You are on page 1of 2

Tunnelling

at roads and railways

The Western Corridor Recycled Water (WCRW) Project is a $2.4 billion


water supply network designed to diversify South East Queensland's
water sources. It involves treating wastewater to the highest standard –
resulting in purified recycled water.
Purified recycled water will be supplied to power stations, industry and
agricultural customers and the Wivenhoe Dam through a 200km
network of large diameter underground pipes, three advanced water
treatment plants and supporting infrastructure.
The WCRW Project is the largest advanced recycled water project of its
kind in the southern hemisphere. When complete, it will have the
capacity to deliver up to 232 megalitres of purified recycled water a day
to end users.
The Queensland Government is contributing $2 billion and the Australian
Government is contributing $408 million through the Water Smart
Australia Program.
This fact sheet explains how the project will tunnel under more than 90 roads
and railways using trenchless technology (tunnel boring and microtunnelling)
techniques.

Why tunnel under road and rail crossings?


Tunnel boring and microtunnelling causes minimal disturbance to sensitive areas where open
cut trenching is not possible or where roads and railways would need to be shut down during
construction. Trenchless technology allows the pipeline to be constructed under these sensitive
areas without causing any significant disturbances to the ground and existing underground
services.

What preparation work is needed?


An excavator digs temporary working pits on each side of the crossing. These pits are the start
and finish point for the microtunnelling/tunnel boring machine as it excavates the tunnel.
Sheet piling is inserted by a crane or excavator around the internal perimeter of the working
pit to provide reinforcement around the pit walls. A concrete base is laid in the pit to provide
a solid working surface. In soft ground, the sheet piling forms a steel wall around the internal
perimeter to support the soil around the pit. In ground where there is hard rock, no sheet
piling is necessary, however rock bolts and other supports may be needed.
The depth of the working pit is determined by the required tunnel/pipe alignment and the
position of nearby underground services. Each working pit will range from 6 to 14 metres in
depth, 12 metres in length and 5 to 12 metres in width.

When will pit construction occur?


The construction of pits will occur during normal working hours. Depending on design, the
depth of the pit and ground conditions, the construction of the working pit may take
between a few days and a few weeks.

Department of Infrastructure and Planning


The location of the pit will ensure the crossing is as The operation of the machine and surface
short as possible. During construction of the pit the equipment will create some noise around the
construction team will minimise any work within working pit, and some crossings may require night-
existing utility easements and work primarily time operation of the machinery. Noise mitigation
within the pipeline easement, unless additional will be implemented at the sites to ensure noise
temporary working space is required and secured. levels are kept at a minimum. Spoil from the
The pit will be fenced off and secured at night to tunnelling operation may be kept temporarily on
ensure security and to prevent public access. site and removed later.

How is the tunnel built? What machines will be used?


A crane lowers the tunnelling machine into the pit A minimum of three modern tunnelling machines,
and machine operators enter the pit. The machine including an American Augers boring machine, a
is propelled forward by successfully jacking the Herrenknecht EPB1500 microtunnelling machine,
machine and casing pipe whilst excavating a and an Akkerman WM48C tunnel boring machine,
tunnel. will allow construction of pipelines under sensitive
areas (such as roads and railways) where open
The tunnels will be approximately 1.5 metres in trenching is not possible.
diameter to allow the 1086mm recycled water pipe
to be inserted inside the casing pipe. Where more The auger boring machine will be used for short
than one recycled water pipe is required in the one crossings, the Akkerman machine will be used for
alignment, separate tunnels are constructed for crossings averaging 100 metres in length and the
each pipeline. Herrenknecht machine will be used for longer
crossings. The machines will excavate the tunnels
using laser guidance systems. This maintains the
correct tunnel alignment for the installation of the
Tunnelling Operation Schematic recycled water pipeline.

What equipment will be used on


the surface?
Surface equipment includes generators, craneage,
equipment storage containers, hydraulic power
packs, Bentonite mixing/pumping equipment and
site amenities.

For more information


Contact the Project Team:
Phone: 1800 997 464 (freecall)
Email: info@westerncorridor.com.au
www.westerncorridor.com.au

March 2008

Printed on recycled paper

Department of Infrastructure and Planning

You might also like