Professional Documents
Culture Documents
GEOgRAphiCAL SiTUATiON
The Vorarlberger Illwerke AG (Illwerke) operate in total nine Alpine Hydroelectric Power Plants in the most western part of Austria in Vorarlberg (Montafon and Walgau) . The rst power plant, the Vermunt plant started operation in 1930. In the course of dierent extension programs a compound group of Hydroelectric Power Plants and water resources was implemented until 1984. The liberalization of the electricity market and the rapid development of wind energy with wind-forces that cannot be inuenced have led to an increasing demand for peak and control energy as well as for the possibility of a pump storage in large Alpine reservoirs. Illwerke responded to this demand by developing and constructing the highly ecient pump storage Power Plant Kops II.
The Hydropower Plant Kops II is located parallel to the existing Kops Plant I in the Inner Montafon. The complete power plant in the municipal territory of Gaschurn extends from Kops (1,800 m) over Tafamunt (1,700 m) into the valley to Rifa (1,000 m) between the tourist centres Gaschurn and Partenen. All parts of the plant, including the power house, are situated inside the mountain. Only the 220 kV switching station executed with space saving indoor SF6 technology and access roads and gates to the facilities situated inside the mountain are visible.
March 20th, 2003 April 2003 September 2003 March 2004 July 2004 August 2004 September 2004 End of 2007/ beginning 2008 June 2008 Construction time Sum invested
Policy decision to build the Hydropower Plant Kops II Initiation of preliminary examination procedure for environmental impact assessment (EIA) Application for implementation of an environmental impact assessment (EIA) Verbal permission request procedure pursuant to the law on the environmental impact assessment Denitive decision by the supervisory board of Illwerke to proceed with construction Building permit becomes legally valid Start of construction Planned commissioning of the rst set of machines Commissioning of machines 2 and 3 3.5 years approx. EUR 360 million
In March 2003 the supervisory boards of the Illwerke made the policy decision to build Hydropower Plant Kops II into the existing Upper Ill Lner Reservoir scheme ( = power plants in the Montafon) for the generation of highly ecient peak and control energy. Hydropower Plant Kops II increases the capacity of Illwerke in pumping mode by 85% and in turbine operation by 36%. No additional water resources are needed, as Kops II uses the existing Kops Reservoir as upper reservoir and the existing balancing reservoir Rifa as lower reservoir.
ThE CONCEpT
Hydropower Plant Kops II has been designed as pump storage plant. The power plant uses the head between Kops Reservoir (1,800m) and Partenen-Rifa (1,000 m). In turbine mode the water from Kops Reservoir will ow through a pressure tunnel and a pressure shaft to the power house. The hydroelectric generating sets, consisting of turbines, pumps and generators are situated in an underground power house, the transformers are situated in the adjacent transformer cavern. The water used in Hydropower Plant Kops II then ows through a tailrace tunnel into the balancing reservoir Rifa, that serves as tailrace balancing reservoir and as pump water reservoir. The 220kV switching station for Hydropower Plant Kops II is designed in space saving indoor SF6 technology and is located near the existing switching yard of Rifa Plant. The energy is transported between Hydropower Plant Kops II and the switch yard Brs using the existing 220 kV line from Partenen to Brs.
Versalspitze 2,000 m Kops Reservoir 1,809 m
ber
Gaschurn
valve
cham
surge tank
Partenen
Characteristic data
n n n n
Installed capacity in turbine mode Installed capacity in pump mode Capacity of generators Height of fall
ThE TEChNOLOgY
The Hydropower Plant Kops II is a pump storage plant that can be used to regulate the grid in turbine mode as well as in pump mode and is located parallel to Hydropower Plant Kops I.
surge tank
pressure tunnel
System components
n Intake / outlet structures in Kops Reservoir n n n n n n
Valve chamber and bypass shaft Pressure tunnel (Versal tunnel II) Two chamber surge tank with inclined shaft and 3 throttles Pressure shaft High-head manifold piping Underground power house - machine cavern - 3 hydroelectric generating sets with Pelton turbine, motor generator, clutch and storage pump - transformer cavern Tailwater system - 3 compressed air surge chambers - tailrace to Rifa balancing reservoir - two chamber trailrace surge tank - low pressure manifold pipes Outlet / intake structures in Rifa balancing reservoir 220-kV-SF6 switching station
underground power house tailrace tunnel gallery Tafamunt
pressure shaft
n n
ThE TEChNOLOgY
Headrace
Pressure tunnel Versal tunnel II
The pressure tunnel runs parallel to the existing pressure tunnel of Hydropower Plant Kops I and was excavated mechanically by a doubleshield tunnel boring machine. The favourable geological and hydrogeological conditions permitted a lining of the 5.5 km long pressure tunnel with precast concrete elements. This type of lining is a construction method perfectly adapted to the high-alpine location of the construction site.
n Length n n
race system, certain amounts of water can get out towards the surge tank. The surge tank is sort of an equalizing reservoir reducing the pressure uctuations and/or limiting the high dynamic pressures in the entire headwater. The surge tank Aussertafamunt is located in the transition area from the pressure tunnel to the pressure shaft and consists of a lower chamber with two connections to the pressure tunnel, an inclined shaft with a throttle in its lower end, as well as of an upper chamber and a ventilation shaft leading into the access tunnel Tafamunt.
total length 250 m internal diameter 7.00 m length 185 m internal diameter 5.10 m longitudinal gradient 49 length 235 m internal diameter 6.20 m
Upper chamber
surge tank
pressure tunnel
ThE TEChNOLOgY
inclined shaft
pressure tunnel
length 1,135 m internal diameter 3.80 m longitudinal gradient 80.0 % (38.7) length 60 m internal diameter 3.80 m
Distribution pipes tapering to 2,20 m with connecting shut-o valves internal diameter 1.50 m
distribution pipes access tunnel underground power house tailrace tunnel outlet structure access portal
ThE TEChNOLOgY
turbine
Transformer cavern
Volume of rock excavated approx. 9,800 cubic meters, length approx. 35 m, width approx. 16 m, height approx. 19 m. Three transformers connected via isolated-phase bus ducts with the generators.
compressed air chamber tailrace tunnel
pump intake
Machine cavern
Volume of rock excavated: approx. 113,000 cubic meters. Width max. approx. 30.5 m, height max. approx. 60.5 m, length approx. 88 m. The total height of the vertically installed hydroelectric generating sets consisting of a three-stage storage pump, an hydraulic clutch, a motor generator and a six-nozzled Pelton turbine is approx. 38 m. Characteristic data
n n n n
220-kV energy transport via cables to the indoor 220-kV-SF6 switching station next to the switching yard of Rifa Plant. The energy is transported between Hydropower Plant Kops II and the transformer station Brs using the existing 220 kV line from Partenen to Brs.
tailrace surge tank machine cavern transformer cavern pressure shaft shaft bottom cavern distribution pipes valve tunnel
Number of hydroelectric generating sets 3 Nominal speed Maximum capacity in turbine operation Pump driving power 500 rev/min 3 x 150 MW 3 x 150 MW
access tunnel
tailrace tunnel
cable subway
reservoir outlet
ThE TEChNOLOgY
Tailrace
The tailrace (turbine discharge and pump feed) crosses underground the road L188, the river Ill and the embankment of the balancing reservoir Rifa. The reservoir outlet and intake works are located in the balancing reservoir Rifa. The water of Kops Reservoir used for the turbine operation is temporarily stored in the Rifa Reservoir and is returned in pump mode from here into Kops Reservoir. The tailrace system from the underground power house to the outlet structure in the balancing reservoir Rifa comprises the following components:
Tailrace tunnel
Total length: 267 m Maximum internal diameter in the area of the rock: 7 m; internal diameter in the area of the steel lined track of alluvions: 5.8 m. Common turbine discharge and pump feed works with roller gate in the balancing reservoir Rifa.
reservoir outlet
culvert
In order to satisfy the market demands, Hydropower Plant Kops II has a full range of control ability of +/- 100 % in turbine operation and in pump mode. Power control should as much as possible be provided in a range between 0 % and 100 % in turbine operation as well as in pump mode in order to cover the deviation of the real and the predicted power demand in the grid. Pelton turbines are used because they guarantee a highest possible eciency for minor power demands and/or power surplus in the grid and an optimal control ability. To this eect the pump and the turbine must be separated, a clutch must be provided and the elements have to be arranged on a machine axis together with the motor generator.
Hydraulischer Kurzschluss
z.B.:
Kops Reservoir
G/M generator/motor runs with 100 MW T turbine (Pelton with Hydropower Plant Kops II) supplies additional 50 MW P pump receives 150 MW Q water ow
Pgrid = 100 MW surplus Q with 100 MW 100 MW Q with 50 MW T 50 MW Q with 150 MW P 150 MW Q with 150 MW G/M Q with 50 MW Q with 100 MW balancing reservoir Rifa
Example of an hydraulic short-circuit with surplus of power in the grid 100 MW, pump capacity 150 MW
G/M
GEOLOgY
ENViRONMENT
Never before, such high ecological demands had to be satised in Vorarlberg for a construction project, as with Hydropower Plant Kops II. It was the rst time an Environmental Impact Assessment (EIA) was initiated and could be closed positively. Such a procedure guarantees that during the construction and the operation of Hydropower Plant Kops II man or nature are spared to the highest possible degree. More than 500 regulations assure that the construction will be made in an environmentally friendly way and that also the later operation will be technically safe and ecological. In general, the geological conditions were favourable for the construction of the power plant, in several sections however, dicult geological conditions were encountered, as anticipated. The facilities of Hydropower Plant Kops II are located completely in the rock series consisting of Silvretta crystalline. These series consist for the most part in solid and hard rock as e.g. amphibolite, hornblende gneiss and other types of gneiss. Other less solid mica-schists have also been encountered. The ndings made during the construction of Hydropower Plant Kops I during the sixties and during the construction of the exploration tunnel excavated in the year 2003 in the area of the actual transformer and machine cavern, as well as further exploration measures were essential. For the operation of Hydropower Plant Kops II no additional natural available water supply will be needed. The plant uses the Kops Reservoir as headwater reservoir, the existing balancing reservoir Rifa in Partenen is used as tailrace reservoir and the energy is transported using an existing high-voltage line. Concerning the operation of the power plant, Illwerke voluntarily adopted an environmental management system pursuant to ISO 14000.
discharge shaft with reservoir outlet works Kops Reservoir pressure tunnel l = 5.5 km valve chamber
surge tank
intake structure
VORARLBERgER ILLWERkE AG
Peak and control energy covers the peak demand periods that occur briey but often during any given day in order to maintain the balance between consumption and generation of electricity. During low demand periods in the grid, especially in case of a high supply of wind energy, Illwerkes power plants take energy of the grid to operate the pumps, a procedure known as pump storage. The water pumped into high-altitude reservoirs is then available for periods of high demand for peak and control energy. This practice of pump storage has proven to be highly eective. Illwerke provides its electricity customers with 1,248 MW turbine output and a pump capacity of 533 MW. Following the commissioning of Hydropower Plant Kops II, this makes up 1,700 MW of turbine output and 980 MW of pump capacity.
Vorarlberger Illwerke AG was founded in 1924 as a limited liability company (GmbH) and has been a joint stock company (AG) located in Bregenz since 1927. The primary shareholder of Illwerke is the Province of Vorarlberg, holding 95.5% of the shares. 4.5 % of the shares are in the possession of WEG-Wertpapiererwerbsgesellschaft m.b.H., Bregenz. With nine power plants, four reservoirs and several pump storage reservoirs, the Illwerke hydroelectric scheme is the basis for generating electricity from alpine water resources in the Montafon and the Walgau. Within the European grid that connects all power plants and consumers concerned, Illwerke supplies peak energy to its consumers and contractual partners: Energie Baden-Wrttemberg AG (EnBW), the Province of Vorarlberg/Vorarlberger Kraftwerke AG (VKW) and the Province of Tyrol/TIWAG-Tiroler Wasserkraft AG, as well as the opportunity to take advantage of pump storage and additional energy services.
Piz Buin 3.312 m
Brand glaciers
Ischgl
Kops Reservoir Galtr Pumping Station Kleinvermunt Hydropower Plant Kops I Hydropower Plant Kops II
Hydropower Plant Lnersee Hydropower Plant Rodund II Hydropower Plant Walgau Bludenz Walgau
Paznaun
group
CONTACT
Vorarlbergs history of electricity industry began more than a century ago. Due to the abounding watercourses and the good geographical conditions, Vorarlberg presented the ideal prerequisites for an economically important development of hydropower. Founded as early as in 1901 as a private company, the Vorarlberger Kraftwerke AG (VKW) became in 1929 a province-owned company that covered the public demand of electricity. The Vorarlberger Illwerke AG (Illwerke) was founded in 1924 in view of the production of peak and control energy for its partners in the European grid.
Zurich
Munich
A8
Lindau
FRG
Bregenz
Altenrhein
A1/A13
Dornbirn
CH
A14
Feldkirch
Bludenz
FL
S16
Innsbruck Vienna
Schruns
L188
Partenen
In the course of the liberalization of the European electricity market the companies merged on January 1st, 2001 as Illwerke/VKW group and have now a common management. The distribution of duties and responsibilities was reorganized within the Illwerke/VKW group. The core business of Illwerke concentrates on the production of energy and the operation of VKW power plants. The VKW concentrates on the distribution of energy in Vorarlberg and in the neighbouring Western Allgu and acts as electricity distributor. The VKW-Netz AG concentrates on the transportation of electricity and the operation of a distributing grid thus assuring a secure electricity supply in Vorarlberg.
group
Vorarlberger Illwerke Aktiengesellschaft Weidachstrae 6, 6900 Bregenz, Austria T +43/5574/601-0, F +43/5574/601-78526 www.illwerke.at www.kopswerk2.at info-kopswerk2@illwerke.at