Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Applies to
SAP Plant Maintenance Module for Master Data upload.

Summary
Manufacturing Industries run on complex business processes and so require huge amount of Master Data like Machines and spare parts from tiny Bearings to giant Rollers. This article describes Creation/ Upload of Master Data in system using LSMW at one-go. Author: Ankur Saraf Company: NTT Data Americas Created on: 5 October 2012

Author Bio
Ankur Saraf is currently working in NTT Data Americas as SAP PM Consultant. He has knowledge in Maintenance Planning, Maintenance Order and Notifications Management, Serial Number Management and PMIS Reporting. Table of Contents Applies to on page 1 Summary on page 1 Author Bio on page 1 LSMW: An Introduction on page 2 Considerations: Before you proceed on page 2 Project preparation: Creating Project, Subproject and Object on page 3 Recording Creation: on page 4 LSM Workbench: Process Steps on page 12 Step 1: Maintain Object Attributes on page 12 Step 2: Maintain Source Structures on page 16 Step 3: Maintain Source Fields on page 17 Step 4: Maintain Structure Relations on page 22 Step 5: Maintain Field Mapping and Conversion Rules on page 23 Step 6: Maintain Fixed Values, Translations, User-Defined Routines on page 26 Step 7: Specify Files on page 27 Step 8: Assign Files on page 30

Generated by Jive on 2014-03-09+01:00 1

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording) Step 9: Read Data on page 31 Step 10: Display Read Data on page 31 Step 11: Convert Data on page 33 Step 12: Display Converted Data on page 34 Step 13: Create Batch Input Session on page 36 Step 14: Run Batch Input Session on page 37 Related Content on page 39

LSMW: An Introduction
LSMW- Legacy System Migration Workbench is an SAP tool used for master data upload/ Create into the system. You can use this tool while uploading data from legacy system into R/3 environment or to create and upload master data of huge amount. This tool follows a step-by-step procedure of 14 steps to create the master data into the system.

Considerations: Before you proceed


There are following considerations which must be taken into account before you proceed with this tool:

Generated by Jive on 2014-03-09+01:00 2

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording) SAP customization is already performed. Transaction to be carried out is identified. Examine carefully which fields in legacy file are mandatory and which can be left as optional from the SAP system point of view. Comparison of functions between the legacy system and the SAP system must have been completed. As a result of comparison, the data to be migrated is determined.

Project preparation: Creating Project, Subproject and Object


Project: The project serves as an organizational unit used to combine mapping and field assignments. Subproject: It is subordinated to the Project. For example, if project comprises of complete migration data for an organization which comprises of severalplant, then subproject comprises the data in the individual plants. Object: A business object, which is used to transfer the data of a project to the SAP system. Enter Transaction code LSMW.

Enter the Project, Subproject, Object and description respectively by placing the cursor in the respective fields.

Generated by Jive on 2014-03-09+01:00 3

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Enter Project, Subproject, Object and Description

Recording Creation:
In the Menu Bar, Goto- Recordings.

Generated by Jive on 2014-03-09+01:00 4

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Create a new recording and give the description. System will automatically populate the owner field.

Now enter the Transaction code: IE01 (Create Equipment)

Generated by Jive on 2014-03-09+01:00 5

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Do not enter any Equipment name if you are willing to get it created referencing internal number range you have assigned while customizing.

In the General tab provide your required details. Here Object type, Manufacturer and Model number details are entered.

Generated by Jive on 2014-03-09+01:00 6

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Enter Location related data in the tab in respective fields.

Generated by Jive on 2014-03-09+01:00 7

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Enter Account assignment and Responsibilities relevant data as per your business requirements.

Generated by Jive on 2014-03-09+01:00 8

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Now Install Equipment in appropriate Function Location.

Generated by Jive on 2014-03-09+01:00 9

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

When Saving the master data, system internally will be creating Recording so as to provide reusabiliy and reference for mass data upload.

The Recording created in the system looks like below:

Generated by Jive on 2014-03-09+01:00 10

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Now click on Default All to populate the fields of which details are accommodated in master data.

Generated by Jive on 2014-03-09+01:00 11

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording) The completed recording overview contains the transaction code:

LSM Workbench: Process Steps


Master data upload through this tool comprises of following 14 steps procedure:

Step 1: Maintain Object Attributes


Start the data upload process by selecting the first step radio button--> Execute

Generated by Jive on 2014-03-09+01:00 12

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

By default, Object Attributes will be in Display mode. There are four Modes of Data Transfer : 1. Standard/ Batch Input : Standard upload Programs 2. Batch Input Recording : Here you can create a recording of your own and use it to upload / change data 3. BAPIs : Standard BAPIs are used to upload Data 4. IDOCs : Any Inbound IDOC function modules can be used to process the data Here, we are using Batch Input Recording method to upload master data.

Generated by Jive on 2014-03-09+01:00 13

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Select Display <-> Change button and get it in change mode.

Generated by Jive on 2014-03-09+01:00 14

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Enter the Recording which was created through beginning steps, i.e. REC_EQUIP and click on Save.

Generated by Jive on 2014-03-09+01:00 15

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

When the first step is completed, the system takes you to previous screen and populates the field against it.

Step 2: Maintain Source Structures


Source structures can be used to design the hierarchy of the files to be uploaded. However, here highest hierarchy level is sufficient. Structures are prerequisites for Maintaining Source Fields. Select the next step radio button and Execute. System then takes you to Display mode of Source Structure.

In Change mode give the Source Structure and Description.

Generated by Jive on 2014-03-09+01:00 16

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

System shows the Source Structure created. Save and go back.

Step 3: Maintain Source Fields


Source Fields are maintained in Source Structures. Click button Object Overview and select Table View.

Generated by Jive on 2014-03-09+01:00 17

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

From Table view, select TABNAME, Type and Length and maintain the excel sheet.

Generated by Jive on 2014-03-09+01:00 18

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

By default system takes to the Display mode of Source Fields.

Go to Change mode, place the cursor on structure and click Table Maintenance button.

Generated by Jive on 2014-03-09+01:00 19

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Now, maintain the excel sheet values in Source Fields for Source Structure.

System takes internal table reference and populates the Field description with reference to Field name.

Generated by Jive on 2014-03-09+01:00 20

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Save and go back.

System maintains the source fields as per hierarchy level

Generated by Jive on 2014-03-09+01:00 21

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Step 4: Maintain Structure Relations


Here, the establishment of the structure relation is checked between Legacy and R/3 system.

Bring the screen into change mode, Save and then Back. No extra maintenance is required.

Generated by Jive on 2014-03-09+01:00 22

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Step 5: Maintain Field Mapping and Conversion Rules


Here we assign source fields to target fields, which is the relationship establishment between legacy and R/3 environment.

All fields of all target structures, which were selected in the previous step, will be displayed.

Generated by Jive on 2014-03-09+01:00 23

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Bring the screen into Change mode and then In menu bar, go to ExtrasAuto Field Mapping

Generated by Jive on 2014-03-09+01:00 24

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Now accept proposal for all the fields which need to upload.

At the end of proposal acceptance for all the entries system displays the below message:

Generated by Jive on 2014-03-09+01:00 25

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

After auto field mapping complete, save and back.

Step 6: Maintain Fixed Values, Translations, User-Defined Routines


No need to maintain this step, unless and until there exists any user defined routines, which may helpful for reusable.

Generated by Jive on 2014-03-09+01:00 26

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Note: To maintain the upload file with required field values, copy the details from Target Fields by clicking the Object Overview--> List

Step 7: Specify Files


Here we define the Files that we use to upload the data. Note: Generally we receive legacy file in excel format, so save this file as Text (Tab delimited).

Generated by Jive on 2014-03-09+01:00 27

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Go to Change mode and specify the file to upload data.

Now, double click on Legacy Data On the PC (Front End)

Generated by Jive on 2014-03-09+01:00 28

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Now Save and go back.

Generated by Jive on 2014-03-09+01:00 29

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Step 8: Assign Files


Here, we make a check whether file is assigned to source structure or not. Click on Execute button.

Now Save and go back.

Generated by Jive on 2014-03-09+01:00 30

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Step 9: Read Data


Here our data which is uploaded by the file would be read. Click on Execute and the data read status and number of records would be displayed on the screen.

Step 10: Display Read Data


Here, we can display the records which were read in previous step.

Generated by Jive on 2014-03-09+01:00 31

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Check, whether data has been correctly fit into fields. We can also give the line selection based on need.

Generated by Jive on 2014-03-09+01:00 32

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Step 11: Convert Data


Here, the legacy data is converted into SAP standards. We can check the data converted later on.

Click on Execute button and system displays the status for the data conversion. Note: Check the number of records from Step 9. Both should be same.

Generated by Jive on 2014-03-09+01:00 33

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Step 12: Display Converted Data


Executing this step displays the data converted in the previous step.

Generated by Jive on 2014-03-09+01:00 34

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Click on any record to check the converted data. Note: Here the visual check can be performed to check the values lifted by the file against the fields of SAP to be correct and as per requirements.

Generated by Jive on 2014-03-09+01:00 35

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Step 13: Create Batch Input Session


In this step, we create batch input session. Make sure to check box for Keep batch input folder.

Generated by Jive on 2014-03-09+01:00 36

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Step 14: Run Batch Input Session


Here, we run the batch input session, which is created in the previous step.

Click on Session and then on Process.

Generated by Jive on 2014-03-09+01:00 37

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Note: Here, the options for the upload can be specified. It is advisable to process few records in Foreground to capture the error while visual inspection.

Now, the Master data for the Equipment will get uploaded in the SAP System.

Generated by Jive on 2014-03-09+01:00 38

Plant Maintenance Master Data Create/ Upload using LSMW (Method: Batch Input Recording)

Related Content
www.help.sap.com www.sap-img.com