You are on page 1of 18

JETTY LNG RECEIVING TERMINAL - PATAS - SINGARAJA - BALI - INDONESIA

No.

Description

GENERAL

Unit
(1)

QUANTITY

UNIT RATE

Contractor Owner estimation

(Rp.)

(2)

(3)

(4)

1.1 Mobilization
(1) Dredging equipment

l.s.

1.00

350,000,000

(2) Piling equipment

l.s.

1.00

270,000,000

(3) Service crane equipment

l.s.

1.00

200,000,000

(4) Batching plant equipment

l.s.

1.00

300,000,000

(5) Moulds and prestress equipment

l.s.

1.00

250,000,000

(6) Genset and lighting equipment

l.s.

1.00

150,000,000

(1) Establishment and Maintenance of Contractor's office

l.s.

1.00

250,000,000

(2) Quality and Testing of Materials

l.s.

1.00

150,000,000

(3) Engineer's Site offices amenities, LCD, Meeting R, internet conection

l.s.

1.00

125,000,000

(4) Establishment Owner's office amenities

l.s.

1.00

250,000,000

(5) Engineer's Vehicles + drivers ( 3 unit )

mth

18.00

22,500,000

(6) Engineer's Container box 40 ft for Site office

no

1.00

65,000,000

(7) Engineer's Movable toilet as per specification

no

1.00

35,000,000

(8) Engineer's Radio communication ( Handy Talky )

no

5.00

1,950,000

(1) Temporary Fencing (maintenance area)

mth

18.00

2,000,000

(2) Documentation

mth

18.00

15,000,000

(1) Project Manager

mth

18.00

30,000,000

(2) General Superintendent/Construction Manager/Site Manager

mth

18.00

20,000,000

(3) QA/QC and Safety Manager

mth

18.00

15,000,000

(4) Site Superintendent/Site Engineer

mth

18.00

25,000,000

mth

18.00

15,000,000

ls

1.00

300,000,000

(3) Electricity, Portable water, Communication, internet conection

mth

18.00

35,000,000

(4) Office boy, servent ( min 2 personal )

mth

18.00

3,500,000

(5) Security for Engineer's site offices (min 6 personnel)

mth

18.00

30,000,000

(1) All the required insurances as stated in the Contract

l.s.

1.00

3,000,000,000

1.6 Provision of Bonds/Security, Permits and Consents

l.s.

1.00

1,750,000,000

1.7 Provision of "As Built drawing/ Manuals"

l.s.

1.00

3,500,000,000

(1) Dredging equipment

l.s.

1.00

350,000,000

(2) Piling equipment

l.s.

1.00

270,000,000

l.s.

1.00

50,000,000

l.s.

1.00

100,000,000

1.2 Offices and Facilities/ Amenities

1.3 Establishment and Access/Amenities

(3) Establishment of Nominated Personnel

1.4 Maintenance of Engineer's Site Office(s) Facilities


(1) Maintenance
(2) Establishing electricity for 50 kVA/ 3 phase/ 380 V/ 50 Hz

1.5 Provision of Insurances

1.8 Demobilization the equipments

1.9 Remove Facilities/ Amenities


1.10 Clean Up Site/ Soil Disposal removing/ etc.

Sub

II

DEMOLITION WORKS

2.1 Demolition and Removal from site


(1) Batching plant

l.s

1.00

50,000,000

(2) Structures behind the building (sea side)

l.s

1.00

200,000,000

(3) Pavement structure at the RF area including retaining wall

l.s

1.00

130,000,000

2.2 Removal to store


(1) Container box etc.

l.s

1.00

30,000,000

Sub

III

PILING WORKS

3.1 Supply of Piles


(1) Steel pipe procurement 12.000 mm/ dia 1.000 mm / t = 20 mm

kg

11,241,000.00

9,500

3.2 Handle, Pitch and Drive


(1) Steel pipe handling

m1

23,268

50,000

(2) Steel pipe piling

m1

23,268

420,000

(3) Splicing

no

1,393

2,000,000

(4) Cutting

no

1,393

500,000

3.3 Pile Head Preparation


(1) Pile head preparation

no

546.00

100,000

no

20.00

9,000,000

3.4 Pile Dynamic Analyzer (PDA) test


(1) Steel pipe piling

Sub

IV

CONCRETE WORKS K-400

4.1 Concrete work on trestle


(1) Trestle cross beam

m3

1,825.00

3,500,000

(2) Trestle precast stringger

m3

1,210.00

3,500,000

(3) Top deck plate

m3

612.00

3,500,000

(4) Trestle pipe concrete

m3

1,100.00

3,500,000

(5) Rivetment concrete

m3

200.00

3,500,000

(1) Cross beam

m3

5,400.00

3,500,000

(2) Precast stringger

m3

3,750.00

3,500,000

(3) Top deck plate

m3

1,825.00

3,500,000

(4) Fender beam

m3

1,630.00

3,500,000

(5) Jetty head pipe concrete

m3

3,705.00

3,500,000

pcs

175.00

4.2 Concrete work on jetty head

(6) Rubber Fender

Sub
Befo

Afte

ING TERMINAL - PATAS - SINGARAJA - BALI - INDONESIA


AMOUNT
(Rp.)
(5) = (3) x (4)
350,000,000
270,000,000
200,000,000
300,000,000
250,000,000
150,000,000

250,000,000
150,000,000
125,000,000
250,000,000
405,000,000
65,000,000
35,000,000
9,750,000

36,000,000
270,000,000
540,000,000
360,000,000
270,000,000
450,000,000
1,926,000,000
270,000,000
300,000,000
630,000,000
63,000,000
540,000,000
1,803,000,000
3,000,000,000
3,000,000,000
1,750,000,000
1,750,000,000
3,500,000,000
3,500,000,000
350,000,000
270,000,000
620,000,000
50,000,000
50,000,000
100,000,000
100,000,000

Sub Total

50,000,000
200,000,000
130,000,000
380,000,000

30,000,000
30,000,000

Sub Total

106,789,500,000
106,789,500,000
1,163,400,000
9,772,560,000
2,786,000,000
696,500,000
14,418,460,000
54,600,000
54,600,000
180,000,000
180,000,000

Sub Total

6,387,500,000
4,235,000,000
2,142,000,000
3,850,000,000
700,000,000
17,314,500,000
18,900,000,000
13,125,000,000
6,387,500,000
5,705,000,000
12,967,500,000
57,085,000,000

Sub Total
Before tax
VAT
After Tax

JETTY LNG RECEIVING TERMINAL - PATAS - SINGARAJA - BALI - INDONESIA


UNIT RATE

AMOUNT

No.

Description

Unit

QUANTITY

(1)

(2)

(3)

(4)

(1) Dredging equipment

l.s.

1.00

350,000,000

350,000,000

(2) Piling equipment

l.s.

1.00

270,000,000

270,000,000

(3) Service crane equipment

l.s.

1.00

200,000,000

200,000,000

(4) Batching plant equipment

l.s.

1.00

300,000,000

300,000,000

(5) Moulds and prestress equipment

l.s.

1.00

250,000,000

250,000,000

(6) Genset and lighting equipment

l.s.

1.00

150,000,000

(Rp.)

(Rp.)

(5)

(6) = (4) x (5)

GENERAL

1.1 Mobilisasi

150,000,000
1,520,000,000

1.2 Offices and Facilities/ Amenities


(1) Establishment and Maintenance of Contractor's office

l.s.

1.00

250,000,000

250,000,000

(2) Quality and Testing of Materials

l.s.

1.00

150,000,000

150,000,000

(3) Engineer's Site offices amenities, LCD, Meeting R, internet conection

l.s.

1.00

125,000,000

125,000,000

(4) Establishment Owner's office amenities

l.s.

1.00

250,000,000

250,000,000

(5) Engineer's Vehicles + drivers ( 3 unit )

mth

18.00

22,500,000

405,000,000

(6) Engineer's Container box 40 ft for Site office

no

1.00

65,000,000

65,000,000

(7) Engineer's Movable toilet as per specification

no

1.00

35,000,000

35,000,000

(8) Engineer's Radio communication ( Handy Talky )

no

5.00

1,950,000

9,750,000
1,289,750,000

1.3 Establishment and Access/Amenities


(1) Temporary Fencing (maintenance area)

mth

18.00

2,000,000

36,000,000

(2) Documentation

mth

18.00

15,000,000

270,000,000

(1) Project Manager

mth

18.00

30,000,000

540,000,000

(2) General Superintendent/Construction Manager/Site Manager

mth

18.00

20,000,000

360,000,000

(3) QA/QC and Safety Manager

mth

18.00

15,000,000

270,000,000

(4) Site Superintendent/Site Engineer

mth

18.00

25,000,000

(3) Establishment of Nominated Personnel

450,000,000
1,926,000,000

1.4 Maintenance of Engineer's Site Office(s) Facilities


(1) Maintenance

mth

18.00

15,000,000

270,000,000

ls

1.00

300,000,000

300,000,000

(3) Electricity, Portable water, Communication, internet conection

mth

18.00

35,000,000

630,000,000

(4) Office boy, servent ( min 2 personal )

mth

18.00

3,500,000

63,000,000

(5) Security for Engineer's site offices (min 6 personnel)

mth

18.00

30,000,000

540,000,000

(2) Establishing electricity for 50 kVA/ 3 phase/ 380 V/ 50 Hz

(7)

1,803,000,000

1.5 Provision of Insurances


(1) All the required insurances as stated in the Contract

l.s.

1.00

3,000,000,000

1.6 Provision of Bonds/Security, Permits and Consents

l.s.

1.00

1,750,000,000

3,000,000,000
3,000,000,000
1,750,000,000
1,750,000,000

1.7 Provision of "As Built drawing/ Manuals"

l.s.

1.00

3,500,000,000

3,500,000,000
3,500,000,000

1.8 Demobilization the equipments


(1) Dredging equipment

l.s.

1.00

350,000,000

350,000,000

(2) Piling equipment

l.s.

1.00

270,000,000

270,000,000

l.s.

1.00

50,000,000

50,000,000

l.s.

1.00

100,000,000

100,000,000

620,000,000

1.9 Remove Facilities/ Amenities

50,000,000

1.10 Clean Up Site/ Soil Disposal removing/ etc.

100,000,000

Sub Total

II

15,558,750,000

DEMOLITION WORKS

2.1 Demolition and Removal from site


(1) Batching plant

l.s

1.00

50,000,000

50,000,000

(2) Structures behind the building (sea side)

l.s

1.00

200,000,000

200,000,000

(3) Pavement structure at the RF area including retaining wall

l.s

1.00

130,000,000

130,000,000
380,000,000

2.2 Removal to store


(1) Container box etc.

l.s

1.00

30,000,000

30,000,000
30,000,000

Sub Total

III

PILING WORKS

3.1 Supply of Piles


(1) Spoon pile 30 m/ dia 1.0 m

m1

34,350.00

500,000

17,175,000,000
17,175,000,000

3.2 Handle, Pitch and Drive


(1) piling

m1

27,480.00

100,000

2,748,000,000

(2) Conector

no

2,748

500,000

1,374,000,000

(3) Cutting

no

1,393

500,000

696,500,000
4,818,500,000

3.3 Pile Head Preparation


(1) Pile head preparation

no

687.00

100,000

68,700,000
68,700,000

410,000,000

3.4 Pile Dynamic Analyzer (PDA) test


(1) Spoon pile piling

no

20.00

9,000,000

180,000,000
180,000,000

Sub Total

IV

22,242,200,000

CONCRETE WORKS K-450

4.1 Concrete work on trestle


(1) Trestle cross beam

m3

6,360.00

5,000,000

31,800,000,000

(2) Joint

m3

310.00

5,000,000

1,550,000,000

(3) Top deck plate

m3

1,687.50

5,000,000

8,437,500,000

(4) Trestle pipe concrete

m3

1,100.00

5,000,000

5,500,000,000

(5) Rivetment concrete

m3

620.00

5,000,000

3,100,000,000
50,387,500,000

4.2 Concrete work on jetty head


(1) Cross beam

m3

19,812.00

5,000,000

(2) Rivetment concrete

m3

1,968.00

5,000,000

9,840,000,000

(3) Top deck plate

m3

4,950.00

5,000,000

24,750,000,000

(4) Fender concrete beam

m3

1,630.00

5,000,000

8,150,000,000

(5) Jetty head pipe concrete

m3

3,705.00

5,000,000

18,525,000,000

99,060,000,000

160,325,000,000

4.3 Breakwater
(1) Breakwater 2877,61m + anchore pipe

m3

86,328.30

5,000,000

431,641,500,000
431,641,500,000

4.4 Rubber Fender


(1) Rubber Fender AD1000

pcs

41.00

40,000,000

1,640,000,000
1,640,000,000

Sub Total
Before tax
VAT
After Tax

Singaraja, 26 Oktober 2013


Menyetuji,

Dibuat oleh:

Ketut Susanta, SH.


Presiden Direktur

Ir. Sjafei Amri. Dipl. E. Eng


Direktur Teknik

643,994,000,000
682,204,950,000
68,220,495,000
750,425,445,000

JETTY LNG RECEIVING TERMINAL - PATAS - SINGARAJA - BALI - INDONESIA

No.

Description

GENERAL

Unit
(1)

QUANTITY

UNIT RATE

Contractor Owner estimation

(Rp.)

(2)

(3)

(4)

1.1 Mobilization
(1) Dredging equipment

l.s.

1.00

350,000,000

(2) Piling equipment

l.s.

1.00

270,000,000

(3) Service crane equipment

l.s.

1.00

200,000,000

(4) Batching plant equipment

l.s.

1.00

300,000,000

(5) Moulds and prestress equipment

l.s.

1.00

250,000,000

(6) Genset and lighting equipment

l.s.

1.00

150,000,000

(1) Establishment and Maintenance of Contractor's office

l.s.

1.00

250,000,000

(2) Quality and Testing of Materials

l.s.

1.00

150,000,000

(3) Engineer's Site offices amenities, LCD, Meeting R, internet conection

l.s.

1.00

125,000,000

(4) Establishment Owner's office amenities

l.s.

1.00

250,000,000

(5) Engineer's Vehicles + drivers ( 3 unit )

mth

18.00

22,500,000

(6) Engineer's Container box 40 ft for Site office

no

1.00

65,000,000

(7) Engineer's Movable toilet as per specification

no

1.00

35,000,000

(8) Engineer's Radio communication ( Handy Talky )

no

5.00

1,950,000

(1) Temporary Fencing (maintenance area)

mth

18.00

2,000,000

(2) Documentation

mth

18.00

15,000,000

(1) Project Manager

mth

18.00

30,000,000

(2) General Superintendent/Construction Manager/Site Manager

mth

18.00

20,000,000

(3) QA/QC and Safety Manager

mth

18.00

15,000,000

(4) Site Superintendent/Site Engineer

mth

18.00

25,000,000

mth

18.00

15,000,000

ls

1.00

300,000,000

(3) Electricity, Portable water, Communication, internet conection

mth

18.00

35,000,000

(4) Office boy, servent ( min 2 personal )

mth

18.00

3,500,000

(5) Security for Engineer's site offices (min 6 personnel)

mth

18.00

30,000,000

(1) All the required insurances as stated in the Contract

l.s.

1.00

3,000,000,000

1.6 Provision of Bonds/Security, Permits and Consents

l.s.

1.00

1,750,000,000

1.7 Provision of "As Built drawing/ Manuals"

l.s.

1.00

3,500,000,000

(1) Dredging equipment

l.s.

1.00

350,000,000

(2) Piling equipment

l.s.

1.00

270,000,000

l.s.

1.00

50,000,000

l.s.

1.00

100,000,000

1.2 Offices and Facilities/ Amenities

1.3 Establishment and Access/Amenities

(3) Establishment of Nominated Personnel

1.4 Maintenance of Engineer's Site Office(s) Facilities


(1) Maintenance
(2) Establishing electricity for 50 kVA/ 3 phase/ 380 V/ 50 Hz

1.5 Provision of Insurances

1.8 Demobilization the equipments

1.9 Remove Facilities/ Amenities


1.10 Clean Up Site/ Soil Disposal removing/ etc.

Sub

II

DEMOLITION WORKS

2.1 Demolition and Removal from site


(1) Batching plant

l.s

1.00

50,000,000

(2) Structures behind the building (sea side)

l.s

1.00

200,000,000

(3) Pavement structure at the RF area including retaining wall

l.s

1.00

130,000,000

2.2 Removal to store


(1) Container box etc.

l.s

1.00

30,000,000

Sub

III

PILING WORKS

3.1 Supply of Piles


(1) Steel pipe procurement 12.000 mm/ dia 1.000 mm / t = 20 mm

kg

11,241,000.00

9,500

3.2 Handle, Pitch and Drive


(1) Steel pipe handling

m1

23,268

50,000

(2) Steel pipe piling

m1

23,268

420,000

(3) Splicing

no

1,393

2,000,000

(4) Cutting

no

1,393

500,000

3.3 Pile Head Preparation


(1) Pile head preparation

no

546.00

100,000

no

20.00

9,000,000

3.4 Pile Dynamic Analyzer (PDA) test


(1) Steel pipe piling

Sub

IV

CONCRETE WORKS K-400

4.1 Concrete work on trestle


(1) Trestle cross beam

m3

1,825.00

3,500,000

(2) Trestle precast stringger

m3

1,210.00

3,500,000

(3) Top deck plate

m3

612.00

3,500,000

(4) Trestle pipe concrete

m3

1,100.00

3,500,000

(5) Rivetment concrete

m3

200.00

3,500,000

(1) Cross beam

m3

5,400.00

3,500,000

(2) Precast stringger

m3

3,750.00

3,500,000

(3) Top deck plate

m3

1,825.00

3,500,000

(4) Fender beam

m3

1,630.00

3,500,000

(5) Jetty head pipe concrete

m3

3,705.00

3,500,000

pcs

175.00

4.2 Concrete work on jetty head

(6) Rubber Fender

Sub
Befo

Afte

ING TERMINAL - PATAS - SINGARAJA - BALI - INDONESIA


AMOUNT
(Rp.)
(5) = (3) x (4)
350,000,000
270,000,000
200,000,000
300,000,000
250,000,000
150,000,000

250,000,000
150,000,000
125,000,000
250,000,000
405,000,000
65,000,000
35,000,000
9,750,000

36,000,000
270,000,000
540,000,000
360,000,000
270,000,000
450,000,000
1,926,000,000
270,000,000
300,000,000
630,000,000
63,000,000
540,000,000
1,803,000,000
3,000,000,000
3,000,000,000
1,750,000,000
1,750,000,000
3,500,000,000
3,500,000,000
350,000,000
270,000,000
620,000,000
50,000,000
50,000,000
100,000,000
100,000,000

Sub Total

50,000,000
200,000,000
130,000,000
380,000,000

30,000,000
30,000,000

Sub Total

106,789,500,000
106,789,500,000
1,163,400,000
9,772,560,000
2,786,000,000
696,500,000
14,418,460,000
54,600,000
54,600,000
180,000,000
180,000,000

Sub Total

6,387,500,000
4,235,000,000
2,142,000,000
3,850,000,000
700,000,000
17,314,500,000
18,900,000,000
13,125,000,000
6,387,500,000
5,705,000,000
12,967,500,000
57,085,000,000

Sub Total
Before tax
VAT
After Tax

BILL OF QUANTITY
JETTY LNG RECEIVING TERMINAL - PATAS - SINGARAJA - BALI - INDONESIA

No.

Description

(1)

(2)

GENERAL

1.1 Mobilisasi
(1) Dredging equipment
(2) Piling equipment
(3) Service crane equipment
(4) Batching plant equipment
(5) Moulds and prestress equipment
(6) Genset and lighting equipment

1.2 Offices and Facilities/ Amenities


(1) Establishment and Maintenance of Contractor's office
(2) Quality and Testing of Materials
(3) Engineer's Site offices amenities, LCD, Meeting R, internet conection
(4) Establishment Owner's office amenities
(5) Engineer's Vehicles + drivers ( 3 unit )
(6) Engineer's Container box 40 ft for Site office
(7) Engineer's Movable toilet as per specification
(8) Engineer's Radio communication ( Handy Talky )

1.3 Establishment and Access/Amenities


(1) Temporary Fencing (maintenance area)
(2) Documentation
(3) Establishment of Nominated Personnel
(1) Project Manager
(2) General Superintendent/Construction Manager/Site Manager
(3) QA/QC and Safety Manager
(4) Site Superintendent/Site Engineer

1.4 Maintenance of Engineer's Site Office(s) Facilities


(1) Maintenance
(2) Establishing electricity for 50 kVA/ 3 phase/ 380 V/ 50 Hz
(3) Electricity, Portable water, Communication, internet conection
(4) Office boy, servent ( min 2 personal )
(5) Security for Engineer's site offices (min 6 personnel)

1.5 Provision of Insurances


(1) All the required insurances as stated in the Contract

1.6 Provision of Bonds/Security, Permits and Consents


1.7 Provision of "As Built drawing/ Manuals"

p, m

l, m

t, m

1.8 Demobilization the equipments


(1) Dredging equipment
(2) Piling equipment

1.9 Remove Facilities/ Amenities


1.10 Clean Up Site/ Soil Disposal removing/ etc.

II

DEMOLITION WORKS

2.1 Demolition and Removal from site


(1) Batching plant
(2) Structures behind the building (sea side)
(3) Pavement structure at the RF area including retaining wall

2.2 Removal to store


(1) Container box etc.

III

PILING WORKS

3.1 Supply of Piles


(1) Spoon pile 30 m/ dia 1.0 m

3.2 Handle, Pitch and Drive


(1) piling
(2) Conector
(3) Cutting

3.3 Pile Head Preparation


(1) Pile head preparation

3.4 Pile Dynamic Analyzer (PDA) test


(1) Spoon pile piling

IV

CONCRETE WORKS K-450

4.1 Concrete work on trestle


(1) Trestle cross beam
(2) Joint
(3) Top deck plate
(4) Trestle pipe concrete
(5) Rivetment concrete

4.2 Concrete work on jetty head


(1) Cross beam
(2) Rivetment concrete
(3) Top deck plate
(4) Fender concrete beam
(5) Jetty head pipe concrete

4.3 Breakwater
(1) Breakwater 2877,61m + anchore pipe

4.4 Rubber Fender


(1) Rubber Fender AD1000

Singaraja, 26 Oktober 2013


Menyetuji,

Ketut Susanta, SH.


Presiden Direktur

JA - BALI - INDONESIA

L, m2

N, bh

(3)

(4)

Volum

Etc
(5)

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

18.00

mth

1.00

no

1.00

no

5.00

no

18.00

mth

18.00

mth

18.00

mth

18.00

mth

18.00

mth

18.00

mth

18.00

mth

1.00

ls

18.00

mth

18.00

mth

18.00

mth

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s.

1.00

l.s

1.00

l.s

1.00

l.s

1.00

l.s

34,350.00

m1

27,480.00

m1

2,748

no

1,393

no

687.00

no

20.00

no

6,360.00

m3

310.00

m3

1,687.50

m3

1,100.00

m3

620.00

m3

19,812.00

m3

1,968.00

m3

4,950.00

m3

1,630.00

m3

3,705.00

m3

86,328.30

m3

er 2013

41.00

pcs

You might also like