Consider the following consulting project: Develop a critical path diagram and determine the duration of the critical path and slack times for all activities. Activity Designation Immed. Pred. Time (Weeks) Assess customer's needs A None 2 Write and submit proposal B A 1 Obtain approval C B 1 Develop service vision and goals D C 2 Train employees E C 5 Quality improvement pilot groups F D, E 5 Write assessment report G F 1 Example 1. CPM with Single Time Estimate Consider the following consulting project: Activity Designation Immed. Pred. Time (Weeks) Assess customer's needs A None 2 Write and submit proposal B A 1 Obtain approval C B 1 Develop service vision and goals D C 2 Train employees E C 5 Quality improvement pilot groups F D, E 5 Write assessment report G F 1 Develop a critical path diagram and determine the duration of the critical path and slack times for all activities. Example 1: First draw the network A(2) B(1) C(1) D(2) E(5) F(5) G(1) A None 2 B A 1 C B 1 D C 2 E C 5 F D,E 5 G F 1 Act. Imed. Pred. Time Example 1: Determine early starts and early finish times ES=9 EF=14 ES=14 EF=15 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=4 EF=9 ES=4 EF=6 A(2) B(1) C(1) D(2) E(5) F(5) G(1) Hint: Start with ES=0 and go forward in the network from A to G. Example 1: Determine late starts and late finish times ES=9 EF=14 ES=14 EF=15 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=4 EF=9 ES=4 EF=6 A(2) B(1) C(1) D(2) E(5) F(5) G(1) LS=14 LF=15 LS=9 LF=14 LS=4 LF=9 LS=7 LF=9 LS=3 LF=4 LS=2 LF=3 LS=0 LF=2 Hint: Start with LF=15 or the total time of the project and go backward in the network from G to A. Example 1: Critical Path & Slack ES=9 EF=14 ES=14 EF=15 ES=0 EF=2 ES=2 EF=3 ES=3 EF=4 ES=4 EF=9 ES=4 EF=6 A(2) B(1) C(1) D(2) E(5) F(5) G(1) LS=14 LF=15 LS=9 LF=14 LS=4 LF=9 LS=7 LF=9 LS=3 LF=4 LS=2 LF=3 LS=0 LF=2 Duration = 15 weeks Slack=(7-4)=(9-6)= 3 Wks Example 2. CPM with Three Activity Time Estimates Task Immediate Predecesors Optimistic Most Likely Pessimistic A None 3 6 15 B None 2 4 14 C A 6 12 30 D A 2 5 8 E C 5 11 17 F D 3 6 15 G B 3 9 27 H E,F 1 4 7 I G,H 4 19 28 EXAMPLE 2 A Select administrative and medical staff. 12 B Select site and do site survey. 9 C Select equipment. A 10 D Prepare final construction plans & layout. B 10 E Bring utilities to the site. B 24 F Interview applicants and fill positions in A 10 nursing, support staff, maintenance, and security. G Purchase and take delivery of equipment. C 35 H Construct the hospital. D 40 I Develop an information system. A 15 J Install the equipment. E,G,H 4 K Train nurses and support staff. F,I,J 6 St. Adolfs Hospital (A sample project) Immediate Activity Description Predecessor(s) Activity Times *We wont assigning Responsibility data, but it is important in project management. St. Adolfs Hospital Diagramming the Network Finish Start A B C D E F G H I J K Immediate Predecessors A 12 B 9 C A 10 D B 10 E B 24 F A 10 G C 35 H D 40 I A 15 J E,G,H 4 K F,I,J 6 Activity Times (wks) St. Adolfs Hospital Activity Paths Finish Start A B C D E F G H I J K Path Time (wks)
A-I-K33 A-F-K28 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Paths are sequences of activities between a projects start and finish. St. Adolfs Critical Path Finish Start A B C D E F G H I J K Path Time (wks)
A-I-K33 A-F-K28 A-C-G-J-K 67 B-D-H-J-K 69 B-E-J-K 43 Project Expected Time is 69 wks. The longest path is the critical path! Earliest Start and Earliest Finish Times K
6 C
10 G
35 J
4 H
40 B
9 D
10 E
24 I
15 Finish Start A
12 F
10 0 Earliest start time 12 Earliest finish time 0 9 9 33 9 19 19 59 22 57 12 22 59 63 12 27 12 22 63 69 2013 Lew Hofmann Earliest Start and Earliest Finish Times Critical Path The Critical Path takes 69 weeks K