Professional Documents
Culture Documents
By A JAD
While designing a piping system, many inputs are required from other disciplines and also inputs are given to other disciplines. There are also few outputs generated by piping which are required for procurement, erection and fabrication of the piping system.
2. Process licensor:
Project design basis, plot plan, PFDs(Process Flow Diagram), P&IDs (Process and Instrumentation Diagram), PDS (Process Data Sheet), process description, equipment list, line list, site data, licensor, capacity etc.
3. Process information:
Process data sheet showing overall dimensions, supporting arrangement, all nozzles location, size, rating, etc. for equipment.
5. Instrument drawing:
Tray width requirement on pipe rack/sleepers. Instrumentation hook-up drawing. Instruments drawings for control valves, safety valves, inline instruments etc.
6. Electrical layout:
Tray width requirement on pipe rack/pipe sleepers and cable trenches width in units/off-site. Electrical cable tray layout.