Construction Field Rework: Total direct cost of redoing work in the field regardless of initiating cause or source
Process Establish Process Design Basis Client business drivers identified Site data collected (elevations, temperatures) Licensors identified Feedstock information collected (composition, rate, etc.) Process design criteria identified Mechanical Preliminary Equipment List - Issue for DBM Historical mechanical data collected Dimensions, weights rough sized in process engineering PFD's - IFR received MSD's - IFR Vendor packaged equipments identified Piping Preliminary Plot Plan Code and standards defined Fire protection requirements defined Building enclosure philosophy determined Meteorological data received Existing facilities information collected Civil/Structural Verification of Site Selection Civil/structural design criteria defined Modularization strategy defined Underground and above ground existing facilities identified Meteorological (snow, winds, etc.) information compiled Topographical map compiled Instrumentation & Controls I&C Inputs for DBM - IFR Client input about operations, control philosophy received Control philosophy defined Preliminary Control system architecture issued Standards and specifications defined Preliminary Control system functional specification defined Control building preliminary sized Preliminary PFD's received Major equipment process datasheets received Critical inline devices identified Area Classification IFR PFD IFD received Preliminary Instrument Index Plot plan IFR received Electrical Electrical Infrastructure and Requirements Defined Code and standards defined Local site conditions and profiles received Preliminary horsepower data received Electrical power studies to define requirements Preliminary electrical equipment list
Historical plot plan data collected Topographic information / coordinates (under/above ground) received Spacing guidelines (installation, hazards, etc.) established
Preliminary geotechnical report received Land issues resolved Regulatory issues (three level government, environmental, etc.) Site infrastructure information collected Transportation/logistic issues information collected Preliminary plot plan issued by plant layout (with civil/structure input)
Electrical underground, aboveground, substation information defined Electrical design criteria defined
Preliminary Equipment Pricing (Quotes) Process Flow Diagram - IFA Licensor information reviewed Functional mechanical specifications Mechanical sparing philosophy defined
PFD's IFA received Main piping tie-ins identified Equipment preliminary data received
Heat and material balance completed Major equipment identified and preliminary sizing Control philosophy decided (including DCS, PLC, etc.)
Vendor list approved Process data/rough equipment data sheets completed Critical equipments shop fabrication milestones identified
Client operational input received Hazardous equipment location analysis completed Civil structural input (ditches, roads, drainage, geotechnical, etc.) Electrical and instrumentation layout input received Civil Input for Plot Plan IFR Preliminary site grading
Instrument tagging procedure IFD P&ID's IFD received Inline devices data sheets IFR
Material selection guidelines issued Preliminary tie-in points identified Preliminary utility balance VIP review and simplification completed Equipment Data Sheets - IFQ/Equipment list - IFD MDMT and other temperature design criteria defined MSD's - IFD PFD's - IFD received DBM (FEED) Items P&ID's - IFR received
Client infrastructure requirements identified Construction input received Logistics and shipping constraints study received Modularization strategy received
Process input on fire water system and drainage received Fire water systems layout Sewers/drainage systems layout Major equipment preliminary size received Spacing guideline/codes received Main pipe racks preliminary sized
Area classifications IFR received Pipe specifications received Process and equipment data received Control system I/O Index defined Control system architecture developed Shutdown key matrix (cause and effect) generated from index Packaged equipment instrument specifications issued
P&ID's IFD received, horsepower defined Equipment list IFD received Preliminary electrical vendor information Lighting load estimated Heat tracing load estimated All electrical loads defined
Winterization philosophy decided Start up/shutdown philosophy published Preliminary drivers identified Process data sheets finished Process hazard analysis completed
Preliminary hydraulic calculations completed Plot plan - IFR received Sparing philosophy and spare parts defined Area classification drawings - IFD received Modularization plan defined
Plot Plan - IFD Field survey of geometer reference point received Main pipe racks sized Modularization execution plan (racks, etc.) established Equipment data sheets (esp. compressors, pumps, etc.) received P&ID's IFR received Material selection diagram received Piping studies for critical lines Fire hazard areas defined
Preliminary large bore pipe layout received Construction and operational access and egress studied Lay down areas identified Cable tray routing identified Transportation, lifting and logistics issues defined
Single Line Diagrams IFD Purchase Inline Devices Vendor list approved Process hydraulic calculations received UPS requirements defined Interfaces with power utility completed Plot plan IFR received
Process logic description finished Preliminary material selection diagram issued Piping material classes published Stream information firm
Battery limit conditions defined Specifications and standards issued Packaged equipment instrument specs issued
Piping specifications IFD received Civil Inputs for Plot Plan IFD Major buildings (size, location) finalized Major pipe racks and large bore piping design frozen (including stress design) Underground scope, location and services identified Final process data provided to instrument data sheets Area classifications IFD received Client review and approval of datasheets
Power generation philosophy defined Power system study (fault study, load flow, utility coordination) completed Process reliability requirements defined Redundancy requirements defined
Client operation requirements defined (equipment, voltage, above/below grade) Construction power defined
Electrical underground, aboveground, substation information received Preliminary vendor data (major vessels, equipment) received Access / egress finalized and confirmed Major cable routing frozen Major equipment coordinates received Control System Purchase
Shop fabrication scheduled Technical evaluations finalized Commercial review input (bid summaries,recommendations and client approval)
I/O count / loop drawings IFD Shutdown keys IFC Marshalling philosophy issued and approved
Purchase Electrical Equipment Modularization strategy defined Electrical equipment data sheets IFD
Preliminary mechanical equipment loads (static and dynamic) and GA's received Preliminary electrical equipment loads and GAs received Preliminary piping drawings (rack, underground, stress) received Pollution abatement (equipment and facilities) defined Loading diagram defined
Mechanical equipment identified and sized Discipline-specific specifications and standards published
Hydraulic calculations finalized Logistics input -- lifting, transportation, routing, receiving and storage Client operation and maintenance review Commissioning support - review of spare parts, training process, and vendor support
Final vendor dimensional data collected Building sizing and layout received
Battery limit tables finished All tie-ins identified Lines sized, specified Relief requirements identified Major instrument list commenced Major valves identified Major control valves identified and sized Licensor P&ID reviewed
Final civil ,road and drainage drawing received Heat tracing LDT's IFD Inline components defined
Electrical control philosophy issued Mechanical vendor information/packaged equipment information received
Instrument Index - IFC Rough Grading Plan IFC Logic/control narratives received FAT procedures and test plan defined Deep Underground IFC P&ID's IFC received All I&C purchase orders issued Input to Plot Plan IFC
Variable frequency drive requirements defined Sparing philosophy finalized Vendor list approved Area classification IFD
Vendor Certified Data Engineering review of vendor drawings finished Client operations buy-in, vendor drawing review P&ID's IFC received Vendor operation and maintenance manuals completed
Large bore stress analysis completed Large bore piping design and layout completed Utility piping definition completed Electrical single line IFD received Electrical, I&C cable trays requirements and data received
Installation instructions completed Support load diagrams completed Tie-in List - IFC P&ID's - IFC received Piling IFC Structural pipe rack model Preliminary structural design Foundations drawings IFD Equipment loads and GAs received Underground piping and electrical locations fixed Large bore pipe stress design frozen Installation plan (hoisting and craning requirements) defined Final Client Model/Layout Reviews Precommissioning / Commissioning Plan Manufacturing records (as-built data book, certified performance) compiled Operating manuals finished OEM support Plot plan IFC Large bore piping layout completed Foundations / Sitewide Concrete IFC Final mechanical equipment loads (static and dynamic) and GAs received Final electrical equipment loads and GAs received Piping drawings IFC (rack, underground, stress) received All penetrations and embeds identified by other disciplines Vendor package equipment loads and GAs certified Building design IFD DBM CCTV FAT FEED FEL GA Structural Steel IFC Piping drawings IFC (rack, underground, stress) HVAC drawings IFD Mechanical drawings IFD Final electrical equipment loads and GAs received Vendor package equipment loads and GAs certified Building design IFD Small bore piping routing completed
Cable tray routing/location defined Plot plan IFC received Electrical equipment layout IFC Control systems layout IFC received All junction box locations defined Certified packaged equipment electrical data received Piping layout and/or 3D model completed Single line diagrams IFC Other systems defined (CCTV, fire system, LAN), third party input completed
P&ID's, UFD's and LDT's - IFD Flare and relief calculations completed All client input completed Hydraulic calculations finished VIP's implemented as applicable Start-up systems defined
Mechanical Inputs to Contracts Equipment list finalized Data lists finalized Vendor data finalized Scope and specification finalized Start-up and commissioning plan defined
LDT's IFC received Survey of pipe wall thickness, metallurgy received Operation philosophy received Schedule of plant planned shutdown received Client approval for operation and engineering
Shutdown keys defined Final line sizing by process engineering Final control valve and PRV sizing
Electrical Heat Tracing ISO's IFC GLOSSARY Piping ISO's IFC received
Large bore stress analysis finished P&ID's - IFC All hydraulic calculations completed
Design Basis Memorandum Closed circuit TV Factory Acceptance Test Front End Engineering Design (Includes FEL 2&3) Front End Loading General Arrangement
MSD MTO NDE OEM P&ID PFD PRV SIL SOC UFD UPS VIP
Material Selection Diagram Material Take Off Non Destructive Examination Original Equipment Manufacturer Process & Instrument Diagram Process Flow Diagram Pressure Relief Valve Safety, Integrity Level Supplier of Choice Utility Flow Diagram Uninterrupted Power Supply Value Improving Practices
P&ID's IFC Final Equipment List received Detailed vendor's information (specification sheet; data sheet; auxiliaries; utilities) received HAZOP issues resolved Vessel levels finalized (operations & elevation)
Structural - pipe racks modeled Equipment modules design finalized Vendor data received Electrical tray modeled Clash analysis completed Constructability review completed
HAZOP Hazard and Operation analysis HT&I Heat tracing and insulation
HVAC Heating, Ventilation, Air Conditioning IFC IFD IFQ IFR IPA ISO Issued For Construction Issued For Design Issued For Quotation Issued For Review Independent Project Analysis Inc. Isometric Drawings Local Area Network Line Designation Table
Operation and maintenance (O&M) review completed IFC line list completed Critical small bore piping (high pressure, toxic, utility/tracing stations etc.) identified and modeled Inline components included All large bore valves indicated Locations for cable trays identified Secondary supports included
IPA Definitions FEL 1 (Block Flow) FEL 2 (Process Flow) FEL 3 (P&ID's) Detailed Design
LAN LDT
First ISO Issue Certified vendor equipment drawings received Welding, hydro test and NDE specifications IFC All piping details and standards IFC (supports, hangers, etc.) MSD IFC Fabrication philosophy determined (field/shop)
Final Grading and Paving IFC Civil Drawing IFC (fencing, signage)
COAA 2004 REV 1.0 This Checklist is intended for the use of Owners, Engineers and Constructors in reducing field rework by ensuring that the correct sequence of activities takes place in the design office.
PROJECT NAME: