Professional Documents
Culture Documents
1.1 Performance Bond as per Clause 37 ( From 203A) 1 L/S 14,965.00 14,965.00 14,965.00 10,000.00 10,000.00 10,000.00 4,965.00
1.2 All Insurances as per clause 32, 33, 34, 35 and 36 (Form 203) 1
L/S 39,977.33 39,977.33 39,977.30 34,298.51 34,298.51 34,298.50 5,678.80
1.3 Contractor's Site Agent and Superintendence as per Clause
1.12 of the specification. 1 L/S 75,000.00 75,000.00 75,000.00 50,000.00 50,000.00 50,000.00 25,000.00
1.4 Establishment of office for the S.O.'s staff as per Clause 1.15.
The site office with all furniture and fittings shall become the
property of the Contractor at the end of Contract :-
1 L/S 22,000.00 22,000.00 22,000.00 15,000.00 15,000.00 15,000.00 7,000.00
(a) Alternative A : JKR design of type * or
(b) Alternative B : Portable cabin type *
* Delete whichever is not applicable.
1.5 Maintenance of office for the S.O.'s staff as per Clause 1.15
1 L/S 8,050.00 8,050.00 8,050.00 7,500.00 7,500.00 7,500.00 550.00
1.6 Establishment and removal of Contractor's office,
accommodation, stores, etc. 1 L/S 12,000.00 12,000.00 12,000.00 12,990.00 12,990.00 12,990.00 -990.00
1.7 Maintenance of Contractor's Office, accommodation, stores,
etc. 1 L/S 8,000.00 8,000.00 8,000.00 15,000.00 15,000.00 15,000.00 -7,000.00
1.8 Provide and maintenance of two (2) nos. of handphone for the
exclusive use of the S.O. and his staff throughout the duration
of the contract 1 L/S 9,200.00 9,200.00 9,200.00 3,000.00 3,000.00 3,000.00 6,200.00
1.9 Allow for all telephone charges incurred throughout the
duration of the contract period 1 Prov. Sum 12,000.00 12,000.00 12,000.00 5,000.00 5,000.00 5,000.00 7,000.00
1.10 Establishment of site laboratory and provide competence
laboratory technician to carry out all tests as directed by the
S.O. complete with all equipement as per Clause 1.18. The
sitelaboratory including equipments shall become the property
of the contractor at the end of contract period and all shall be
removed from site upon completion
1 L/S 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 -
1.11 Ditto - Allow for maintenance 1 L/S 10,000.00 10,000.00 10,000.00 12,500.00 12,500.00 12,500.00 -2,500.00
1.12 Setting out and levelling works including provision of chainmen
and survey instruments as per Clause 1.19 1 L/S 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 -
1.13 Provide all necessary machinery, labour, material etc. to
construct and maintain temporary road diversions including a
temporary bridge as per Clause 1.20 and as specified in the
drawing and provide all necessary temporary access to the
exisiting adjoining roads at all sites as directed by S.O
1 L/S 10,350.00 10,350.00 10,350.00 9,000.00 9,000.00 9,000.00 1,350.00
1.14 Allow for make good the access to all the affected existing
adjoining roads including filling and compaction with approved
suitable materials, road pavement, close turfing to slopes,
drainage, etc. including supply of labour, all materials,
machineries, transport, etc as directed by S.O.
1 L/S 5,750.00 5,750.00 5,750.00 5,000.00 5,000.00 5,000.00 750.00
1.15 Water and Electricity Supply required as per Clause 1.22. 1 L/S 8,050.00 8,050.00 8,050.00 6,300.00 6,300.00 6,300.00 1,750.00
1.16 Provide Project Signboard as per Clause 1.23 2 No 5,000.00 5,000.00 10,000.00 4,000.00 4,000.00 8,000.00 2,000.00
1.18 Provide one (1) no. Cable Fault Detector for locating existing
public utilities and services to ensure zero failure of existing
services. The Contractor's shall furnish utility mapping to the
Government as directed by the S.O. The equipment shall
become the property of the Government. 1 No. 28,750.00 28,750.00 28,750.00 20,000.00 20,000.00 20,000.00 8,750.00
1.19 Provide for the exclusive use of the S.O., one (1) no. of new
digital camera including all consumable items as specified and
shall become the property of the Government at the end of the
contract. 1 No. 6,000.00 6,000.00 6,000.00 3,000.00 3,000.00 3,000.00 3,000.00
1.23 Provide for clearing of sites on completion. 1 L/S 3,162.50 3,162.50 3,162.50 2,750.00 2,750.00 2,750.00 412.50
(a) Safety Helmets 8 No. 34.50 34.50 276.00 30.00 30.00 240.00 36.00
(b) Industrial Safety Boots 8 Pair 172.50 172.50 1,380.00 150.00 150.00 1,200.00 180.00
(c) Raincoats 8 No. 32.20 32.20 257.60 28.00 28.00 224.00 33.60
(d) Umbrellas 10 No. 17.25 17.25 172.50 15.00 15.00 150.00 22.50
1.27.1 Provide two (2) nos. Of brand new project vehicles for
exclusive use of the S.O. and his staff as specified in the
specifications. Type E shall become properties of Government
and Type A shall be reverted back to Contractor upon issuance
Certificate Defect Liability Periods.
2 No. 105,000.00 105,000.00 210,000.00 218,623.00 218,623.00 218,623.00 -8,623.00
1.28 REPORTS