For the NorthMet Mining Project and Land Exchange March 13, 2014 Comment 1. Executive Summary, p. ES-7 The third paragraph states that the United States Army Corps of Engineers (USACE) and the Minnesota Department of Natural Resources (MDNR) studied the original NorthMet Proj ect Proposed Action between 2005 and 2009. Use of the defined term NorthMet Project Proposed Action in this context is confusing because the proposed action studied in the Draft EIS was substantially different than the proposed action being studied in the SDEIS. To avoid confusion over the nature of the alternatives studied in the two documents, PolyMet recommends changing the l anguage to state that Between 2005 and 2009, the USACE and MDNR evaluated PolyMets original mining proposal. Comment 2. Executive Summary, pp. ES-7 and ES-10 The terms NorthMet Mining Project and Land Exchange, rather than the defined terms NorthMet Proj ect Proposed Action and Land Exchange Proposed Action, are used on these pages. To avoid confusion, PolyMet recommends consistent use of the defined terms. Comment 3. Executive Summary, p. ES-9 Under the heading Cooperating Agencies, the SDEIS describes USEPAs responsibilities to review and comment on an EIS under Section 309 of the Clean Air Act. USEPA does this for all Environmental Impact Statements, even when it is not acting as a cooperating agency. USEPA has formally participated in the preparation of the current SDEIS as a cooperating agency, which is not the same thing as fulfilling its responsibilities under CAA Section 309. PolyMet recommends cl arifying this point by adding a sentence to this paragraph that explicitly notes EPAs status as a cooperating agency. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 2 of 70 Comment 4. Executive Summary, p. ES-23 The first sentence on this page indicates that completion of mining in the East Pit will occur in approximately year 11 after the start of mining. By contrast, the first sentence in the paragraph following the three bullet points states that mining in the East Pit will end by year 11 after the start of mining. The second statement is inaccurate. Mining in the East Pit will end approximately 11 years after mining, but not necessarily by year 11. Comment 5. Executive Summary, pp. ES-23 ES-24 In the last paragraph of the Mining Operations Section on page ES-23, the SDEIS defines process water in connection with the Mine Site. On page ES-24, the SDEIS refers to Pl ant Site process water. To clarify and define terms, page ES-23 should be changed to refer to Mine Site process water, and Plant Site process water should be defined by adding a sentence (see bold text below) to the l ast paragraph of the Processing Operations Section on page ES-23: Water seepage from the Tailings Basin would be collected by the groundwater containment system and sent to either the Tailings Basin pond or the Plant Site WWTP. All other water that is collected at the Plant Site, such as water used during processing, and water that contacts the plant site facilities (collectively referred to as Plant Site process water) will also be treated at the Plant Site WWTP. Treated water would be used to augment flows in the streams that would otherwise receive reduced fl ows because of the Tailings Basin groundwater containment system. Comment 6. Executive Summary, pp. ES-35 to ES-36 PolyMet recommends that the Executive Summary explicitly state that aluminum concentrations in the water, or the l owering of the hardness caused by storm water, represent natural or background concentrations and/or are the result of natural processes, not process water from the NorthMet Project. Comment 7. Executive Summary, pp. ES-38 ES-39 The SDEIS indicates that the NorthMet Project could potentially affect water quality by increasing solute concentrations above Cl ass 2B (aquatic life) standards. This appears PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 3 of 70 to refer to the aluminum and lead exceedances discussed earl ier in the Executive Summary. As explained in Comment 6 above, PolyMet recommends that the Executive Summary explicitly state that any such exceedances would be the result of background and/or naturally occurring concentrations or processes, not process water from the NorthMet project. Comment 8. Executive Summary, p. ES-40 The second full paragraph beginning with the phrase natural resources does not accurately summarize the discussion of cultural resources in the SDEIS. PolyMet recommends that the paragraph be replaced with the following: Cultural resources under NEPA can also include natural resources of cultural importance to the Bands. The Co-lead agencies have considered the effects of the Proposed Action on such resources, including 1854 Treaty resources, under NEPA. The Co-lead agencies have concluded that, whil e the Proposed Action has the potential to have effects on 1854 Treaty resources, construction and operation of the Proposed Action is not likely to significantly reduce overall avail ability of 1854 Treaty resources that are typically part of subsistence activities in the 1854 Ceded Territory. Comment 9. Executive Summary, p. ES-42 PolyMet addresses the issue of alternatives devel opment, which is discussed in this section of the Executive Summary, in Attachment A to these comments. Comment 10. Executive Summary, p. ES-43 PolyMet addresses the issue of the Land Exchange Proposed Action, which is discussed on these pages, in Attachment B to these comments. Comment 11. Executive Summary, p. ES-48 In Tabl e 1, the Land Use effects of the Proposed Connected Actions are described in the first bullet point as [n]o effects on land use that would require changes in ordinances or comprehensive forest plans. This language is confusing, given that the NorthMet Proj ect Proposed Action would invol ve the construction of an open pit mine. PolyMet proposes changing this language to say: Changes in land use would occur PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 4 of 70 after the Land Exchange Proposed Action and would not require changes in ordinances or comprehensive forest pl ans. Comment 12. Executive Summary, p. ES-52 Although the co-lead agencies have concluded that a segment of the Beaver Bay to Lake Vermilion Trail is an eligible historic property, the SDEIS alternates between referring to the BBLV Trail and the BBLV Trail Segment. To ensure consistency with the co-leads eligibility determination, PolyMet recommends that the agencies consistently refer to the property as the BBLV Trail Segment. This comment applies throughout all Cultural Resources sections in the SDEIS. Comment 13. Executive Summary, p. ES-52 PolyMet recommends that the section of the chart dealing with Cultural Resources & Historic Properties be referred to simply as Cultural Resources since that term is inclusive of historic properties. Comment 14. Section 1.4.5, pp. 1-17 1-18 The second sentence in section 1.4.5, Financial Assurance, explains that financial assurance instruments covering the estimated costs of recl amation must be submitted to and approved by the MDNR. As discussed elsewhere in the SDEIS, Minnesota non- ferrous mining rules also require that that financial assurance estimates be updated annually. PolyMet recommends noting that fact here. Comment 15. Section 2.3.2.2, p. 2-5 The first sentence in Section 2.3.2.2, Revised Proposed Action and Alternatives, states that the NorthMet Project Proposed Action has changed greatly since the rel ease of the DEIS. The use of the phrase changed greatly is ambiguous. The modifications to the proposal studied in the DEIS are described in detail elsewhere in the SDEIS. PolyMet accordingly recommends revising the first sentence in Section 2.3.2.2 to read: As a result of input from the public, Cooperating Agencies, and the Co- lead Agencies via the workgroups, and additional modeling and impact analyses, PolyMets mining proposal has been modified since the rel ease of the DEIS. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 5 of 70 Comment 16. Section 2.4.2, p. 2-8 The second bullet point in Section 2.4.2, Adequacy Determi nation/Records of Deci sion, states that the USACE will issue a ROD [f]ollowing a 30-day comment period. Under NEPA, the 30-day period following issuance of a Final EIS is not a comment period. Rather, under 40 C.F.R. 1506.10(b), agencies are simply prohibited from making a decision on the proposed action until 90 days after publication of a notice of availability for a draft EIS, or 30 days after publication of a notice of availability for a final EIS. The Council on Environmental Quality regulations do not require agencies to solicit comments on the FEIS during this 30-day waiting period. Comment 17. Section 2.5, p. 2-8 The first bullet on this page does not specify which permits would be transferred to PolyMet. The Minnesota Pollution Control Agency has stated that the NPDES permit for the Tailings Basin would not be transferred. Instead, a new permit would be issued. Comment 18. Section 3.1.1.5, p. 3-3 The south seepage management system is not mentioned at all in this section. This is a rel ativel y new engineering feature that was constructed as part of the Consent Decree. It should be listed as part of the existing infrastructure, since it is already in place. Comment 19. Section 3.2.1, p. 3-7 The fifth bullet on this page refers to temporary features that will be removed and reclaimed before or at cl osure, including roads. It is important to note, however, that not all of the roads will be removed or reclaimed, as some are needed for the post-cl osure period. Comment 20. Section 3.2.1, p. 3-13, Table 3.2-1 (Column: NorthMet Project Proposed Action, Row: Plant Site) The fourth bullet on this page refers to a bentonite layer on top of the Tailings Basin to restrict oxygen and water infiltration with pond. PolyMet recommends clarifying that there is a bentonite layer on the outer dam slopes during construction and that, during PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 6 of 70 closure, a bentonite layer will be added to the top of the Tailings Basin. As currently written, the reader may incorrectly assume that a bentonite layer will be added at construction, below the new tailings. Comment 21. Section 3.2.1, p. 3-17, Table 3.2-2 Recl amation of the Category 1 Stockpile is schedul ed to begin in Year 14. As currently written, reclamation of the Category 1 Stockpil e is included only in Years 16-20. It should also be included in Years 11-16. Comment 22. Section 3.2.1, p. 3-17, Table 3.2-2 The movement of waste rock from the Category 2/3 stockpile to the pit will be compl eted by the end of operations (Year 20). As currently written, the SDEIS incorrectly indicates that this activity will occur after year 20. Comment 23. Section 3.2.2.1.1, pp. 3-23 3-31, Figures 3.2-5 through 3.2-9 The transmission lines are not shown correctly on these figures. The figures should show a connection between the transmission line south of the Central Pit and the line south of the Category 1 stockpile. Comment 24. Section 3.2.2.1.1, p. 3-31, Figure 3.2-9 The process water piping from the Category 1 Stockpile should connect to the WWTF. The drainage from the Category 1 Stockpile Groundwater Containment System will be treated at the WWTF. Comment 25. Section 3.2.2.1.7, p. 3-43, Table 3.2-7 This table is titled Key Characteristics of Overburden and Waste Rock Management. However, it does not include any information about overburden management. The Category 2/3 and 4 stockpiles will be used to store saturated overburden; however, there is no indication of this in these sections and the Maximum Volume listed for these stockpil es only includes the volume of waste rock, not the maximum volume of the stockpil es. The peat and unsaturated overburden will be stored in the Overburden Storage and Laydown Area (OSLA), which is also not included in this table. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 7 of 70 Recommend either changing the table title to Key Characteristics of Waste Rock Management or update the table to include maximum capacity of the stockpiles for overburden storage, as listed in the Rock and Overburden Management Pl an (v5) Section 6.2 (Adaptive Management) and information about the OSLA. Comment 26. Section 3.2.2.1.7, p. 3-43, Table 3.2-7 The Category 1 Stockpile category shows that the maximum footprint of 526 acres is reached in year 6. However, the Category 1 Stockpile will reach the maximum footprint of 526 acres in Year 21, after it is reclaimed for the cover. The stockpil e footprint is 508 acres at the end of Year 6, when the footprint is built with slopes at an angle of repose. The stockpile is regraded to a 3.5:1 sl ope prior to pl acement of the stockpil e cover, which makes the final footprint 526 acres in Year 21. Comment 27. Section 3.2.2.1.7, p. 3-43, Table 3.2-7 The Phases of Devel opment section for the Category 4 Stockpile category shows waste from the Category 4 Stockpile being transferred to the East Pit in Years 11-20. However, the Category 4 Stockpile will be moved completely by Year 11 to allow for mining of the Central Pit to start that same year. Comment 28. Section 3.2.2.1.7, p. 3-44 The second paragraph on this page states that unsaturated overburden use would require MDNR approval. This is not accurate. Unsaturated overburden should not require approval from the MDNR. Comment 29. Section 3.2.2.1.7, p. 3-44 The fourth sentence of the third paragraph on this page should state: Applications for saturated overburden would include those where water contacting the construction material would be collected or drained to the mine pits, where it would be placed back below the water table or above a membrane liner system. There should be an or in this sentence. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 8 of 70 Comment 30. Section 3.2.2.1.8, p. 3-46, Category 1 Stockpile Water Containment System and Cover For clarity, PolyMet suggests editing the second paragraph and the beginning of the third paragraph in this section as follows: Figure 3.2-11 shows the containment system that would consist of a cutoff wall (a low permeability compacted soil hydraulic barrier extending down to bedrock) combined with a drainage collection system surrounding the perimeter of the stockpile near its toe. The cutoff wall would be constructed by excavating a trench down to bedrock backfilling it with a compacted soil material or by pl acing a manufactured geosynthetic cl ay barrier in the trench. Compacted soil The cutoff wall material would have a hydraulic conductivity specification of no more than 1x10-5 centimeters per second (cm/sec). Comment 31. Section 3.2.2.1.8, p. 3-47 In the first paragraph, the description of the Category 1 Stockpil e groundwater containment system does not adequately describe the sumps. There are two sumps: one at the northeast corner and one on the south side, al ong the center of the stockpile. To more accurately describe the system, Pol yMet recommends making the following changes: Stockpile drainage collected in the sumps would be conveyed to a low point near the northeast corner of the stockpil e. From the sumps, there, a non-perforated pipe would convey the drainage to a collection sump where it would be pumped to the WWTF. Comment 32. Section 3.2.2.1.10, p. 3-63, Proposed Action and Alternatives The l ast sentence in the paragraph under the heading Reclamation Planning correctly states that PolyMet will submit an annual Contingency Recl amation Plan pursuant to Minnesota Rul es 6132.1300. In the interest of completeness, the paragraph should also note that the rul es require PolyMet to provide financial assurance sufficient to carry out that recl amation plan. Comment 33. Section 3.2.2.1.10, p. 3-63, Rail Transfer Hopper The second paragraph inaccurately refers to disposal of material (remaining ore and sediment from ditches and process water ponds) in the West Pit. This material would be PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 9 of 70 disposed in the East Pit, as described in Section 2.1.2 of the Reclamation Plan (v3) (Rail Transfer Hopper). Comment 34. Section 3.2.2.1.10, p. 3-64, Mine Pit Reclamation The fifth sentence of the second paragraph on this page refers to the overburden sloping as height-to-vertical ratio of 2.5:1. Height and vertical mean the same thing (i.e., both refer to the vertical plane). PolyMet suggests changing this to read either horizontal-to-vertical or l ength-to-height. Comment 35. Section 3.2.2.1.10, p. 3-64; Section 3.2.2.3.10, p. 3-123 On page 3-64, the SDEIS states: The WWTF would be upgraded to include RO treatment to achieve an effluent with a sulfate concentration of less than 10 mg/L. Similarly, the SDEIS states on page 3-123: The WWTP would be constructed south of the Tailings Basin near the coarse-crusher and would include a RO unit designed to achieve a sulfate concentration of 10 mg/L in effluent. The design of the WWTP could be adjusted to accommodate varying influent streams and discharge requirements. It is not cl ear when reading the two statements copied above that the water treatment goal for the effluent sulfate concentration of 10 mg/L is based on meeting the current 10 mg/L sulfate standard for waters used for the production of wild rice (Minnesota Rule 7050.0224, Class 4A water quality standard). To clarify, and because that standard is subject to adjustment, the statement to achieve an effluent sulfate concentration that meets the sulfate standard for waters used for the production of wild rice should be used instead of to achieve an effluent with a sulfate concentration of less than 10 mg/L. Comment 36. Section 3.2.2.1.10, p. 3-65, Stockpile Reclamation The last sentence inaccurately states state the Category 4 Stockpile would be compl etel y removed by year 12 to allow mining in the Central Pit. The Central Pit mining begins in Year 11, as stated earlier in the SDEIS (such as Tabl e 3.2-4). Therefore, the Category 4 Stockpil e would be completely removed by year 11. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 10 of 70 Comment 37. Section 3.2.2.1.10, p. 3-65 The second paragraph describes recl amation of the Ore Surge Pile as any remaining material would be relocated to the West Pit after operations cease. However, no material will be disposed of in the West Pit. As described in Section 7.2.2 of the Rock and Overburden Management Plan (v5), any material remaining in the Ore Surge Pile at the end of operations will be transported to the Process Pl ant for processing or disposed of in the East Pit. Comment 38. Section 3.2.2.1.10, p.3-71, Watershed Restoration The fifth paragraph on this page, which lists all ponds that would be either filled or converted to wetlands, should include the Rail Transfer Hopper Pond. Comment 39. Section 3.2.2.1.10, p. 3-72, Proposed Action and Alternatives The fourth paragraph under the heading Water Management states that [b]ased on the current GoldSim P90 model predictions, treatment activities could be required for a minimum of 200 years at the Mine Site . . . . This statement is inaccurate and inconsistent with the discussion of the GoldSim water quality modeling elsewhere in the SDEIS. Comment 40. Section 3.2.2.2.2, p. 3-83, Existing Conditions This section inaccurately describes both the existing Cliffs Erie railroad and Dunka Road as being within the Transportation and Utility Corridor (see Figure 3.2-20). Cliffs Erie railroad actually is not within the Transportation and Util ity Corridor, as Figure 3.2- 20 accurately shows. Comment 41. Section 3.2.2.2.3, p.3-83, New Construction and Pre-production Development The bulleted list on this page should include construction of approximately 5,750-foot connecting track between the Cliffs Erie track and the existing PolyMet track that serves the Coarse Crusher Building at the Process Plant. This new track is accurately shown PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 11 of 70 on Figure 3.2-20 as a new construction Railroad Connection, but it is not described in this sections text. Comment 42. Section 3.2.2.3.4, p. 3-102, Beneficiation Process Water The SDEIS states: Throughout operations, the average annual makeup water drawn from Colby Lake would vary between 20 and 810 gallons per minute (gpm), with an average annual demand of 275 gpm. These numbers are inaccurate. The sentence should be revised to show a variation between 120 and 860 gallons per minute (gpm), with an average annual demand of 320 gpm. This section should also acknowl edge that additional Colby Lake water would be needed for stream augmentation. Comment 43. Section 3.2.2.3.10, p. 3-117, Engineered Water Controls In the second full paragraph on this page, PolyMet recommends providing additional details on the probable maximum precipitation (PMP) to make it clear that the likelihood of the emergency overflow channel being used is extremely low. PolyMet suggests editing the text to read: Pond elevation would be controlled by pumping any excess FTB pond water to the WWTP. An emergency overflow channel would be constructed as a backup means of controlling pond el evation, but discharge from the emergency overfl ow is not expected. The emergency overflow is provided for protection of the dams in the rare event that freeboard within the FTB is not sufficient to contain all stormwater. Such instances have the potential to occur in the event of a probable maximum precipitation (PMP) rainfall event or some fraction thereof. PMP rainfall events are rare and such an event has a low likelihood of being experienced during the life of the basin. The PMP does not have an assigned return period, but it is usually assumed by hydrologists to be on the order of 100 million to 10 billion years. Based on extrapolation of 72-hour rainfall depth data from US Weather Bureau-Office of Hydrology Technical Paper TP 49, and the assumed return period of the PMP of 100 million years, a 1/3 PMP event could occur roughly once in 1,000 years and a 2/3 PMP could occur once in 500,000 years. On this basis, even though there is a low likelihood of overfl ow, it is standard practice in dam design to accommodate even low probability overflows in a manner that protects the integrity of the dams. Given the low likelihood that there would ever be flow in the emergency overflow channel, it is not considered in the impact analysis. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 12 of 70 Comment 44. Section 3.2.2.3.12, p. 3-124, Proposed Action and Alternatives The third paragraph in Section 3.2.2.3.12, Reclamation and Long-term Cl osure Management, contains a list of reclamation objectives and post-reclamation activities. These terms are not used consistently with the applicabl e Minnesota Rul es. Under the non-ferrous rules, there are two distinct periods during reclamation: cl osure and post-cl osure. Cl osure is a process that begins when mining ceases, and ends when the recl amation standards identified in the reclamation plan have been achieved. Thus, while it may be reasonable to describe recl amation objectives for the NorthMet Project Proposed Action, it would be more accurate to indicate that these objectives will be achieved during the closure process. Post-closure maintenance activities are defined in the applicable rules as activities necessary to sustain recl amation. Post- closure maintenance activities begin when the cl osure process is complete, and end when active recl amation (e.g., water treatment plants) is no longer necessary to sustain reclamation standards. Thus, the activities described in this paragraph as post- reclamation are more accuratel y described as post-closure maintenance activities. The same comment applies to text on page 3-137. Comment 45. Section 3.2.2.4, p. 3-136, Proposed Action and Alternatives The first sentence of the third paragraph in Section 3.2.2.4, Financial Assurance, states that the engineering design and planning needed to calcul ate financial assurance is typically made availabl e during the permitting process and was not avail able at the time that this SDEIS was prepared. While this statement is generally accurate, it leaves a misleading impression that something is missing from the SDEIS. The paragraph should specify that NEPA and MEPA regulations do not require a discussion of financial assurance, and that PolyMet has voluntarily provided as much information as possible at the present time. Comment 46. Section 3.2.2.4.1, p. 3-137, Proposed Action and Alternatives The first sentence in the second full, non-bulleted paragraph on this page indicates that a final Reclamation Plan and Contingency Reclamation Cost Estimate will be based on studies final ized through permitting (pursuant to the EIS process). This reference to permitting pursuant to the EIS process is confusing and should be clarified. PolyMet is not certain what the SDEIS is trying to convey about the rel ationship between the permitting and EIS processes, but it should be noted that those are separate processes PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 13 of 70 and that information gathered during the EIS process will be used when agencies make permitting decisions. Comment 47. Section 3.2.3, p. 3-139, Alternatives PolyMet addresses the issue of alternatives devel opment, which is discussed in this section, in Attachment A to these comments. Comment 48. Section 3.2.3.3, p. 3-147, Development of the Northmet Project Proposed Action Tabl e 3.2-16 on page 3-147 provides a comparison of DEIS and SDEIS proposed actions. The table cell corresponding to the first row/first column of the table should state that Category 1 and 2 waste rock would be stored in a permanent lined/ soil- covered stockpile (Category 1/2 Stockpil e) north of the west pit (years 1-11). This edit makes clear that the SDEIS proposed action (described in the second column of the table as including a geomembrane cover system) will include a significantly improved cover system rel ative to the cover described in the DEIS. The third column of Table 3.2-16 should also acknowl edge the other improved outcomes rel ated to the addition of a geomembrane cover system to the Category 1 Stockpile. For example, the following additional bullet could be added to column three: Substantial reduction of stockpile seepage volume that will need to be collected and treated at the WWTF and significant improvement in West Pit water quality in cl osure. Comment 49. General comment on all Cultural Resources Sections in Chapters 4, 5 and 6 The SDEIS often references consultation with the Bands and SHPO, but fails to include PolyMet in these references. When discussing consultation under Section 106 of the NHPA, PolyMet, as the project proponent, should be identified as a consulting party and should be included in the explanation of the Section 106 process. Examples of where PolyMet should be noted/included as a consulting party include: the third to l ast sentence on page 4-259 (Section 4.2.8.3); the l ast full sentence on page 4-262 (Section 4.2.9.2.1); the second to last sentence in Section 4.2.9.2.2 on page 4-263; the second to last sentence in the second to l ast paragraph on page 4-264; the second to last paragraph on page 4-302; the last full paragraph on page 4-303; the third paragraph on page 4-555; the second and third paragraphs on page 5-479; the first full paragraph on page 5-482; the second to last full paragraph on page 5-483; the last paragraph on page 5-673; and the first paragraph on page 6-89. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 14 of 70 Comment 50. Section 4.2.2.1.2, p. 4-29, Table 4.2.2-2 This table lists the mercury TMDL target date for Sabin Lake, Esquagama Lake, and Colby Lake as 2015. The target date for those water bodies is 2025. (source: MPCA 2013. Minnesotas Final 2012 TMDL List (Section 303(d) Impaired Waters List. List approved by USEPA, July 25, 2013). Comment 51. Section 4.2.2.1.4, pp. 4-37 and 4-41 The monitored mercury concentration at PM-13 (Embarrass River) is inaccurately stated as 4.0 ng/L. In fact, PolyMets evaluation of the Plant Site at PM-13 used a background concentration of 3.1 ng/L. The same comment applies to Table 4.2.2-4, and the cumulative impact discussion at p. 6-33. Comment 52. Section 4.2.2.1.4, p. 4-37 The first two paragraphs of this section characterize the Tailings Basin mercury samples as consistent with baseline level s. This is not consistent with the later conclusion that the Tail ings Basin acts as a sink for mercury. Data from locations in and near the existing LTVSMC Tailings Basin is actually l ower than concentrations observed in the Partridge River and Embarrass River. This same comment applies to the second paragraph under Direct release of mercury to the Embarrass river watershed from the tailings basin in Section 5.2.2.3.3 on page 5-205. Comment 53. Section 4.2.2.2.1, p. 4-43 In the first sentence of the second paragraph, the order of Duluth Complex and Partridge River intrusion should be switched. The Partridge River intrusion is part of the Duluth Complex. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 15 of 70 Comment 54. Section 4.2.2.2.1, p. 4-43 In the second sentence of the second paragraph, the use of "Mesabi Iron Range" is misleading, as it could give the impression that the Duluth Complex is in direct contact with the Biwabik Iron Formation, which is not the case. PolyMet recommends listing a geologic unit (Virginia Formation) here, rather than the more vague term "Mesabi Iron Range." In addition to the cross-section shown on Figure 3.2-10, it would be helpful to include a plan view bedrock geology map to illustrate the geometric rel ationships between the various bedrock units. Comment 55. Section 4.2.2.2.1, p. 4-46, Groundwater Resources The second sentence of the second full paragraph states: Based on limited MDNR well records within the NorthMet Proj ect area, natural groundwater levels in the glacial till vary seasonally between 3 and 10 ft bgs. This sentence incorrectly states that the data is limited. Site-specific data on seasonal water level fluctuations is found in the Water Modeling Data Package Volume 1 Mine Site (referenced in the SDEIS as PolyMet 2013i). PolyMet 2013i provides information on water level fluctuations observed in 24 wells compl eted in the glacial till at the Mine Site, some with over nine years of water level measurements. Water level fluctuation varies between wells, but the overall range observed in a single well is typically less than 4 ft. Comment 56. Section 4.2.2.2.1, p. 4-53 The range of dates cited in the bullets listed under Baseline Groundwater Quality is inconsistent with the groundwater data used for water quality modeling. For example, 2012 data from MW-05-02, MW-05-08, and MW-05-09 were used for the model ing. PolyMet recommends removing the dates from these bullets or revising the list so that range of dates is consistent with data used to devel op Tabl e 4.2.2-6. The range of dates for groundwater data used for the water qual ity modeling is as follows: Three older wells in the surficial aquifer, sampled from March 2005 through June 2012. 21 newer wells in the surficial aquifer, installed in November 2011 February 2012, sampled following installation through June 2012. Five observation wells in the upper 100 ft of the bedrock, sampled from 2006 to 2010 (current SDEIS text is correct for this bullet). PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 16 of 70 Four large-diameter bedrock wells, sampl ed during aquifer testing in 2005 and 2006. Comment 57. Section 4.2.2.2.1, p. 4-42, Table 4.2.2-6; Section 4.2.2.3.1, p. 4-94, Table 4.2.2-22 It is not cl ear how the baseline values that are shown in Tabl e 4.2.2-6, and used for comparison with the site-specific data, were selected. The Northeast MN baseline data appear to be derived only from the "unconfined buried Quaternary aquifer" category. However, the MPCA study also includes data for buried Quaternary artesian aquifers and Quaternary water table aquifers. Either the range shown in Tabl e 4.2.2-6 should refl ect data from all Quaternary aquifers in the MPCA report or the Final EIS should provide an explanation as to why only a certain subset of data presented is provided. Comment 58. Section 4.2.2.2.2, p. 4-61 The first paragraph describes USGS gage 04015475 as the flow record most representative of the Project area. However, this section also should acknowledge the presence of the recently-installed (for Teck American) flow gage at the Dunka Road crossing near the southeast corner of the proposed Mine Site (monitoring location PM- 3/SW003) and note that, while closer to the Mine Site, the short period of record is insufficient for use in the SDEIS. This gage also should be shown on Figure 4.2.2-1. Comment 59. Section 4.2.2.2.2, p. 4-67 The first paragraph discusses why the use of the l owest expected baseflow is conservative with respect to impacts to surface waters. The paragraph should acknowledge that the use of a higher modeled basefl ow would lead to higher recharge into groundwater, which would transl ate into faster solute transport times in groundwater (although not necessarily significantly varied peak concentrations). In addition, higher recharge would increase the expected groundwater inflow into the dewatered mine pits. Comment 60. Section 4.2.2.2.2, p. 4-74 In the first paragraph, the text describing existing upper Partridge River water quality should mention mercury and aluminum concentrations exceeding water quality standards. The text also describes dissol ved oxygen at SW002 as the only consistent PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 17 of 70 exceedences. PolyMet reads the term consistent as meaning that all samples at that location exceeded the standard, but that should be made more cl ear the text. The term consistent exceedences also appears in section 4.2.6.1.2 (page 4-220), and it should be used in the same way in that section. Comment 61. Section 4.2.2.2.2, p. 4-77, Table 4.2.2-14 There are multipl e inaccuracies in Table 4.2.2-14 that should be addressed: 1. The average concentrations presented in Table 2.2.2-14 should include 2012 data. The 2012 data is included in Large Tabl e 10 of the Water Modeling Data Package, Volume 1 Mine Site v12. 2. The number of samples at SW004a and SW004b in footnote 5 is incorrect and should also include 2012 samples. The 2012 data omitted from the number of samples is included in Large Tabl e 10 of the Water Modeling Data Package, Volume 1 Mine Site v12. The number of samples at SW004a and SW004b should be 12 samples for each location. 3. The ranges of concentrations presented in Table 4.2.2-14 do not include the 2012 data and, therefore, may be inaccurate if maxima or minima occurred in 2012. 4. The range provided for mercury concentrations (<0.0025 ng/L to 0 ng/L) is not accurate; mercury concentrations provided in the Water Modeling Data Package Volume 1 Mine Site v10 range from <0.5 ng/L to 18.5 ng/L. Comment 62. Section 4.2.2.2.2, p. 4-77, Table 4.2.2-14, Section 4.2.2.2.2, p. 4-80, Table 4.2.2-15, Section 4.2.2.2.2, p. 4-87, Table 4.2.2-18, Section 4.2.2.3.2, p. 4- 123, Table 4.2.2-29, Section 4.2.2.3.2, p. 4-132, Table 4.2.2-35 The minimum values in constituent concentration ranges shown in these tables are presented as less than half the minimum detection limit. Minimum concentrations (when not detected) should be presented consistently as either l ess than the minimum detection limit (e.g., < 10 mg/L) or as a numeric value equal to half the minimum detection limit without a less than symbol (e.g., 5 mg/L). If the latter approach is used, the footnotes should note that minimum values represent one half the detection limits. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 18 of 70 Comment 63. Section 4.2.2.3.1, p. 4-95 The third sentence of the fourth paragraph presents a recharge rate of 0.3 in/yr, which is inconsistent with the mean value of 0.61 in/yr used in the GoldSim model. As discussed in Sections 5.2.1.3.1 and 5.2.1.3.2 of this document, average net recharge in the Embarrass River watershed is estimated at 0.61 inches per year. A recharge rate of 0.3 in/yr represents the minimum value used in the GoldSim recharge distribution (PolyMet, 2013j; Section 5.2.1.3.2); however, it would be more appropriate to use the average value, rather than the minimum value, for the groundwater flow discussion in the SDEIS. Comment 64. Section 4.2.2.3.1, p.4-110, Table 4.2.2-23 Data for the Cell 1E pond should be included in this table. Cell 1E pond data are shown in Large Tabl e 7 of the NorthMet Project Water Modeling Data Package, Volume 2 - Plant Site, Version 9, March 1, 2013. Comment 65. Section 4.2.2.3.2, p. 4-121 Regarding the first sentence, PM-13 is not just downstream of the Heikkila Lake tributary. It is more accurate to say PM-13 is downstream of the Unnamed Creek tributary. Comment 66. Section 4.2.2.3.2, p.4-121 In the second sentence, it is unclear what low flows refers to. Based on the low fl ows presented in Tabl e 4.2.2-27, PolyMet assumes the co-leads are referring to baseflow. This should be cl arified. Comment 67. Section 4.2.2.3.2, p. 4-122 In the third paragraph, the text describing the number of samples collected at PM-12.2, PM-12.3, and PM-12.4 should include data from 2012 (2012 data appears to be included in subsequent Table 4.2.2-29). The 2012 data is included in Large Tabl e 4 of the Water Modeling Data Package, Volume 2 Plant Site v9. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 19 of 70 Comment 68. Section 4.2.2.3.2, p. 4-125, Table 4.2.2-30 The row for PM-12 should reflect that data was collected in 2012 at this location. Comment 69. Section 4.2.2.3.2, p. 4-129, Table 4.2.2-34 Data for PM-11 should not be presented in Table 4.2.2-34, which is titled Summary of Surface Water Quality Monitoring Data for the Tailings Basin Surface Seeps. Monitoring location PM-11 is located downstream of the Tailings Basin on Unnamed Creek and is not representative of a seep. Data for PM-11 should be included in Table 4.2.2-35 (which includes tributary streams) instead. Comment 70. Section 4.2.3.2.2, p. 4-166, Hydrology, Wetland Vegetation, and Community Types In the second to last sentence of the first full paragraph, it should be cl arified that seepage and dead spruce trees are not a cause-and-effect rel ationship. There are many beaver dams in the area that likely play a rol e in the presence of dead spruce trees. Comment 71. Section 4.2.4.2.1, p. 4-174 The last sentence under National Hierarchical Framework of Ecol ogical Units reads: Inclusion of the One Hundred Mile Swamp would likely complete representation of prominent ELTs in LTA 212Le11. Polymet suggests clarifying by revising this sentence is to say: The One Hundred Mile Swamp and the two other sites surveyed provide a compl ete representation of the prominent ELTs present within LTA 212Le11. Comment 72. Section 4.2.7.2, p. 4-252, Table 4.2.7-1 Footnote 1 indicates it is a State standard, but the listed value is federal standard. The State 1-hr standard is 0.5 ppmv. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 20 of 70 Comment 73. Section 4.2.7.2, p. 4-252, Table 4.2.7-1 Regarding the entry for sulfur dioxide 3-hour, the table could be misunderstood as saying that the state and Federal secondary standard is 0.5. In fact, the state primary standard is 0.5, and state secondary state standards are as indicated by footnotes. This should be clarified in the Standard Type column and the footnotes. Comment 74. Section 4.2.3, p. 4-135, Wetlands The third sentence of the third paragraph suggests that PolyMet will submit a revised wetland permit application. In fact, Pol yMet has already submitted a revised wetland permit application, which appears as PolyMet 2013q. NorthMet Proj ect Revised Wetland Permit Application, Version 1. Issued August 19, 2013 in the references. Comment 75. Section 4.2.3.1, p. 4-139, Mine Site and Transportation and Utility Corridor The first sentence of this section references three figures for the location of the Mine Site, in rel ation to Iron Lake and the Laurentian Divide. However, none of the figures show Iron Lake or the Laurentian Divide. The text should be revised to account for this or the figures should be edited to include Iron Lake. This issue occurs in other sections as well, such as the first sentence of Section 4.3.3.1. Comment 76. Section 4.2.3.1.1, p. 4-148, Wetland Delineation and Classification The third sentence of the first paragraph should cite the USACE memo (USACE, May 2013) in addition to the baseline wetl and type evaluation. Comment 77. Section 4.2.3.1.2, p. 4-149, Hydrology, Wetland Vegetation, and Community Types The first sentence of the third paragraph reads as though vegetation types are indicative of pre-settlement conditions. However, this is misleading, as there has been a significant amount of l ogging disturbance throughout the mine site. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 21 of 70 Comment 78. Section 4.2.4.2.3, p. 4-179, Table 4.2.4-4, Endangered Plant Species The new Minnesota ETSC list became effective (August 19, 2013). Botrychi um pallidum (pal e moonwort) is not a state-endangered species anymore. Botrychium rugulosum (St. Louis grapefern) and Eleocharis nitida (neat spikerush) are not state-threatened anymore. All three plant species are now special concern, which means they are not protected under Minnesotas Endangered and Threatened Species Statute (MN Statute 84.0895). Sparganium glomeratum (clustered bur reed) is not a special concern species anymore, and has been removed from the Minnesota ETSC list. The text and Table 4.2.4-4 should be revised to reflect the new Minnesota ETSC list. Changes should be made throughout Section 4.2.4.2.3, including the Species Life Histories discussion, to make the information current and accurate. Comment 79. General comment in Sections 4.2.4, 4.3.4, 5.2.4 and 5.3.4 Scientific and common names are used inconsistently throughout these sections. PolyMet recommends using consistent terms throughout the document for cl arity. Comment 80. Section 4.2.4.2.1, p. 4-170 On page 4-170, there continues to be an inconsistency between the first paragraph under Habitat Types and the first sentence of the first paragraph under Plant Community Surveys. The first paragraph under Habitat Types states that upland- conifer mixed forest types are among the l east represented cover types. This is further supported by Table 4.2.4-1, which shows upland conifer-deciduous mixed forest as <1% of the Mine Site acreage for cover types. However, under Plant Community Surveys, the first sentence following Table 4.2.4-1 states that the primary cover types at the Mine site are mixed pine-hardwood forests on the uplands. Mixed pine- hardwood forest is an upl and conifer-deciduous mixed forest cover type. PolyMet recommends resolving this inconsistency by using MIH data in the table, rather than GAP. Comment 81. Section 4.2.4.2.2, p. 4-174, Invasive Non-native Plants The first sentence of the second paragraph under Invasive Non-native Pl ants states that a survey was conducted on mine sites al ong the Mesabi Iron Range, and that PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 22 of 70 some species are currently present. The text should clarify where (i.e., the Mesabi Iron Range or on the NorthMet Mine Site) these species are present. Similarly, in Tabl e 4.2.4-2, it is uncl ear how two of the three species with the highest percent occurrence are estimated to be uncommon on the site, while three of the five species with the lowest percent occurrence are estimated to be common on the site. This inconsistency should be corrected or expl ained. The EIS should also explain how estimated abundance at the Mine Site was determined, since the text says that no inventories of non-native invasives were conducted. Comment 82. Section 4.2.4.3.2, p. 4-193, Non-native Invasive Plants The first paragraph text states that no invasive species inventories have been conducted within the Transportation and Utility Corridor. However, the paragraph later discusses field survey data. This could be confusing. The text should clarify that the field survey data discussed was not a quantitative survey (i.e., not an inventory), but rather is part of a broader ETSC and qualitative vegetation survey conducted by Barr. Comment 83. Section 4.2.4.3.3, p. 4-192, Table 4.2.4-7, ETSC Species The text on page 4-192 names three ETSC species in Transportation and Utility Corridor, but Tabl e 4.2.4-7 only lists one of these species. This inconsistency should be resol ved. Comment 84. General Comment to Sections 4.2.5, 4.3.5, 5.2.5, 5.3.5 PolyMet recommends either substituting the word bat for the term Myotis or adding (bat) after Myotis. Comment 85. Section 4.2.5.1.1, p. 4-201, Canada Lynx The Canada lynx is a Minnesota special concern species effective August 19, 2013. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 23 of 70 Comment 86. Section 4.2.5.1.1, p. 4-201, Canada Lynx In the fifth paragraph, the statement that lynx critical habitat includes most of northeastern Minnesota is imprecise. Pol yMet recommends adding the clarification that the USFWS designated critical habitat does not include most of the Iron Range. Comment 87. Section 4.2.5.1.1, p. 4-203, Gray Wolf The last sentence of the third paragraph references forest and brush habitats but parenthetically cites MIHs 1 to 14. PolyMet believes the citation was intended to be MIHs 1 and 14. Comment 88. Section 4.2.5.1.1, p. 4-204, Bald eagle Regarding the last sentence of the third paragraph, there are no standing dead trees in the existing LTVSMC Tailings Basin. Comment 89. Section 4.2.5.1.3, p. 4-208, RFSS In the third paragraph, it should be noted that the northern Myotis (Myotis septentrionalis, Northern long-eared bat) was proposed as a federally listed endangered species by the USFWS on October 2, 2013. Comment 90. Section 4.2.5.1.4, p. 4-210 The second paragraph should reference Moose zone 3, not Moose zone 30. Comment 91. Section 4.2.5.2.2, p. 4-211 The fourth sentence of the second paragraph incorrectly states that the Tailings Basin is unlikely to be heavily used by wildlife. The Tailings Basin is a local refuge for herds of deer, small mammals and wol ves. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 24 of 70 Comment 92. Section 4.2.6.1.1, p. 4-214, Aquatic Biota The first sentence in the first paragraph references the Longnose, Wetl egs and Wyman creeks as surface water features in the Upper Partridge River Watershed. However, there is no discussion on these creeks or a reference to a previous discussion in the SDEIS. PolyMet recommends either providing a similar discussion of that provided for Mud Lake, Yelp Creek, and Second Creek on page 4-214 or explaining why such analysis is not provided. Comment 93. Section 4.2.6.1.1, p. 4-219, Aquatic Biota, Watershed Level Riparian Connectivity The second sentence uses the term watershed while the third sentence uses the term larger watershed. Pol yMet suggests expl aining the difference between a "watershed" and a "larger watershed." Comment 94. Section 4.2.6.1.3, p. 4-221, Aquatic Biota, Fish Communities The first sentence of the third paragraph should be revised to add Yelp Creek to the list of streams where no fish or macroinvertebrate community or habitat characteristics could be documented . . . . Comment 95. Section 4.2.6.3.3, p. 4-241, Table 4.2.6-11, Aquatic Biota The source of data for these stream surveys should be revised as Source: Breneman 2005, Barr 2011b, and MPCA 2011c. Barr 2011b is the source of the information for the PM sites. Comment 96. Section 4.2.9.1, p. 4-261 PolyMet recommends that the introductory paragraph state that the NHPA process is proceeding on a parallel path to the NEPA process, and that effects on cultural resources have also been considered and analyzed under NEPA. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 25 of 70 Comment 97. Section 4.2.9.1, p. 4-261 The l ast sentence of the introductory paragraph states: Cooperating agencies have not participated in production or endorsement of any components of the EIS or the NorthMet Project. This statement is not entirely accurate, since the tribes have participated in the production of components of the EIS rel ative to cultural resources as well as the Major Differences of Opinion. The EIS should describe the tribes participation in the devel opment of the EIS. Comment 98. Section 4.2.9.2.3, p. 4-269. The second-to-l ast paragraph is uncl ear, both with respect to whether it is discussing groundwater and/or surface water, and with respect to how that discussion fits into the APE anal ysis. Figure 4.2.9-5, which is not referenced in this paragraph, is a groundwater quality APE, but most of the paragraph discusses surface water quality. PolyMet recommends revising this paragraph to explain how groundwater and surface water affect the APE. Comment 99. Section 4.2.11.1.2, p. 4-349, Visual Resources The discussion of the NorthMet Projects impacts upon visual resources notes that tribal members exercise rights to hunt, fish, and gather on Superior National Forest lands near the Mine Site. However, it also states that [t]he frequency with which tribal members exercise these rights in portions of Superior National Forest with views of the Mine Site is not known. In particul ar because the Bands are cooperating agencies, they have had every opportunity to provide evidence of frequency. Accordingly, PolyMet recommends adjusting this language to state that there is no evidence that tribal members regul arly exercise their rights in this portion of the forest. Comment 100. Section 4.2.14.2.2, p. 4-373, Figure 4.2.14-3 The term Sensitive Fines is used on the Figure, yet neither Geotechnical Data Package, Vol. 1, Version 4, nor preceding versions use the name Sensitive Fines. April 12, 2013 Geotechnical Data Package, Vol. 1, Version 4 uses the name Fine Tailings/Slimes. This material type is missing from the Legend on the l ower l eft corner of Figure 4.2.14-3. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 26 of 70 Comment 101. Section 4.2.14.2.2, p. 4-373, Figure 4.2.14-3 Units and labels are missing from axes (e.g., el evation in feet amsl and distance in feet) and the dashed lines in the figures are not in the legend (l ayers of material). Comment 102. Section 4.3.3.1.1, p. 4-434, Hydrology, Wetland Vegetation, and Community Types In the first full sentence, fl oodplains should be cl early defined, and PolyMet recommends including a figure showing mapped floodplains with wetl ands. Comment 103. Section 4.3.3.2.1, p. 4-447, Table 4.3.3-4 The table combines coniferous bogs and coniferous swamps. PolyMet recommends separating these two wetland types here, in the same way that they are separated for discussions of the federal lands. This is also an issue in Tables 4.3.3-6, 4.3.3-8, 4.3.3-10, 4.3.3-12. Comment 104. Section 4.3.3.2.2, p.4-450, Table 4.3.3-6 The table contains inaccurate acreage for open bog and shallow marsh. Open bog should be 2.1 acres, and shallow marsh should be 84.1 acres. In addition, the third sentence under Tabl e 4.3.3-6 should also be edited from: Large bogs dominate much of the east-central portion of Tract 1 to the suggested Shrub swamps dominate much of the east-central portion of Tract 1. The current sentence is inaccurate because there are only 2 small bogs (2.1 acres total) on the Hay Lake parcel. Comment 105. Section 4.3.4.1.1, p. 4-469, Invasive non-native plants The first sentence states that non-native invasive species on the federal l ands are the same as the Mine Site because they occupy the same area. This is not accurate. The Mine Site is smaller than the federal lands. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 27 of 70 Comment 106. Section 4.3.4.1.1, p. 470, Table 4.3.4-5 In footnote 2, PolyMet suggests deleting the phrase additional populations may be present in more marginal, secondary habitat that was not surveyed, or in wetter areas. There is no evidence (no survey) of additional populations in marginal, secondary habitat, and the SDEIS should make that cl ear. Comment 107. Section 4.3.4.2.4, p. 4-477, Regional Forester Sensitive Species The second paragraph appears to suggest that there is a correl ation between the acreage of a given MIH cover type and the likelihood that an RFSS species that prefers that cover type will actually be present. This is not entirely accurate. The paragraph fails to take into account other qualitative factors that influence the likelihood of an RFSS species being present. PolyMet recommends revising the paragraph to state that the presence of RFSS species would be further influenced by the quality of the habitat availabl e, not just the quantity. Comment 108. Sections 4.3.5.2.1 and 4.3.5.2.5 In both of these sections, there is a contradiction between text under federal and state- listed species and the text under RFSS. The text under federal and state-listed species says that northern myotis and eastern pipistrelle are potentially present on Tracts 1 and 5. The text under RFSS states that only northern myotis is potentially present. This inconsistency should be resol ved. Comment 109. Section 4.3.5.2.1, Other wildlife species This section discusses species of tribal concern. This is not a legal category. PolyMet recommends del eting this phrase. Comment 110. Section 4.3.6, p. 4-521, Aquatic Species The first sentence in the second paragraph should be revised to read Some of tThe non-federal lands. . Not all of the non-federal lands have streams, creeks, rivers, or lakes on them. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 28 of 70 Comment 111. General Comment on all Land Exchange sections The Land Exchange analysis must review FEMA floodplains. Therefore, the Land Exchange sections should define whether the floodplains are FEMA or non-FEMA. For exampl e, the first sentence of the second paragraph in Section 4.3.6.2.1, p. 4-522, should be revised to read approximately 376 acres of non-FEMA floodpl ain. This change should be reflected throughout the Land Exchange sections. Comment 112. Section 4.3.6.2.3, pp. 4-531 4-541, Aquatic Species This paragraph incorrectly compares Coyote Creek with Stony River. These are not comparabl e systems. The Stony River is a higher order, more diverse aquatic system than the first order, headwaters Coyote Creek. It cannot be assumed that the conclusions drawn from the studies for Stony River are applicabl e to Coyote Creek. Comment 113. Section 4.3.6.2.5, p. 4-541, Aquatic Species, Surface Water Features The second paragraph is one sentence and cites MIH 14. Pol yMet recommends that this paragraph first provide some description of the MIH 14 before making the statement it currently contains. Comment 114. Section 5.2.2, p. 5-5, Water Resources The first sentence of the second full paragraph states that the groundwater containment system would capture at least 90 percent of seepage from the Tailings Basin. This is incorrect. The system will capture 100% of surface seepage and upwelled water, and at least 90% of seepage that remains as groundwater flow. Overall, 99% of seepage from both surface and groundwater will be captured. The sentence, as written, implies that the system will be less effective than it will be. Similarly, PolyMet suggests revising the first sentence in the second full paragraph on page 5-6 to read: PolyMet proposes a containment system that would capture about 99 percent of seepage from the Tailings Basin... PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 29 of 70 Comment 115. Section 5.2.2, p. 5-7 The 4th paragraph states: With the proposed design modifications and engineering controls, the water quality model predicts that the NorthMet Proj ect Proposed Action would not cause or increase the magnitude of an exceedance of the groundwater and surface water quality evaluation criteria at the P90 level for any of 28 solutes at 29 groundwater or surface water evaluation locations within the Partridge River and Embarrass River watersheds PolyMet proposes the following language: With the proposed design modifications and engineering controls, the water quality model predicts that the NorthMet Proj ect Proposed Action would not cause or increase the magnitude of an exceedance of the groundwater and surface water quality evaluation criteria at the P90 level for any of the 27 solutes and mercury (further addressed bel ow) at 29 groundwater or surface water evaluation locations within the Partridge River and Embarrass River watersheds Comment 116. Section 5.2.2.1.2, p. 5-19 The 3rd paragraph states: Within the water quality modeling, estimated concentrations for these six metals are compared to hardness-based standards at each model evaluation location and each model time step to determine compliance with the evaluation criteria. PolyMet proposes the following l anguage: Within the water qual ity modeling, modeled concentrations for these six metals are compared to hardness-based standards at each model evaluation location and each model time step to determine compliance with the evaluation criteria. Comment 117. Section 5.2.2.1.1, p. 5-20 The 4th paragraph states Methylmercury is much more of a problem than inorganic mercury, in that it can accumul ate to concentrations of concern in the aquatic food chain, it is more bioavailable than inorganic mercury, and it can bioaccumul ate in fish, wildlife, and humans. The term problem suggests a conclusion, when this sentence is actually describing concerns. PolyMet proposes the following language: Methylmercury is more of a concern than inorganic mercury, in that it can accumulate to concentrations of concern in the aquatic food chain, it is more bioavailabl e than inorganic mercury, and it can bioaccumulate in fish, wildlife, and humans. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 30 of 70 Comment 118. Section 5.2.2, p. 5-21, Mercury Evaluation Criteria The first sentence at the top of the page reads: Research suggests that total mercury concentrations in streams and methylmercury content in fish are roughly proportional within individual watersheds (USGS 2010), such that, for example, a 5 percent increase in total mercury in water would be expected to result in about a 5 percent increase in mercury content in fish within that watershed. This sentence should be changed to clearly state that the potential incremental change in fish mercury concentration is an evaluation criterion and that MPCAs Mercury Risk Estimation Method (MMREM) was used to assess the potential changes in fish mercury concentrations in nearby lakes. The MMREM is a method that relies on empirical fish contamination data, combined with the principl e of proportionality between mercury in fish and atmospheric deposition (MPCA 2006, MMREM guidance document). In addition, the following is noted with regard to the first sentence at the top of the referenced page in the SDEIS, and to the principle of proportionality. In the references section to the SDEIS, the USGS 2010 reference cited above l inks to the following web page: Some Ecosystems Will Respond to Reductions in Mercury Emissions. USGS July 29, 2010. 1 The first sentence on this webpage states: An international team of scientists investigating mercury cycling in an experimental watershed in Ontario, Canada, conclusivel y demonstrated at the ecosystem scale that changes in mercury loadings are expected to result in proportional or near proportional changes in mercury bioaccumulation in fish. PolyMet believes this conclusion of proportionality is not applicable to this proj ect for at least three reasons. First, the cited website summarizes the results from a study referred to as the Mercury Experiment to Assess Atmospheric Loading in Canada and the United States (METAALICUS) study, which was conducted on a headwater lake, not in a stream. The METAALICUS study itself cites that runoff dominated lakes (fl ow through systems) would not respond the same as a precipitation-dominated headwater lakes (Harris et al., 2007). Because a stream can also be thought of as a flow through system, it will not respond in the same way to increases or decrease in atmospheric deposition as a precipitation-dominated headwater lake. In other words, for a run-off dominated lake (flow-through system), the contribution of ambient (pre-existing) mercury from the watershed to the lake is much greater than the contribution of new mercury to the water surface. The same would be true of a stream wherein the new mercury from atmospheric deposition would be minor compared to the contribution of ambient mercury. In addition, Minnesotas Statewide Mercury TMDL (MPCA 2007, Section 4.1) states that The primary source of mercury to the states water bodies is atmospheric deposition, which is approximately uniform across the state. Mercury concentrations in 1 Available at http://toxics.usgs.gov/highlights/mercury_response.html . PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 31 of 70 fish, however, vary widely on both large and small scal es. . Nutrient l oadings, hydrology, presence/absence of wetl ands and other factors contribute to different fish mercury concentrations in lakes that are rel ativel y cl ose to each other. Therefore, using the concept of proportionality is expected to result in an overestimate of the potential incremental change in fish mercury concentrations due to an individual projects mercury air emissions as the concept of proportionality does not seem to be supported for individual streams or l akes based on the avail able data. Second, steady state was not reached during the 3 year METAALICUS study. Ghorpade (2010 thesis) identifies that 8 years after the study started, steady state was not reached and the researchers are not able to predict when steady state might be reached. Therefore, the assumption of proportionality based on the METAALICUS study is uncertain. Third, there are several USGS reports that indicate a relationship between filtered methyl mercury concentration in stream water and fish mercury concentration. However, likely because of the watershed specific factors affecting methyl ation of mercury, there is not a USGS report, 2010 or otherwise, that identifies a statistically significant relationship between total mercury in surface water and fish mercury concentrations. Comment 119. Section 5.2.2.2.1, p. 5-23, Figure 5.2.2-6 Modeling results for location UC-1 are not presented in the SDEIS. Therefore, this location should not be shown in Figure 5.2.2-6 as a model evaluation location. Comment 120. Section 5.2.2.2.1, p. 5-26 The 3rd and 4th sentences of the first paragraph should be cl arified to reflect that the Plant Site MODFLOW model was not calibrated to baseflow in the Embarrass River, nor was the model used to estimate baseflow. Comment 121. Section 5.2.2.2.1, p. 5-26 Regarding the last sentence on the page, the regional MODFLOW model calibration was not updated to the revised baseflow estimates from XP-SWMM. The Mine Site Water Modeling Data Package Attachment C provides: The regional model calibration was not updated because the original calibration did not incorporate a baseflow estimate and previous sensitivity analysis indicated that the local-scal e model results were not sensitive to the l ateral boundary conditions that were defined by the regional PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 32 of 70 model (Barr, 2007). Therefore, the perimeter boundary conditions for the l ocal-scale model remained unchanged. Comment 122. Section 5.2.2.2.1, p. 5-41, Table 5.2.2-9 The footnote on the Specific yield column of the table only applies to the surficial deposits, not the entire column in the data table. Comment 123. Section 5.2.2.2.3, p. 5-47 The 1st paragraph states: GoldSim was programmed with a suite of complex algorithms to estimate the rel ease of contaminants from mine facilities (i.e., sources) and their transport to groundwater and surface water evaluation locations. PolyMet suggests the following language: GoldSim was programmed with a suite of algorithms to estimate the release of contaminants from mine facilities (i.e., sources) and their transport to groundwater and surface water evaluation locations. Comment 124. Section 5.2.2.2.3, p. 5-51 The 1st paragraph states: The onset of acidic pore water is also probl ematic, as these conditions cause the rate of sulfide oxidation to increase and the concentration of metals to increase as precipitates dissol ve. PolyMet suggests the following revision: The onset of acidic pore water is also of concern, as these conditions cause the rate of sulfide oxidation to increase and the concentration of metals to increase as precipitates dissolve. Comment 125. Section 5.2.2.2.3, p. 5-52, Water Quality Modeling (GoldSim), NorthMet Waste Rock Geochemistry The bulleted list near the middle of the page provides slightly incorrect sulfide sulfur ranges for the waste rock cl assification criteria, as well as an incorrect reference for this information. The sulfide sulfur cl assification criteria for the categories of waste rock should be revised as follows: Category 1 sulfur content l ess than or equal to 0.12%. Category 2 sulfur content greater than 0.12% and less than or equal to 0.31%. Category 3 sulfur content greater than 0.31% and less than or equal to 0.60%. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 33 of 70 Category 4 sulfur content greater than 0.60%. Categories 2 and 3 are combined to produce Category 2/3 with sulfur content greater than 0.12% and l ess than or equal to 0.60%. This information can be found in Section 4.4.1 of the Waste Characterization Data Package v10 (Pol yMet 2013) Comment 126. Section 5.2.2.2.3, pp. 5-53 5-54, Water Quality Modeling (GoldSim), NorthMet Waste Rock Geochemistry, Constituent Release from Waste Rock The first sentence of the last paragraph on page 5-53 states that the GoldSim model simulates constituent release from waste rock based on assumptions that either extrapol ate from conditions observed under field-scale weathering of similar rock (Category 1 waste rock) or in laboratory tests (Category 2, 3, and 4 waste rock, and ore). This should be revised to indicate that constituent release for all categories of rock is based on data from laboratory tests. Constituent release rates for all categories of rock are estimated by applying a scaling factor to l ab rates to account for likely differences between field and lab conditions. The scal ing approach differs between Category 1 and the other categories of rock, but release rates for all categories of rock are based on laboratory data. The first sentence on page 5-54 states that for Category 1 rock, instead of using lab tests, the rate of oxidation and constituent release was estimated from studies of seepage rel ease measured in Dunka Mine rock. .. PolyMet suggests revising the first sentence to read instead of using lab tests, the rate of oxidation and constituent rel ease in the field was estimated from lab release rates that were scaled using the results of studies of seepage release measured in Dunka Mine rock . Comment 127. Section 5.2.2.3.1, p. 5-80, Plant Site The second paragraph states: The 80 percent rate is used because seepage from the south side of Tailings Basin is likely higher than the fl ow contribution to Second Creek that would occur from the Basin footprint for natural ground conditions (i.e., if the Tailings Basin were not present). This statement is not correct. The 80% is to limit the proj ect impact on flow to +/- 20% of existing conditions, as is recommended by MDNR on Page 5-14. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 34 of 70 Comment 128. Section 5.2.2.3.1, p. 5-80, Plant Site PolyMet suggests revising the third full paragraph as follows: WWTP effluent that would be used remaining after flow augmentation to Second Creek would be discharged to the three Embarrass River tributaries (Unnamed, Trimble, and Mud Lake creeks), as partial or complete fulfillment of required augmentation to maintain downstream hydrology and wetl and function in Second Creek and the three Embarrass River tributaries (Barr 2013a). Pumping from Colby Lake would be used to meet any remaining augmentation requirement. Comment 129. Section 5.2.2.3.1, p. 5-89, Plant Site The second paragraph states: Tailings seepage bypassing the containment system (approximately 19.4 gpm) would continue . On page 5-8 (Section 5.2.2) and in Table 5.2.2-36, the flow bypassing the containment system is said to be about 21 gpm. PolyMet recommends revising for consistency. Comment 130. Section 5.2.2.3.2, p. 5-.97, Table 5.2.2-19 (Row: Category 4 Stockpile) The active source period for the Category 4 Stockpile is incorrect. The stockpil e will be removed during the development of the Central Pit and will be entirely removed by the end of Mine Year 11. Comment 131. Section 5.2.2.3.2, p. 5-102 The last full paragraph should acknowl edge that the pH in the East Pit backfill will be monitored and adjusted by the addition of alkaline water from the WWTF as backfilling progresses in order to maintain circum-neutral conditions in the backfill pore water. Comment 132. Section 5.2.2.3.2, p. 5-104, West Pit The SDEIS states: The quality of this aquifer infl ow would reflect the quality of the pit lake water, which would gradually improve over time due to cycling through the WWTF. However, the West Pit water will not be cycl ed through the WWTF during reclamation. PolyMet suggest revising the text to: The quality of this aquifer inflow would refl ect the PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 35 of 70 quality of the pit lake water, which would gradually improve over time due to the effectiveness of the reclamation activities at the site. Comment 133. Section 5.2.2.3.2, p. 5-105, Groundwater Transport and Evaluation Locations The SDEIS states: Cobalt was generally used to illustrate groundwater transport at the Mine Site because it is not attenuated and would enter the surficial flowpaths at concentrations higher than baseline groundwater. This statement is misleading. PolyMet suggests rewording to the following: Cobalt was generally used to illustrate groundwater transport at the Mine Site because the model did not account for attenuation, and would enter the surficial flowpaths at concentrations higher than baseline groundwater. Comment 134. Section 5.2.2.3.2, p. 5-121 The first paragraph incorrectly states that flow augmentation must be at least 145 or 180 gpm, which is 80% of capture fl ow rate of the current south-side seepage. Tabl e 5.2.2- 40 shows 400 gpm, which is the correct rate for augmentation (see The Water Modeling Data Package Volume 2 Plant Site v9). The same error is made in the last paragraph on Page 5-153 (Section 5.2.2.3.2). Comment 135. Section 5.2.2.3.2 p. 5-123, Category 1 Stockpile Seepage The first paragraph of this section only discusses quantities of seepage during cl osure and not operations. The paragraph bel ow could be added to discuss these aspects during operation: During operations, the Category 1 Stockpil e would be uncovered. Infiltration would percolate to the bottom of the stockpil e and be collected by the surrounding groundwater containment system. As the stockpile footprint is expanded, the total seepage during operations will increase up to a maximum annual flow of between 290 gpm and 440 gpm. Most of this seepage would be collected and sent to the WWTF for treatment; an estimated peak fl ow of 20 gpm to 30 gpm would pass below the containment system and be drawn by gravity into the dewatered West Pit. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 36 of 70 Comment 136. Section 5.2.2.3.2, p. 5-126, Table 5.2.2-28 This table is consistent with what was provided in the AWMP, but the corresponding text on Page 5-125 leaves the inaccurate impression that the effluent targets were what was modeled as effluent concentrations. The text should be modified to match the tabl e. Comment 137. Section 5.2.2.3.2, p. 5-127, Table 5.2.2-29 The use of the term non-contact stormwater in this table and elsewhere in the text is somewhat confusing, as it seems to imply that this is water being managed by PolyMet. PolyMet recommends using the more appropriate term unimpacted watershed runoff. Comment 138. Section 5.2.2.3.2, p. 5-143 The first paragraph on this page should acknowledge that there is a low probability for exceedances caused by the project. Comment 139. Section 5.2.2.3.3, p. 5-163, Figure 5.2.2-40 Unnamed Creek should be included in the discharge l ocations for the WWTP effluent. SD006 is the l ocation for Unnamed Creek, not Second Creek. The tabl e organization contradicts language found in the last paragraph of page 5-177, which states augmentation flow to Unnamed Creek would be via a single discharge near the current SD006 discharge. Comment 140. Section 5.2.2.3.3, p. 5-165, Groundwater Transport and Evaluation Locations The text states: The rate at which contaminants would move through the groundwater would be the same as the groundwater seepage velocity downgradient of the containment system for all but four constituents (arsenic, antimony, copper, and nickel). (See Comment p.5-105). Because no attenuation values are used for the constituents other than arsenic, antimony, copper, and nickel the modeled rate of groundwater transport will be faster than the actual rate of transport in the ground. PolyMet recommends noting this fact in the text. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 37 of 70 Comment 141. Section 5.2.2.3.3, p. 5-165 The last sentence of the l ast paragraph states: Transport of other non-attenuated solutes should be similar to l ead, but the change in concentrations is not al ways as visually noticeable as it is for l ead. This statement is misleading. Lead is the only solute of interest where l oading to the environment is predicted to increase as a result of the proj ect, which is why it is the only solute to show a visible concentration front moving through groundwater down gradient of the tailings basin. Thus, other solutes do not show a similar behavior as lead. Comment 142. Section 5.2.2.3.3, p. 5-182 The second to last paragraph states: the concentrations of these metals in the WWTP effluent would be significantly higher than the concentrations in the current Tailings Basin seepage This sentence should be revised to use the term modeled concentrations The modeled effluent concentrations from the WWTP are higher than the values reported in pilot testing of the proposed treatment systems for the WWTP, but were selected to be near, and slightly bel ow, the potential effluent limit for the modeled constituents to provide a conservative assessment of potential consequences rel ated to downstream water quality. PolyMet also recommends making this adjustment in Table 5.2.2-47 on page 5- 188. Comment 143. Section 5.2.2.3.3, p. 5-189 The second to last paragraph states: the average aluminum concentration in the Comment 144. Section 5.2.2.3.3, p. 5-189 The first paragraph following the bulleted list states: This dilution effect is demonstrated by the increase in measured aluminum concentrations from upstream tributary locations (UC-1, TC-1, and MLC-3) to downstream locations (PM-11, PM-19, and MLC-2), where modeled conditions. The use of the term measured implies reference to actual, observed data, but stating that upstream locations would average less than implies PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 38 of 70 or observed. Comment 145. Section 5.2.2.3.3, pp. 5-19 and 5-191 There appears to be inconsistency in the chromium standard that is used in this chapter. The referenced pages state: Among the six constituents with hardness-based evaluation criteria (cadmium, chromium (III), copper, lead, nickel, and zinc), and Tabl e 5.2.2-4 lists chromium (III), as the evaluation criteria with a hardness based standard. However, later in the document, the standard for chromium (VI) is used in Tabl es 5.2.2-30 and 5.2.2-42 for example. Please cl arify which standard was used for chromium, and why. Comment 146. Section 5.2.2.3.4, p. 5-202, Table 5.2.2-49 The number of pit lakes should be 16, not 21 as reported in this tabl e. Comment 147. Section 5.2.2.3.4, p. 5-202 The third paragraph states precipitation, which averages about 9.8 ng/L based on average volume-weighted mercury in precipitation as measured at the Marcell Experimental Forest deposition site in Itasca County (NADP 2013). Barrs analysis, consistent with the tabl e on the next page, is based on 13 ng/L deposition based on the Fernberg Road site. PolyMet recommends citing the Fernberg Road concentration of 13.2 ng/L instead of the Marcell concentration of 9.8 ng/L. This comment also applies to the SDEISs cumulative impact discussion in the first paragraph of p. 6-31 and second paragraph of p. 6-33 (Section 6.2.3.3.4). Comment 148. Section 5.2.2.3.4, pp. 5-204 and 5-207 The second full paragraph on page 5-204 states: The NorthMet Proj ect Proposed Action is predicted to result in a net decrease in mercury-loading to the Partridge River from 24.2 to 23.0 grams per year. The basis for these numbers is not indicated and not consistent with data provided by Barr 2012b. The loading memo indicated a net decrease from 12.1 to 10.8 grams per year. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 39 of 70 Similarly, the first paragraph on page 5-207 states: The NorthMet Project Proposed Action is predicted to result in a net increase in mercury l oading to the Embarrass River of up to 0.6 grams per year (from 22.3 to 22.9 grams per year), about a 3 percent increase. The l oading memo indicated a net increase from 18.5 to 19.1 grams per year. These same comments also apply to pages 6-31 and 6-34 discussing cumulative impacts (Section 6.2.3.3.4). Comment 149. Section 5.2.2.3.4, p. 5-207 The second bullet, when explaining the predicted increase in mercury loading to the Embarrass River, states: Tailings Basin containment system, which would collect seepage from the Tailings Basin, with an estimated mercury concentration of 1.1 ng/L, and route it to the WWTP, which would discharge with an assumed mercury concentration of 1.3 ng/L, for a net increase of 0.2 ng/L of mercury as a result of wastewater treatment, which is a conservative assumption. PolyMet suggests expl aining that the reason this is conservative is because the WWTP would reduce mercury concentrations, and any additional mercury removal from installing a greensand filter, are not accounted for. Comment 150. Section 5.2.2.3.4, p. 5-210, Mercury Summary The SDEIS states: Overall, mercury loadings are predicted to increase slightly in the Embarrass River (3 percent) as a result of the NorthMet Project Proposed Action, but would be offset by a larger decrease (5 percent) in the Partridge River, resulting in a net decrease in overall mercury l oadings (0.6 grams per year) to the St. Louis River as a result of the NorthMet Proj ect Proposed Action. The basis for these percentages is not indicated and not consistent with data provided (Barr, 2012b). According to the loading memo analysis, the increase at the Embarrass River would be 0.2% and the decrease at the Partridge would be 0.9%. This comment also applies to page 6-18 in Section 6.2.3.3.4. Comment 151. Section 5.2.2.3.5, p. 5-210, Proposed and Recommended Mitigation Measures The second bullet under NorthMet Project Proposed Action Design Changes states: The location of the Category 4 Stockpile was shifted such that seepage would be captured in the Central Pit and East Pit and would minimize effects on surficial PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 40 of 70 groundwater. The terminology and locations used here are confusing. PolyMet suggests the following instead: The location of the Category 4 Stockpil e was shifted such that water contacting the stockpile would be captured in the East Pit and would minimize effects on surficial groundwater. It is important to note that the Central Pit will not exist until after the Category 4 Stockpile has been decommissioned and the Category 4 waste rock has been relocated to the East Pit for subaqueous disposal. The most apparent benefit of relocating the Category 4 Stockpile as part of the Proposed Action Design Changes is that by locating the stockpile over an area that will be subsequently engulfed by the Central Pit, the overall area of surface disturbance (including vegetation, wetlands, etc) of the NorthMet proj ect will be reduced. Comment 152. Section 5.2.2.3.5, p. 5-211, Proposed and Recommended Mitigation Measures The sixth bullet states: Refined Hydrometallurgical Flowsheet A singl e (rather two) autocl ave would be fed with nickel concentrate and produce copper concentrate produced with beneficiation refinements. The production of hydrometallurgical residue would be cut approximately in half with this design change. Residual copper would be recovered by cementation (contacting the leach solution with copper concentrate) to further upgrade the copper concentrate and to further reduce the production of hydrometallurgical residue. To be more precise, the last phrase should be changed to: , and to potentially further reduce the production of hydrometallurgical residue. Comment 153. Section 5.2.2.3.5, p. 5-211 The first bullet discusses subaqueous disposal of reactive waste rock, but it does not mention subaqueous disposal of some of the Category 1 waste rock. Although Category 1 waste rock is considered the least reactive waste rock, it should still be mentioned here. Comment 154. Section 5.2.2.3.5, p. 5-211 The fourth bullet discusses the use of side dump cars to haul ore and states: Ore Transport PolyMet proposes to use side-dump rail ore cars that would minimize ore spillage (PolyMet 2013c). Side dump rail cars were proposed as part of the DEIS, as documented in DEIS Section 3.1.3; therefore, this is not a design change and should not be included in this section. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 41 of 70 Comment 155. Section 5.2.2.3.5, p. 5-211 The l ast bullet discusses the WWTP and states: A WWTP would be added at the Plant Site to treat Tailing Basin seepage through operations. Treatment at the WWTP will not end at the end of operations. The WWTP will actually treat this water through operations and cl osure. Comment 156. Section 5.2.2.3.5, p. 5-212, Tailings Basin Seepage Groundwater Containment System The seventh bullet discusses the tailings basin containment system and refers to it as being on the western, northern, and northeastern sides of the existing LTVSMC Tailings Basin. The containment system is not located al ong the northeastern side of the tailings basin; it is located on the western and northern sides of the tailings basin, as described appropriately on SDEIS Page 3-116 (under Engineering Water Controls). Comment 157. Section 5.2.2.3.5, p. 5-213, Proposed and Recommended Mitigation Measures The first bullet, as part of a tabul ation of fixed engineering controls, states: Process water management, including pipes, pumps, and process water ponds that would be used to separate and control stormwater and process waters. This statement does not account for the fact that the process water ponds are lined. Accordingly, PolyMet recommends inserting lined before process water ponds. Comment 158. Section 5.2.2.3.6, p. 5-218, Table 5.2.2-53, Stormwater Summary The flow monitoring for stormwater has footnotes stating that flows would be monitored continuously. There are no pumps associated with this infrastructure, so continuous flow monitoring is not proposed for stormwater flows. Fl ows are proposed to be monitored on a monthly basis as specified in the Water Management Pl an Mine (v2) Section 5.2. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 42 of 70 Comment 159. Section 5.2.2.3.6, p. 5-219, Table 5.2.2-53, Surface Water, Colby Lake and Whitewater Reservoir This tabl e includes water level monitoring for Whitewater Reservoir. This was not included in the Water Management Plan Mine and has never been discussed with the agencies. Comment 160. Section 5.2.3.1.2, p. 5-227, Potential Indirect Wetland Effects Resulting from Changes in Hydrology Due to Drawdown at the Mine Site The fourth bulleted item is misl eading and should be clarified by changing the text in parentheses to say within Area 1. Comment 161. Section 5.2.3.1.2, p. 5-227 The first paragraph states The anal og approach was based on similar mine settings (e.g., within the gl acial till region). PolyMet proposes the following revision: The analog approach used observations of groundwater response adjacent to iron range mines characterized by moderate to high hydraulic conductivity gl acial and fluvial deposits overlying lower hydraulic conductivity bedrock. Comment 162. Section 5.2.3.2.2, p. 5-277 The third sentence of the first full paragraph should be clarified by identifying the source and rationale behind using 675 square meters of watershed area per meter of track in the contributing watershed as the method for identifying potentially impacted wetl ands. Comment 163. Section 5.2.3.3.2 p.3-313, Wetland Mitigation In the second sentence of the third paragraph, it is an overstatement to suggest that wetlands represent pre-European settlement conditions, as the area was likel y logged several times since settlement. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 43 of 70 Comment 164. Section 5.2.3.3.2, p. 5-312 The second bullet should read: In-kind mitigation means the replacement of the impacted aquatic site with the same wetl and plant community type. See USACE, 2009, II.D.3. Comment 165. Section 5.2.3.3.2, p. 5-312 The third bullet should read: Out-of-kind mitigation means the replacement of an impacted aquatic site with a different wetl and plant community type. See USACE, 2009, II.D.3. Comment 166. Section 5.2.3.3.2, p. 5-313 In the second paragraph, the rule citation is incorrect as is the interpretation of the rule. The second paragraph should read: The Federal Mitigation Rule also states that difficult-to-replace aquatic resources include bogs (33 CFR 332.3(e)(3) and Preamble, page 19633). The majority of the wetl ands that would be affected by the NorthMet Project Proposed Action would be difficult-to-replace (coniferous bog and open bog) (USACE 2013). The Federal Mitigation Rule includes a provision for a case-by-case determination of mitigation ratios higher than the minimum 1:1 where necessary to account for the difficulty of restoring or establishing the desired aquatic resource type and functions. Comment 167. Section 5.2.3.3.2, p. 5-313 The third sentence of the third paragraph is not supported by the data collected for the proj ect. None of the wetlands proposed to be affected by the project were rated as having exceptional vegetative diversity/integrity ratings. Comment 168. Section 5.2.3.3.2, p. 5-313 The second to l ast sentence in the fourth paragraph should read: For effects on wetlands with rare or exceptional functions or difficult-to-repl ace bogs, the USACE may PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 44 of 70 require additional compensation in accordance with District Policy and the Federal Mitigation Rule. Comment 169. Section 5.2.3.3.2, p. 5-313 The first sentence of the second to last paragraph should read: If none of these incentives are met, the minimum mitigation ratio required is 1.5:1. Comment 170. Section 5.2.3.3.2, p. 5-314 The third paragraph states that base compensation ratios could be increased to 2:1. There is not rational e or reference provided for this statement, which is not specifically stated in the District Policy or Federal Mitigation Rul e. The same comment applies to page 5-316 and page 5-321. Comment 171. Section 5.2.3.3.2, p. 5-314 In the fourth paragraph, it is stated that Minnesota Rules 8420.0552 requires financial assurances to ensure successful wetland replacement. This provision only applies to wetland replacement that is not in advance. In addition, the local government unit may waive this requirement if it determines the financial assurance is not necessary to ensure wetl and replacement. Comment 172. Section 5.2.3.3.2, p. 5-315 The first paragraph states that because the compensatory wetland mitigation is planned in advance, that financial assurance would not be required under Section 404. This may not be true because the purpose is to ensure successful completion of the mitigation, and it may not be possible to determine success within one year of wetland mitigation construction. Comment 173. Section 5.2.3.3.2, p. 5-315, Table 5.2.3-17 The 6 rows beginning with <50%... and <80%... are not relevant to the PolyMet proj ect and could be removed in order to maintain clarity. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 45 of 70 Comment 174. Section 5.2.3.3.2, p. 5-316 The first paragraph after the list should read: The financial assurance requirements would be part of the WCA permitting process for the NorthMet Project Proposed Action. Wetland repl acement for the NorthMet Project Proposed Action is expected to be approved and constructed in advance of any authorized wetland effects (under the WCA approval ) and, therefore, would not require financial assurance. Comment 175. Section 5.2.3.3.2, p. 5-319 No reference is provided for the statements made in the fourth paragraph. Justification for why the wetland mitigation opportunities discussed in this paragraph were determined to not be practicable was provided in Wetl ands Mitigation Plan Supplement Wetl and Mitigation Pl anning and Siting Documentation, RS20T Draft-04, PolyMet, June 1, 2008. One additional difficulty with such wetland mitigation opportunities that was not discussed in the reference provided is the presence of severed mineral rights on many of those lands. In order to place restrictions on the l and, as required for wetland mitigation, those mineral rights would need to be controlled. Comment 176. Section 5.2.3.3.2, p. 5-321 In the last paragraph, the third sentence should read: The mitigation would be considered in advance if the initial phases of restoration on all of the proposed off-site wetland mitigation sites would be completed at least one full growing season in advance of the authorized wetland effects provided initial performance standards are met for which the mitigation would compensate. Also, in the last paragraph, 939.4 acres is stated with no reference. That number should be referenced to Tables 5.2.3-19 and 5.2.3-20 of the 404 permit application. Comment 177. Section 5.2.3.3.2, p. 5-322 In the fifth paragraph, the first sentence should read: The minimum replacement ratio that would be allowed by the USACE is 1:1 (USACE, 2009) for those wetl ands that would be replaced with the same wetland type, and at least one full growing season in advance of the authorized wetland effects provided initial performance standards are met; however, base compensation ratios could be increased to 2:1 (add reference) for PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 46 of 70 effects on wetlands with rare or exceptional functions or difficult-to-repl ace bog wetlands. The second to l ast sentence should read: Compensation proposed at the Aitkin Site would be expected to meet in-kind compensation, resulting in a compensation ratio for effects to wetlands with rare or exceptional functions or difficult-to-repl ace bogs of 1.75:1, and if in advance, the ratio would be reduced to 1.5:1. Comment 178. Section 5.2.3.3.2, p. 5-322 The first sentence in the last paragraph (before the bullet), should read: Under the Minnesota WCA, the replacement ratio that would likely be allowed is 1.5:1, because the Aitkin Site wetlands are out of the NorthMet Project area watershed (see Tabl es 5.2.3-18 and 5.2.3-20). Comment 179. Section 5.2.3.3.2, p. 5-324 The first sentence in the second paragraph should read: The minimum replacement ratio that would be allowed by the USACE is 1:1 (USACE, 2009) for those wetl ands that would be replaced with the same wetland type, and at least one full growing season in advance of the authorized wetland effects provided initial performance standards are met; however, base compensation ratios could be increased to 2:1 (add reference) for effects on wetlands with rare or exceptional functions or difficult-to-repl ace bog wetlands. The second to l ast sentence in the second paragraph should read: Compensation proposed at the Hinckley Site would be expected to meet the in-kind incentive, resulting in a compensation ratio for effects to wetlands with rare or exceptional functions or difficult-to-replace bogs of 1.75:1, and if in-advance, the ratio would be reduced to 1.5:1. Comment 180. Section 5.2.3.3.2, p. 5-324 The first sentence in the third paragraph should read: Under the Minnesota WCA, the repl acement ratio that would likely be allowed is 1.5:1, because the Hinckl ey Site wetlands are out of the NorthMet Proj ect area watershed (see Tabl es 5.2.3-18 and 5.2.3-20). PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 47 of 70 Comment 181. Section 5.2.3.3.2, p. 5-325 The first sentence in the l ast paragraph should read: The minimum replacement ratio that would be allowed by the USACE is 1:1 for those wetlands that are repl aced with either the same wetl and type, or at least one full growing season in advance of the authorized wetland effects provided initial performance standards are met; however base compensation ratios could be increased to 2:1 for effects on wetl ands with rare or exceptional functions or difficult-to-repl ace bog wetlands. The last full sentence on the page should read: Compensation proposed for the Zim Site would be expected to meet both in-kind and in-place incentives, thereby reducing the compensation ratio for effects on wetl ands with rare or exceptional functions or difficult-to-replace bogs from 2:1 to 1.5:1. Comment 182. Section 5.2.3.3.2, p. 5-325 The first sentence on the page (continuing from the previous page) should read: For low- to moderate-quality wetlands, the recommended base ratio of 1.5:1 would be reduced to 1.25:1 for in place and could be reduced to 1:1 if also either in-advance or in-kind. Comment 183. Section 5.2.3.3.2, p. 5-325 The section on the Zim Site does not include any description of restoration methods and sequencing, which is included in the descriptions for the Aitkin and Hinckley sites. See Zim Sod Wetl and Mitigation Site Wetland Mitigation Plan (PolyMet, November 2011) for an appropriate description. Comment 184. Section 5.2.3.3.2, p. 5-327, Table 5.2.3-18 A footnote should be added to the table describing why there is 101.8 acres of on-site wetland mitigation shown in the second to l ast column but no associated wetl and credits in the l ast column. Similarl y, the same acreage is shown in the On-Site (acres) column, but no associated credits are shown in the Total Credits column. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 48 of 70 Comment 185. Section 5.2.3.3.2, p. 5-333 The last paragraph states, Approximately 72 percent of credits proposed would be located outside of the watershed. This statement is misleading because all of the proposed credits are above the minimum 1:1 replacement ratio. In fact, 48 percent of the proposed impacts are proposed to be replaced in-kind, in-pl ace, and ahead of time. If the on-site wetland mitigation were factored in, approximatel y 56 percent of the wetland impacts would be replaced within the watershed. Comment 186. Section 5.2.3.3.2, p. 5-333 The last paragraph states that the Federal Mitigation Rule places additional emphasis on replacing coastal wetland losses within a coastal watershed. However, the Rule simply states that unavoidable wetland impacts within a coastal watershed should be repl aced within a coastal watershed, where practicable. The Federal Mitigation Rule states that when sufficient bank credits are not available, permittee-responsible mitigation is the only option. It further states that, where practicable and l ikely to be successful and sustainable, permittee-responsible mitigation should be determined using the principles of a watershed approach (33 CFR 332.3 (b)(4)), which should be used to the extent appropriate and practicable. Therefore, the approach for compensatory mitigation for unavoidable wetland impacts within coastal watersheds appears to match the approach for wetland impacts in other watersheds. Comment 187. Section 5.2.3.3.3, p.5-334, Mitigation Summary The numbers in the second sentence of the second paragraph are inaccurate. In this sentence, 7,350.7 acres should be 1,771.5 acres (based on Table 5.2.3-3; excluding the no effect acres) and 6,498.1 acres should be 587.1 acres (based on Table 5.2.3-4; excluding the no effect acres). Comment 188. Section 5.2.3.3.4, p. 5-337 In the third paragraph, the third sentence should read: At The Mine Site, an additional 16 monitoring locations are proposed and are planned within all wetl ands that have received effect factor ratings of 3, 4, or 5 near the North Met Project area features and in several wetland with effect factor ratings of 1 or 2 located throughout the areas of PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 49 of 70 potential indirect wetland impacts. This is consistent with the information provided on page 5-336, second paragraph of the SDEIS. Comment 189. Section 5.2.4.1, p. 5-340 The last sentence of the first full paragraph states: Indirect effects were estimated by comparing the proximity of the NorthMet Proj ect area infrastructure footprints to existing natural features. Polymet suggests revising the text to read: Vegetation communities can be affected by more than one of these types of indirect effects. For this reason, indirect effects on vegetation cannot be precisely quantified, as this would result in double-counting of vegetation community acreage where multiple indirect effects are manifested. The relative magnitude of indirect effects on vegetation communities can, however, be estimated. Typically, indirect effects are more l ikely to occur and/or are more likely to be evident in vegetation communities that are cl oser to Project components and other infrastructure (e.g., roads). Indirect effects tend to diminish with increasing distance from Project components and other infrastructure. Comment 190. Section 5.2.4.2.1, pp. 5-341 5-342, Culturally Important Plants In the discussion of the NorthMet Projects effects on culturally important plants, the SDEIS discusses wild rice but notes that that a distinct l ist of plant species important to the Bands is not availabl e. The Bands were cooperating agencies in preparation of the SDEIS, and accordingly had every opportunity to provide a distinct plant species list. If such a list is not avail able, PolyMet recommends stating that the Bands have not identified culturally important plants not already identified and discussed in the SDEIS. Comment 191. Section 5.2.4.1, pp. 5-345 5-351, Threatened and Endangered Plant Species The text describes indirect effects as a certainty, when there is no basis for determining the likelihood and/or magnitude of indirect effects. Where the text makes statements such as [Species name] may be indirectly affected by changes in hydrology, the word potentially should be inserted (may potentially be indirectly affected ) to more accurately refl ect the uncertainty over the likelihood and/or magnitude of indirect effects. The relative magnitude of indirect effects on ETSC or RFSS species would vary between ETSC/RFSS species and between locations of individuals or populations of a given ETSC or RFSS species. The potential for indirect effects on ETSC or RFSs species cannot be quantified, but can be estimated. Typically, indirect effects are more PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 50 of 70 likely to occur in ETSC or RFSS popul ations that are closer to Proj ect components and other infrastructure (e.g., roads). Indirect effects on ETSC or RFSS species tend to diminish with increasing distance from Project components and other infrastructure. Comment 192. Section 5.2.4.2.1, p. 5-348 The eighth sentence of the second paragraph states: Disturbance-tolerant species may, in some cases, actually be disturbance-dependent. PolyMet recommends providing a citation for this claim or removing the sentence. Comment 193. Section 5.2.4.2.4, p. 5-359, Mine Site Mitigation Measures The last sentence makes an assumption about how impacts to a state-listed species could be mitigated through the purchase of an unprotected site. PolyMet recommends noting in this section that appropriate, acceptable mitigation will be determined by the MDNR. Comment 194. Section 5.3.4.2.4, p. 5-616 The last sentence of the second paragraph assumes that the non-federal lands rank lower for biodiversity because no studies have been conducted to designate Sites of Biodiversity Significance and native vegetation communities. This is specul ative and inconsistent with the data that demonstrate similarities in the cover types between the federal and non-federal lands. On that basis, it is reasonable to assume that, once the non-federal lands are surveyed, Sites of Biodiversity Significance will be designated, and native pl ant communities will be mapped. Comment 195. Section 5.2.5.2.1, p. 5-364, Canada Lynx In the second sentence of the eighth paragraph, it is misl eading to state that an average of 2,066 miles per day of vehicular traffic would contribute to potential lynx impacts. The maj ority of those miles would be travel ed within the pit/mine site and not along outside roads where lynx encounters would be far more likely. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 51 of 70 Comment 196. Section 5.2.5.2.3, p. 5-374, Wetlands The fourth paragraph inaccurately states: This would not replace in-kind the wetland habitat affected (primarily coniferous bog and shrub/conifer swamp). This issue is addressed in Comments 164 to 187 above. Comment 197. Section 5.2.5.2.3, p. 5-374, Wildlife Corridors Second paragraph: The Transportation and Utility Corridor runs both parallel and perpendicular to the identified wildlife travel corridors. Comment 198. Section 5.2.6.2.2, p. 5-392 The last paragraph states: Effects on aquatic biota from the lead exceedance due to changes in hardness are not well understood, but would likely increase the potential to adversely affect aquatic life. This statement does not acknowl edge that the modeling results predict increased potential for a l ead exceedance (due to the use of a probabil istic model); rather, the statement incorrectly implies that there will inevitably be a lead exceedance. Comment 199. Section 5.3.3, p. 5-595, Wetlands In the second paragraph, it should be noted that most of the floodplain on the federal land is outside of the Proj ect Area. Comment 200. Section 5.3.3.1.1, p. 5-598, Table 5.3.3-4, Wetlands and Floodplains The right-most table column heading should be renamed Non-FEMA regulated floodpl ains. A column should be added for FEMA-regul ated fl oodplains. This comment also pertains to Tabl e 5.3.3-7. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 52 of 70 Comment 201. Section 5.3.3.1.1, p. 5-599, Table 5.3.3-5 The subtotal for open bog on non-federal lands is not accurate. The number should be 7.1 acres. Comment 202. Section 5.2.7.1.3, p. 5-402, Proposed Action Emissions The second sentence of the third paragraph lists lean ore as a handled material. However, lean ore has been eliminated from the Mine Plan. Comment 203. Section 5.2.7.1.3, p. 5-402, Proposed Action Emissions The last sentence of the third paragraph refers to the proposed monitors at the Mine Site as ambient air quality monitors. This may be confusing because they are not intended to assess compliance with NAAQS/MAAQS, but to provide information for fugitive dust control. PolyMet suggests using PM 10 monitors instead. Comment 204. Section 5.2.7.1.3, p. 5-403, Table 5.2.7-4, Plant Site Emissions The Plant site emission totals include some double counting for natural gas and propane combustion emissions and do not refl ect potential to emit or estimated actual emissions. The column heading (and text) using Projected Controlled Emissions may be confusing. PolyMet recommends using standard air permitting nomenclature: potential, actual, allowable, etc. Comment 205. Section 5.2.7.1.3, p. 5-404, Table 5.2.7-6, Plant Site and Mine Site Emissions Plant site emissions are estimated actuals. The controlled potential would be more appropriate to compare to maj or source level. The Mine Site max singl e HAP emissions in table are for Mn. Max Plant + max Mine Site single HAP emissions are for Ni at 5 tpy. PolyMet suggests removing Prevention of Significant Deterioration-regul ated from table titl e. Major source determination under NEAHAPS includes fugitive sources; PSD for non-listed source category does not. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 53 of 70 Comment 206. Section 5.2.7.1.3, p. 5-405, Greenhouse Gas Emissions The first two sentences of the first paragraph indicate that emissions in Table 5.2.7-7 are potential emissions. However, they are not for the Pl ant Site as these totals refl ect some double counting for natural gas and propane combustion emissions (see Comment 204 above). Although the SDEIS distinguishes between potential and maximum potential emissions, it is not clear what the difference is. PolyMet suggests providing an expl anation of the use of short tons in Table 5.2.7-7 and metric tons in Tabl e 5.2.7-8. Comment 207. Section 5.2.7.1.3, p. 5-405, Table 5.2.7-7, Plant Site Emissions Plant site emissions are not PTE or estimated actual emissions or proposed limited emissions. Comment 208. Section 5.2.7.1.4, p. 5-407, NAAQS, MAAQS and Class II Increment Modeling The bulleted items require revision. The Northshore Mine does not consume increment. It was included in the increment analysis in that it was considered and eliminated as an increment consuming source (constructed before applicabl e baseline dates). The same comment applies to the text on page 5-410. Comment 209. Section 5.2.7.2.1, p. 5-410, Prevention of Significant Deterioration Class II Increment Analysis In the second to last sentence, Polymet suggest cl arifying that the other sources were also model ed at maximum emission rates to show the modeling essentially constituted worst case scenario. Comment 210. Section 5.2.7.2.1, p. 5-411, Mine Site Receptors Analysis The text implies that mobiles sources were modeled for Class II criteria pollutant modeling. However, they were not (per EPA guidance and the approved modeling protocol). They were included in AERA and Class I modeling. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 54 of 70 Comment 211. Section 5.2.7.2.1, p. 5-411, Plant Site Receptors Analysis In the third sentence of the first paragraph, the increment result of 18 g/m^3 is for the cumulative analysis. The accurate result is 27 g/m^3, as shown in table 5.2.7-11. Comment 212. Section 5.2.7.2.1, p. 5-412, Mine Site The first sentence of the second paragraph is incorrect. All sources were modeled together. Comment 213. Section 5.2.7.2.1, p. 5-412, NAAQS and MAAQS Impact Analysis The second sentence in the first paragraph states that modeling analysis included the entire NorthMet Project area and nearby sources. The Plant Site results with nearby sources are in Chapter 6. Comment 214. Section 5.2.7.2.2, p. 5-414, Table 5.2.7-13, Isle Royale 24-hour SO 2 result The figures for 2002 should be 0.001 and max 0.001. Comment 215. Section 5.2.7.2.3, p. 5-426, Table 5.2.7-22 Inhalation only acute and chronic non-cancer HI should be displayed with 1 significant figure i.e. 1 not 1.0. Comment 216. Section 5.2.7.2.4, p. 5-430, NorthMet Proposed Action and Climate Change In the second paragraph, PolyMet suggests noting that if metals are obtained from proj ects elsewhere, the projects are likely to be subject to much less overall environmental regul ation. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 55 of 70 Comment 217. Section 5.2.7.2.5, p. 5-431, Mercury Deposition Impact Analysis In the last paragraph, the incremental risk at Wynne Lake for a recreational fisher should be as 0.07 in Pl ant Site AERA report, not 0.08. Comment 218. Section 5.2.7.3, p. 5-421, Mine Site Air Emission Risk Analysis The third sentence of the first paragraph inaccurately states that H 2 SO 4 was screened out. The estimated risk was added to the other chemicals evaluated to obtain the total. Comment 219. Section 5.2.7.3, p. 5-423, Mine Site Air Emission Risk Analysis The third sentence of the last paragraph lists NO 2 from natural gas combustion as an acute risk driver. However, natural gas is not avail able at the Mine Site. Rather, NO 2 is from diesel fuel combustion. Comment 220. Section 5.2.7.3, p. 5-424, Plant Site Air Emission Risk Analysis The sixth sentence of the first paragraph inaccurately states that H 2 SO 4 was screened out. The estimated risk was added to the other chemicals evaluated to obtain the total. Comment 221. Section 5.2.7.3, p. 5-425, Plant Site Air Emission Risk Analysis The second sentence of the third paragraph inaccurately states that the risk assessment was refined by considering where maximum concentrations occur in space. The results were acceptabl e without this refinement. This comment also applies to text on page 5-426. Comment 222. Section 5.2.7.2.4, p.5-427, Greenhouse Gases Impact Analysis The first paragraph in this section states: The science, policy, and regul atory frameworks regarding GHGs are continually evolving and are often subject to differing interpretation. For the purposes of the SDEIS, the information presented bel ow is PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 56 of 70 intended to provide the current understanding through June 15, 2012 with subsequent information regarding climate change updated in the FEIS. PolyMet supports the SDEISs stated intent to supplement the GHG analysis with recent analysis and devel opments on the topic of climate change and greenhouse gases. PolyMet bel ieves two recent devel opments in particular warrant acknowledgement in the FEIS. The first is President Obamas directive to the EPA l ast summer to promulgate carbon pollution New Source Performance Standards (NSPS) for existing electric utility generating units by June of this year, adopt a final standard by June 2015 and require state implementation plans be submitted by June 2016. The second is the 2013 Minnesota law that will require Minnesota Power to generate at l east 1.5% of its electricity through solar by 2020. These initiatives are expected to decrease the amount of indirect, power-production-related greenhouse gas emissions by the utilities that are expected to supply electricity to the NorthMet Project. Comment 223. Section 5.2.7.4, p. 5-432, Mitigation Measures The first sentence of the first paragraph says: If, during permitting, it is determined that mitigation measures are necessary, the measures described in this section could be considered. However, most of the measures described are already an integral part of the proposed Project. PolyMet suggests deleting first sentence. Comment 224. Section 5.2.7.5, p. 5-434, Amphibole Mineral Fibers PolyMet addresses information that is critical to the discussion of the health risks associated with amphibole mineral fibers in more detail in Attachment C to these comments. Comment 225. Section 5.2.7.5.3, p. 5-441, NorthMet Proposed Action PolyMet recommends deleting the second to l ast sentence in the second to l ast paragraph on the page, which reads: At the time this review was conducted, PM 2.5 was not regulated under PSD and at the beginning of the sentence and starting with [T]he NorthMet Project Proposed Action is not subj ect to PSD Comment 226. Section 5.2.7.5.3, p. 5-442, NorthMet Project Proposed Action PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 57 of 70 In the second paragraph, PolyMet recommends adding a statement that PolyMet agreed to apply more rigorous dust control procedures for unpaved roads at the Mine Site to also reduce fugitive emissions. Comment 227. Section 5.2.10.2.6, p. 5-509; Section 6.2.3.11, p. 6-101 The text in the above two sections makes reference to a potential Environmental Justice (EJ) impact for Band members and other subsistence consumers of fish due to increased mercury concentrations and associated increases in mercury bioaccumulation in fish tissue. This conclusion is reportedly based on the analysis presented in Section 5.2.2.3.4 and rel ates specifically to the Embarrass River and downstream chain of lakes. Page 5-509 states: Operations could affect individuals who consume fish harvested from nearby water bodies. The NorthMet Project Proposed Action would increase mercury concentrations in the Embarrass River Watershed, as well as some nearby lakes, although it would decrease mercury concentrations in the Partridge River watershed (see Section 5.2.2.3.4). The discussion in Section 5.2.2.3.4 states that there would be a slight increase of up to 0.6 grams per year (from 22.3 to 22.9 grams per year), about a 3% increase. Although not directly referenced in Sections 5.2.10.2.6 or 6.2.3.11, text in the first paragraph on Page 5-21 is the only attempt in the document to correlate mercury concentrations in a water column to mercury content in fish. This is a critical connection if one attempts to suggest there is a potential EJ issue. As stated in Comment 118 above, PolyMet does not believe this rel ationship is substantiated by either site specific data or more general research presented in the literature. The statement that there is a potential EJ impact due to increased mercury concentrations and associated increases in mercury bioaccumulation in fish tissue is unsubstantiated by fact. Comment 228. Section 5.2.13.2.4, p. 5-542, Emergency Planning and Community Right to Know The third full paragraph inaccurately states that PolyMet will be required to develop a risk management plan for HCl. Only HCl at a concentration of 37% or greater is subject per 40 CFR 68.130. PolyMet will be required to develop a risk management plan for liquid SO2. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 58 of 70 Comment 229. Section 5.2.14, p. 5-545 The third paragraph states: Conceptual designs of the waste rock stockpiles, Tailings Basin, and Hydrometallurgical Residue Facility have been devel oped and shown by PolyMet, through an iterative design and model process, to meet the minimum safety factors and water qual ity criteria (see Section 5.2.2) acceptable to the Co-lead Agencies. PolyMet suggests changing the word conceptual to preliminary. Comment 230. Section 5.2.14.2.1, p. 5-555, Modeling Results The required and computed Slope Stability Factors of Safety for the stockpil es are not presented. Stockpil e Sl ope Stability Safety Factors are reported in Tabl es 2, 3 and 4 of Attachment G of the May 29, 2012 Geotechnical Data Package, Vol. 3, Version 2. Comment 231. Section 5.2.14.2.2, p. 5-556, Tailings Basin The second bullet under Design Criteria states: Factor of safety greater than or equal to 1.3 for short-term, undrained strength conditions for soils that are not prone to static liquefaction using undrained strength conditions. This sentence should be revised to indicate that this analysis does not include static liquefaction. Liquefaction is addressed subsequently. Comment 232. Section 5.2.14.2.2, p. 5-561, Design The second paragraph uses the phrase bulk tail ings. PolyMet recommends defining bulk tailings to limit potential confusion. LTVSMC Coarse Tailings are proposed for use in dam construction but since the Coarse Tail ings may have occasional inclusions of fine tailings and slimes, the term Bulk Tailings has been used by PolyMet to describe the pl anned tailings borrow. The same comment applies to page 5-562, which states: The proposed dams would be constructed from mechanically placed and compacted bulk tailings taken from the existing LTVSMC Tailings Basin as needed to produce the desired dam lift height and geometry. LTVSMC bulk tail ings are currently defined as a mixture of tailings from the existing LTVSMC Tailings Basin. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 59 of 70 Comment 233. Section 5.2.14.2.2, p. 5-562, Design The eighth paragraph states: As dams are constructed, exterior slopes would be covered with bentonite and vegetated. Upon reaching.. This statement is not compl etel y accurate. On the exterior face of new dams, bentonite will be integrated into the near-surface l ayer of tail ings. The dams will not be covered with bentonite. Comment 234. Section 5.2.14.2.2, p. 5-565, Slope Stability The second sentence states: The predicted Factor of Safety values for Cross Section F at various stages of development of the Tailings Basin are summarized in Tabl e 5.2.14- 1. All slope stability factors are designed to meet the factors of safety required by the NorthMet Geotechnical Modeling Work Plan (PolyMet 2013n, Attachment A). It is more appropriate to say that the slope stabil ity factors are designed to meet the applicable requirements of Minnesota Rules 6115.0300 through 6115.0520 and the factors of safety required by the Co-Lead agencies in the NorthMet Geotechnical Modeling Work Plan (PolyMet 2013n, Attachment A). The first paragraph under Design Criteria on p. 5-556 contains similar language. Comment 235. Section 5.2.14.2.2, p. 5-567, Long-term Closure Stability Conditions The third paragraph states: Model ing was undertaken to predict the long-term stability of the Tailings Basin. As shown in Table 5.2.14-1 and Tabl e 5.2.14-4, the long-term closure sl ope stability Factors of Safety are above the minimum value required under the Work Plan. It is more appropriate to say that the slope stability Factors of Safety are above the minimum value deemed acceptable to the Co-lead Agencies and required under the Work Plan. There is similar language in the last paragraph on p. 5-566. Comment 236. Section 5.2.14.2.3, p. 5-569, Proposed Maintenance and Mitigation The second paragraph states: Where monitoring or model updates indicate that the Factor of Safety for the Tailings Basin no longer meets design criteria, appropriate modifications to the Tailings Basin would be considered, modeled, and, if necessary, undertaken. This sentence leaves doubt that prompt action will be taken if Factor of Safety values fall below design requirements. PolyMet recommends clarifying that PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 60 of 70 mitigating measures will be explored and impl emented as needed if at any time it is determined that Factor of Safety values have fallen bel ow design requirements. Comment 237. Section 5.2.14.2.3, p. 5- 570, Methodology The first paragraph states: PolyMet took the steps listed below in order to demonstrate that the design of the Hydrometallurgical Residue Facility would meet the respective geotechnical requirements and would be in accordance with the NorthMet Geotechnical Modeling Work Pl an (PolyMet 2013n, Attachment A): PolyMet recommends revising the sentence to read: PolyMet took the steps listed below in order to demonstrate that the design of the Hydrometallurgical Residue Facility would meet the Co-Lead Agencies respective geotechnical requirements and would be in accordance with the NorthMet Geotechnical Modeling Work Pl an (PolyMet 2013n, Attachment A) which was reviewed by the Co-Lead Agencies. Comment 238. Section 5.2.14.2.3, p. 5-570, Methodology The third item under the first paragraph states: Devel oped seepage and stability models using Geo-Slope International, Inc. modeling software (i.e., SLOPE/W, SEEP/W and SIGMA/W as necessary) for maximum facility dam height with minimum and maximum pond el evation, and post-closure cover effective with minimum pond elevation the maximum. The last phrase is poorly written and confusing. PolyMet suggests using the following revised text: Devel oped seepage and gl obal stability models using Geo-Slope International, Inc. modeling software (i.e., SLOPE/W, SEEP/W and SIGMA/W as necessary) for hydrometallurgical residue facility dam lifts 1, 2 and 3; each with maximum pond elevation, and an infinite stability model to analyze facility liner stability. Comment 239. Section 5.2.14.2.3, p. 5-574, Figure 5.2.14-6, Cross Sections A and B of the Hydrometallurgical Residue Facility at Year 20 The text describing the figure (see paragraph under Identification of Design Cross Section on p. 5-571) makes reference to Node A. Yet, Node A is not shown in the figure. There also is a blue dashed line (presumably denoting the phreatic surface in surrounding materials) that is not defined in the figure legend nor is the dashed line label ed in the figure. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 61 of 70 Comment 240. Section 5.2.14.2.3, p. 5-575, Modeling Results This Section does not clearly distinguish between (1) the settlement of the Hydrometallurgical Residue Facility (HRF) foundation materials and resulting movement of the HRF liner system and (2) future consolidation of the residue deposited within the HRF and resulting movement of the residue surface. PolyMet recommends more detail to provide clarification. Comment 241. Section 5.2.14.2.3, p. 5-575, Modeling Results The first paragraph states: The results reported in Geotechnical Data Package Volume 2 Version 3 indicate that the proposed design of the Hydrometallurgical Residue Facility would meet all respective factors of safety as required (PolyMet 2012a). The modeling undertaken and results are summarized bel ow. PolyMet suggests revising the statement to say that the design would meet all of the Co-Lead agencies respective factors of safety as required (PolyMet 2012a). Comment 242. Section 5.2.14.2.3, p. 5-575, Global Slope Stability The first paragraph states: Analysis of the new dams (i.e., those not supported by the existing LTVSMC Tailings Basin or natural topography) at their greatest height (at year 20) resulted in a computed Factor of Safety for the ESSA of 2.32, which is greater than the required minimum of 1.5. The sentence should be revised to state that the resulting Factor of Safety is greater than the Co-Lead Agencies required minimum of 1.5. Comment 243. Section 5.2.14.2.3, p. 5-575, Infinite Slope Stability The fourth sentence of the first paragraph states: The minimum infinite sl ope stability safety factor for all Hydrometallurgical Residue Facility liner system components is 1.5. It would be more appropriate if the sentence was revised to read: The Co-Lead Agencies required minimum infinite slope stability safety factor for all. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 62 of 70 Comment 244. Section 5.3.5, p. 5-625, Wildlife The third sentence of the third paragraph incorrectly states that the Land Exchange alternatives were not analyzed in the Biological Assessment. These alternatives were analyzed in the Biol ogical Assessment (BA). This sentence should be revised to state Land Exchange alternatives were analyzed in the Biological Assessment for the Proposed NorthMet Mining Project and Land Exchange (USACE and USFS November 2013). Comment 245. Section 5.3.6.2.4, pp. 5-646 5-652, Aquatic Species The last sentence in this paragraph is inaccurate because Coyote Creek and Stony River on Tract 3-Wolf Lands are not comparable systems. The Stony River is a higher order, more diverse aquatic system than the first order, headwaters Coyote Creek. It cannot be assumed that the conclusions drawn from the studies for Stony River are applicable to Coyote Creek. Comment 246. General Comment on Chapter 6 PolyMet addresses the issue of cumulative impacts, which is discussed in this chapter, in Attachment D to these comments. Comment 247. Section 6.2.3.3.1, p. 6-17 The fifth paragraph states: The only two reasonably foreseeable actions with the potential to significantly affect fl ow within the Partridge River and Embarrass River are the Mesaba Energy Proj ect East Range Alternative Site and the Mesabi Mining Proj ect, which would result in a net increase in Lower Partridge River flow as a result of pit dewatering for the foreseeable future. This statement seems to ignore the eventual closure of the Northshore Peter Mitchell Pit (which is recognized elsewhere in the SDEIS). When that pit begins filling, Northshore will stop dewatering discharge to the Upper Partridge River. This would be a net decrease in fl ow relative to existing and modeled conditions. This action is anticipated within the model ing period but is not incorporated into the GoldSim model because the actual date of when this change would be made is not known. However, the potential for no discharge from Northshore to the Partridge River was considered in the sensitivity analysis conducted for the Project. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 63 of 70 Comment 248. Section 6.2.3.3.4, p. 6-32, Table 6.2-6 Tabl e 6.2-6 lists cumulative sulfate loadings to the Embarrass River by activity and includes NorthMet uncaptured groundwater seepage and NorthMet WWTF effluent. Tabl e 6.2-6 does not include NorthMet augmentation fl ow from Colby Lake to Embarrass River tributaries. This source has a higher sulfate concentration than the WWTF effluent, and should be included in the Table. Comment 249. General Comment on Section 6.2.3.4 The introduction to Section 6.2.3.4, Wetlands, on page 6-34 states that the cumulative effects analysis focuses on direct effects on wetl ands. Page 6-43 indicates that there will not be indirect cumulative effects on wetl ands because water fl ows will not be changed. This discussion is in some tension with the effects analysis in Chapter 5, which anticipates the potential for some indirect effects on wetlands. PolyMet recommends referencing the discussion in Chapter 5 as part of the cumulative effects discussion. Comment 250. Section 6.2.3.5.1, p. 6-43 Regarding the third sentence of the third paragraph, no federally-listed pl ant species would be affected by the proj ect because there are no federally-listed plant species in all of St. Louis or Lake Counties. PolyMet recommends re-phrasing the sentence to read, No federally-listed plant species are known to occur on the NorthMet Proj ect site. Comment 251. Section 6.2.3.5.4, p. 45, Existing Baseline Conditions and Past Losses The text states that least grapefern (Botrychi um simpl ex) is most likely to occur in lowland deciduous cover types. However, l east grapefern has a broader habitat range than the text implies. The MDNR Rare Species Guide provides: Botrychium simplex var. simplex occurs primarily in open sites, including prairies, wetlands, and abandoned mine sites. Botrychium simplex var. tenebrosum prefers PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 64 of 70 forest interiors, especially l ow moist spots in mesic hardwood forests (Source: MDNR Rare Species Guide: Botrychium simplex). 2 The text also conflicts with Tabl e 6.2-14, which lists both Disturbed and lowland deciduous as the likely habitat types. Finally, the section underestimates the range of least grapefern. The Preferred Pl ant Species Habitat column for least grapefern should include habitats other than l owland deciduous types, as discussed in the MDNR guide. Comment 252. Section 6.2.3.5.4, p. 6-45, Existing Baseline Conditions and Past Losses In the final paragraph bel ow Table 6.2-13, the qualifying statement regarding the lack of precision and the degree of uncertainty inherent in the evaluation methodol ogy should be stated up front in Sections 4.2.4, 5.2.4 and 6.2.4. Comment 253. Section 6.2.3.5.4, p. 6-47, Environmental Consequences of Reasonably Foreseeable Actions on ETSC and RFSS Plant Species In the second sentence, it is unclear what is meant by MDNR minerals division data and how this data pertains to ETSC or RFSS pl ant species. PolyMet recommends clarifying and expl aining why this data is used in this section, but not in Sections 4.2.4 or 5.2.4. Comment 254. Section 6.2.3.5.4, p. 6-49, Environmental Consequences of Reasonably Foreseeable Actions on ETSC and RFSS Plant Species The last paragraph states that forestry management offers a greater range of options for ETSC plants to co-exist with the practice, as it can mimic natural disturbances. This statement seems to be based on the previous statement in Section 5.2.4.2.1, p. 5-348, that Disturbance-tol erant species may, in some cases, actually be disturbance- dependent. As stated in a prior comment, PolyMet believes this statement is misleading and that it is inaccurate to suggest that ETSC pl ants favor and/or are increased by disturbance regimes. 2 Available at http://www.dnr.state.mn.us/rsg/profile.html ?action=elementDetail&selectedElement=PPOPH010E0. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 65 of 70 Comment 255. Section 6.2.3.7, p. 6-62, Effects from Mercury Deposition In the l ast sentence of the l ast paragraph, the increased percentage from the NorthMet Project Proposed Action al one should be 0.2 to 1.6 percent, not 0.2 to 1.8. Comment 256. Section 6.2.3.7, p. 6-63, Effects from Mercury Deposition PolyMet also recommends adding the following additional sentence at end of the paragraph at the top of the page: This potential change is not likely statistically measureabl e and does not have any effect on the background fish Hg concentrations nor the current fish consumption advisories for the respective l akes." Comment 257. Section 6.2.3.7, p. 6-63, Effects from Mercury Deposition In the first complete paragraph, the description of how the HQ is calculated does not refl ect the calculations in the MMREM spreadsheet. To estimate the potential incremental HQ, the incremental methyl mercury exposure in mg/kg body weight per day and the reference dose are accounted for in the calculation. The derivation of the incremental HQ can be described as noted below: The incremental HQ calcul ation in the MMREM Spreadsheet uses the following methodol ogy: Incremental daily mercury consumed (mg) = estimated incremental increase in fish mercury due to the Proj ect (mg/kg) x the amount of fish consumed (e.g. 0.142 kg for a subsistence fisher) Incremental methylmercury exposure (mg/kg BW day) = Incremental daily mercury consumed x 1.07945 / adult body weight (70 kg) Incremental HQ = Incremental methylmercury exposure (mg/kg BW day) / Reference Dose of 1.00E-04 mg HgCH3/kg bw-day (i.e., the ratio of the incremental methylmercury exposure divided by the reference dose in the same units). PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 66 of 70 Comment 258. Section 6.2.3.8.4, p. 6-77, Table 6.2-19, Total Cumulative Modeled Air Concentration The cumul ative emissions modeling includes NorthMet, so adding this result to the Project impacts includes some double counting of impacts. See also second to l ast sentence in paragraph under Section 6.2.3.8.4 header on p. 6-64. PolyMet suggests the following text changes and note additions to Tabl e 6.2-19: Class I Area Averaging Time Maximum Modeled Air Concentration For NorthMet Modeled Emissions Maximum Modeled Air Concentration For Cumulative Modeled Emissions (MPCA Inventory 1 ) Conservative Estimate of Total Cumulative Modeled Air Concentration 3) 2 PSD Increment 3) BWCAW 24-hour 0.33 1.76 2.09 8 Voyageurs National Park 24-hour 0.13 0.22 0.35 8 1 The MPCAinventory includes the Project, but not the same emission datathat was modeledfor the SDEIS. 2 The value is conservative because the Project is included in both the MPCA inventory and the modeling done for the Project alonefor the SDEIS. Comment 259. Section 6.2.3.8.11, p. 6-87, Potential Cumulative Inhalation Risk Assessment Regarding the last sentence of the first paragraph, the cumulative analysis included both the Mesabi Nugget Large Scale Demonstration Pl ant and the Mesabi Mining Project. Comment 260. Section 6.2.3.8.11, p. 6-88, Table 6.2-22 The incremental result for Mesabi Nugget noncancer acute should be 0.03. The percentages at the bottom should be 9% for Cancer and 7% for Noncancer Chronic. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 67 of 70 Comment 261. Section 6.2.3.8.5, p. 6-77, Cumulative Effects of Acid Deposition on Ecosystems Regarding the third sentence of the first paragraph, dry deposition, as well as wet deposition, was in the cumulative assessment. Comment 262. Section 6.2.3.8.8, p. 6-86, Summary of Visibility Cumulative Effects Analysis PolyMet suggests editing the header of Point 4 to read: "15 percent of 2018 visibility impairment proj ected to be due to northeast Minnesota emissions and 70 percent of visibility impairment due to out of state emissions" Comment 263. Section 6.2.3.8.8, p. 6-86, Summary of Visibility Cumulative Effects Analysis PolyMet suggests the last sentence of Point 4 be revised to read: "Emissions from Minnesota are the single largest contributor to regional haze and its own Class I areas; however, most of the visibility impairment in these areas is due to out of state emissions." Comment 264. Section 6.2.3.8.9, p. 6-86, Summary of Visibility Cumulative Effects Analysis PolyMet recommends adding language to Item 5 that indicates national emission reductions are likely to drive further improvement of visibility in MN Class I areas. Comment 265. Section 6.2.3.11.2, p. 6-96, Cumulative Effects The third paragraph under the heading 1854 Treaty Resources states that the NorthMet Project Proposed Action could affect treaty resources through the bioaccumulation of mercury in fish tissue. This statement is inconsistent with the SDEISs evaluation of cumulative effects on aquatic resources, which states that there will not be a significant increase of mercury in fish tissue. Because the subj ective belief PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 68 of 70 that such an effect may occur does not qualify as an effect under NEPA, the statement on page 6-95 should be removed from the SDEIS. Comment 266. Section 6.2.3.13.4, p. 6-105, Cumulative Effects The statement on hazardous materials in Section 6.2.3.14 indicates that there could be a small likelihood of cumulative effects associated with increased traffic carrying hazardous materials. This is a mischaracterization of the potential cumulative effect. The sentence should state that the small increased risk associated with traffic carrying hazardous materials is not a significant cumulative effect. Comment 267. Section 6.3, Land Exchange Proposed Action PolyMet recommends clarifying whether acres are reported in GLO or GIS throughout the entire section. Comment 268. Section 6.3.4.4.3, p. 6-121, Effect of Cumulative Actions on GAP Analysis Program Land Cover Types The text in the last paragraph is somewhat misl eading by stating that there would be a decrease to MBS Sites of High and Moderate Biodiversity Significance. The non- federal lands have not been surveyed for MBS sites yet. Therefore, you cannot accurately say that there would be a decrease; the surveys could potentially indicate that there would be an increase, or an even exchange. Comment 269. General Comment on Section 7.2 PolyMet addresses the issue of the Land Exchange Proposed Action, which is discussed on this section, in Attachment B to these comments. Comment 270. Section 7.3.1, p. 7-10, Comparison of Alternatives and Other NEPA Considerations The final sentence in Section 7.3.1 indicates that the federal lands contain certain natural resources that are culturally important to the Bands. Whil e it is accurate that these resources would be l ost if the NorthMet Proj ect Proposed Action moves forward, it PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 69 of 70 is also true, and should be noted, that there is no evidence of the Bands accessing any resources at the Mine Site. Comment 271. Section 7.3.1, p. 7-10, Comparison of Alternatives and Other NEPA Considerations The third sentence in the third paragraph of Section 7.3.1, Irreversi ble or Irretri evable Commitment of Resources, states that whil e cultural resources may be adversely affected, those effects would be minimized through avoidance. Under Section 106 of the National Historic Preservation Act, avoidance is not the only means of addressing adverse effects on historic properties, including the cultural resources identified in the SDEIS. Agencies may also choose to adopt minimization or mitigation measures. Those options should also be recognized in this paragraph. Comment 272. Section 7.3.3, p. 7-12, Comparison of Alternatives and Other NEPA Considerations The final sentence in the first paragraph of Section 7.3.3, Unavoi dable Adverse Effects, states that effects on water quality would remain after the implementation of mitigation measures. The paragraph should note that these effects would be minor, and not qual ify as significant environmental effects. Comment 273. Section 7.4, p. 7-12, Comparison of Alternatives and Other NEPA Considerations The first paragraph of Section 7.4, PREFERRED ALTERNATIVE, states that CEQ regul ations do not require agencies to select a preferred alternative in a Draft EIS like the SDEIS. The same paragraph states that the USACEs NEPA regulations (Appendix B of 33 C.F.R. Part 325) supersede the CEQ regul ations requirement to identify an agency-preferred alternative. This description of these requirements is confusing. Neither the CEQ regul ations nor the USACE regul ations require the selection of a preferred alternative in the SDEIS. Comment 274. Appendix B, p. 1, 1.2 Assessment of Material In the first sentence, semi-qualitative should be changed to semi-quantitative. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 Page 70 of 70 Comment 275. Appendix B, p. 4, 2.2 Availability The last sentence of this section should be changed to: Notwithstanding economic considerations the underground mining alternative is available at the NorthMet Deposit. Comment 276. Appendix B, p. 5, 2.4.1 Mineralization at the NorthMet Deposit With respect to the bullet list of metal prices after the first paragraph, the referenced price for cobalt should be $17.69 per pound. Comment 277. Appendix B, p. 7, 2.4.2 Underground Mining Costs In Table 2, the Pre-production Capital Costs ($ million) of 300 should be changed to 250. The Profit: Metal Value Costs ($ million) of -$193 should be changed to -$192 and -$364 should be changed to -$314. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 1 ATTACHMENT A ALTERNATIVES COMMENTS The Supplemental Draft Environmental Impact Statement (SDEIS) indicates that the NorthMet Project Proposed Action and alternatives were developed during project scoping in 2005. SDEIS p.3-142. The SDEIS further explains that several refinements were made to the proposed action in the 2009 Draft Environmental Impact Statement (DEIS), such that the NorthMet Project Proposed Action studied in the SDEIS is not identical to the proposed action in the 2009 DEIS. Id. At the same time, the SDEIS points out that because some of the alternatives to the proposed action were eliminated during the scoping and DEIS phases of the project, they were not re-evaluated in the SDEIS. Id. at 3-142, 3-143 & Figure 3.2-32. The alternatives review for the NorthMet Project fulfilled all of NEPAs and MEPAs requirements. Indeed, the careful review, refinement and elimination of alternatives is a paradigm of proper environmental review. Section 3.2.3 of the SDEIS would be improved if it better reflected the thoroughness of the Co-lead agencies alternatives review, including review that occurred during scoping and the 2009 DEIS. To that end, this comment attachment offers a brief overview of the entire alternatives review process, and a recommendation for minor changes in the Final EIS. 2005 Scoping Decision The formal scoping process for the NorthMet Project began nearly a decade ago, with the June 2005 publication of a Scoping Environmental Assessment Worksheet (EAW) and a Draft Scoping Decision. The next month, the U.S. Army Corps of Engineers (USACE) published a Notice of Intent to prepare an EIS for the project. The agencies engaged in public reviewand comment of these documents, including comment on potential project alternatives. On October 25, 2005, after consideration of potential project alternatives and environmental effects, the agencies published a Final Scoping Decision Document (FSDD) that describes various alternatives in each of the categories required by Minnesota lawalternative sites, alternative technologies, modified designs or layouts, modified scale or magnitude, and alternatives incorporating mitigation measures. As discussed below, the scoping document explains why some of these alternatives were eliminated from further consideration, while others were carried forward for more detailed study in the 2009 DEIS. SiteAlternatives The FSDD explained that, because the mineralization dictates the location of the mine site, an alternative site would not meet the projects purpose and need and should be eliminated from further consideration. FSDD p.3. An alternative plant site was likewise eliminated from further consideration on the grounds that the re-use of an existing facility would have fewer environmental effects than other, greenfield sites. Id. Two alternative waste rock disposal sites and one alternative tailings basin site were carried forward for further consideration in the DEIS. Id. pp.2-3. TechnologyAlternatives The agencies considered two alternative technologies for the project. They decided not to evaluate alternative hydrometallurgical technologies, concluding that they would not have significant environmental benefits over what PolyMet had proposed. FSDD p.4. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 2 The agencies also briefly addressed an underground mining alternative, noting that [i]f the cost of developing an underground mining alternative were so high that [PolyMet] could not develop the project, this alternative would not meet the purpose and need of the project. Id. p.5. The underground mining alternative was carried forward for further consideration in the DEIS. ModifiedDesignsor Layouts The agencies eliminated alternative designs for the transportation corridor and the plant site, neither of which offered environmental benefits greater than those offered by the proposed project. FSDD p.5. With respect to the mine site, the agencies considered a number of different design and layout modifications, including using two mine pits instead of three, chemical modification and lined tailings basin disposal of reactive waste rock stockpiles, pre-treatment of certain wastewater, and use of reactive wastewater as make-up water for the plant site. Id. p.6. Each of these alternatives, along with several technical design reports, was slated for further consideration in the DEIS. Scaleor MagnitudeAlternatives The FSDD evaluated the possibility of changing the scope of the proposed project, but concluded that the return on investment for a smaller scale project was infeasible. Accordingly, the FSDD concluded that a reduced scale would not meet the purpose and need of the project. FSDD p.7. AlternativesIncorporatingMitigationMeasures In addition to alternatives that would modify the project, the FSDD also included alternatives that incorporated reasonable mitigation measures. The first of these mitigation alternatives proposed monitoring programs for waste rock stockpiles and the tailings basin. FSDD p.7. The second mitigation alternative included a lined tailings storage facility within the tailings basin, and continued testing to determine tailings reactivity. Id. pp.7-8. Both of these mitigation alternatives were carried forward for additional consideration in the DEIS. 2009 DEIS Following the publication of the FSDD, PolyMet provided a project description to the co-lead agencies. Over the next three years, PolyMet continued to gather data and consult with the agencies, which led to several modifications to the proposed action. Among these modifications was the incorporation of certain mitigation measures, as well as the two mine pit alternative, into the proposed action. In addition to a no-action alternative, the DEIS analyzed the following alternatives to PolyMets proposed action: MineSiteAlternative The Mine Site Alternative consisted of modifications to the mine site design or layout intended to reduce potential effects on surface water and groundwater. The Mine Site Alternative proposed, among other things, sub-aqueous disposal of the most reactive waste rock and lined, temporary stockpiles for other waste rock. DEIS p.3-51. TailingsBasin Alternative The Tailings Basin Alternative included various modifications to the tailings basin intended to increase geotechnical stability and capture seepage from the tailings basin. DEIS p.3-52. The Tailings Basin Alternative resulted fromthe comprehensive mitigation planning effort by the co-lead agencies, and included input from all Cooperating Agencies and consulting tribes. DEIS Table 3.2.2 lists twenty-seven individual mitigation measures developed PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 3 by this effort. DEIS Table 3.2-3 lists eleven combinations of individual mitigation measures that were considered before selecting the Tailings Basin Alternative. AlternativesConsideredBut Eliminated On the basis of analysis performed in connection with the 2009 DEIS, several of the alternatives identified in the FSDD were eliminated from further consideration. These included: (1) alternative waste rock disposal sites (DEIS p.3-62); (2) the underground mining alternative, which was found to have costs so high that it failed to meet the purpose and need of the project, and to pose safety hazards from mine ceiling collapse (id. pp.3-58, 3-64, 3-69); and (3) pretreatment of runoff and use of runoff as make-up water at the mine site (id. p.3-70). The DEIS also used a table (DEIS Table 3.2-4) to explain in detail the reasons that twenty-one different alternatives were eliminated from further consideration. The discussion in this section of the 2009 DEIS remains the best explanation for the elimination of the various alternatives that were identified and advanced for additional consideration by the FSDD. 2013 SDEIS As noted above, the SDEIS contains a brief summary of the alternatives evaluation that took place during the scoping and DEIS processes. When the agencies determined that a supplemental environmental document was necessary, PolyMet continued to refine its proposed action, taking into account the analysis in the DEIS, as well as comments on that analysis from agencies and the public. The most significant changes to PolyMets proposal involved improved waste and water management at both the Mine Site and the Plant Sitethe key features of the Mine Site Alternative and the Tailings Basin Alternative from the 2009 DEIS. SDEIS p.3-142. Consequently, instead of three action alternatives, the SDEIS contained just one action alternativethe NorthMet Project Proposed Actionwhich effectively combined the three alternatives studied in the 2009 DEIS, in addition to making other improvements and including a number of new mitigation measures. Id. The SDEIS also reconsidered in more detail certain alternatives that had been eliminated by the analysis in the 2009 DEIS. Those reconsidered alternatives included alternatives for a cover system on the Tailings Basin, one of which PolyMet ultimately adopted (SDEIS p.3-149); an underground mining alternative, which the SDEIS again rejected (id. p.3-150 & App. B); and a West Pit backfill alternative, which was likewise eliminated from further consideration (id. p.3- 151). Table 3.2-17 in the SDEIS summarizes the alternatives from the 2009 DEIS that were re- screened during the SDEIS process, and explains why those alternatives were either eliminated or incorporated into the NorthMet Project Proposed Action. Table 3.2-18 summarizes the site, technology, design/layout and scale alternatives considered during the entire NEPA and MEPA process, with reference to the alternative identification numbers used in the 2009 DEIS. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 4 Conclusions and Recommendations As the above discussion makes clear, the FSDD, 2009 DEIS and SDEIS contain a careful, thorough reviewof numerous alternatives to the NorthMet Project Proposed Action that fully satisfies the requirements of both NEPAand MEPA. It is unnecessary to discuss all the details of that review in the SDEIS. Nonetheless, PolyMet recommends three changes to clarify the process by which alternatives were considered and either eliminated from further consideration, or incorporated into the NorthMet Project Proposed Action. First, PolyMet recommends explicitly referencing and incorporating into the SDEIS those portions of the FSDD and the 2009 DEIS that address alternatives. This should increase understanding of the iterative process of alternatives reviewthat the SDEIS already references in several places. Second, PolyMet recommends including an updated version of Table 3.2-4 from the 2009 DEIS somewhere in the Final EIS, either directly in the discussion of alternatives or as an appendix. This would provide context for the discussion of alternatives review and the elimination of alternatives that are not discussed as part of the SDEIS process. Lastly, these changes should also be reflected in the Executive Summary, which tends to focus on the SDEIS alternatives reviewprocess, without fully acknowledging the role played by alternatives review in the FSDD and the 2009 DEIS. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 1 ATTACHMENT B LAND EXCHANGE COMMENTS This attachment to PolyMets comments on the Supplemental Draft Environmental Impact Statement (SDEIS) includes detailed comments on the Land Exchange Proposed Action. The Land Exchange Is Independently Justified The SDEIS properly acknowledges that the U. S. Forest Service (USFS) decision on the Land Exchange Proposed Action must be based on applicable USFS standards. But the SDEIS could more clearly state that the Land Exchange Proposed Action can proceed if those standards are met, regardless of what happens with the NorthMet Project Proposed Action. Accordingly, consistent with the discussion in the 2009 Draft Environmental Impact Statement (DEIS), PolyMet recommends that the Final Environmental Impact Statement (Final EIS) clarify that the Land Exchange Proposed Action may occur independently of the NorthMet Project Proposed Action. The SDEIS includes ample information demonstrating that the Land Exchange Proposed Action independently satisfies applicable regulatory standards. For convenience and ease of comparison, PolyMet is providing a detailed matrix with these comments that compares the record information concerning the federal lands and non-federal lands proposed for exchange. The fact that the Land Exchange Proposed Action and the NorthMet Project Proposed Action are treated as connected actions in the SDEIS does not mean that the two actions are completely interdependent. Rather, the two actions are treated as connected in the SDEIS because there is sufficient relationship between the two separate federal actions that addressing both in a single NEPA document is appropriate. Polymet recognizes USFSs position that mining (i.e., the NorthMet Project Proposed Action) could not occur on National Forest System Lands within the Superior National Forest. The land exchange has the effect of eliminating any dispute over PolyMets right to mine. But even though USFS maintains that the mining cannot occur without the Land Exchange, USFS and PolyMet agree that the Land Exchange is not contingent on regulatory approval of the NorthMet Project. The Final EIS accordingly should clearly state that the Land Exchange Proposed Action can proceed entirely apart from the NorthMet Project Proposed Action, so long as the USFS determines that the land exchange is in the public interest and the regulations governing land exchanges are satisfied. The environmental effects of both the Land Exchange Proposed Action and the NorthMet Project Proposed Action are fully and separately evaluated in the SDEIS. As a result, it is not necessary to create an entirely newalternative for NEPAevaluation. As Section 3.3.3.3 of the SDEIS explains, alternatives need not be analyzed in detail if they are already represented in the review of other alternatives environmental effects. The Final EIS accordingly should clarify that the alternative of proceeding with the Land Exchange Proposed Action in the absence of the NorthMet Project Proposed Action was considered but eliminated from detailed analysis in the SDEIS because it is represented by the combination of no action on the NorthMet Project Proposed Action and Land Exchange Proposed Action Alternative A. This could be accomplished by adding a brief description of the Land Exchange Proposed Action as a stand alone action in Section 3.3.3.3. The alternative would not be eliminated as unreasonable, but rather it would not require further analysis because its impacts were already revealed and evaluated in the SDEIS detailed evaluation of other alternatives. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 2 Relatedly, the USFS purpose and need statement in the Final EIS should clearly state that the Land Exchange Proposed Action is intended to consolidate and enhance the functional boundaries of the Superior National Forest, improve public access to National Forest System lands, and implement the overall goals of the Forest Plan for the Superior National Forest. This language will expand on the SDEISs accurate statement that the USFS will observe the regulatory requirements for land exchanges. The statement of purpose and need should not suggest that the sole purpose of the Land Exchange Proposed Action is to avoid a disagreement over PolyMets right to mine under its minerals lease. PolyMet further recommends adding to the front of the Final EIS a discussion of the regulations that require the USFS to ensure there is equalization of exchange values between the federal and non-federal lands, and more clearly linking these regulations with subsequent discussions of this topic in the record. In doing this, the USFS should make clear moving forward that Polymet intends to transfer all of the non-federal lands to the United States, whether they are needed for the Land Exchange Proposed Action exchange or not. At the same time, the USFS can highlight the possibility of a cash equalization if the offered non-Federal lands are deemed insufficient to provide an equal value exchange. Finally, in light of the discussion above, PolyMet recommends that the USFS ensure that the Executive Summary is updated to conform to any changes made in the Final EIS. The independent grounds for undertaking the Land Exchange Proposed Action should be particularly clear in the revised Executive Summary, because many readers likely will rely on the Executive Summary to understand the contents of the EIS. Detailed Comments on the Land Exchange Proposed Action In the paragraphs that follow, PolyMet identifies certain sections of the SDEIS (in numerical order) where it recommends changes to the discussion of the Land Exchange. In the enclosed attachment, PolyMet identifies additional sections/text for proposed revision. Depending on the nature and extent of the changes to the Final EIS, there may be other sections of the document that would also benefit from clarification. Section 1.1.2, Land Exchange Section 1.1.2, Land Exchange, uses the phrase depending on the results of the environmental analysis and real estate appraisals to mean that the USFS will comply with applicable regulations and Executive Order (EO) 11990 and 11988 to require equalization of exchange values for the federal and non-federal lands, both in terms of market value and acreage of wetlands. As the USFS is aware, Section 3.3.1.1 (among others) discusses the applicable regulations in 36 CFR Part 254 and EOs 11990 and 11988. Discussing these applicable orders and regulations in Section 1.1.2when the Land Exchange Proposed Action is first introducedand stating expressly that the USFS will require equalization of exchange values, would help to clarify subsequent uses of the phrase. In addition, modifying this phrase (each time it appears) to say something more along the lines of depending on the results of the environmental analysis and real estate appraisals, and in order to ensure equalization of exchange, would also improve understanding of this issue. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 3 In this regard, it is important to note that Polymet is committed to transferring all of the non- federal lands to the United States under the Land Exchange Proposed Action for management within the Superior National Forest, regardless of the results of the analysis of equalization of the exchange. If the USFS determines that all of the non-federal lands are not needed for an equal exchange under the Land Exchange Proposed Action, PolyMet would transfer title on a voluntary basis. Conversely, if the non-federal lands are not sufficient for an equal exchange, Polymet would make a cash payment as authorized under governing regulations. Ultimately, under the Land Exchange Proposed Action, all of the non-federal lands identified and described in the SDEIS will become part of the Superior National Forest. Section 1.3, Purpose and Need Section 1.3, Purpose and Need, would be strengthened by a more robust discussion of the purpose of the Land Exchange Proposed Action, which clearly incorporates the relevant regulatory and public interest factors. While the discussion in Section 1.4.3, Land Exchange Requirements, identifies the regulatory and public interest factors that the ROD will need to address in determining whether the Land Exchange Proposed Action should go forward, it should be made clear that the phrase in Section 1.3.2.2, meet desired conditions in the Superior National Forest Land and Resource Management Plan (Forest Plan), includes the regulatory and public interest factors discussed later in Section 1.4.3. Thus, PolyMet would recommend the Final EIS specifically identify these factors in the initial discussion in Section 1.3, and include a cross-reference to the more detailed discussion in Section 1.4.3. In addition, although it is true the proposed land transfer will eliminate the need to otherwise resolve a conflict between PolyMet and the USFS regarding the companys right to mine, the Final EIS should be clear that the land exchange will be justified under governing regulatory and public interest standards. Fundamentally, the Land Exchange Proposed Action will allow for the consolidation of lands within the Superior National Forest in a manner consistent with governing authorities. Section 1.3.2.1 accordingly should highlight this consolidation of lands as a primary purpose of the Land Exchange Proposed Action, instead of focusing on the elimination of the potential conflict. To ensure that the reader is fully informed on the potential conflict, however, Section 1.3.2.2 should identify the fact that PolyMet does not agree with the USFS legal position. This could be done by cross-reference to the appropriate sections in the 2009 DEIS that discuss this issue in greater detail than the SDEIS. For example, a simple cross-cite to Section 1.3.2.2 of the 2009 DEIS would ensure that the reader is aware that additional information on this topic is contained in the 2009 DEIS. PolyMet notes that the SDEIS repeats the USFS position (i.e., that mining cannot occur within the Federal Lands) in many places; as a result, it would be appropriate to note that PolyMet does not agree in most of the places where this issue is described. Section 3.3, Land Exchange Proposed Action Detailed Description In various places in Section 3.3, Land Exchange Proposed Action Detailed Description, PolyMet recommends clarifying that the Land Exchange Proposed Action may proceed even if the NorthMet Project Proposed Action does not. As discussed above, PolyMet recommends the PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 4 Final EIS clearly state that the Land Exchange Proposed Action can occur independent of the regulatory approvals for the NorthMet Project Proposed Action. Federal Lands Non-federal Lands Feature Definition Proposed Action Alternative B No Action Total for Proposed Action Hay Lake Lands (Tract 1) Lake County Lands (Tract 2) Wolf Lake Lands (Tract 3) Hunting Club Lands (Tract 4) McFarland Lake Lands (Tract 5) Public Net Gain (Loss) GENERAL Location County St. Louis St. Louis St. Louis --- St. Louis County Lake County Lake County St. Louis County Cook County NA Located within 1854 Ceded Territory yes yes yes yes yes yes yes yes yes yes Total size of lands Acres (GLO) 6,650.2 4,900.7 no change 6,722.5 4,651.5 4,651.5 1,559.4 160.0 32.1 yes Ownership Current Surface Estate USFS USFS USFS Lake County Lands, private PolyMet; mortgage from IRR Lake County tax forfeit lands; purchased in name of Lake- Forest Enterprise, Inc. on a land contract from Lake County. All right, title and interest in land will be assigned to PolyMet. Purchased in name of Lake- Forest Enterprise, Inc through options from Wolf Lands, Inc. All right, title and interest in land will be assigned to PolyMet. PolyMet Mining, Inc. PolyMet; mortgage from IRR NA Current Mineral Estate/Mineral Development Potential (MDP) private;USFS high MDP private;USFS high MDP private;USFS high MDP Outstanding, State of MN, private low MDP Outstanding low MDP Outstanding; State of MN low MDP Anton T. Anderson, Kimberly Clark, Duluth & Iron Range Railroad Co. Low MDP Mineral rights owned by surface owner low MDP Outstanding low MDP yes Current Land Use Authority USFS USFS USFS St. Louis County, Lake County, Cook County St. Louis County zoning ordinance Lake County zoning district Lake County zoning district St. Louis County zoning ordinance Cook County zoning ordinance NA Existing/Proposed USFS Management Unit (see 4.2.1 and 4.3.1) General Forest, General Forest-Longer Rotation General Forest, General Forest-Longer Rotation General Forest, General Forest- Longer Rotation General Forest, General Forest- Longer Rotation, Riparian Emphasis, cRNA General Forest , cRNA General Forest, General Forest- Longer Rotation, Riparian Emphasis Area General Forest, General Forest- Longer Rotation, Riparian Emphasis Area General Forest- Longer Rotation General Forest- Longer Rotation NA NATURAL RESOURCES MDNR resource categories Page 1 of 5 Federal Lands Non-federal Lands Feature Definition Proposed Action Alternative B No Action Total for Proposed Action Hay Lake Lands (Tract 1) Lake County Lands (Tract 2) Wolf Lake Lands (Tract 3) Hunting Club Lands (Tract 4) McFarland Lake Lands (Tract 5) Public Net Gain (Loss) GENERAL Dominant MDNR GAP Cover Types (acres of GAP types that represent at least 20% of area) lowland coniferous forest (2,979), upland coniferous forest (1,619) lowland coniferous forest (2,065), upland coniferous forest (1,366) no change lowland coniferous forest (2,921), shrubland (1,845) shrubland (1,665), lowland coniferous forest (1,524), upland deciduous forest (1,000) lowland coniferous forest (186) lowland coniferous forest (1,202) upland deciduous forest (85), shrubland (45) upland deciduous forest (27) NA Wildlife species (special status) Federal-listed 1 1 no change 1 1 0 0 0 0 NA State-listed (ETSC) 2 2 no change 2 2 0 0 0 0 NA Wildlife corridors (identified) none none no change none none none none none none NA Wildlife species habitat Critical Canada lynx habitat Yes Yes no change Yes Yes Yes Yes Yes Yes Yes Suitable lynx habitat 6,371.5 4,697.2 no change 6,808.4 4,675.1 376.1 1575.9 150.7 30.6 Yes Suitable lynx denning habitat 5,393.4 3,912.9 no change 5,364.3 3,720.0 267.9 1,254.1 92.2 30.1 NA Federal or State Wolf Zone Yes Yes no change Yes No Yes Yes Yes Yes NA Wolf forage habitat 271.1 271.1 no change 778.2 533.8 67.7 149.7 27 0 Yes Wolf cover habitat 5,393.4 3,912.9 no change 5,364.3 3,720.0 267.9 1254.1 92.2 30.1 NA WATER RESOURCES Wetlands Total Acreage 4,164.4 2,860.9 no change 4,669.9 2,930.8 282.9 1,392.6 63.6 0 Yes Dominant Types (acres) Types representing at least 20% of the wetland area are included coniferous bog (1,961.4), coniferous swamp (1,287.8) coniferous bog (1,677.0) no change coniferous swamp (3,242.4), shrub swamp (1,062.4) coniferous swamp (1,953.9), shrub swamp (706.1) coniferous swamp (167.4) coniferous swamp (1,105.7) shrub swamp (32.0), coniferous swamp (15.4), shallow marsh (13.0) none NA Functional assessment high/moderate high/moderate no change high/moderate high/moderate high/moderate high/moderate high/moderate NA NA Lakes (number) 1 1 1 3 3 0 0 0 lake is adjacent but not on the Tract Yes Names Mud Lake Mud Lake Mud Lake Hay Lake, Little Rice Lake, Unnamed Lake Hay Lake, Little Rice Lake, Unnamed Lake none none none McFarland Lake is adjacent to the Tract NA Size (acres) 30.5 30.5 30.5 513.6 129.6 NA NA NA 384.0 Yes Frontage (feet) 4,550.0 1,200.0 4,550.0 17,414.0 16,424.0 NA NA NA 990.0 Yes Documented wild rice lakes none none none Hay Lake Hay Lake none none none none Yes Rivers, streams, creeks (number) 2 2 2 2 1 none 1 none none Yes Names Yelp Creek, Partridge River Yelp Creek, Partridge River Yelp Creek, Partridge River Pike River, Coyote Creek Pike River NA Coyote Creek NA NA NA Length (miles) 5.3 5.3 5.3 9.0 8 NA 1.0 NA NA Yes Page 2 of 5 Federal Lands Non-federal Lands Feature Definition Proposed Action Alternative B No Action Total for Proposed Action Hay Lake Lands (Tract 1) Lake County Lands (Tract 2) Wolf Lake Lands (Tract 3) Hunting Club Lands (Tract 4) McFarland Lake Lands (Tract 5) Public Net Gain (Loss) GENERAL Frontage (includes both sides, feet) 60,523.0 55,968.0 60,523.0 83,424.0 72,864.0 NA 10,560.0 NA NA Yes Aquatic Connectivity Index (ACI) extent of dams, bridges, and culverts along stream segments Floodplains associated with the Pike River none associated with the Coyote Creek none none NA FEMA 0 0 no change 0 0 NA 0 NA NA NA ACCESSIBILITY Public access points via road, trail, or lake No practical public access No practical public access No Yes - Tracts 1, 4 and 5; No - Tacts 2 and 3 yes - via road, trail, and lake CR715 forms part of east boundary yes - trail is present but difficult access no - parcels 1 and 2; yes - parcel 3 via trail; yes, parcel 4 via nearby road yes, from nw via trail from a gravel road yes - via lake or adjacent USFS land Yes Future access to Lands No No No open to public as USFS lands open to public as USFS lands open to public as USFS lands open to public as USFS lands open to public as USFS lands open to public as USFS lands Yes Recreation Opportunity Spectrum (ROS) - Classes total (acres) 0.0 0.0 no change 7,075.0 4,926.3 381.9 1,556.1 179.9 30.8 Yes Semi-primitive motorized (acres) 0.0 0.0 no change 3,285.1 1,303.8 265.0 1,556.1 160.2 0.0 Yes Semi-primitive non-motorized (acres) 0.0 0.0 no change 2,319.9 2,162.2 116.9 0.0 0.0 30.8 Yes Roaded natural (acres) 0.0 0.0 no change 1,480.0 1,460.3 0.0 0.0 19.7 0.0 Yes Hunting/trapping No No No Yes no but old sand/gravel pit used as shooting range. Deer stands observed. Yes Yes no Yes Fishing No No No Hay Lake, Little Rice Lake, Unnamed Lake, Pike River, Coyote Creek, McFarland Lake Hay Lake, Little Rice Lake, Unnamed Lake, Pike River none Coyote Creek none McFarland Lake is adjacent to the Tract Yes CULTURAL RESOURCES Within 1854 Ceded Territory resources yes yes no change yes yes yes yes yes yes NA Usufractory rights of 1854 Ceded Territory resources could be available No practical access to exercise rights No practical access to exercise rights no change yes yes yes yes yes yes Yes SOCIOECONOMIC Page 3 of 5 Federal Lands Non-federal Lands Feature Definition Proposed Action Alternative B No Action Total for Proposed Action Hay Lake Lands (Tract 1) Lake County Lands (Tract 2) Wolf Lake Lands (Tract 3) Hunting Club Lands (Tract 4) McFarland Lake Lands (Tract 5) Public Net Gain (Loss) GENERAL Forestry products not accessible; no current economic activity although timber harvesting is permitted by the Forest Plan. Company has granted access for timber harvest in the past. Such access may not be granted due to public safety and conflict with neighboring mining activities. not accessible; no current economic activity although timber harvesting is permitted by the Forest Plan. Company has granted access for timber harvest in the past. Such access may not be granted due to public safety and conflict with neighboring mining activities. not accessible; no current economic activity although timber harvesting is permitted by the Forest Plan. Company has granted access for timber harvest in the past. Such access may not be granted due to public safety and conflict with neighboring mining activities. positive economic effects due to the value of forestry products made available on the non-federal lands, as well as jobs and revenue due to increased visitation of the non-federal lands positive economic effects due to the value of forestry products made available on the non-federal lands, as well as jobs and revenue due to increased visitation of the non-federal lands positive economic effects due to the value of forestry products made available on the non-federal lands, as well as jobs and revenue due to increased visitation of the non-federal lands positive economic effects due to the value of forestry products made available on the non-federal lands, as well as jobs and revenue due to increased visitation of the non-federal lands positive economic effects due to the value of forestry products made available on the non-federal lands, as well as jobs and revenue due to increased visitation of the non-federal lands positive economic effects due to the value of forestry products made available on the non-federal lands, as well as jobs and revenue due to increased visitation of the non-federal lands Yes Environmental Justice and Subsistence No road or trail access, difficult access for subsistence use under usufractory rights No road or trail access, difficult access for subsistence use under usufractory rights no change likely positive effects but as yet undetermined effects for EJ populations and subsistence activities, due to the net increase in the amount of public land available for subsistence activities, but unknown changes in the type and extent of subsistence resources on the federal and non-federal lands Available for subsistence use under usufractory rights Available for subsistence use under usufractory rights Available for subsistence use under usufractory rights Available for subsistence use under usufractory rights Available for subsistence use under usufractory rights Yes Hazardous Materials Page 4 of 5 Federal Lands Non-federal Lands Feature Definition Proposed Action Alternative B No Action Total for Proposed Action Hay Lake Lands (Tract 1) Lake County Lands (Tract 2) Wolf Lake Lands (Tract 3) Hunting Club Lands (Tract 4) McFarland Lake Lands (Tract 5) Public Net Gain (Loss) GENERAL Phase I ESA results No Issues No Issues Legacy Contamination Structure removal and debris prior to closing Structure removal and debris prior to closing no issues no issues no issues no issues - Tract 5 was formerly owned and used by Wheaton College. A bunkhouse, fire ring, outhouse, and cistern are present, although these structures would be removed prior to the completion of the Land Exchange Proposed Action. NA Page 5 of 5 PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 1 ATTACHMENT C AMPHIBOLE MINERAL FIBERS COMMENTS This attachment includes PolyMets detailed comments on the issue of amphibole mineral fibers in the Supplemental Draft Environmental Impact Statement (SDEIS). Background The Background discussion in SDEIS Section 5.2.7.5.1 rightly recognizes that [r]egulatory definitions for classifying fibers vary. In fact, Minnesota statutes and regulations do not define the term amphibole mineral fibers. The description of [t]he State of Minnesotas definition of amphibole mineral fibers in the Background discussion appears instead to be a reference to the permit-specific definition of fibers included in Northshore Mining Companys Title V permit. That definition does not have general applicability. It is also important to note, as background, that neither the U.S. Environmental Protection Agency (EPA) nor the Minnesota Pollution Control Agency (MPCA) has ever promulgated an ambient air fiber standard, level or limit. International Symposium on the Health Hazard Evaluation of Fibrous Particulates Associated with Taconite and the Adjacent Duluth Complex Although the SDEIS indicates that ERM conducted a literature review in 2009, it does not appear that review included the studies resulting from the 2003 International Symposium on the Health Hazard Evaluation of Fibrous Particulates Associated with Taconite and the Adjacent Duluth Complex (International Symposium). The International Symposiumwhich was co-organized by the Minnesota Department of Health, with input from a committee including members of the MPCAand the Minnesota Department of Natural Resourcesis the most comprehensive study of the health risks associated with taconite mining-related ambient fiber emissions ever undertaken. The purpose of the International Symposium is highly relevant to much of the discussion in Section 5.2.7.5 of the SDEIS: [T]o assess the current state of knowledge concerning the health hazards that might be associated with the ingestion and inhalation of fibrous particles produced from the processing of taconite ore. International Symposium on the Health Hazard Evaluation of Fibrous Particulates Associated with Taconite and the Adjacent Duluth Complex, Introduction, Regulatory Toxicology and Pharmacology, Vol. 52, No. 1, Supp.1, October 2008 (RT&P), S4. In particular, the International Symposium included [r]isk-assessment scenarios . . . for taconite-derived fibers at environmental exposure levels related to the operation of the Silver Bay taconite processing facility that is discussed throughout this section of the SDEIS. Id. The conclusion of these risk assessment scenarios was that calculated risks were found to be trivial even after it was assumed that all mineral fibers were as carcinogenic as amphibole asbestos. Id. (emphasis added). Those studies, and that conclusion, are not adequately reflected in the SDEIS. Research papers presented at the International Symposiumwere peer reviewed and eventually published in the October 2008 issue of Regulatory Toxicology and Pharmacology, a copy of which is attached to these comments. Among the highlights of the International Symposiums published, peer-reviewed findings are the following: PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 2 The fibers generated by Northshore Mining Companys operations in the Peter Mitchell Mine, approximately two miles away from the NorthMet Project, are cleavage fragments, separate and distinct from amphibole asbestos in their morphological characteristics and, more importantly, lacking asbestos carcinogenic properties. 1 A mineralogical survey found a tiny fraction of one percent of the total taconite deposit mass at the Peter Mitchell Mine contained fibrous minerals, with an even smaller percent of those mineral fragments entering the ambient air during the mining or the milling of the taconite. RT&P, S49 (Ross 2008b). The survey found no asbestos of any type at the mine. Id. Even in the late 1970s, during the time of the Reserve Mining litigation, the vast majority of the fibrous particulates collected through the monitoring process were cleavage fragments, with less than one percent of those fibers being truly asbestiform in nature. C. Axten and D. Foster, Analysis of Airborne and Waterborne Particles Around a Taconite Ore Processing Facility , RT&P, S68 (Axten and Foster 2008). The Occupational Safety and Health Administration (OSHA) removed cleavage fragments from its Asbestos Standard in 1994 after it reviewed morphological, epidemiological and other data on the differences between cleavage fragments and asbestos, concluding that exposure to non-asbestiformcleavage fragments was not likely to produce a significant risk of developing the asbestos-related diseases. Identification and enumeration of asbestos fibers in the mining environment: Mission and modification to the Federal Asbestos Standard, A. Langer, RT&P, S213 (Langer 2008). Fibers collected during ambient air samples taken at Northshores Silver Bay processing facility and in the town of Silver Bay are predominantly non-asbestos ferroactinolite and grunerite fibers. RT&P, S49 (Ross 2008b). The asbestos that was detected in the ambient sampling is consistent with background levels of airborne asbestos reported by the World Health Organization (WHO) and EPA. RT&P, S49 (Ross, 2008b); RT&P, S240 (Wilson 2008). In fact, the levels 1 See, e.g., Ross, M., Langer, A.M., Nord, G.L., Nolan, R.P., Lee, R.J., Van Order, D., Addison, J., The mineral nature of asbestos, RT&P, S26 S30 (Ross, 2008a); Ross, M., Nolan, R.P., Nord, G.L., The search for fibrous minerals within the Peter Mitchell Taconite Mine, Babbitt, Minnesota, RT&P, S43 S50 (Ross 2008b); Gamble, J.F., Gibbs, G.W., An evaluation of the risk of lung cancer and mesothelioma from exposure to amphibole cleavage fragments, RT&P, S154 S186 (Gamble 2008); Addison, J., McConnell, E.E. A reviewof carcinogenicity studies of asbestos and non-asbestos tremolite and other amphiboles, RT&P, S187 S199 (Addison 2008); Mossman, B.T., Assessment of the pathogenic potential of asbestiform vs. nonasbestiformparticulates (cleavage fragments) in vitro (cell or organ culture) models and bioassays, RT&P, S200 S203 (Mossman 2008); Wilson, R., McConnell, E.E., Ross, M., Axten, C.W., Nolan, R.P., Risk assessment due to environmental exposures to fibrous particulates associated with taconite ore, RT&P, S232 S245 (Wilson 2008). See also, Ilgren, E.B., The biology of cleavage fragments: A brief synthesis and analysis of current knowledge, Indoor and Built Environment, October 2004, 343- 356. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 3 observed in Silver Bay are at what WHO considers the lowend of background levels for airborne asbestos. RT&P, S240 (Wilson 2008). Even if the all of the fibers detected in Silver Bay had been asbestos, the monitored levels were at least 700 times lower than the current permissible exposure level for asbestos. RT&P, S325 (Wilson 2008). This peer-reviewed analysis of the risks associated with ambient fiber emissions associated with the nearby Peter Mitchell Mine should be incorporated into the Final EISs discussion of amphibole mineral fibers. For example, where the SDEIS mentions that the Peter Mitchell Mine and the Silver Bay processing plant have been associated with releases of amphibole mineral fibers (5-438), it should be noted that peer-reviewed risk assessments of those releases indicate that they present a trivial risk to human health. Minnesota Taconite Workers Health Study The SDEIS properly acknowledges the ongoing University of Minnesota-led Taconite Workers Health Study (TWHS), including its finding that worker mortality is primarily due to commercial asbestos exposure, rather than exposure to the minerals being mined. (5-439, 5-440). The TWHS also contains several other findings that support the conclusion that ambient fiber emissions pose no threat to the health and safety of mine workers or the general public: Current workplace dust exposure levelswhich by their nature would be higher than community ambient levelsare considered safe. Minnesota Taconite Workers Health Study: Annual Report to the Legislature, dated April 19, 2013 (TWHS 2013 Report), Executive Summary, p. 5; Minnesota Taconite Workers Health Study: Public Presentation, Mountain Iron, Minnesota, April 12, 2013 (TWHS 2013 Presentation), slide # 21. Mesothelioma and lung cancer rates among iron ore workers in Zone 4the easternmost portion of the Iron Range, which includes the NorthMet Project areaare comparable to rates within the far western Zone 1. The highest rates for mesothelioma and lung cancer are found in Zone 2, which is also far west of the NorthMet Project, outside the Duluth Complex. TWHS 2013 Report, Section II, Table 4, p. 30; Section III, Tables 1 and 2. A respiratory health study found no increased rates of mesothelioma or lung cancer among the spouses of iron ore workers. Because spouses would likely have more exposure than those in the communities, this finding suggests individuals living in the communities in close proximity to the mining operations would not be expected to have higher amounts of dust-related respiratory disease TWHS 2013 Report, Section IV, p. 45 (Emphasis added). See also TWHS 2013 Presentation, slides # 20, 47. Ambient air samples taken at five Mesabi Iron Range (MIR) communities, including Babbitt and Silver Bay, registered total particulate matter (TPM), PM 10 and PM 2.5 levels that averaged one-to-two orders of magnitude lessthan the applicable national or Minnesota ambient air quality standard for those pollutants. TWHS 2013 Report, Section PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 4 V, pp. 50, 54; TWHS 2013 Presentation, slides #23, 65, 66. The community averages for TPM and PM 2.5 are particularly significant because they remained one-to-two orders of magnitude belowthe applicable ambient air quality standards, even during active taconite processing or mining. TWHS 2013 Report, p. 54. Particulate levels (PM 1 , PM 2.5 , PM 10 and TPM) increased slightly during plant or mine activity, but the increase was not statistically significant as compared to times of plant or mine inactivity. TWHS 2013 Report, p. 57; TWHS 2013 Presentation, slide #69. NoasbestiformElongateMineral Particleshavebeenidentifiedtodatein anyof the MI R communities, including Babbitt and Silver Bay. TWHS 2013 Report, p. 57; TWHS 2013 Presentation, slide #65. Particulate matter concentrations in the MIR communities were comparable to those of the two northeast Minnesota background sites (Ely and Duluth), and were lower in all cases compared to concentrations in Minneapolis. TWHS 2013 Report, p. 56; TWHS 2013 Presentation, slides #23, 65. This study further buttresses the conclusion that the release of amphibole mineral fibers from mining presents a trivial risk to human health. Conclusions The SDEIS accurately states that the probability of amphibole asbestos being released to the air as a result of the NorthMet Project is very low. 5-440. Based on the evidence from the International Symposium and the TWHS, it is also accurate to state that, in the extremely unlikely event of an amphibole mineral fiber release, those fibers would present a trivial risk to human health. For this reason, PolyMet recommends removing from the Final EIS statements indicating that the release of amphibole mineral fibers . . . could propose a potential public health risk of uncertain magnitude (SDEIS at 5-439) or that there remains an uncertain level of potential health risk from airborne amphibole fibers for the NorthMet Project Prosed Action (SDEIS 5-440). Those statements ignore the evidence discussed above. It would be more appropriate to state that the available scientific evidence, including the evidence from the International Symposium and the TWHS, indicates that amphibole fibers from the NorthMet Project will not present a significant risk to human health. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 1 ATTACHMENT D CUMULATIVE IMPACTS COMMENTS While it is clear that the co-lead agencies have carefully examined the cumulative impacts of the NorthMet Project Proposed Action and the Land Exchange Proposed Action, PolyMet believes that the explanation of that analysis could be strengthened by providing more detail and clearer language throughout Chapter 6. In particular, the presentation of the cumulative impacts analysis can be strengthened by: (1) clarifying the difference between a reasonably foreseeable project and a speculative project; (2) using the term no significant cumulative impact when minor impacts are expected; (3) explicitly incorporating the analyses in Chapter 4 and Chapter 5; and (4) providing a more detailed explanation of how the assessment area was determined for each resource. These recommendations are discussed in more detail below. Reasonably Foreseeable Actions Acumulative impact is defined as the impact on the environment which results from the incremental impact of the action when added to other past, present, and reasonably foreseeable future actions. 40 C.F.R. 1508.7. Whether an action is reasonably foreseeable naturally plays a critical role in the cumulative impacts analysis. But because neither NEPA nor the CEQ regulations define that term, agencies must make their own determinations about what projects are reasonably foreseeable. Courts have held that a project is reasonably foreseeable if it is sufficiently likely to occur that a person of ordinary prudence would take it into account. Arkansas Wildlife Federation v. U.S. Army Corps of Engrs, 431 F.3d 1096, 1102 (8th Cir. 2005). An agency need not speculate about all conceivable impacts; they need not discuss undevelopedbut contemplatedprojects where not enough information is available to give meaningful consideration to the project. See Environmental Protection Information Center v. U.S. Forest Service, 451 F.3d 1005, 1014 (9th Cir. 2006). Many courts accordingly have held contemplated projects to be speculative where the action has yet to develop into a proposal. See, e.g., Theodore Roosevelt Conservation Partnership v. Salazar, 616 F.3d 497 (D.C. Cir. 2010); Environmental Protection Info. Center, 451 F.3d 1005; Airport Inpact Relief, Inc. v. Wykle, 192 F.3d 197 (1st Cir. 1999). U.S. Forest Service NEPA regulations define reasonably foreseeable actions as those federal or nonfederal activities not yet undertaken, for which there are existing decisions, funding, or identified proposals. 36 C.F.R. 220.3. An identified proposal means the Forest Service has a goal and is actively preparing to make a decision on one or more alternative means of accomplishing that goal and the effects can be meaningfully evaluated. 220.4(a)(1). The SDEIS appears to have used the Forest Service regulations as a model for its definition of a reasonably foreseeable action. PolyMet agrees with this approach and believes that the Forest Service regulations provide an accurate description of reasonably foreseeable that can be applied easily and understandably to the cumulative impact analysis for the NorthMet project. Those regulations can be concisely summarized as follows: For the purposes of this assessment, an action is reasonably foreseeable if it is included in approved planning documents and has approved funding, is permitted, PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 2 or has a currently active federal or state permit or site plan application under review. Projects without funding or a permit or site plan application under review are in the initial stages of development and do not have enough information to allow for meaningful consideration. These projects are considered speculative. Section 6.2.2.1.21 (Speculative Actions) should reiterate that these actions have not been considered in the cumulative analysis because not enough information is available at this time to allow for meaningful consideration of impacts. In addition, the basis for the determination that each of these projects is speculative should be stated clearly. For example, where the SDEIS states that a company is proposing a project, it should also clearly state that either funding has not been procured or that an application has not yet been submitted to the relevant federal or state agencies. Finally, the criteria should be applied consistently throughout the cumulative impacts. For example, the SDEIS states that the United Taconite expansion/Highway 53 relocation is a speculative action. However, the SDEIS also acknowledge that a DEIS for the relocation is expected in the next several months. Because the Highway 53 relocation appears to meet the reasonably foreseeable criteria, its impacts should be considered in the FEIS. No Significant Cumulative Impact In several places throughout the Chapter 6, the SDEIS concludes that the NorthMet project will have no cumulative impact on a specific resource. However, the corresponding section evaluating that resource in Chapter 5 shows a small, but insignificant, impact. In these situations, it is confusing to state that the NorthMet project will have no cumulative impact, which suggests that the project will not have any cumulative impact at all. Rather, it is more appropriate to state that the NorthMet project will not have a significant cumulative impact. For example, on page 6-29, the SDEIS states that [s]ince the NorthMet Project Proposed Action and other cumulative projects contributions would not cause or increase an exceedance of the water quality evaluation criteria, cumulative effects are not expected. However, finding no exceedance is not technically the same as finding no impact. Here, it would be more accurate, and in keeping with the analysis in other parts of the SDEIS, to conclude that there would be no significant cumulative impact on water quality. Similarly, the SDEIS concludes that there will be no cumulative impact on recreational and visual resources. It bases this conclusion on the fact that there are no significant cumulative impacts on individual specific resources that factor in to the assessment of recreational and visual resources (such as air quality, wetlands, etc.). The phrasing used implies that the co-leads have analyzed the effects on recreational and visual resources from impacts to these specific resources individually, rather than collectively. PolyMet suggests clarifying that the agencies have analyzed whether the impacts on these resources, although insignificant when considered individually, would have any impact on recreational and visual resources when combined and has concluded that there would be no significant impact. PolyMet Comments NorthMet Mining Project and Land Exchange SDEIS March 13, 2014 3 Incorporating Chapters 4 and 5 As noted above, the cumulative impacts assessment must look at all past, present and reasonably foreseeable actions. In Section 6.2.2, the SDEIS states that [e]xisting conditions that may be related to past or present actions on the specific environmental resources are fully described in their respective section in Chapter 4 and the direct and indirect impacts of the NorthMet Proposed Action are described in Chapter 5. While PolyMet agrees that it is sufficient to rely on analysis performed elsewhere in the SDEIS, and that it would be unnecessary to include that analysis verbatim in Chapter 6, PolyMet recommends providing references to the specific sections or subsections in Chapter 4 and Chapter 5 where the reader can find the basis for the conclusions made on each specific resource in Chapter 6. This relatively simple change will increase readability and make clear the basis of the conclusions in Chapter 6. Cumulative Effects Assessment Areas The SDEIS should also use consistent language regarding the scope of the cumulative effects assessment areas throughout Chapter 6. On page 6-2, the SDEIS states: For all resources, future temporal boundaries are the expected service life of the mining activities, including closure (years 20 to 40) and post-closure restoration (year 40 and beyond). PolyMet recommends removing this sentence, which is not an accurate description of the temporal boundaries for all resources. Indeed, the very next sentence on page 6-2 rightly states that temporal boundaries for each resource are defined within the respective resources sections of this analysis. That sentence should remain as the sole, accurate explanation of temporal boundaries. CEQs guidance on considering cumulative impacts provides the following steps for determining the scope of the cumulative impacts analysis: 1) Determine the area that will be affected by the proposed Project. This is the project impact zone. 2) Make a list of resources within that zone that could be affected by the proposed action. 3) Determine the geographic areas occupied by those resources outside of the project impact zone. In most cases, the largest of these areas will be the appropriate area for the analysis of cumulative impacts. Considering Cumulative Effects Under the National Environmental Policy Act at 15 (Jan. 1997). The SDEIS appears to have followed this CEQ guidance in setting the scope of cumulative impacts. PolyMet recommends, however, more clearly providing the basis for the geographic and temporal scope in each resource-specific section within Chapter 6.