SAP Production Planning and Execution for SAP PP MM SD Beginners

G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
Material Availability check
Material availability check for all BOM Components.
You can carry out an availability check either for the entire order, or for an individual material component in
the order.
The system carries out an availability check. If material components are not available on their requirements
date, the system activates the status "material shortage" in the production order.
If you make changes in an order, which could affect the availability of its components (for example date or
quantity changes), this does not automatically trigger a new availability check. For up-to-date information on
any missing parts in an order, you should restart the availability check manually after you have made the
changes.
Production order Releasae

Once you released production order following activities can be performed :
Shop floor papers can be printed.
Goods movements for the order can be executed
Confirmations for the order can be executed.
Manual production order creation- Manual
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Path : Logistics->Production ->Shop Floor Control -> Order -> Create
T-Code : CO01
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Check capacity

Enter Order Quantity & Start or Finish Date manually.
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Check material

Release order
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in



Goods Movements In Discrete Manufacturing
Contents
Goods issue to production order (GI)
Goods receipts to production order (GR)
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
GI

Goods Issue for production can done in one of the following way :
Automatic (Backflush) confirmation automatically post goods issue for components
Manual Operator will post Goods Issue for production order
Stock and consumption fields are updated at the storage location level.
The component reservation is reduced.
The actual costs are determined and updated in the order.
If the material withdrawn does not have a reservation, then it is an unplanned issue. Example: Material
withdrawn as a replacement material.
Goods issues can be posted only if movement for the reservation is allowed. For example, an order status of
created but not released, blocked or technically complete disallows such movement.
Production order confirmation
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
Production Order confirmation is used for entering activities carried out within your company for an order.
Production order confirmations enable you to monitor the progress of work carried out for a production
order.
With a confirmation you specify
The quantity in an operation that was produced as yield, scrap and the quantity to be reworked
How much work was actually done
Which work center was used for the operation
Who carried out the operation
The following business transactions can be executed via confirmations:
Updating order data (for example, quantities, activities, dates, status)
Backflushing of components
Automatic goods receipt (for one operation per order max.)
Capacity reduction in the work center
Updating costs based on confirmed data
Production order confirmation types
Most widely used confirmation are :
For an Operation
You have the following options:
To confirm quantities, durations, activities or personnel data, enter a time ticket
confirmation or a progress confirmation.
To make a confirmation at a particular point in time (for example, at the start of setup or the
finish of processing) enter a confirmation for a time event.
When you confirm time events, the system calculates the required duration. For example,
the setup duration is the time between setup start and setup finish.
For an Order
If you enter a confirmation at order header level, the system confirms all the operations that have a
control key in which confirmation is optional or necessary. The quantities confirmed in the
operations are proportional to the quantities confirmed in the order header.
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Goods Movement

Goods receipt from production can be posted either manually or automatically.
Automatic goods receipt can be controlled specific to either operation (operation control key) or material
(production scheduling profile).
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
When we do goods receipt manually againt production order, we need to specify:
Plant
storage location
stock type
final delivery indicator
Material and accounting documents are assigned according to their numbers.
The delivered quantity can be updated in the order.
The inward movement of material is valuated.
The order is credited.
The plant activity account is updated
GR from Production order

SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Production Execution In Repetitive Process
Repetitive Manufacturing (REM)
In Repetitive Manufacturing, products remain unchanged over a longer period and are not manufactured in
individually defined lots. Instead, a total quantity is produced over a certain period at a certain rate.
Repetitive Manufacturing, normally involves a relatively constant flow on production lines. Semi-finished
products are usually processed further immediately without being put in interim storage. Routings tend to
be relatively simple.
In Repetitive Manufacturing, components are often staged at the production line without reference to a
particular order. Completion confirmations are less detailed, and the recording of actual data is simplified.
Goals of Repetitive Process
Creation and revision of production quantities on a period and quantity basis (reduction in individual lot and
order-specific processing).
Reduction in the production control effort and simpler backflushing tools (with the option of using the full
scope of the PP functionality).
You can implement Repetitive Manufacturing if the following is true of your production process:
You produce the same or similar products over a lengthy period of time.
You do not manufacture in individually defined lots. Instead, a total quantity is produced over a
certain period at a certain rate per part-period.
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
Your products always follow the same sequence through the machines and work centers in
production.
Routings tend to be simple and do not vary much.
Integration
Within logistics, Demand Management precedes Repetitive Manufacturing:
SD Sales Operations (receipt of sales orders)
PP Demand Management (creation of planned independent requirements)
PP MRP
The following Logistics components are also relevant:
PP Work Centers
PP Routings
PP Bills of Materials
If required, Line Design for mapping complex production lines.
Master Data
Following master data is required to work with Repetitive Manufacturing :
Repetitive manufacturing profile : The repetitive manufacturing profile is a mandatory prerequisite for
repetitive manufacturing. Using the control parameters, you define the following, for example:
Whether you want to back-flush activities.
Whether you want to work with reporting points n make-to-stock REM.
How you want to process errors which occur when back-flushing
Production Version : The production version determines the different production techniques that
can be used to manufacture a material.
Production Line : A production line is used as a work center in planning in flow and repetitive manufacturing.
It can either be a grouping of several processing stations or an individual processing station. In the simplest
case, you only need to create two work centers for the whole production line.
Product Cost Collector : Cost object in Product Cost by Period that collects the periodic actual costs incurred
in the production of a material. When you use a product cost collector, the product is the main cost object.
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
Repetitive manufacturing Process overview
Create standard cost estimate for material
Marking and releasing material price
Demand management generates primary planning requirements, which are a prerequisite for the later MRP
run. This is short-term planning, with a maximum time frame of four weeks. In material requirements
planning, the BOM for the material is exploded and planning takes place right down to component level.
As a result, planned orders are generated for the material that is to be produced. If insufficient warehouse
stock is available, purchase requisitions for the raw materials required are created.
Before production starts a product cost collector is created. It is a pure CO object to which all costs will be
posted. Other than in lot-based production, in REM. quantities and their corresponding cost amounts are not
stored on the same order.
Perform repetitive manufacturing backflush.
Repetitive Manufacturing can be used in :
Make to stock production REM
Repetitive Manufacturing Make to stock production : In this processes , manufacturing is carried out
without reference to any sales order, production is based on run schedule headers. This means that
production is controlled without a direct reference to the sales order. Run schedule quantities
determine the dates and quantities. Requirements are created in Demand Management.
Run Schedule Header : run schedule quantities represent the quantities that are to be manufactured
in a certain period. Technically, RS Header quantities are created as planned orders. As opposed to
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
other planned orders, RS Header quantities must not be released and converted into production
orders.
Make to stock production REM-Material requirement Planning
The daily MRP run generates planned orders for the material that is to be produced. The system
automatically generates purchase requisitions for purchased parts within the opening period for the
planned order.
Product cost collector

How product cost collector works
Collecting costs in a production cost collector
Costs are collected and settled via a production cost collector.
Goods issue of the components used to manufacture the product is debited to the product cost collector.
The goods receipt of the product is credited to the production cost collector.
Crediting the product cost collector at goods receipt is linked to the crediting of the stock (valuated stock).
The difference between debits and credit in the production cost collector is posted to a price difference
account at period-end. No variance calculation (lot size variance, price variance, ...) takes place.
Backflushing
You use this component in Repetitive Manufacturing to record work process in the system. Back-flushing is a
very lean process, corresponding to the requirements of repetitive, mass or flow manufacturing .
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
Types of Backflushing
Final back-flush : You use this function to carry out the final backflush at the end of the production process.
In the final back-flush, you can link the following processes:
Posting goods receipts for finished products
Posting goods issues for the components
Reducing planned orders or run schedule quantities
Posting production costs to product cost collector
Updating statistics in the Logistics Information System (LIS), such as goods receipt statistics or
material consumption statistics.
Reporting point back-flush : You use this function for make-to-stock REM for back-flushing unfinished
materials (work in process) at predefined operations.
Separation of back-flushing processes : If you want to back-flush high volumes of data, you can significantly
cut system response times by posting the goods receipt immediately and then posting all other data later.
Back-flushing several materials collectively (Collective back-flush) : You use the collective entry to back-flush
several materials together.
Back flushing Process
When back-flushing in make-to-stock REM, the following functions are carried out:
The system posts the goods receipt of the stock material in the receiving storage location. You can enter the
receiving storage location at various stages:
Back-flush screen
Production version
The system determines the components by exploding the current BOM, the revision level BOM, or the
planned order BOM.
The system then posts the goods issue of these components from the production storage location.
The system reduces the planned orders or the run schedule quantities according to the logic set in
Customizing for Repetitive Manufacturing.
If the actual production times differ from the times defined in the routing, you have the option of posting
the actual times. See also Back-flushing Actual Times (Actual Activities.
The system posts the material and the production costs to the product cost collector.
The system updates the statistics for the Logistics Information System (LIS).
The system creates individual documents for each posting as well as a full document.
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

PP - PI Processes
Here I am giving an overview of process Industry related Process.
The component Production Planning for Process Industries (PP-PI) provides an integrated planning &
execution tool for batch-oriented process manufacturing.
It is primarily designed for the chemical, pharmaceutical, food and beverage industries as well as the batch-
oriented electronics industry.
PP-PI supports:
The integrated planning of production, waste disposal, and transport activities within a plant
The integration of plants within the company:
Vertically by means of an information flow, ranging from central business applications down
to process control
Horizontally by the coordination of planning between production plants, recycling and
waste disposal facilities, and production laboratories.
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in


PP-PI Functions
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Module Overview Manufacturing Process (PP PI)



Process order Life cycle overview
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

process order is the vehicle for providing instructions to the factory floor about what to make, how much, when,
using which materials and which resources. It is also used to collect information about transactions that occur during
the manufacture of the product.
Factory Related Data

SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in


Process Orders come from Demand and Supply Planning (DSP)
Process Orders are released by manufacturing personnel in order to start Production Execution.

Process order overview
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Creating Process Order
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Path : Logistics->Production -Process ->Process Order -> Create
T-Code : COR1
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Capacity check

Enter Manually
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Check Material

Release Process Order
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Please note the status change in Process order from CRTD to REL

Process order confirmation
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

GI to Process order

SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

GR from Process order

SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Release PO to production Execution
Pre-op checks and verifications
Covers manual steps taken prior to Executing Production
Help to guarantee the success of Production Execution and safe work practices

Production execution components
Consumption of Components
Declaration of Production of Materials
Resource Confirmations
Variance Reporting, Managing Process Messages and Exception Handling
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
Process order- Technical Completion
Purpose of Process Order Technical Completion:
It indicates that no further processing is anticipated
Releases unused materials so that they can be used by other PO's
Flag for identifying PO's to be completed for period end financial reporting
status is set to 'TECO'
Prerequisites for Process Order Completion:
All production related steps must be completed
All transactions must be recorded in SAP (consumption, production, confirmations,...)
PI sheet (if used) must be completed.
Measure and Analyze Production Performance

If performance is to be improved, it must first be measured
Input for measuring and analyzing Production Performance
Target data maintained in the master data
actual data from Production Execution activities recording
Timely and accurate feedback must be provided to enable factory people to better manage their operations
and improve performance
Output of measuring and analyzing Production Performance
Continuous Improvement activities
Review of production process failures
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Efficiency describes how well the line operates when the crew is present on the production line
Performance describes how effectively the line is used during the time which it is occupied with some type
of activity or is incapable of production (down time)
Performance and efficiency
Manufacturing Reports
Monitor Line Efficiency and Performance
Downtime
Line Efficiency and Line Performance
Process Order Confirmation Errors
Monitor Labour Efficiency
Labour efficiency
Monitor Labour Variance
Labour Variance
Monitor Capacity
Monitor Capacity
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in
Monitor Asset Productivity
Monitor Asset Productivity Index
Material Usage Variance
Material Usage Variance reflects usage deviations comparing actual to target and zero loss figures
To provide a financial value, the Material Usage Variance is multiplied by the standard Material cost
Factory Output
Provides quantity of units produced for Finished Goods and Semi finished Goods in chosen unit of
measure
Units of Measure (cases, kilograms or liters) determined from the Material Master data
Material Yield
Material Yield reflects the amount of the material used compared to the actual output at a material
level and a component level
Yield information is used to measure the output of a given process compared to the input quantity.
Rework Report
Rework Report provides the amount of rework consumed versus standard, the amount of rework
generated versus standard, and the amount of components that were utilized in the Process Order
compared to the planned utilization of the rework.
I am not having any good idea in COPA. So Omitting it. Hope
PP & FICO Experts can explain more on this.
SAP Production Planning and Execution for SAP PP MM SD Beginners
G.V.SHIVAKKUMAR venkatesansivakumar@yahoo.co.in

Hope i have satisfied our friends requirement to some extent and I know that this document is not covering the
entire information and concepts in PP. But i am getting my internal satisfaction that this document will suffice to
some fresh consultants requirement to know about the basic process of Production Planning and Execution.
Requesting involvement of expertise consultants... so that we can make the document meaningful. Thanks to all.