41 Bulgaria PERI BULGARIA EOOD PERI Formwork Systems, Inc. Kv. Vragdebna 45 Nixon Road m. Nova machala Nr. 46 Bolton, Ontario 1839 Sofia, Bulgarien L7E 1K1 Tel.: +3 59 /2/ 8 14 40 40 Tel.: +1 /9 05/ 9 51 54 00 Fax: +3 59 /2/ 8 14 40 50 Fax: +1 /9 05/ 9 51 54 54 peri.bulgaria@peri.bg bbaxa@peri.ca www.peri.bg www.peri.ca 37 Lebanon PERI GmbH Lebanon Representative Office AYA Commercial Center, 7th Fl, Dora Highway P.O box: 90 416-Jdeideh Beirut - Lebanon Tel: + 961 / 1 24 33 65 Fax: + 961 / 1 24 33 67 Mob: + 961 / 3 73 73 67 afady@hotmail.com lebanon@peri.de 38 Lithuania PERI UAB Titnago st. 19 2053 Vilnius Tel.: +370 /5/ 2 31 14 54 Fax: +370 /5/ 2 32 19 66 info@peri.lt www.peri.lt 39 Morocco PERI S.A. Route de Rabat, km. 5 Piste de Beni Touzine Tanger Tel.: +212 /39 31 75 48 Fax: +212 /39 31 75 49 perimaro@menara.ma 42 Iceland MEST ltd., Malarhofdi 10 110 Reykjavik Tel.: +354 / 44 00-4 00 Fax: +354 / 44 00-4 01 mest@mest.is www.mest.is 43 Kazakhstan PERI Kazakhstan Rubenstein Street 10 (corner Dostyk Str.) 050010 Almaty Tel.: +7 /32 72/ 93 00 66 Fax: +7 /32 72/ 91 77 59 perialmaty@peri.com.tr www.peri.com.tr

46 Ukraine TOW PERI Ukraina 23, M. Raskowoj Str. 02002 Kiev Tel.: +380 /44/ 5 68 53 57 Fax: +380 /44/ 5 68 51 45 peri@peri.com.ua www.peri.com.ua 47 Egypt PERI GmbH Egypt Branch Office 24 A, Obour Gardens, 4th floor, apt. #1 Salah Salem Street 11361 Heliopolis / Kairo Tel.: +20 /2/ 4 04 85 24/26 Fax: +20 /2/ 4 04 57 84 peri@link.com.eg 48 Serbia PERI - Oplate d.o.o. Jurija Gagarina 81 11070 Novi Beograd Tel.: +3 81/ 11/ 2 15 31-48 /-49 Fax: +3 81/ 11 / 3 18 59 62 office@peri.co.yu www.peri.co.yu

51 Turkmenistan PERI Kal p ve skeleleri Agabat Branch Office Oguzhan Kesi No: 112 Kat:3 Agabat Tel : +993 12 45 66-83/84 Fax : +993 12 45 23 50 periashgabat@peri.com.tr 52 Belarus PERI GmbH Gikalostr. 3 Bro 413 220000 Minsk / Belarus Tel : +3 75 / 1 72 / 84 72 38 Fax: +3 75 / 1 72 / 84 72 38 peri@mail.belpak.by 53 Croatia PERI Oplate i Skele d.o.o. Dolenica 20 10 250 Zagreb/Donji Stupnik Tel : +3 85 /1/ 6 55 36 36 Fax: +3 85 /1/ 6 55 36 37 peri1@zg.t-com.hr www.peri.de 54 Iran PERI GmbH Iran Branch Office Valiasr Ave., No. 1075 Flat 904, Tehran / Iran P.O. Box 15 11 73 49 11 Tel : + 98 / 21 / 88 71 27 10 Fax: + 98 / 21 / 88 71 27 09

35 United Arab Emirates 40 Israel PERI (L.L.C.) PERI Formwork Brashy Building, Office No. 212 Engineering Ltd. Shk. Zayed Road 16 Moshe Dayan st. P.O. Box 27933 P.O. Box 10202 Dubai Kiriat Arie Tel.: +971 /4/ 3 39 44 94 Petach Tikva 49002 Fax: +971 /4/ 3 39 44 34 Tel.: +972 /3/ 9 24 93 32 perillc@perime.com Fax: +972 /3/ 9 24 93 31 www.perime.com info@peri-il.com www.peri-il.com

49 Mexico 44 Russian Federation OOO PERI PERI Cimbras y Andamios, Ul. Krasnaja Presnja, 24 S.A. de C.V. Business-Center Cerrada de Tejocotes, Krasnaja Presnja , 8. Etage Lote 4, Bodega A 123022 Moskwa Fracc. San Martin Obispo Tel.: +7 / 4 95/ 2 23 88 44 C.P.54763 Cuautitln Izcalli Fax: +7/ 4 95/ 2 23 88 17 Estado de Mxico moscow@peri.ru Tel.: + 52 / 55 / 58 87 72 30 www.peri.ru Fax: + 52 / 55 / 58 87 71 09 info@peri.com.mx 45 South Africa www.peri.com.mx PERI Wiehahn (Pty.) Ltd. P.O. Box 2668 50 Azerbaijan Bellville 7535 PERI BAKU Tel.: +27 /21/ 9 05 18 15 Baku Branch Office Fax: +27 /21/ 9 05 47 07 Mehdi Hseyn 71/9 team@wiehahn.co.za Baku / Aserbaidschan www.periwiehahn.co.za Tel : + 994 12 97 64 24 Fax : + 994 12 92 45 51 peribaku@peri.com.tr

37

The PERI Range


Panel Formwork TRIO, TRIO-L, TRIO 330 Versatile panel system TRIO HOUSING TRIO REPLIABLE DOMINO Light weight panel system HANDSET The "one man" panel system Girder Wall Formwork VARIO GT 24 Wall, column formwork RUNDFLEX and GRV Circular formwork FTF Facade formwork Shoring Systems ST 100 Stacking tower HD 200 Heavy duty prop PERI MULTIPROP The Alu prop PERI PEP Prop PEP = PERI EURO-PROP Climbing Formwork KG and CB Climbing systems ACS Self climbing formwork SKS and SSC Single sided climbing formwork Scaffolding UP T 70 / T 100 Frame scaffolding UP Rosett Modular scaffolding UP Rosett Shoring PERI GmbH P.O. Box 12 64 89259 Weissenhorn Tel.: 0 73 09 / 9 50 -0 Fax: 0 73 09 / 9 51 -0 info@peri.de www.peri.de Further Systems Software for formwork and scaffolding planning Plywood Site equipment Brace frames Formwork accessories Custom forms
pr 8.10 e 01/2007 10ho Art. Nr.: 790937 Copyright by PERI GmbH D

Column Formwork RAPID Alu column formwork TRIO Column formwork QUATTRO The fast column formwork PERI SRS Circular column formwork Girder Slab Formwork MULTIFLEX Girder slab formwork UNIPORTAL / Table Modules Table form PD 8 1 system for 3 applications Platform Systems Folding Platform FB 180 Universal working and protective scaffold to DIN 4420 ASG 160 The light platform system for building trades Alu-Slab Formwork PERI SKYDECK Alu slab formwork system

You might also like