The document outlines a tentative construction schedule for building an underpass at Wind Tunnel Road Junction over 11 stages. It involves mobilizing staff and equipment, soil investigation and design approval in stage I. Stage II involves dismantling utilities, setting up construction facilities. Stage III involves earthwork excavation for retaining walls and box structure for the northern half. Stage IV involves the same activities for the southern half. Stage V involves constructing footpaths, handrails and drains for the northern half. Stage VI involves widening and paving the road for the northern half. Stages VII-XI involve completing the remaining construction, finishing works, and installing road furniture, paintings, lighting, and signals.
The document outlines a tentative construction schedule for building an underpass at Wind Tunnel Road Junction over 11 stages. It involves mobilizing staff and equipment, soil investigation and design approval in stage I. Stage II involves dismantling utilities, setting up construction facilities. Stage III involves earthwork excavation for retaining walls and box structure for the northern half. Stage IV involves the same activities for the southern half. Stage V involves constructing footpaths, handrails and drains for the northern half. Stage VI involves widening and paving the road for the northern half. Stages VII-XI involve completing the remaining construction, finishing works, and installing road furniture, paintings, lighting, and signals.
The document outlines a tentative construction schedule for building an underpass at Wind Tunnel Road Junction over 11 stages. It involves mobilizing staff and equipment, soil investigation and design approval in stage I. Stage II involves dismantling utilities, setting up construction facilities. Stage III involves earthwork excavation for retaining walls and box structure for the northern half. Stage IV involves the same activities for the southern half. Stage V involves constructing footpaths, handrails and drains for the northern half. Stage VI involves widening and paving the road for the northern half. Stages VII-XI involve completing the remaining construction, finishing works, and installing road furniture, paintings, lighting, and signals.
iv).Construction of Retaining wall, ramp and RCC box
structure (for half portion along Northern side) viii).Construction of Retaining wall, ramp and RCC box structure (for remaining half portion along Southern side) ix).Construction of Footpath, Hand Rail, Lead Drain and Man hole Chambers etc., (for remaining half portion along Southern side) x).Widening and construction of surface level road (for remaining half portion along Southern side) V VV V III III III III v).Construction of Footpath, Hand Rail, Lead Drain and Man hole Chambers etc., (for half portion along Northern side) ConstructionofSignalFreeCorridoralongIdentifiedStretchesofRoadfromVellaraJunctiontoHopeFarmJunction(viaOldAirportRoad,Kundalahalliand ConstructionofSignalFreeCorridoralongIdentifiedStretchesofRoadfromVellaraJunctiontoHopeFarmJunction(viaOldAirportRoad,Kundalahalliand ConstructionofSignalFreeCorridoralongIdentifiedStretchesofRoadfromVellaraJunctiontoHopeFarmJunction(viaOldAirportRoad,Kundalahalliand ConstructionofSignalFreeCorridoralongIdentifiedStretchesofRoadfromVellaraJunctiontoHopeFarmJunction(viaOldAirportRoad,Kundalahalliand Whitefield)inBangalore Whitefield)inBangalore Whitefield)inBangalore Whitefield)inBangalore Tentative Construction Schedule for the Construction of Underpass at Wind Tunnel Road Junction. Stage Stage Stage Stage ConstructionStages(Activities) ConstructionStages(Activities) ConstructionStages(Activities) ConstructionStages(Activities) Monthwise Program I II I i).Mobilisation of Staff & Equipment, Soil Investigation, Design Approval. ii).Dismantling, Utility Shifting, Setting up of Casting yard, Batching plant, QC laboratory etc., II II II II iii). Earthwork excavation for retaining wall and box structure (for half portion along Northern side) vi).Widening and construction of surface level road (for half portion along Northern side) VI VI VI VI xi).Road xi).Road xi).Road xi).Road Furniture, Furniture, Furniture, Furniture, Painting, Painting, Painting, Painting, Lightings, Lightings, Lightings, Lightings, Signal Signal Signal Signal and and and and Other Other Other Other finishingworks finishingworks finishingworks finishingworks Milestone Milestone Milestone Milestone IV IV IV IV vii).Earthwork excavation for retaining wall and box structure (for remaining half portion along Southern side) 1 2 3 4 5 6 7 8 9 10 11 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Tentative Construction Schedule for the Construction of Underpass at Wind Tunnel Road Junction. Stage Stage Stage Stage ConstructionStages(Activities) ConstructionStages(Activities) ConstructionStages(Activities) ConstructionStages(Activities) Monthwise Program Activity Activity Activity Activity