You are on page 1of 31

CUR - Recommendation 102

Recommendation 102

Inspection and assessment of concrete structures in which the presence of ASR is suspected or has been established
An alkali-silica reaction (ASR) is a reaction between the alkalis present in the pore water of concrete and certain components of the aggregate that contain reactive silica. The reaction leads to the formation of a gel, which expands when it absorbs water. As a result of this expansion cracks are formed and the mechanical properties of the concrete may change. This may have an adverse effect on the behaviour and the load-bearing capacity of the structure. ASR is characterised by a crazed pattern of cracks. Depending on the design of the structure and stresses in the material, however, more or less straight cracks may also occur. It is important to recognise the presence of ASR in view of its potential consequences for the load-bearing capacity and the structural safety of the structure. This Recommendation provides a procedure on the basis of which it can be established whether cracks that are present are actually caused by an alkali-silica reaction in the concrete. To be able to estimate the effect on structural safety a procedure is described in this Recommendation for gathering all the material characteristics required of the structures in question, including strength properties. In this CUR Recommendation guidelines are provided for the structural assessment of a number of specific structures on the basis of these material properties. Finally, this Recommendation also discusses the maintenance measures that are to be taken when ASR is present. At the time this Recommendation was published CUR Research Committee C 106, Structural aspects of alkali-silica reaction in concrete structures, had the following members: ir. J.D. Bakker (chair), ir. C.A. van der Steen (secretary and reporter), ir. G. Chr. Bouquet, dr. M.A.T.M. Broekmans (corresponding member), ing. J. Dudar, ir. J. Hartogsveld*, ing. N. Kaptijn*, ir. E.J.C. Rademaker, ir. R. van Selst, ir. A.J.M. Siemes*, dr. ir. C. van der Veen*, drs. E. Vega (coordinator) en W. Buist (mentor). The structural section, chapter 8, of this Recommendation was prepared by a designers working group, consisting of the committee members above indicated by an *, together with ir. G.G.A. Dieteren, ir. U. Frster, ir. F.B.J. Gijsbers, dr. ir. E. Schlangen and ir. J.A. den Uijl. Furthermore, an important contribution to establishing the calculation methods in this Recommendation was made by ir. A.J. Wubs. CUR Recommendation 102 was approved by the General Regulations Committee Concrete and is supported by NEN/CUR Committee 353 039 / RC 12 Concrete and NEN/CUR Committee 353 001 09 / RC 20 TGB concrete structures. This Recommendation was found to be consistent with NEN 6702, NEN 6720, NEN 6723, NEN-EN 206-1 and NEN 8005.

|1

CUR - Recommendation 102

content
1 2 3 4 4.1 4.2 4.3 5 5.1 5.2 5.2.1 5.2.2 5.3 5.3.1 5.3.2 5.4 5.4.1 5.4.2 5.4.3 5.5 5.5.1 5.5.2 6 6.1 6.2 6.3 6.4 7 7.1 7.2 7.3 7.3.1 7.3.2 7.4 7.4.1 7.4.2 7.4.3 7.5 7.5.1 7.5.2 7.6 Subject Area of application Terms and definitions Classification Inspection and study classes Reporting Specification of study and reporting, data Nature and scale of the study General information Exploratory inspection Contents of inspection Performance method Technical study Contents of study Performance method Targeted study Contents of study Performance method Establishing the reinforcement configuration Structural study General information Contents of study Sample-taking General information Marking and drilling Treatment of drilled cores Repairing drilled holes Measuring and assessment methods Crack pattern, crazing Cumulative crack width Assessment of data and structure Assessment of data Assessment of structure Polarisation and fluorescence microscopy (PFM) Procedure Aspects to be established Microscope requirements Uniaxial tensile strength Determination of the uniaxial tensile strength Verification of uniaxial tensile strength measured Compression strength 4 4 4 5 5 8 8 9 9 9 9 10 10 10 10 11 11 11 12 12 12 13 13 13 14 14 14 14 14 14 16 16 17 17 17 17 18 18 18 18 19

2|

CUR - Recommendation 102

8 8.1 8.2 8.3 8.3.1 8.3.2 8.3.3 8.3.4 8.3.5 8.4 9 9.1 9.2 9.3 9.4 9.4.1 9.4.2

Structural analysis Analysis principles Deflection verification Verification of shear forces Principles Design value of shear stress according to NEN 6720, based on average tensile strength Design value of shear stress based on experimental research Upper limit of the design value of shear stress Special load combinations Punch and torsion Reporting Class A Class B Class C Control strategy and control measures Data required for control measures Specification of control measures

19 19 19 19 19 20 20 21 22 22 22 22 22 22 23 23 23 25 26 28

Titles of standards and CUR Recommendations stated Appendix A Preparation of fluorescent epoxy Appendix B Preparation Of Thin Sections

|3

CUR - Recommendation 102

Subject

This CUR Recommendation provides procedures and guidelines for: establishing whether an alkali-silica reaction (ASR) is present in concrete; establishing the relevant material properties; assessing a concrete structure for ASR, whereby methods are given for the structural assessment of a number of specific structures. In addition to this, possible control measures are discussed. These depend on the extent of the damage by ASR.
2 Area of application

This CUR Recommendation applies to concrete structures in the Netherlands. The structural assessment methods in chapter 8 of this Recommendation are only valid for certain structures with structurally deleterious ASR. More specifically, the calculation methods determined from experimental research (8.3.3) may only be used if: it concerns plate-shaped structures (plates, walls) with a thickness of at least 400 mm; a bidirectional reinforcement (in one plane) is used in these plates; the damage by ASR has resulted in delamination parallel to the plane of the plate; this has resulted in anisotropy of the uniaxial tensile strength. Explanation For newly to be built concrete structures, please refer to CUR Recommendation 89 Measures to prevent damage to concrete by alkali-silica reaction (ASR). The limitation to concrete structures in the Netherlands is necessary, as the calculation methods were derived from Dutch calculation regulations or as these calculation regulations are used for the assessment. The limited applicability of calculation methods determined by experimental research stems from the fact that only the structure described was studied.
3 3.1 Terms and definitions Alkali-silica reaction (ASR): the reaction of certain components of aggregate containing

reactive silica with the alkalis that are present in the pore water of concrete, which leads to the formation of gel-like reaction products. Explanation These reaction products may absorb pore water, which makes them swell up and exert pressure within the concrete. As a result of this, some of the mechanical properties will initially deteriorate, including the tensile strength, and the concrete may eventually start to crack. The deterioration of mechanical properties can be deleterious to the structure.
3.2 Structurally deleterious ASR: the situation whereby the occurrence of ASR results in

deterioration of the mechanical properties of the concrete to such an extent that this affects structural safety and usability.
3.3 Exploratory inspection: a mainly visual assessment of the structure with the aim to

establish whether any (deleterious) ASR may be present.


3.4 Technical study: a study performed on the structure and in a laboratory to establish

whether ASR is actually present, including exploratory tests to determine whether material properties, such as compression and tensile strength, have been adversely affected.

4|

CUR - Recommendation 102

3.5

Targeted study: a study with the aim to determine the strength properties of the concrete

affected by ASR more extensively.


3.6 Structural study: a study into the structural consequences for the concrete affected by

ASR.
3.7 PFM (polarisation and fluorescence microscopy): a microscopic research technique that

is applied on very thin, impregnated preparations of concrete in order to obtain an image of the microstructure of the cement paste, the water-cement ratio, the type of cement, the lithological composition of the aggregate and any converted substances in it, the presence of cracks as well as the spatial distribution and the homogeneity of these properties.
3.8 Reactive silica: the amorphous or low-crystalline silica present in some aggregates that

reacts faster with alkalis on the basis of its less well-ordered crystal structure and/or its greater specific surface area compared to coarse crystalline quartz. Explanation Well-known reactive components are opal, chalcedony, moganite, cristobalite, tridymite, cryptocrystalline quartz, (porous) flintstone (silex / chert / flint), impure sandstone (grey wacke, siltstone), siliceous limestone and certain types of volcanic rock due to the glass that is present in it.
3.9 Relative cumulative crack width ASR: an indicative measure for the extent to which

cracks have formed that is determined by adding all the widths of the cracks that intersect with a measuring line placed along a cracked area of the structure and then dividing it by the length of the measuring line.
3.10 Structural risk: a measure for the seriousness of the consequences relating to the possible presence of ASR.

Explanation The structural risk is determined by analysing the reinforcement configuration and the consequences of the damage observed for aspects such as safety and functioning.
3.11 Control strategy: the strategic choice of the period in which and level at which a structure will be maintained by performing control measures. Control measure: the package of measures that are to be taken immediately and in the

3.12

future to keep a structure in a prearranged condition or to achieve a predetermined situation. Explanation Examples of control measures are reinforcing the structure or measures to delay or prevent the progress of the damage mechanism, such as limitation of the moisture load.
4 4.1 Classification Inspection and study classes

The class of inspection and/or nature and scale of the study to be performed must be agreed upon in advance by reporting a class as stated below. It is possible to agree on several different classes at the same time (see table 1).

|5

CUR - Recommendation 102

Explanation The tests described in this Recommendation serve as a supplement to the inspection and test methods in CUR Recommendation 72, Inspection and testing of concrete structures, and describe tests that are related to ASR in more detail. In certain cases it is recommended to ascertain whether it is desirable to perform an inspection or study according to CUR Recommendation 72 at the same time, supplementary to a study according to this Recommendation. Class I Exploratory inspection The purpose of this inspection is to find out whether ASR is present in the structure or whether the cracks that were observed are more likely to have a different cause. Class II Technical study The purpose of this study is to confirm that ASR is indeed present, as well as to obtain an initial indication of the seriousness of the damage. Among other things, this is done by establishing whether a relatively low uniaxial tensile strength is present. Class III Targeted study The purpose of this study is to gather more information in a targeted manner, to be able to determine reliable material properties on the basis of this, among other things, for the structural assessment calculation and the specification of control measures. Class IV Structural study The purpose of this study is to obtain an insight into the structural safety of the structure. The structural study is divided into: Class IVA Manual inspection of transverse forces in representative cross-sections, either with or without basic calculation software. Class IVB Numerical inspection of transverse forces in representative cross-sections. Class IVC Structural assessment of the entire structure. A representative cross-section is the cross-section in which the modified mechanical properties of the concrete have the greatest effect on the load-bearing capacity and the structural safety of the entire structure. Explanation To assess the structural safety calculation models are used that are only valid for certain structures, see 8. The determination of representative cross-sections requires a good structural understanding and can therefore best be left to an experienced structural engineer. Figure 1 shows the relationship between the various components. The various studies are specified in more detail in 5.2 to 5.5. The diagram in Figure 1 will only have to be followed if the structural risk is medium or high, see 7.3.1.

6|

CUR - Recommendation 102

Explanation of flow chart In the flow chart used the various study classes are described in a mutual context. Generally speaking, an increasing amount of information is obtained from top to bottom in the flow chart, whereby the study effort also increases. Please note that a step-by-step approach was chosen, whereby different levels of study are performed in succession. In some situations the additional costs and nuisance (traffic measures) may be such, that it will be better to decide to take all the samples in advance, in anticipation of a possible targeted study in the laboratory. With regard to this, it is important to have a clear image of the desired results of the study in advance. The studies mentioned will only be useful in practice if the structural risk is medium or high.

Class I exploratory inspection

Report

ASR possible Y Class II technical study

Possibly further study into cause of cracks

N ASR

Y Report

Indication of low tensile strength

Y Class III targeted study

Low tensile strength

Report

Y Class IV structural study

Safety now guaranteed

Report with safety measures

Report

Figure 1

Flow chart for inspection and studies

|7

CUR - Recommendation 102

4.2

Reporting

Based on their contents, reports are divided into: Class A Class B Class C Reporting of data. Reporting of data and measures to be taken. Reporting of data and control measures to be taken.

For the contents of the reports, please refer to chapter 9. Explanation Please note that a link exists between the type of study and the possible reports. For example, an inspection according to class 1 will provide insufficient data to prepare a report according to class C. This Recommendation is aimed at identifying ASR and the consequences of it. If ASR cannot be identified as a cause or the only cause of the cracks observed, it is advisable to have these cracks and the consequences of them assessed further by an expert. It may also be useful for maintenance purposes to obtain information about other defects and shortcomings in the structure. For the recording of a study different to one concerning ASR, please refer to the various inspection classes that are stated in CUR Recommendation 72.
4.3 Specification of study and reporting, data

In order to determine which study is required and which type of report is to be prepared, at least the following must be agreed: a. the type of inspection or study, based on the classification in 4.1; for an exploratory inspection it must also be agreed whether the pattern of cracks is to be recorded in accordance with 7.1; for a technical study it must also be agreed whether impregnated cores are to be assessed; for a targeted study it must also be agreed whether the reinforcement configuration is to be determined; b. the method and contents of the required report, based on the classification in 4.2. Prior to an inspection or study of a concrete structure at least the following data must be available: the definition of the problem relating to the inspection or the study; the location of the structure to be studied; the nature and type of the structure; the shape and size of the structure; the age of the structure and, where available, the design life; the component or components of the structure to be studied; whether any previous studies have been performed on these components or the structure; the accessibility of the structure as a whole and of the most important structural components at which the study is aimed; the possibilities of closing-off the building site as well as the need to take traffic measures. If a structural study is prescribed the following must also be agreed: whether the (original) design calculations, verification calculations and reinforcement drawings are available; the number of representative cross-sections that must be tested (see 5.5). If any control measures are to be specified, the client should provide information about the control strategy that applies to the concrete structure in question.

8|

CUR - Recommendation 102

Explanation The reliability of statements relating to the damage, the consequences and the measures to be taken is determined for a large part by the study. For example, an exploratory inspection provides an insufficient basis for specifying control measures. Table 1 shows which studies are considered to be required at the least to be able to make a particular statement. If any previous studies were performed on the structure, either with regard to ASR or other types of damage, it will be useful to provide this information as well. Depending on the nature and scale of the previous study it may be decided to limit the study described in this Recommendation.
5 5.1 Nature and scale of the study General information

In this chapter the inspection and studies stated in 4.1, which may either be performed separately or together, are described in more detail. When prescribing a particular study or a combination of studies the intended objective must be clear, for example, merely determining whether ASR is present or, for example, answering the question of whether the structural safety is still guaranteed. Table 1 indicates which study is required to obtain a particular result. Table 1 Overview of relevant questions and studies required
Scale of study at least Question Exploratory inspection See 5.2 Could ASR have occurred? To be performed See 5.3 See 5.4 See 5.5 Technical study Targeted study Structural study

Could the mechanical properties have been affected in a negative manner? Has ASR currently led to a structurally unsafe situation?

To be performed

To be performed

To be performed

To be performed

To be performed

5.2

Exploratory inspection Contents of inspection

5.2.1

For each component to be studied, an exploratory inspection must at least consist of the following: Establishing whether a crazed pattern of cracks is present, which is the case if the cracks are more or less perpendicular to each other. The crazing may exhibit a preferred direction, for example, due to the forces in the structure. Establishing whether the crazing is uniform over the entire surface or whether there are areas with limited crazing and areas with a large amount of crazing. Identifying other cracks and crack patterns, whereby at least the following is recorded: the shape of the cracks, the crack distance, the crack width and an estimate of the cumulative crack width. If this has been agreed, the crack pattern should also be recorded in accordance with 7.1. The following must also be recorded for the structure that contains the component to be assessed: Any visually identifiable expansion and deformation of the structure, for example, the structure being out of centre at joint interfaces, lopsidedness of bearings as well as unusual curvature, lopsidedness or shifting of faces.

|9

CUR - Recommendation 102

Any environmental factors relating to the moisture load, for example, for car decks the possibility of loads exerted as a result of de-icing salts and excessive forms of moisture load as a result of the design and/or inadequate drainage of the structure. Any secretion of alkali-silica gel present or the spalling of pieces of concrete for reasons other than reinforcement corrosion. The presence of a coating or signs of concrete repairs performed previously. In particular, the possibility must be taken into account here that a coating may hide previous damage by ASR that was repaired. Explanation To recognise damage patterns that may be related to ASR, please refer to the ASR picture-book, a publication of the Public Works Service of the Directorate-General for Public Works and Water Management, which can be accessed via www.bouwdienst.nl. 5.2.2
Performance method

Where agreed, the pattern of cracks must be recorded in accordance with 7.1 in at least three locations where the most severe form of crazing is visible. Explanation It may be useful to draw and record the pattern of cracks in order to monitor possible developments.
5.3 Technical study Contents of study

5.3.1

The technical study must at least consist of: Removing drilling cores for polarisation and fluorescence microscopy (PFM test) and to determine the mechanical properties. Recording the relative cumulative crack width according to 7.2 in at least 3 locations with a crazed pattern of cracks. An analysis of the structure on the basis of information provided, see 7.3.1, including any exploratory inspections performed. A verification of the tensile strength of the cores measured against the designed tensile strength and the low tensile strength criterion according to 7.5.2. Explanation Depending on the size of the object, it may be decided to have the pattern of cracks recorded in a greater or smaller number of locations. For possible testing of the uniaxial tensile strength perpendicular to the span, in other words, in the plane of the element, it is recommended that at least three cores be drilled. To establish the necessity of a test of the uniaxial tensile strength in the plane of the element, please refer to 8.3.1. 5.3.2
Performance method

For the technical study a sufficient number of cores with the correct length must be drilled out of the structure or structural components in order to perform the test of the mechanical properties and for the presence of ASR. The diameter of the drilling cores must be around 75 mm. The length of the drilling cores is derived from the property that is to be determined.

10 |

CUR - Recommendation 102

The number of cores required and the length of the cores is: at least 6 to determine the uniaxial tensile strength according to 7.5, their length must be equal to twice the diameter of the core; at least 3 to determine the compression strength according to 7.6, their length must at least be equal to the diameter of the core. The drilling locations of the cores must be spread out over the bad areas, but not on a crack and preferably in representative cross-sections in terms of transverse force. In addition to the cores stated, it may be necessary to collect additional sample material for a PFM test. These cores must have a length of at least 100 mm and should preferably be drilled on a crack. The core must also include the outside surface. All drilled cores must be assessed visually for signs of ASR. At least one core containing material suitable for the PFM test according to 7.4 must be selected from the available sample material. Explanation Additional cores are required for PFM testing, as a sufficient number of cores must be available to test the mechanical properties. It cannot be excluded that additional material is obtained when drilling cores for mechanical testing before the number of cores with the correct length stated is collected. This material could be used for PFM testing. A drilling core can be used for more than one purpose, provided that its length is sufficient. Please note that a core with a greater diameter, for example, 100 mm, and a length of more than 300 mm may provide more information when this core is fully impregnated compared to the minimum dimensions prescribed. This is simply because more material will then be available. By impregnating cores with a fluorescent resin a greater insight is obtained into the cause and the severity of the cracks that are present. The presence of ASR is often shown with PFM, but it is difficult to ascertain whether ASR really is the primary cause of the cracks that are present due to the limited dimensions of the test piece. A better insight is obtained by impregnating entire cores.
5.4 Targeted study Contents of study

5.4.1

The targeted mechanical study must at least consist of drilling cores for mechanical testing. Where agreed, the reinforcement configuration must also be determined. 5.4.2
Performance method

Drilling cores The locations where drilling cores are to be removed for the structural test must be determined by an experienced concrete maintenance expert with a structural understanding, or else in consultation with the structural engineer who is responsible for the more detailed structural study. The cores should basically be removed from areas in which transverse forces are present. Explanation Please note that the areas in which the transverse force is normative are particularly interesting; more so than areas in which it is at its maximum.

| 11

CUR - Recommendation 102

A sufficient number of cores must be drilled from each area designated for the test. The diameter of the drilling cores must be around 75 mm. The number of cores must be: at least 3 to determine the uniaxial tensile strength according to 7.5, their length must at least be equal to twice the diameter of the core; at least 3 to determine the compression strength according to 7.6, their length must at least be equal to the diameter. The cores for the uniaxial tensile strength and compression strength test should preferably be taken from one and the same location to prevent weakening as much as possible, for example, by drilling a core with a length of at least 250 mm and then cutting it into sections. If cores were already drilled before in the cross-section in question as part of a technical study in accordance with 5.3, the compression strength and uniaxial tensile strength of these were determined and if these results are available, the number of cores may be reduced in accordance with the number of tests performed before. 5.4.3
Establishing the reinforcement configuration

It must be ascertained whether the configuration of the (outside) reinforcement matches the reinforcement pattern stated on the drawing. In at least two locations per structural component the diameter of the reinforcement present and the type of reinforcement must be determined by means of destructive testing. If the reinforcement configuration differs this must be discussed with a structural engineer. If drawings are unavailable the scale of the study into the reinforcement configuration must be such that an image is created of the main reinforcement present in the structural component to be assessed that is sufficiently reliable to allow a verification calculation to be performed on the basis of it. Explanation To be able to determine the diameter the surrounding reinforcement will have to be cleared away sufficiently. The type of reinforcement can be derived from the profile of the rebar. In consultation, the number of locations where destructive testing is to be performed may be limited. The purpose of establishing the reinforcement configuration is to obtain an impression of whether the structure was built in accordance with the drawings. If this is not the case, a structurally unsafe situation may also be present even without ASR. It is therefore advisable to assess the consequences of a differing reinforcement configuration first.
5.5 Structural study General information

5.5.1

Regardless of the type of structural study (IVA, IVB or IVC) at least the following aspects must be considered: cracks as a result of ASR; deformation of the structure by ASR; the compressive and tensile strength present with special attention for uniaxial tensile strength; the variation in the uniaxial tensile strength and possibly other mechanical properties for each cross-section observed and between the various individual cross-sections observed.

12 |

CUR - Recommendation 102

5.5.2

Contents of study

A structural class IVA study at least includes: A verification calculation of the transverse force on the agreed cross-sections, performed either manually or with basic computer software. Here the design calculation with regard to the distribution of forces in the structure may be used if it is available and usable. A structural class IVB study at least includes: A numerical calculation of the shear stress present in the agreed cross-sections. In this case the modelling of the structure must be performed using shell elements. A structural class IVC study at least includes: An assessment of the transverse force stated under IVA and IVB. A test of the entire structure, taking into account the material properties that were derived from the test results in accordance with chapter 8. A study according to classes IVA, IVB or IVC does not require a test of the bending moment capacity. Explanation Practical tests on severely damaged structural parts and theoretical studies have shown that the failure moment does not differ from that of a structural part not affected by ASR. The tension in the reinforcement must be allowed to build up gradually. The ends of the bars must be located in the zero points of the moments or the reinforcement must include hooks or bends that can transfer the force in the reinforcement to the concrete. The practical tests were performed on beams cut from sheets with severe horizontal cracks, whereby the uniaxial tensile strength in a direction perpendicular to the sheet plane had dropped to 1/7 of the expected value for the tensile strength based on a splitting test. For the assessment method, please refer to chapter 8.
6 6.1 Sample-taking General information

When removing drilling cores the drilling through structural reinforcement present must be prevented as much as possible. To achieve this at least the outside reinforcement must be located in advance using a concrete cover meter. Prestressed reinforcement must not be drilled through. The load-bearing capacity of the structure must not be affected substantially by the sample-taking. If this is a possibility, the number of drilling cores to be removed must be agreed in advance. For each core the following must be recorded: The location of the core by indicating the position of the centre of the drilling core on a drawing or relative to recognisable parts of the structure with an accuracy of 0.1 m. Visually recognisable aspects of the removed core that may be a sign of ASR and that provide information about the condition of the concrete, for example, the presence of reaction edges around coarse aggregate, stained drying, the presence of gel, cracks, a layered structure, honeycombing, construction joints, etc. Visually recognisable aspects of the concrete surrounding the core, for example, extensive cracking, weathering, moist patches, etc. Whether anything unusual has occurred while drilling, for example, breakage while drilling.

| 13

CUR - Recommendation 102

6.2

Marking and drilling

The location and orientation of the core in the structural component to be tested must be indicated clearly on both the core and in a drawing or sketch of the structure in question. The following must be indicated on the core with a permanent marker: An orientation cross on the top face, whereby the axes match the span direction of the component and the transverse direction of the component, respectively. Both directions must be recognisable by different colours or a pattern of lines. Which side of the core was in the original structural surface. An unambiguous number of the core. The drilling core must be drilled and removed with care. The occurrence of undesirable effects such as cracks, which may adversely affect both the observations during the PFM test and the values measured during the mechanical study, must be prevented. Explanation It is recommended to attach the drilling installation to the structure in a fixed position and prevent wobbling of the core drill.
6.3 Treatment of drilled cores

After removing and assessing the core it must be handled and stored as follows: Clean the core immediately after removing it using a minimum amount of water to remove any attached material. A unique sample number must be applied additionally or again. Wrap the core in an uncoloured, hand-wrung cloth and wrap it in self-adhesive film to prevent drying-out and damage during transport. Place each of the cores in one piece with a diameter-length ratio of 1:2 or more slender and cores that already consist of various fragments in a tightly fitting, durable plastic tube for transport. Short, compact whole cores may be transported after wrapping them in cloth and film. The number of the drilling core must be printed on the wrapping. The cores must be placed in the means of transport or in additional packaging in such a way that they cannot be damaged during the journey to the laboratory.
6.4 Repairing drilled holes

Unless agreed differently, drilled holes must be sealed using a cement-based lowshrinkage mortar in accordance with CUR Recommendation 54, application class RC2, environmental class 3. Holes in asphalt must be sealed with liquid asphalt. Ancillary materials, such as formwork, must be stripped from the mortar after hardening. Drilled holes, etc. must be sealed.
7 7.1 Measuring and assessment methods Crack pattern, crazing

Crazing must be recorded by marking the cracks on a measuring square, preferably with edges of 1 metre in length. The orientation of the measuring square should preferably match the orientation of the pattern of cracks.
7.2 Cumulative crack width

The relative cumulative crack width ASR must be determined as follows: draw two orthogonal lines within the measuring square; measure the crack width wi of all the cracks n that cross the line in question. The crack width must be measured perpendicularly to the crack; measure the angle i between crack i and the edge in question;

14 |

CUR - Recommendation 102

adjust the crack width wi to the direction of the measuring edge according to wi /cos I (Figure 2); for each measuring line add the corrected crack widths and divide them by length l of the relevant measuring line, as a result of which the relative cumulative crack width ASR is obtained:
i =1 cos i

wi

ASR =

in which: ASR is the relative cumulative crack width in mm/m; l is the length of the measuring line when determining ASR, in m; wi is the crack width of crack i in mm; i is the angle between measuring line and crack i when determining ASR.

Figure 2

Principle of measuring the relative cumulative crack width ASR

Figure 3

Detail of measuring the crack width and angular correction

Instead of the previous procedure, it will also be sufficient to estimate the value of ASR for the exploratory inspection. This can be done simply by counting the number of cracks n that cross a measuring line with length l. Following this the average crack width waverage can be estimated or roughly measured. Then the relative cumulative crack width ASR can be calculated as follows:

ASR =

n waverage l

in which: ASR is the relative cumulative crack width in mm/m l is the length of the measuring line when determining ASR, in m n is the number of cracks waverage is the average crack width in mm The cumulative crack width that is determined must be classified in a class on the basis of table 2.

| 15

CUR - Recommendation 102

Table 2

Classification based on relative cumulative crack width


Class none very little little limited significant very significant 0 mm/m < 0.6 mm/m 0.6 mm/m to 1.0 mm/m 1.0 mm/m to 1.5 mm/m 1.5 mm/m to 2.5 mm/m 2.5 mm/m

Relative cumulative crack width

7.3

Assessment of data and structure Assessment of data

7.3.1

The assessment of the available data must at least consist of the following, see table 3: Determining the high-risk components with regard to ASR based on the reinforcement configuration. Determining high-risk components with regard to safety and the functioning of the concrete structure. A classification of the risk of ASR for a structure (structural risk). Aspects that must at least be weighed when determining high-risk components with regard to safety and functioning are: The feeling or perception of safety. The risk of significant consequential damage and/or loss of function as a result of continued expansion, for example, the jamming of moving parts. The (economic) damage, both direct and indirect, as well as the amount of human, emotional and/or social suffering if the structure fails entirely or partially. Table 3
Reinforcement configuration High-quality 3D reinforcement, see Figure 4, for example

Structural risk derived from reinforcement configuration and the consequences for safety and functioning
Consequences for safety and functioning Major Minor Structural risk = low Structural risk = medium

Notes on reinforcement configuration

The concrete is enclosed on all sides. ASR expansion is slightly tensioning the reinforcement. This limits the consequences. Watch out for detachment of the prestress and delamination in the plane of the prestress. Watch out for detachment of lap joints due to the ASR expansion.

3D reinforcement with moderate anchoring

Structural risk = medium

Structural risk = low Structural risk = medium

2D reinforcement with good or moderate anchoring or no reinforcement, Figure 5.

ASR expansion concentrated in 1 direction. In this direction the tensile strength drops. Layers may form in the concrete. The ASR may cause transverse force or shearing problems.

Structural risk = high

Figure 4

Cross-section of beam, column

Figure 5

Cross-section of plate, wall

16 |

CUR - Recommendation 102

7.3.2

Assessment of structure

When assessing the structure watch out for signs that may indicate ASR. Special attention must be paid here to aspects such as: (Restrained) deformation of components. Indications of possible failure. When indications of possible failure are found for critical components of the structure, measures must be taken immediately. Explanation Due to the reinforcement configuration or an irregular moisture load ASR expansion may occur irregularly in the concrete. As a result of this deformations may occur, resulting in tensions that were not taken into account during the design, for example, as a result of eccentricity in columns. Deformation by ASR can be prevented by the surroundings of the components affected by ASR. As a result of this tensions may occur in the affected component and the neighbouring component. These tensions were often not taken into account during the design and in some cases they may result in damage to one component or both components. Indications of possible failure are large cracks and deformation. Other indications are: detachment of lap joints, buckling of components or, if cracks are present, mutual shifting of the crack planes. For the observations mentioned above no generally decisive criterion can be defined. Which measures are to be taken depends on the specific structure.
7.4 Polarisation and fluorescence microscopy (PFM) Procedure

7.4.1

For each PFM study the drilling core with a length of at least 100 mm must be impregnated as a whole in vacuum with a UV-fluorescent epoxy resin prepared in accordance with Appendix A. After the epoxy resin has fully hardened the impregnated core must be cut lengthwise in two pieces and both halves must be petrographically tested for cracks and other relevant signs (of damage) as stated in 7.4.2. An impregnated thin section must be prepared from at least one of the two halves according to the method described in Appendix B. The thickness of the thin section must be (20 1) m and the surface area must be at least 30 mm x 45 mm. 7.4.2
Aspects to be established

The combined data of the assessment of the impregnated core and the thin section must at least establish the following: whether any cracks are present or not, assessed for various scale sizes, as well as the excessive presence of these; whether any potentially reactive components with regard to ASR are present and whether these components actually show signs of a reaction; the bonding of the cement matrix to the aggregate; the number of aggregate grains affected in the overall concrete (level of ASR); a qualitative impression of the amount of gel that is present; the lithological composition of the entire aggregate, regardless of any ASR-sensitive behaviour assumed or observed; the possible type of cement, an indication of the water-cement ratio and the level of hydration; whether, on the basis of observation, ASR could be the primary cause of any cracks observed and whether the ASR observed is more than would be expected for a material without a reactive aggregate.

| 17

CUR - Recommendation 102

7.4.3

Microscope requirements

The assessment of the thin sections must be performed using a stereo microscope with a magnification factor of around 50 to 80. To assess a thin section the petrographic polarisation microscope must have a blue-light fluorescence system. Explanation For the best possible results the following characteristics are recommended for the fluorescence filters: A so-called band-pass excitation filter for blue light with a wavelength range of 450 to 490 nm. An emission filter for green light for a wavelength of 515 nm or more. A frequency splitter (beam splitter) that is centred around a wavelength of 510 nm.
7.5 Uniaxial tensile strength Determination of the uniaxial tensile strength

7.5.1

The uniaxial tensile strength must be determined for cylinders with a diameter of 75 mm and a length of 150 mm. Both ends of the cylinder must be flattened in a planeparallel fashion, perpendicularly to the axis of the core. The required smoothness is 0.1 mm per 100 mm. Steel tie plates with a diameter equal to the diameter of the core must be attached to the ends by glueing them on. The test pieces must be conditioned at 20C and 98% R.H. for at least 2 periods of 24 hours. After sufficient hardening the test pieces must be pulled from the glue in a tensile testing machine tester. Their capacity must not be more than 5x the expected tensile strength. It must be possible to read the load with an accuracy of 1%. The load must be increased gradually at a rate of (0.05 0.01) N/mm2 per second. The tensile strength must be calculated with an accuracy of 0.1 N/mm2 using:

f ct =

F A

in which: fct is the tensile strength in N/mm2 F is the force at failure in N is the surface area of the core in mm2 A If failure occurs directly underneath the pulling head the measurement will be invalid. 7.5.2
Verification of uniaxial tensile strength measured

It must be determined whether the uniaxial tensile strength measured is much lower than the strength assumed during design. This will be the case if the following applies: bm,ref < 0,7 (1,00 + 0,05 c,design) in which: is the average uniaxial tensile strength based on test pieces in accordance fbm,ref with 7.5.1, in N/mm2; cc,design is the average cube compressive strength used during design, in N/mm2; 0.7 is the conversion factor to convert the splitting tensile strength into uniaxial tensile strength.

18 |

CUR - Recommendation 102

Explanation: For the calculations in this Recommendation it was assumed that ASR causes a significant reduction in the uniaxial tensile strength perpendicular to the plane of the element, which was also established in the experiments on which the calculation methods are based (see explanation 5.5.2). It may happen that the uniaxial tensile strength is relatively low, both in the plane of the element and perpendicular to it, even without ASR. In that case the calculation methods included in 8.3.3 may not be used. If a low uniaxial tensile strength is measured compared to the original compressive strength, it is strongly recommended to complete the flow chart in figure 1 to determine the structural safety or to determine which control measures to take.
7.6 Compression strength

The compression strength of cylinders (diameter equal to height) must be determined in accordance with CUR Recommendation 74. The lowest value measured, using at least 6 cylinders, is the value for the characteristic compression strength present.
8 8.1 Structural analysis Analysis principles

a. Regardless of the type of structural study (IVA, IVB or IVC) it must be established whether one of the following may be the case due to the deformation of the structure: changes to the distribution of internal forces; changes to the eccentricity of normal forces; additional external loads to the structure due to kinematical restraint of swelling deformation, for example, a bridge deck that rubs against abutment. If the deflections in the structure are smaller than the allowable deflection according to NEN 6702 or if the eccentricities are smaller than 30% of the eccentricity to be taken into account according to 7.3.4 of NEN 6720 the changes mentioned above will not require further structural consideration. b. The structural analysis must be based on NEN 6702, NEN 6720 or NEN-EN 206-1 with the accompanying NEN 8005 and, for bridges and similar structures, NEN 6723. c. Contrary to the standards and regulations mentioned above, the material strengths derived from the test results using the method described in this chapter must be used.
8.2 Deflection verification

For a structural analysis of the structure in accordance with this Recommendation no verification of bending is required, see the explanation of 5.5.2.
8.3 Verification of shear forces Principles

8.3.1

a. The verification of shear forces and the calculation of the calculation value of the resulting shear stress must be performed in accordance with 8.2.1 and 8.2.2 of NEN 6720:1995, respectively. b. To calculate the design value of shear stress the calculation methods in 8.3.2 must be used. If c has been met the calculation methods in 8.3.3 may also be used, whereby the more favourable result may be used. c. The calculation methods in 8.3.3 may only be used if the conditions stated in it are met. d. For the design value of shear stress 1 no value greater than the upper limit according to 8.3.4 may be taken into account, regardless of the value calculated in 8.3.2 or 8.3.3.

| 19

CUR - Recommendation 102

Explanation The Recommendation contains provisions that differ from NEN 6720 with regard to the calculation principles and the determination of material properties. In NEN 6720 the tensile strength of concrete is considered equal to the splitting tensile strength. For concrete damaged by ASR this will result in values for the tensile strength that are too high. As a result, the uniaxial tensile strength is not derived from the compression strength, but is determined on the basis of cores drilled from the (affected) concrete. 8.3.2 states how the calculation value for the uniaxial tensile strength should be determined. This value can then be entered in the formula in 8.2.3.1 of NEN 6720. This calculation method provides a rather conservative estimate for the transverse force capacity for concrete that is severely affected by ASR. A less conservative value for the design value of shear stress is usually the value that is obtained from a calculation according to 8.3.3 of this Recommendation. This calculation method is based on the results of a study into the transverse force capacity of a number of beams that were cut from fly-overs, which were severely affected by ASR, and it therefore only applies to situations that are comparable to this. 8.3.2
Design value of shear stress according to NEN 6720, based on average tensile strength

The calculation value for the tensile strength fb must be determined from:

f b = 1,1ld

f bm ,ref

m
0,75 n

f bm ,ref = f bm ,e ( n )

in which: ld is the factor for calculating the long-term tensile strength of the concrete = 0.9; is the average uniaxial tensile strength based on test pieces, in N/mm2; bm,ref m is the partial material factor (= 1.35); is the average uniaxial tensile strength, determined in a direction bm;e: perpendicular to the axis of the structural component, of n test pieces, in N/mm2; n is the number of test pieces (at least 3). The calculated value for fb must be entered in formula 8.2.3.1 of NEN 6720. Explanation As the uniaxial tensile strength is taken as the basis for determining the calculation value rather than the splitting tensile strength a correction factor of 1.1 applies. The value of 0.75 is obtained by multiplying 1.64, corresponding with a 95% reliability interval, with a mandatory standard deviation of 0.45 N/mm2. 8.3.3
Design value of shear stress based on experimental research

The following calculation methods, determined from experimental research, may only be applied if: it concerns plate-shaped structures (plates, walls) with a thickness of at least 400 mm; a bidirectional reinforcement (in one plane) is used in these plates; the damage by ASR has resulted in delamination parallel to the plane of the plate; this has resulted in anisotropy of the uniaxial tensile strength.

20 |

CUR - Recommendation 102

If these conditions are met the calculation value for the design value of shear stress 1 may also be calculated from:

1 = 0,6ld 1,m / m
in which: 0.6 is a coefficient used for determining the characteristic lower limit of the design value of shear stress from the average ultimate design value of shear stress 1,m; ld is a factor for calculating the long-term tensile strength of the concrete (= 0.9); 1,m is the average ultimate design value of shear stress, in N/mm2; m is the material factor (= 1.5). The effect of any transverse force reinforcement that may be present must not be taken into account. If the calculated value is more favourable than the value calculated according to 8.3.2, the calculated value may be used, taking into account the maximum value stated in 8.3.4. The average ultimate value of shear stress 1,m must be calculated with the formula:

1, m =

I dS

f ct ,0, ref .( f ct ,90 + 'bmd )

in which: I is the second moment of area of the cross-section that is assumed to be uncracked, in mm4 d is the effective depth, in mm S is the largest value for the first moment of area of the cross-section, in mm3 bmd is the average concrete compressive stress in the cross-section due to the normal force generated by the prestress load and the other loads on the structure (+bmd for pressure; -bmd for tension), in N/mm2; = bm,ref: the average uniaxial tensile strength of n test pieces. The tensile ct,0,ref strength must be determined in a direction perpendicular to the axis of the structural component, in N/mm2;

f ct ,90 =

f ct ,0, ref (1 + 0,05 f 'cc , measured ) , in N/mm2

in which: cc, measured is the measured average cube compressive strength, in N/mm2. Explanation The material factor m of 1.5 is a rather safe value due to model uncertainties (as the formulas are based on a limited number of experiments). In the formula for fct,spl it is tacitly assumed that the value of 1 is a fixed value. This is not actually the case. The value is subject to scatter and the formula too is an approximation of reality, based on the best line that can be fit through a large number of test results. 8.3.4
Upper limit of the design value of shear stress

The maximum value to be used for 1 is

1 = 0,4 f b k k h 3 0

(1 not smaller than 0.4 fb)

| 21

CUR - Recommendation 102

For an explanation of k, kh and 0 and the values to be used for these, please refer to 8.2.3.1 of NEN 6720. The value for fb must be calculated from the characteristic concrete compression strength as stated in 6.1.2 of NEN 6720. However, a value of 0.9 can be used for the long-term strength. 8.3.5
Special load combinations

For special load combinations the factor for the long-term effect (ld = 1.0) is no longer used and m can be reduced to - m = 1.1 for a calculation according to 8.3.2; - m = 1.25 for a calculation according to 8.3.3; - m = 1.0 for the calculation of the upper limit according to 8.3.4.
8.4 Punch and torsion

The values calculated for the design value of shear stress may not be used for the verification of punch and torsion. Explanation The effects of structurally deleterious ASR on punch and torsion are still not sufficiently known.
9 9.1 Reporting Class A

A written report according to class A should at least include: the definition of the problem; a description of the structure in question; a description of the study performed and the measurements, including the test method; an indication of the measuring locations; the results of the visual inspection; a description of the cracks found and the classification of the cumulative crack width (crazed pattern, etc.); the results of any measurements performed and laboratory testing; the results of the calculations performed.
9.2 Class B

A written report according to class B should include the points stated in 9.1, with the addition of: a discussion of the results; the consequences of the findings and results for the component assessed or the structure; any measures or actions to be taken immediately. And more specifically for the various studies: Technical study: a statement whether ASR is present; the classification of the relative cumulative crack width ASR; a statement whether a relatively low uniaxial tensile strength determined in accordance with 7.5.2 is present. Targeted study: a statement whether the results show that a further structural study is required. Structural study: a statement whether the structure can still be considered safe.
9.3 Class C

A report according to class C should at least include the points stated in 9.2, with the addition of possible control measures, see 9.4.

22 |

CUR - Recommendation 102

9.4

Control strategy and control measures Data required for control measures

9.4.1

The client must indicate what the control strategy is for the structure in question. At least the following must be recorded here: the planned period in which the client wishes to continue using the structure; the minimally required state of repair of the structure, for example, whether damage to preservations on concrete is allowed or not, or the presence of concrete damage; the loads and/or traffic class the structure must be able to absorb. For the specification of a control plan at least the following data must be available and must have been verified: the control strategy; the exposure conditions of the various structural components; the current damage. 9.4.2
Specification of control measures

Which control measures are to be taken depends on many factors and they may therefore differ for each structure. As an indication, Table 4 provides an overview of possible control measures depending on the risk classification according to Table 3, the presence of a relatively low uniaxial tensile strength and the level at which cracks are present. Explanation of table 4 V Sealing against moisture; targeted drying of the concrete More damage is usually observed in locations where moisture transport is high compared to locations where a structure is fully submerged. Where possible, one measure may therefore be aimed at limiting moisture transport through (ASR) cracks. Puddles must be prevented from remaining directly on the concrete. Targeted drying of the concrete can be achieved by draining moisture correctly, keeping moisture out of wet faces and allowing drying on dry faces. It is pointless to wrap up a structure completely, as any moisture present will not be able to get out. Here a role is played by the fact that structures with their base in the water easily absorb moisture through the cracked concrete. In this case wrapping-up the concrete will increase the wetness of the structure. M Monitoring Cracks can be monitored in a number of ways: The easiest way is to monitor the development of cracks in the structure. In some cases it will be sufficient to visit the structure periodically. Periodically marking the cracks in the same location (see also 7.1) and copying these cracks to a sheet of Perspex, whereby crack widths are measured and stated. It is advisable to use the same person for this each time, as the width of a crack changes starting at the surface and the edges of cracks are not always clear-cut. This means that different people may interpret things differently. Monitoring the cumulative crack width as described in 7.2. Several measuring techniques (wire recorders) are available for monitoring expansion in concrete. In this case it must be taken into account that expansion is always related to temperature and, to a limited degree, moisture. Moisture can be measured in various ways. Moisture can be measured indirectly based on the relative humidity of the concrete. The electric alternating-current resistance and the electric impedance of the concrete are also moisture indicators.

| 23

CUR - Recommendation 102

These moisture measurements are often related to temperature. It is therefore recommended to determine both parameters at the same time. By measuring the moisture content periodically it can be established whether the structure is drying up. VF Measures for guaranteeing safety and functioning When considering measures for guaranteeing safety and functioning, they must always be tuned to the specific situation. The Recommendation provides a number of guides for this in Table 4. However, these are not exhaustive. Examples of measures to guarantee safety / functioning are limiting the load or applying a local reinforcement or support. If structural damage is about to occur due to jamming of a structure, room for expansion may be created. C Limiting the risk of reinforcement corrosion If a structure damaged by ASR is cracked, reinforcement corrosion may occur by penetration of chlorides and carbonation in these cracks. Depending on the local situation, measures may be taken to seal the concrete from chlorides. One option is to inject cracks. This will be required especially if a changeable wetdry situation is present with enough moisture.

Table 4

Selection table for control measures. The table only provides an initial indication for possible measures; these require further consideration for each situation
Level of crack formation (indicative) < 1 mm/m > 1 mm/m < 1 mm/m > 1 mm/m < 1 mm/m > 1 mm/m < 1 mm/m > 1 mm/m < 1 mm/m > 1 mm/m < 1 mm/m 1 2 6 2 5 5 6 6 4 6 6 4 4 4 4 5 2 2 1 2 4 5 2 4 2 4 4 2 1 2 2 3 Necessary measure(s) V 1 2 4 5 M VF C Optional measures V 2 4 2 4 4 M 4 1 3 1 1 2 1 1 2 1 2 1 2 2 2 1 1 VF C

Risk classification of the structure

Relatively low tensile strength indication *) Yes Yes No No

Low

Medium

Yes Yes No No

High

Yes Yes No

No > 1 mm/m 6 6 3 4 1 2 *) obtained from 7.5.2, as the number of options may be limited based on the results if a structural study has already been performed. Table 4 indicates the importance of the measures using the numbers 1 to 6. The number 6 indicates that the measures are highly recommended, the number 1 indicates that the measures are considered to be the least urgent. If a cell is empty this means that the measure will not be useful. The ratio of the numbers for necessary and optional measures provides an indication as to whether it is better to choose the necessary or optional measure.

24 |

CUR - Recommendation 102

Titles of standards and CUR Recommendations stated

NEN 6702:2001

Technical principles for engineering structures. TGB 1990. Loads and deformations. Concrete regulations. Structural requirements and calculation methods (VBC 1995), incl. amendment A3:2004. Concrete regulations. Bridges. Structural requirements and calculation methods (VBB 1995), incl. amendment A1:2003 Dutch specification of NEN-EN 206-1. Concrete, part 1. Specification, performance, production and conformity. Concrete; part 1. Specification, performance, production and conformity. Concrete repair using manually applied or poured cementbased mortar. Inspection and testing of concrete structures. Studying of concrete structures Studying of compression strength. Measures to prevent damage to concrete by alkali-silica reaction ASR.

NEN 6720:1995

NEN 6723:1995

NEN 8005:2004

NEN-EN 206-1:2001

CUR Recommendation 54

CUR Recommendation 72 CUR Recommendation 74

CUR Recommendation 89

Dutch standards are publications by Stichting Nederlands Normalisatie-instituut, Vlinderweg 6, Postbus 5059, 2600 GB Delft. Orders can be placed at NEN, sales and information hotline, tel. +31 (0)15 2690391.

| 25

CUR - Recommendation 102

Appendix A Preparation of fluorescent epoxy


A1 Introduction

This appendix describes the preparation of fluorescent epoxy for the impregnation of sample material.
A2 Composition

For the preparation of fluorescent epoxy the following substances and materials are required: a fluorescent dye, namely finely ground powder of Hudson Yellow, for example, EpoDye produced by Struers or equivalent; epoxy resin, for example, BY 158 by Ciba Geigy, or equivalent; epoxy hardener, for example, HY 2996 by Ciba Geigy, or equivalent; materials required: fume cupboard, plastic beaker, wooden spatula, bucket/tray of cold water, magnetic stirrer, balances with a variety of weighing ranges. Explanation Hudson Yellow is also known as Brilliant Yellow and by the trade name Epodye; it is a fluorescent dye that lights up as light yellowish green under filtered blue light with a wavelength of around 476 nm when viewed through an LWP 515 emission filter.
A3 Safety

If the instructions and safety regulations of the manufacturer are not strictly observed the handling of epoxy resin may be harmful to a persons health. Epoxy resin must therefore only be handled in a fume cupboard.
A4 A4.1 Procedures Adding dye to the resin

Carefully add one weight percent of dye to a weighed quantity of epoxy resin in a sealable container; also add a stirring magnet. Be careful with the dye, as it may even contaminate the laboratory if a slight draught is present. Seal the container and firmly mix the contents by hand. Place the glass on a magnetic stirrer and leave it to stir for at least two days. Firmly shake the glass again by hand at least once every 24 hours. Remove the stirring magnet with a steel pin after stirring and clean it thoroughly. The hardener and the coloured resin must be stored in the dark in a ventilated location or in a fume cupboard.
A4.2 Mixing the two components

The coloured resin must be mixed with the hardener according to the instructions of the manufacturer. Table A1 provides the current mixing ratio for products by Ciba Geigy. Place a plastic beaker on a balance and add the required amount of coloured resin to it first, then add the correct amount of hardener. Explanation The final amount of coloured resin in the glass may contain a few lumps of undissolved fluorescent dye. To prevent false-positive fluorescence this contaminated amount of resin must not be used for the impregnation of slices.

26 |

CUR - Recommendation 102

Table A1
BY 158 40 80 120 200

Mixing ratio by weight (g) for Ciba Geigy products


Hardener HY 2996 12 24 36 60 52 104 156 260 Coloured resin + hardener

Coloured resin

Start stirring the mixture immediately with a wooden spatula; stir in a circular motion and in figures of eight in both a horizontal and vertical direction. Regularly scrape the sides and bottom of the beaker. Stir vigorously for two whole minutes. In addition to other problems, incomplete mixing may result in insufficient hardening. The mixed epoxy must be used for impregnation within 30 minutes of mixing. The hardening of the epoxy generates heat. Keep any epoxy that has not (yet) been used in plastic beakers that are placed in cold water to prevent the epoxy from boiling. Make sure that no water is added to the epoxy. After hardening (the next day) the excess epoxy can be removed as regular waste.

| 27

CUR - Recommendation 102

Appendix B Preparation of thin sections


B1 Introduction

These instructions describe the procedure for the preparation of thin sections for the PFM test.
B2 Materials required

The following materials are required for the preparation of thin sections: diamond cutter with water cooling and a fully straight cutting blade that does not vibrate; suitable diamond cutting (and lapping) equipment with water cooling; support slide matted on one side to be used as a reference for plane-parallel treatment when impregnating and also as external glued-on reinforcement for fragile samples; sample slide with one matted side; covering slide; UV-hardening glue; UV lamp; polarisation microscope; micrometer (optional); soft brush, or better yet, a clean ultrasonic cleaning bath to clear the sample of cutting and grinding sludge; soft brush, or better yet, an electrostatic brush to clean the slide and the samples before glueing; acetone and/or alcohol; soft paper, for example, cleaning paper for optical lenses; siphon or spray bottle of alcohol (60% V/V).
B3 B3.1 Procedures General information

The slices are prepared as follows: select a location for a slice in the drilling core that was cut in half; cut a piece of at least 30 x 40 x 10 mm3 from the selected section of the impregnated sample; never reduce the amount of surface cut off; this will affect the representative character of the sample; glue the section that was cut off to the support slide using a thin and even layer of Loctite 330 or a similar alternative; cut off the sample parallel to the support slide so that a thickness of 2 to 5 mm is obtained; grind the surface parallel to the support slide with a fine-grained diamond so that a smooth and even surface is formed; glue a sample slide to the final surface; cut off any excess material; grind the surface further with increasingly fine diamond to a thickness of (20 1) m; print the sample number on the finished slice. A number of procedures are described in more detail below.
B3.2 Sample number

It is of essential importance that the unique sample number remains linked to the samples at all times. This is why samples must be placed and processed in a logical

28 |

CUR - Recommendation 102

order. Any residue that is cut off must be kept with the sample during all practical procedures. Reattach the sample code to the treated sample as quickly as possible.
B3.3 Cutting with a diamond wheel

The following applies to cutting with a diamond wheel: 1. Use the thinnest possible diamond wheel. 2. Cut with the diamond wheel using an even pressure that is as low as possible and always use water cooling (for some special applications, for example, for watersoluble substances, cooling with alcohol is recommended). A sharp diamond cutter will cut through the material almost without pressure. 3. If the cutting is too slow the diamond wheel may be worn-out or it may require sharpening or needs to be replaced.. It may be that the wrong type of diamond wheel is mounted to the cutter. 4. Diamond wheels require inspection and maintenance, and they must be replaced where required: Where required, sharpen the wheel by cutting a soft material, for example, a brick. Use a magnifying glass to check whether the outer layer is still covered in diamond grains. Replace the diamond wheel if it is worn-out or if any wobbling, vibration or shocking occurs, as this may damage the sample.
B3.4 Grinding

The grinding procedure largely depends on the equipment used. For good results the following general points must be taken into account: Grinding is to be performed with a gradually decreasing grain size. Grinding with a particular grain size will not be finished until all the scratches from the previous, coarser treatment (grinding or cutting) are removed. Prevent grains or particles from breaking free from the surface, especially along the edges of the sample, by making sure that the sample is fully impregnated. After each grinding round, check the surface under an angled beam of light (floodlight) for completely even grinding results, in other words, a flat surface without ridges. Clear the surface of grinding waste after every treatment and then moisturise the surface with alcohol by spraying, then dry it off with soft paper in a single swipe. The preparation may never dry up during the entire treatment. Water may leave circles of microscopically small crystals, may contribute to artificial carbonation of the cement paste and has a negative effect on the UV-hardening glue. The final surface quality must be sufficient for an unambiguous identification of components and microstructural characteristics.
B3.5 Glueing-on the sample slide and the covering slide

It has been shown that the procedure below results in good and even glueing: Apply a diagonal cross of glue to the impregnated and finished sample surface (to prevent air bubbles from becoming trapped). Place the slide at the centre of the sample. Only for the sample slide: leave the layer of glue to even out by itself for 5 minutes and recentre the slide; hold the sample and the slide together for 10 minutes using a force that is evenly distributed over the surface; expose the sample to UV light for 20 minutes.

| 29

CUR - Recommendation 102

Only for the covering slide: leave the glue to even out by itself for 5 minutes; remove any excess glue from the edges of the covering slide with a pipe cleaner, recentre the slide; place the sample under UV light for around 1 minute; carefully remove any excess glue with a Stanley knife and acetone or alcohol; place the sample under UV light for around 10 minutes; clean all surfaces with acetone or alcohol.
B3.6 Checking the thickness

The thickness of the thin section is checked with the polarisation microscope. The correct thickness of around 20 m is determined based on the white or light-grey birefringent colour of quartz For some automatic grinding equipment the thickness can also be measured with a micrometer, whereby the thickness of the UV-hardening glue must be taken into account.
B4 Storing impregnated fluorescent thin sections

The fluorescent power of the thin sections is reduced noticeably if they are exposed to strong light for a prolonged period of time. This is why thin sections must be stored in the dark.

30 |

CUR - Recommendation 102

It should be pointed out that this CUR Recommendation reflects the state of the art at the moment of publication. Any suggestions for experiences with the use of this Recommendation will be gratefully received by CURNET. CUR Recommendations are evaluated three years after publication and are updated if necessary. This will be reported in the press. Copyright All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording and/or otherwise, without the prior written permission of CURNET. It is allowed, in accordance with article 15a Netherlands Copyright Act 1912, to quote data from this publication in order to use this in articles, essays and books, provided that the source of the quotation, and, insofar as this has been published, the name of the author, are clearly mentioned. CUR-Recommendation 102 Inspection and assessment of concrete structures in which the presence of ASR is suspected or has been established, April 2008, Gouda, The Netherlands. Liability CURNET and all contributors to this publication have taken every possible care in the preparation of this publication. However, it cannot be guaranteed that this publication is complete and/or free of errors. The use of this publication and data from this publication is entirely at the users own risk and CURNET hereby excludes any and all liability for any and all damage which may result from the use of this publication or data from this publication, except insofar as this damage is a result of intentional error or gross negligence of CURNET and/or the contributors. Gouda, April 2008 The Board of CURNET Stichting CURNET, Groningenweg 10, P.O. Box 420, 2800 AG GOUDA, The Netherlands tel. +31 (0)182540600

| 31

You might also like