Introduction to

Offshore Structures
Part II Hodjat Shiri Centre for Offshore Foundation Systems (COFS) July 2009

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Offshore Installation of Fixed Platforms:

Topsides :

Lifting by HLV

Jackets :

Floatover by FLB

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:


HLV Positioning & Mooring Transportation Barge approach Transportation Barge Mooring alongside HLV Lifting rig connection Slings Tensioning Sea-fastening cutting Topside lifting Transportation Barge release HLV Re-positioning Deck mating Installation Completion

Topside Lifting Installation:


CENTRE FOR OFFSHORE FOUNDATION SYSTEMS
Topside

Barg e

HLV

Topside Lifting Installation:


CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:


CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:


CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:


CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:


CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:


HLV Positioning & Mooring Transportation Barge approach Transportation Barge Mooring alongside HLV Lifting rig connection Slings Tensioning Sea-fastening cutting Topside lifting Transportation Barge release HLV Re-positioning Deck mating Installation Completion

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Float Over Installation:


FLB Anchoring FLB Approach to Jacket FLB Enter Jacket Inside FLB Mooring to Jacket Sea-Fastening Cutting Barge Ballasting Deck Mating & Load Transfer (Jacking, Ballasting) Mating Completion FLB Release FLB Anchor recovery Installation Completion

Topside Lifting Installation:


CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Topside Lifting Installation:


CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Lifting Installation:


HLV Positioning & Mooring Transportation Barge approach Transportation Barge Mooring alongside HLV Lifting rig connection Slings Tensioning Sea-fastening cutting Jacket lifting and upending Transportation Barge release HLV Re-positioning Jacket positioning ( Position, Orientation, Direction) Pile Driving Installation Completion

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Launching Installation:


Launch Barge Anchoring Launching Arms Preparation Buoyancy Tanks check Barge Approach to right position Sea-fastening Cutting Barge Ballasting and Tilting Jacket Sliding & Barge Moving Jacket launching & Floating Jacket Upending (Lifting or Self-Upending) Jacket Positioning ( Tugs or HLVs) Pile Driving Installation Completion

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Launching Installation:


Launch Barge Anchoring Launching Arms Preparation Buoyancy Tanks check Barge Approach to right position Sea-fastening Cutting Barge Ballasting and Tilting Jacket Sliding & Barge Moving Jacket launching & Floating Jacket Upending (Lifting or Self-Upending) Jacket Positioning ( Tugs or HLVs) Pile Driving Installation Completion

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Launching Installation:

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Launching Installation:

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Launching Analysis:

Launching

Barge Release

Self-Upending

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Pile Driving :


Pile Transportation Barge comes alongside HLV Pile Preparation Jacket Preparation Hammer Preparation Pile Lead Section lifting up and Stabbing into jacket leg or Sleeve Hammer lift up and stabbing on top of pile Pile driving according to engineering sequences Lifting up the First add-on, Stabbing to Lead section, Welding Non Destructive Tests on Welds (NDT) Pile Stopper Removal and Driving first add-on Regular check of Jacket level ness Continuos Blow Count and Dynamic Stress Applied on Pile Continue to Finish Pile Driving Installation of Crown Plates Installation of Transition Pieces

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Pile Driving :


Piles Arrangement

Pile Lift Up

Hydraulic Hammer

Diesel Hammer

Hammer Stabbing

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

Jacket Pile Driving :

Pile in Driving

Completed Jacket

Pile Cut-off

Crown Plate Welding

CENTRE FOR OFFSHORE FOUNDATION SYSTEMS

End of Part Two