Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 1


Improving Software Estimation Using Monte Carlo Simulation
Using statistical simulation to provide a software delivery date and the
probability of meeting a given deadline
Troy Magennis, July 2008
Introduction
Software estimations are commonly viewed with the same skepticism by well informed executives,
as the automotive history provided by a used-car salesperson in New Orleans after the devastation
of Hurricane Katrina. Its not unreasonable for executive level management to desire some
indication of when a software project may be delivered, however, they are often furnished with
massive ranges; wild estimates presented as fact with no indication that it was likely calculated from
the sell-by date on the milk container in the engineering teams kitchen.
What is the most likely delivery date for a current project? What is the probability of hitting this go-
live date? These are fair questions for any executive or investor to ask, but they are often answered
by a sweating and nervous looking development manager who presents a date with no mention of
probability. This date holds the key to making better executive decisions, and risk is a normal aspect
of any decision process. Padding estimates to cover all risks will give a date too far out to be
acceptable; the counter case of aggressive estimates might get the project funded, but actual
delivery of a quality product unlikely. What is the likelihood of successful delivery by a given date?
This article borrows a techniques described as Applied Information Economics (AIE) that will quickly
build an estimation framework and statistically driven simulation mechanism to reflect the normal
distribution of estimate risk ranges, presenting the probability of completion in a certain time. E.g.
80% chance of 66 days, and 34% of success in 60 days. It is also a simple charting step to present the
same simulation data as a histogram showing the level of confidence that a given date is achievable.

Figure 1 - Our desired outputs. A probability calculator and a probability histogram of a specific completion date.
The technique described exhibits the following characteristics
Allows an initial date estimate to be achieved quickly
Provides a constant probability of hitting a date
0
20
40
60
80
4
7
5
1
5
5
5
9
6
3
6
8
7
2
7
6
F
r
e
q
u
e
n
c
y
Bin (Days)
Histogram of
Days to Completion
(n = 1,000 iterations)
Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 2
Allows a date estimate to be progressively firmed up as more information comes to hand
Works for an iteration of a project and/or the entire project schedule (E.g. 92% chance of
hitting an iteration with x features, but only a 63% chance with y set of features)
Provides a mathematical proven mechanism for presenting the risk profile of a project (E.g.
Given a target of 65 days, there is a 73% chance of hitting that mark)
Avoids the common issue of massive over-estimation in an attempt to highlight risk (this
often gets projects cancelled before they begin)

This technique was generically described by Douglas Hubbarb in his book titled How to Measure
Anything: Finding the Value of Intangibles in Business (Hubbard, 2007), and this article proposes
one implementation that migrates those principles into the software estimation problem domain.
Hubbarbs approach borrows and explains techniques commonly used in many decision fields.
Wikipedia is a good starting source for understanding the basic principles of Applied Information
economics, its history and adoption: http://en.wikipedia.org/wiki/Applied_information_economics

The simulation method used is very commonly employed in other fields to solve probability
problems, such as in electronic component simulation software (Monte Carlo method) which the
author has some experience. Monte Carlo methods are used in calculations where it is not possible
to deterministically solve for an exact result. Instead, repeated calculations using bounded random
inputs are used in an attempt to discern the probability histogram among viable results.
Software Estimation Basics
In the aftermath of many failed software projects, the technique of simply asking the development
manager for an accurate delivery estimate between lunch and 2pm whilst they eat pizza, has been
re-considered best practice in many organizations. Mentally solving the complex risk relationships
for even a small software project is unlikely at best.
Software estimation practices vary, but often share the common principle of breaking down the
larger project into smaller chunks. Smaller tasks are thought of as easier to accurately estimate,
following the logic is more likely to accurately estimate the time to walk across the room than it is to
estimate how long it would take to walk across the country (exclude narrow countries like New
Zealand, Chile, Italy, etc). The actual act of breaking down the project into smaller pieces also
clarifies specification intention and forces some basic design decisions to be resolved up-front,
reducing the risk that these will be uncovered later.
To break down the tasks for even a small project can take a considerable time. The conflict between
getting a rough estimate in reasonable time, while breaking down enough detail to reduce the risk of
missing a considerable feature is hard to solve. Nobody likes giving an inaccurate estimate, but
estimation time will grow exponentially in order to narrow in on more accuracy and this might take
more time than available. Some estimates will have to be accepted as having a higher uncertainty
than others. This is often portrayed as a low, medium and high scale, which is used to multiply the
estimate by an increasing factor. One example is low risk estimates are multiplied by 1, medium
level multiplied by 1.5 and high risk estimated are doubled (these are common, but some people use
higher multipliers- Im trying to keep the number real).
Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 3
Feature
Name
Raw
Estimate
Estimate
Risk
Weighted
Estimate
A 10 Low 10
B 5 Medium 7.5
C 7 High 14
D 3 Low 3
E 2 Medium 3
F 8 High 16
G 5 Low 5
H 6 Medium 9
I 1 High 2
J 4 Low 4
51 73.5

Risk Weight Key
Low 1
Medium 1.5
High 2
Table 1 - Example of a common technique for arriving at a quick project estimate. Estimates are allocated a low, medium
or high risk. These risks are used to weight the estimates in order to give a low and a high date.
Table 1 would indicate an estimate between 51 units and 73.5 units (lets say days for this
experiment). Is an over 40% increase acceptable? If you were being charges $1,000 per day that
would be a dollar range of $51,000 to $73,500. If $60,000 was the budgeted limit you just lost your
project.
Problems with Range Estimates
One issue with weighted risk estimation techniques is that the weighted estimate is often
interpreted at the extremes. Well intentioned in an attempt to cater for in-accurate estimates
means some people over-estimate, making the prediction is long. Other estimators are more
susceptible to under-estimating, creating unrealistic expectations.
What are the issues with a simple weighted range?
Not all values within the 51 to 74 day range have an equal chance
There is no measure of probability for whether any given date is achievable
One person hears 51 days, the other 74 days. Both parties will start the project with
different expectations a sure recipe for discontentment in the future
In real life some estimates wont always be at the extreme high end of the risk multiplier, nor will
they all be at the low end. There is no way of predicting how many will be at which end of the risk
multiplier scale; Well, almost no way. Statistics offers some hope by introducing the concept of
Normal Distribution, often referred to as the bell curve.
Real World Simulation Simple Monte Carlo Method
If you were to sit down and pick random estimates of each task within a given range, and continue
doing this and tabulating the results for thousands of imaginary cycles, you would achieve a
Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 4
statistical average following the Normal Distribution pattern. This is exactly what Monte Carlo
simulation does.
To carry out this simulation we need the following inputs
1. A sum for each risk level; Sum of all low estimates, medium estimates and high estimates
2. A lower and upper bound for each risk level; Low, medium and high
3. The estimated mean (average) for each risk level; Low medium and high
From these inputs, it is possible using random functions, to pick a viable value for the multiplier for
each risk segment. Monte Carlo methods repeat and tabulate what the total estimate might look like
for these random scenario iterations.
Step 1 - Estimates and Risk Allocation
The simulation needs an estimate to work with. Each feature needs to have an allocated
estimate, and a well considered low, medium or high risk estimate. It goes without saying
the better these estimates, the better the calculated data. However, the intention of this
estimation technique is to get a result in a reasonable time. Know when you need to mark
an estimate high risk and move on.
One technique the author uses is to allocate a medium to every estimate, then work through
the list and allocate a low when Im certain there are no mis-understood or new concepts
and a high when there are many unknowns. Depending on whether you are after a rough-
cut estimate, or a fairly accurate solution, make a decision as to how much research is
undertaken for each feature, prioritizing in an attempt to decrease the high risks to
medium or low. After moving through the list, a table similar to that shown in Table 2 should
be produced (yours will be bigger, and feature names hopefully more descriptive than A, B,
C, etc).
Feature
Name
Low
Risk
Med
Risk
High
Risk
A 10
B 5
C 7
D 3
E 2
F 8
G 5
H 6
I 1
J 4
Total: 22 13 16
Table 2 - Feature estimate partitioned by risk level.
(Hubbard, 2007) advises that estimators be calibrated. His work demonstrates a simple
technique of asking calibration questions of individuals and determining that when someone
says they are 90% sure, how often they actually are. Some people will estimate their own
Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 5
accuracy low, some people will estimate high. Profiling your estimation team will bring
immediate rewards in accuracy and help refine the initial upper and lower bounds for risk
multipliers. Calibrating estimators aside, nothing improves estimate accuracy more than
applying the lessons learnt by comparing real values versus estimates over time and
determining your specific projects trend.
Step 2 Create Initial Risk Bounds
At the start of any project, the lower and upper boundary for each risk level multiplier is
subjective. As a project progresses and actual values can be compared to estimates, a
pattern that profiles the development team, and also profiles the estimation teams bias can
be used to refined weights.
For initial rough-cut estimates, the values shown in Table 3 are the starting point used for
this article. In addition to the upper and lower bounds, the average (or mean) value for each
risk level needs to be determined.
The mean value does not have to be centered in the bounds. In fact, for the medium and
high risk levels, Table 3 shows the offset the average towards the higher bound. The logic is
that low risk estimates might go either way (be under or over by a small amount), but as the
risk grows, estimates are more likely to be low, and the actual features taking longer due to
un-identified unknowns.
Low Medium High
Upper Bound 110% 150% 200%
Mean 100% 125% 150%
Lower Bound 90% 85% 80%
Table 3 - Initial risk boundaries and mean values

Figure 2 - The High Risk estimates will be multiplied by random samples selected statistically spread over the
Normal Distribution function (Bell Curve) between 80% and 200%. The Mean is slightly offset towards the
higher end, ensuring more values will be around 150%.
Step 3 Build the Random Function
Our random selection of multiplier for an estimate has to follow the Normal Cumulative
Distribution profile, falling between the lower and upper bound, centered on the mean. Our
formula determines random values within the bounds, falling off at a rate consistent with
the traditional bell curve function closer to the bounds.
x 0.8 x 1.5 x 2.0
Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 6
The examples in this article use built-in functions in Microsoft Excel, although any
spreadsheet will perform similar calculations. Excels NORMINV function according to the
Excel 2007 (Microsoft Corp, 2007) documentation Returns the inverse of the normal
cumulative distribution for the specified mean and standard deviation. We will use this
function and the built-in random number function RAND to compute a likely risk multiplier
for each of our risk levels.
The general form is: NORMINV(Probability, Mean, Standard Deviation)
=NORMINV(RAND(),LowMean,(LowUpperBound-LowLowerBound)/3.29)
=NORMINV(RAND(),MediumMean,(MediumUpperBound-
MediumLowerBound)/3.29)
=NORMINV(RAND(),HighMean,(HighUpperBound-HighLowerBound)/3.29)
Figure 3 - Random function used to determine the multiplier value for each iteration scenario
The Standard Deviation is used to determine the fall-off rate either side of the Mean in our
ranges. The only complexity in the Standard Deviation calculation involves the division by
3.29. The Normal Cumulative function falls off to 0.997 within the first 3 Standard Deviations
from the Mean. Dividing the range by 3.29 would include the values out to 0.999. More
experimentation is required to determine if this will have any real impact on the outcomes.
Step 4 Perform Multiple Iterations and Compute Totals
Monte Carlo analysis now dictates computing an outcome hundreds or thousands of time.
This allows the computation of a likely distribution, and the likelihood a certain date would
be possible (what percentage of the iterations fall below a given date).
Iteration Low
Mult
Med
Mult
High
Mult
Low
Weighted
Med
Weighted
High
Weighted
Total
1 0.93
(see
fig 2)
1.09
(see
fig 2)
1.89
(see
fig 2)
20.54
(22 * 0.93)
22 = Original
Low Estimate
17.46
(16 * 1.09)
30.31
(16 * 1.89)
68.30
(20.54 +
17.46 +
30.31)
2 0.97 1.14 1.36 21.45 18.23 21.80 61.48
3 1.05 1.37 1.74 23.12 21.94 27.82 72.87
4 0.97 1.31 2.11 21.37 21.00 33.75 76.12
5... 1.00 1.29 1.10 21.98 20.61 17.67 60.26
Table 4 - The first 5 iterations of ideally hundreds or thousands. How many iterations fall within your desired
range? This is the key to calculating probability versus a simple average.
Step 5 Calculate Probabilities
From the set of iteration scenarios, the Monte Carlo analysis returns a set of Total estimates.
The probability calculation is a matter of counting those below a given threshold and
presenting this as a percentage.
% probability of success = (count of # iterations < [target] / number of iterations) * 100
Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 7

Figure 4 - Sample Target Probability calculator. This allows the spreadsheet user to see what percentage of
simulation iterations fell under a desired target number of days.
Excel has a neat function for counting rows that match a certain criteria, and the Chance of
Success columns in Figure 4 use the following basic formula
=(COUNTIF(*simulation total cell range+,"< " & [target days])/[iterations])
In addition to this single value, the entire result set can be displayed in a Histogram as
demonstrated in Figure 5. This graph shows the full spread of scenario total estimates. It is
also useful to understand what risk level contributes to the total, and a histogram for each
risk level total is often helpful to determine that more time spent on analysing high or
medium risks will improve the probability estimate by narrowing the range.

Figure 5 - Histogram of 1,000 iterations. This shows the most common scenarios are centred between 58 to 63
days.
Building Confidence and Refinement
Once the project is underway, it is possible to measure how close estimates and actual are aligning.
This insight allows the estimated completion date to be refined by
1. Narrowing the range of risk multipliers by understanding the estimations teams bias
2. High tasks being understood and moved to medium tasks, and medium tasks to low
The most important contributor to accuracy though is the initial estimates. If the estimates are
incorrect, then there can be no mathematical magic that will bring accuracy to the endeavor. The
process of deriving these estimates should in the absence of actually understanding every unknown,
0
10
20
30
40
50
60
70
80
90
4
3
4
8
5
3
5
8
6
3
6
8
7
4
7
9
F
r
e
q
u
e
n
c
y
Bin (Days)
Total Estimate Histogram
Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 8
be at the very least - consistent. Define the rules as to what qualifies a feature as high, medium and
low risk early and keep to that recipe.
Consider running a higher number of iteration scenarios. The higher number of iterations, the less
impact statistical outliers will skew values. Even the long-shot pays dividends occasionally, and the
random function and distribution pattern we are using allows these to be represented in the data.
The histogram show in Figure 5 clearly demonstrates that we dont yet have a perfect Normal
Distribution pattern (61 is highest, but 62 is lower than 63). More repetitions would bring this
outcome into conformity. However, your actual project will have an iteration of 1! We are looking
for probabilities, there are no absolutes.
The issue of testing and other dark matter (tasks that need to be done, but arent captured in the
estimates) also needs to be represented. This can be achieved in one of the following ways
1. Add an estimate for each iteration for dark matter
2. Move the mean value for the risk multipliers further towards the upper bound
3. Add a separate random function for each iteration scenario to create a random estimate for
each simulation. If you choose to do this, increase the permutations and keep the range low
to avoid it over-influencing the outcome. If dark matter is such a problem, some important
tasks must be overlooked in the estimates.
Summary
Applied Information Economics (AIE) of which this technique has adapted to the software estimation
process, is a well respected method for bringing statistical and mathematical rigor to business
decision problems. It allows probability to be part of the decision process, alongside tables of
numbers and dates.
Monte Carlo simulation brings normal probability distribution patterns to the intangible risks in
order to find the most likely outcomes from thousands of possibilities. Averaging the risks values
would give a result in the likely range; however the simulation technique derives a probability
measure. It is this probability measure that offers so much value in the decision making discussion
and negotiation process.
The ability to quickly estimate a project, iteration or probability of hitting a specified date should be
a key competency practiced by anyone who seriously wants to improve the software planning and
development process. Monte Carlo simulation and other Applied Information Economic principles
should be another weapon in your arsenal.
About the author: Troy Magennis is a software developer and Enterprise Software Architect located
in Seattle, WA. He has worked on numerous enterprise scale software projects over the last 14
years, and is a Microsoft MVP for Visual C#. He can be contacted and welcomes feedback by sending
email to troy@aspiring-technology.com.
Sample Spreadsheet and More Information
A sample spreadsheet is available to support this article. Download it from the following location:
http://blog.aspiring-technology.com/page/Technical-Articles.aspx
Improving Software Estimation Using Monte Carlo Simulation

Troy Magennis July 2008 Page 9
Updates to this article will be posted at the same location.
The author intends to blog about updates and new ideas enhancing this technique. You can follow
these on the blog:
Blog: http://blog.aspiring-technology.com
RSS feed: http://feeds.feedburner.com/LinqedIn
The author welcomes feedback (good and bad), and can be reached at the following email address
troy@aspiring-technology.com
Bibliography
Hubbard, D. (2007). How to Measure Anything: Finding the Value of "Intangibles" in Business. Wiley.
Microsoft Corp. (2007). Excel 2007 Help File.
Wikipedia. (n.d.). Applied Information Economics. Retrieved 07 14, 2008, from Wikipedia:
http://en.wikipedia.org/wiki/Applied_information_economics