EXAMPLE 1

Example 1. CPM with Single Time Estimate


Consider the following consulting project:
Develop a critical path diagram and determine
the duration of the critical path and slack times
for all activities.
Activity Designation Immed. Pred. Time (Weeks)
Assess customer's needs A None 2
Write and submit proposal B A 1
Obtain approval C B 1
Develop service vision and goals D C 2
Train employees E C 5
Quality improvement pilot groups F D, E 5
Write assessment report G F 1
Example 1. CPM with Single Time
Estimate
Consider the following consulting project:
Activity Designation Immed. Pred. Time (Weeks)
Assess customer's needs A None 2
Write and submit proposal B A 1
Obtain approval C B 1
Develop service vision and goals D C 2
Train employees E C 5
Quality improvement pilot groups F D, E 5
Write assessment report G F 1
Develop a critical path diagram and determine
the duration of the critical path and slack times
for all activities.
Example 1: First draw the network
A(2) B(1) C(1)
D(2)
E(5)
F(5)
G(1)
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
G F 1
Act. Imed. Pred. Time
Example 1: Determine early starts and early finish
times
ES=9
EF=14
ES=14
EF=15
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
ES=4
EF=9
ES=4
EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5)
G(1)
Hint: Start with ES=0 and go
forward in the network from A
to G.
Example 1:
Determine late starts
and late finish times
ES=9
EF=14
ES=14
EF=15
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
ES=4
EF=9
ES=4
EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5)
G(1)
LS=14
LF=15
LS=9
LF=14
LS=4
LF=9
LS=7
LF=9
LS=3
LF=4
LS=2
LF=3
LS=0
LF=2
Hint: Start with LF=15 or the total
time of the project and go
backward in the network from G to
A.
Example 1: Critical Path & Slack
ES=9
EF=14
ES=14
EF=15
ES=0
EF=2
ES=2
EF=3
ES=3
EF=4
ES=4
EF=9
ES=4
EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5)
G(1)
LS=14
LF=15
LS=9
LF=14
LS=4
LF=9
LS=7
LF=9
LS=3
LF=4
LS=2
LF=3
LS=0
LF=2
Duration = 15 weeks
Slack=(7-4)=(9-6)= 3 Wks
Example 2. CPM with Three Activity Time
Estimates
Task
Immediate
Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
EXAMPLE 2
A Select administrative and medical staff. 12
B Select site and do site survey. 9
C Select equipment. A 10
D Prepare final construction plans & layout. B 10
E Bring utilities to the site. B 24
F Interview applicants and fill positions in A 10
nursing, support staff, maintenance,
and security.
G Purchase and take delivery of equipment. C 35
H Construct the hospital. D 40
I Develop an information system. A 15
J Install the equipment. E,G,H 4
K Train nurses and support staff. F,I,J 6
St. Adolfs Hospital
(A sample project)
Immediate
Activity Description Predecessor(s) Activity Times
*We wont assigning Responsibility data, but it is important in project management.
St. Adolfs Hospital
Diagramming the Network
Finish Start
A
B
C
D
E
F
G
H
I
J
K
Immediate
Predecessors
A 12
B 9
C A 10
D B 10
E B 24
F A 10
G C 35
H D 40
I A 15
J E,G,H 4
K F,I,J 6
Activity Times
(wks)
St. Adolfs Hospital
Activity Paths
Finish Start
A
B
C
D
E
F
G
H
I
J
K
Path Time (wks)

A-I-K33
A-F-K28
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
Paths are sequences of activities
between a projects start and finish.
St. Adolfs Critical Path
Finish Start
A
B
C
D
E
F
G
H
I
J
K Path Time (wks)

A-I-K33
A-F-K28
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
Project Expected
Time is 69 wks.
The longest path is the critical path!
Earliest Start and Earliest Finish Times
K

6
C

10
G

35
J

4
H

40
B

9
D

10
E

24
I

15
Finish
Start
A

12
F

10
0
Earliest start time
12
Earliest finish time
0 9
9 33
9 19 19 59
22 57 12 22
59 63
12 27
12 22 63 69
2013 Lew Hofmann
Earliest Start and Earliest Finish Times
Critical Path
The Critical Path takes
69 weeks
K

6
C

10
G

35
J

4
H

40
B

9
D

10
E

24
I

15
Finish
Start
A

12
F

10
0 9
9 33
9 19 19 59
22 57 12 22
59 63
12 27
12 22 63 69 0 12
Path Time (wks)

A-I-K33
A-F-K28
A-C-G-J-K 67
B-D-H-J-K 69
B-E-J-K 43
2013 Lew Hofmann
K

6
C

10
G

35
J

4
H

40
B

9
D

10
E

24
I

15
Finish
Start
A

12
F

10
0 9
9 33
9 19 19 59
22 57 12 22
59 63
12 27
12 22 63 69 0 12
Latest Start and Latest Finish Times
(You start with the last activity and work toward the first activity)
48 63
53 63
59 63
24 59
19 59
35 59
14 24
9 19
2 14
0 9
Latest
finish
time
63 69
Latest
start
time
2013 Lew Hofmann
Activity Slack
Analysis
K

6
C

10
G

35
J

4
H

40
B

9
D

10
E

24
I

15
Finish
Start
A

12
F

10
0 9
9 33
9 19 19 59
22 57 12 22
59 63
12 27
12 22 63 69 0 12
48 63
53 63
59 63
24 59
19 59
35 59
14 24
9 19
2 14
0 9
63 69
Slack is the difference between LS
and ES or EF and LF
Node Duration ES LS Slack
A 12 0 2 2
B 9 0 0 0
C 10 12 14 2
D 10 9 9 0
E 24 9 35 26
F 10 12 53 41
G 35 22 24 2
H 40 19 19 0
I 15 12 48 36
J 4 59 59 0
K 6 63 63 0
2013 Lew Hofmann