Professional Documents
Culture Documents
is the rating of i
th
DER in KW, C
cup
is the
capital cost of i
th
DER in Rs/KW and PIAF
is
present value annuity factor for a life of i
th
DER.
Annualised net replacement cost comes into picture to
account the cost of replacing a component with new
one whose life (I
-
N
I=1
PvAF
I
rcp
PvAFP
(6)
Where FIAF
.
The annualised O&M cost is given by,
IC
o&m
unn
= |C
onm
(E
unn
) +C
0
|
N
=1
. A
(7)
A
.
Annualised fuel cost:
The cost of the fuel required by a DG is normally
accounted under this cost. But to find amount of fuel
needed it is required to find a relation between energy
generated and fuel needed. This relation can be
derived from the data provided by the manufacture.
Annualised fuel cost is given by,
IC
]ucI
unn
= c
. F
unn
N
DGM
=1
(8)
Where c
unn
can be obtained as
F
unn
= o
(E
unn
)
2
+b
(E
unn
) +c
(9)
However the constants o
, b
, c
unn
). The energy output from fuel based
DGs during any interval of a day depends on the
optimal share. The annual energy output is given by,
E
,]ucI
unn
= S6S - _P
]ucI
(]). I
]=1
_ (12)
Where I, size of the interval and D is number of
intervals. These two are related as, - I = 24
WTG are analysed using aerodynamic modelling [2].
The mechanical power developed by the turbine rotor
of a WTG is given by,
P
mcch
=
1
2
- nR
2
-
p
u
p
std
- (u
]
)
3
- p
std
(1S)
Where,
R = Rauius of the winu tuibine iotoi,
p
std
= stanuaiu aii uensity,
p
u
= Bensity of the aii in the site,
u
]
= winu velocity in the inteival j.
The electrical power output of WTG system is given
by,
P
LIc
= P
mcch
- (p
gcncuto
- p
gcu & tubnc
)
The annual energy output available from WTG system
is given by,
E
wtg
unn
= N
wtg
- S6S - _P
LIc
]
- I
]=1
_ - p
conctc
wtg
(14)
The output power from solar photo voltaic cell is given
by
P: (t) = N
p
. Im(t). Im(t) (1S)
Where P: (t) is power generated by solar system, N
p
is the number of modules used in solar system. Im(t)
& Im(t) are the values of maximum voltage and
current of module in the interval t, respectively.
And the annual energy output from SPV cells is given
by,
E
sp
unn
= S6S - _P:(t) - I
]=1
_ - p
conctc
sp
(16)
The total annual energy supplied by the microgrid
given,
E
unn
= E
,]ucI
unn
=1
+E
wtg
unn
+E
sp
unn
(17)
Where is the number of DGs which require fuel.
Unlike fuel generators, WTG systems and SPV cells
are not always favourable to the load. Distributed
storage came into scenario to balance/match load and
450
unfavourable generation. In general the size of the
storage system is fixed by the level of back up
required. Battery storage system will supply power to
the load under power deficiency situations by storing
the power through charging under surplus power
situations. However the minimum level during any
interval should not be less than the desired backup
level. Like storage tanks, battery systems are modelled
using cumulative sum of energy acquired. This
cumulative sum during any interval is an indication to
the capacity remained in the battery bank. By
assuming fully efficient operation of batteries, SOC
(State of Charge) can be expressed as,
S0C(t) = (1 -o). S0C(t -1)
+(P
n
(t) -P
out
(t)) (18)
Where,
o is self discharging factor of battery storage system,
P
n
(t) = P
]ucI
(t) +P
sp
(t) +P
wtg
(t) +P
mpo
(t),
P
out
(t) = P
Ioud
(t) +P
cxpo
(t).
The maximum limit on the SOC is fixed by sizing and
the minimum is fixed by desired level of backup. The
constraints are formed by load balance equations,
maximum & minimum limit of the generators.
The output of any generator must not exceed its
rating. But rating of the unit is not known prior to
the optimization. Hence temporarily choose a
maximum limit say, the maximum available size
of the same unit in the market, i.e. P
u
t
P
u
mux
The output of any generator is non-negative, i.e.
P
u
t
u
Rating of i
th
DER is the maximum share that it has
to commit, i.e.S
= Hox(P
u
t
); t = 1 to 24
The status of the battery at any instant should be
greater than the energy required to desired back up
under dead source day, i.e. S0C(t)
Bockup
dcscd
Export of the power is not allowed during off-peak
hours, i.e. from 10pm to 6am [8]. This can be
modelled using a permission variable,
say cxpo(t). Where,
cxpo(t) = _
1; i cxport is ollowcJ
u; i cxport is not ollowcJ
Export cannot exceed the limits of the contract
during export allowed hours. i.e. Export
mn
Export(t) Export
mux
Power import should not happen in peak hours. i.e.
from 6PM to 10PM.
3. CASE STUDY
In order to conduct a case study a petrochemical
industry in India has been selected. The plant has two
standby generators along with 11KV utility connection
from local distribution company. In the plant site an
average wind speed of 6 to 6.5 m/s, in south-west
direction was recorded. Available wind power in KW
from a single 50KW WTG and solar power available
in KW from a 5KW SPV panel are given in appendix.
The load curve of the plant is highly nonlinear due to
switching operations various motors. The majority of
the load is motor-pump sets used to pump crude oil,
refinery output products to their respective storage
tanks, and filling the wells with water after extracting
crude oil (to maintain ecological balance). The load
curve is also given in appendix. The plant has two
standby units of each size 600 KW (i.e. 750KVA at
0.8PF) generators coupled to diesel and gas engines
respectively. An optimization study has been
conducted on this plant by considering the maximum
limit of export is 1500KW. After running optimal
sizing, it was found that a combination of 100, 5KW
SPV panels and 10, 50KW WTG systems are optimal
to install in the plant.
4. RESULTS & CONCLUSIONS
Optimal Scheduling of the existing units after
installing WTG, Battery storage and Solar PV systems
against the load is shown figure. Depending upon the
choice given by the operator, the optimization package
will look for the possibility of power import from and
export to utility. Here it is considered that a backup
capacity of 50% of the peak load is required for one
hour. The results obtained were quite encouraging,
since storage systems (battery) are charging in the
excess power situations and contributing the same in
peak and export hours. In spite of the standby units, it
is economical to import power from the utility during
451
off-peak hours. Even if the load is less in off-peak
hours, the battery systems are scheduled to charge so
as to use the same power at peak hours. Here it is also
assumed that the battery systems installed will have
self discharging factor of 0.01% per interval.
According to local utility norms export should not
exceed 1500KW and minimum limit is 250KW and
export is allowed only in peak hours. In Figure1
negative bars reflect the charging of storage system.
The optimal sizing on the plant under case study suggested
that a combination of 100 SPV cells of each 5KW & 10
WTG sets of each 50KW is optimal to install. Optimal
scheduling study reported that unit cost of energy after
installing aforementioned combination decreases to Rs
1.15/KWH. But neither WTG nor SPV alone can give this
price. The unit cost of energy after installing WTG sets
alone is Rs. 2.05/KWH whereas SPV cells alone is
2.10/KWH.
Figure 1: Optimal scheduling of the plant after installing WTG & SPV systems.
5. REFERENCES
[1] www.leonardoenergy.com
[2] R. Yokoyama, N. Saito, Modelling and Evaluation of
Supply Reliability of Microgrids including PV and Wind
Power, IEEE-P&E, 2008
[3] Daniel J. Cox, Tom Davis, Distributed Generation
and Sensing for Intelligent Distributed Microgrids,
proceedings of IEEESMC (International Conference on
System of Systems Engineering), Los Angeles, CA, USA
- April 2006, pp 179-183.
[4] H.Asano, S.Bando, Economic Evaluation of
Microgrids, IEEE 2008.
[5] In-Su Bae and Jin-O Kim, Reliability Evaluation
of Customers in a Microgrid, IEEE Transc- Power
Systems, Vol. 23, NO. 3, August 2008, pp 1416-
1422.
[6] A. P. Agalgaonkar, C. V. Dobariya, M. G. Kanabar,
S. A. Khaparde, and S. V. Kulkarni, Optimal sizing of
distributed generators in micro-grid, Paper No. 349,
IEEE Power India Conference, April 10-12, 2006, New
Delhi.
[7] http://certs.lbl.gov/certs-der-micro.html
[8] www.powermin.nic.in
[9] http://www.rrbenergy.com/
[10] http://www.vestas.com/
-500
0
500
1000
1500
2000
2500
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
IMPORT
BAT
SHARE
SOLAR
SHARE
GAS
SHARE
WIND
SHARE
DISEL
SHARE
LOAD
EXPORT
452
Figure A: Hourly data of
Figure B: Hourly
42
44
46
48
50
1 2 3 4 5 6
P
o
w
e
r
i
n
K
W
0
1
2
3
4
5
6
1 2 3 4 5 6
P
o
w
e
r
i
n
K
W
0
200
400
600
800
1000
1200
1 2 3 4 5 6
L
o
a
d
i
n
K
W
APPENDIX
wind power available from a 50 KW WTG on a typical sunny day at pl
y data of power available from a 5KW SPV cell on a sunny day at plant
Figure C: Hourly load data of the plant
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2
Time of the day
7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time of the day
6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time of the day
ant site
t site.
21 22 23 24
21 22 23 24
21 22 23 24
453