Professional Documents
Culture Documents
Graphisoft
Visit the Graphisoft website at http://www.graphisoft.com for local distributor and product availability information.
Copyright 2009 by Graphisoft, all rights reserved. Reproduction, paraphrasing or translation without express prior written permission is strictly prohibited. ArchiCAD, Virtual Building and Virtual Building Solutions are trademarks of Graphisoft. All other trademarks are the property of their respective holders.
PROBLEM DEFINITION
Problems of the construction industry affect all areas of the construction process, including the design, subcontractor costs, construction and facility management. Here we list only the most critical of these issues. Design No direct cost feedback on design decisions Coordination of trades Subcontractor Cost Missing / Incorrect Design Information Inability to reuse data for shop drawings Field rework required for prefabricated components Padding to compensate for risks Poor subcontractor work flow Starts and Stops Inadequate quantity information for planning Construction Lack of owner trust difficulties in communicating cost and schedule issues Production control is based on subjective information Frequent starts and stops Estimating is time-consuming and occasionally inaccurate Facility Management Insufficient as-built project documentation Renovation, addition and demolition planning is time-consuming
OBJECTIVES
The needs and the point of view of construction companies are different from those of the architects. Construction must excel in two areas: winning bids and effectively managing the money, manpower, machinery, and materials required to construct buildings. If construction processes and results can be predicted more accurately, that means better business for construction firms.
Objectives Winning the bid Fast design feedback loop Fast & accurate estimates Value engineering Constructability analysis Managing the 4 Ms Money Manpower Machinery Materials
CONSTRUCTION PLANNING
Applying automated construction coordination solutions for construction planning offers significant advantages during the modeling, estimating, sequencing, procurement and site management phase as listed below
Model Constructability Analysis Drives Estimating Provides Locations Zone Planning Design to Build/Build to Design Estimating Fast & Accurate Easy Updates - Linked Drives Sequencing Sequencing Schedule Analysis Line of Balance Integrated Monte Carlo 4D Simulation
BIM Curriculum Lecture Notes
Drives Procurement Procurement Data Mining for Supplier Negotiations Tracking of High Risk, Long Lead Items Integrated with the Project Schedule Drives Site Management Process Site Management Short Lead Procurement Site Planning for Materials, Equipment and Locations
However, the difficult task is to provide a connection that doesnt change the level of detail existing team members currently use. Estimators, schedulers and other team members manipulate information in very different ways. Graphisofts 5D solution has solved this problem in the following way. The next slide describes the information flow.
5D WORK FLOW
The 5D model serves as the bases for all elements of the project control including constructability analysis, cost estimation and construction documentation.
CONSTRUCTION MODELING
The construction modeling process is somewhat different from those in architectural modeling. The following image illustrates the basic conceptual differences between the two approaches. Since the construction model is primarily used to extract quantities for estimating and to identify any possible constructability problems, it is critical that the construction elements are modeled precisely and with correct connections. On the other hand, non-construction elements like furniture or landscape objects that are standard parts of any architectural documentation are not required in the construction model.
The slide shows the construction model of a recessed slab structure. The very same structure is typically modeled with just one plain slab element in the architectural model.
RECIPES
Lets see how complex elements are modeled in Graphisofts 5D solution. A single model object, such as a column, is connected to estimating recipes that describes the methods and resources used to build them.
METHODS
Each recipe stores a series of methods. Most building objects are built at multiple stages. Again using the column as an example, a column is not built at one time. The rebar for a series of columns is built and then the crew returns to place the formwork, and again to pour the concrete, and again for the finishing. Each method represents a separated work activity.
RESOURCES
Each method requires a series of resources. For example, the concrete pour for the column requires: Equipment Concrete Mixer Crane Materials 5
BIM Curriculum Lecture Notes
THE 5D MODEL
Because the recipes are divided into methods and the model into zones, a schedule can be extracted based on data on how many activities are performed on each object the group of objects on which an activity will be repeated before the next type of activity begins. Once the schedule is updated to reflect actual start times and durations, a full 5D model exists, while still allowing the estimating and scheduler to work at their normal level of detail.
On the following slides well have a quick overview of the main advantages of the Virtual Construction Solution.
VARIANCE ESTIMATING
The Graphisoft 5D method offers a solution for this problem by assigning cost ranges to the building elements. Consequently, cost variances can be estimated even at the very early design phase of the project.